Investor update

Nov 12, 2026

Summary

The raise will fund early procurement and works to reduce PLS execution risk, while the project targets CNSC decisions by end-2027 or early 2028, FID in early 2028 and first production in 2031. Annual drilling of 30,000 m will advance Triple R and Atlas exploration.

Operator

I would now like to hand the conference over to Paul Hemburrow, Managing Director and CEO. Please go ahead.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Good morning, good afternoon, hello. Thank you for joining us today. I want to do a quick recap and then talk a bit about the transaction and why we're doing this transaction today. Let me start with the U market. If we look back, we've seen the continuing strengthening of the U market, fundamentally driven by 440 operable nuclear reactors and 80 currently being built, plus 120 in the pipeline for future construction. This underpins the supply from miners, but what we're seeing on the supply side is this growing deficit that by 2030, 2035, will be + 150 million pounds per annum in deficit. What we've done at Paladin Energy is we've addressed the supply through the restart of Langer Heinrich now four years ago. Through that, we've demonstrated the capability to deliver a project on time, on budget.

We've demonstrated the capacity to build a contract book. And now we have 17 contract counterparties that account for approximately 50% of global nuclear energy production. These are first-tier counterparties. That project and delivering into those contracts has also enabled us to undertake the acquisition of Fission Uranium Corp about two years ago. In the last two years, we've continued to reduce the risk of that project through the permitting process. We've achieved our provincial EIS. We've closed out three of the four mutual benefit agreements. We've achieved our NROC, and now we're into the CNSC process to achieve our licence to construct. We've also conducted an engineering review, which we closed out in August 2025, and updated the economics of the project, which are incredibly strong.

The project has a CapEx demand at this point in time of $1.23 billion at a U price of $90 per pound. We're seeing spot prices now upwards of $92 per pound, and we're seeing term prices reaching $99 per pound. The economics are continuing to improve this project. Why are we doing this now? We want to attack this project from a position of strength. The project economics are positive at all plausible scenarios. We are currently in the process of updating the FEED study, and through that FEED study, what we won't be doing is changing the scope of the project. We're very confident, as of the last engineering review, with the scale of the project. We're confident with the surge capacity, the footprint, and through the FEED study, we'll update the engineering detail.

My expectation is that we will update the concrete costs, steel price, labor rates, and component costs, and by Q1 next year have a reasonable basis for an update to the capital estimate. My view is that all plausible scenarios, the economics of this project remain incredibly strong. What we are doing with this raise is further reducing the risk of project execution. Paladin Energy is an explorer, a developer of projects, and a miner. This is not a spreadsheet project, and there are practical realities to executing a project of this scale. This fundraise enables us to undertake early procurements of long lead time items, including things like tunnel boring machines, underground mining equipment, camps, roads, runways, and other infrastructure. It enables us to secure production slots for things like pumps, pipes, steelwork, components such as tanks and power generation units, compressors, et cetera.

What this does for us is it continues to de-risk the execution of the project. Looking forward, we have one mutual benefit agreement to conclude. We are currently in negotiations, and I think conclusion of that is imminent. I am talking months, not weeks, but months away, and I am feeling quite optimistic about that process. In terms of permitting, the next stage is locking in with the CNSC timelines for the hearings. Our expectation as a consequence of signing a memorandum of understanding with CNSC is to conclude those hearings by the end of calendar year 2027 and reach FID somewhere in early calendar year 2028. With the long lead time item acquisition, early works, this enables us to launch very quickly into construction, post-permitting, post-FID, and as soon as the seasonality allows for. This enables us to maintain our project momentum.

It also enables us to continue with our exploration program, and our plan is 30,000 m of drilling per annum. With that, we can continue to grow our resource at Triple R deposit, which remains open along strike and at depth. It also enables us to continue to grow our resource in areas like the Atlas Discovery and the Saloon East trend. I think Paladin is in great shape. I think the time is right now to execute a fundraise, and we can deploy those funds to continue to de-risk the project and grow value for the company. On that basis, I will conclude my commentary and happy to hand over for questions.

Operator

Thank you. If you wish to ask a question, please press star one on your telephone and wait for your name to be announced. If you wish to cancel your request, please press star two. If you are on a speakerphone, please pick up the handset to ask your question. Your first question comes from Branko Skocic with JP Morgan. Please go ahead.

Branko Skocic
Analyst, JPMorgan

Yeah, appreciate your time, team. My first question is going back to comments that you made around the timing of the raise. I think, well, at least when I look at our model, we had a raise in our numbers, but we think it is a little bit too early, just given the strength of the balance sheet and obviously the recent share price weakness. I guess when you look at your equity price today, what gave you the confidence to pull the trigger now rather than waiting for six, 12 months, given the headroom that you had on the balance sheet, please?

Anna Sudlow
CFO, Paladin Energy

Oh, yeah. Hi, Branko. I am happy to take that. I guess if you look at it from our perspective, we are realistically 12 months away from an FID. It is a fairly sizable cap ticket, and what this raise has allowed us to consider is further de-risking, acknowledging the competitive environment in Saskatchewan for resources and schedule. I think it does de-chunk the capital that we need for the project, so we felt that this was a good time to de-risk the project and go ahead and do that. I think the other thing, the benefit opportunity for our lenders in saying that we have got a strengthened balance sheet going into 2027. You do appreciate there are some fairly big swings in our working capital position quarter to quarter as well, so I think we came to bolster our balance sheet ahead of starting this de-risking scope.

Branko Skocic
Analyst, JPMorgan

I would appreciate that color . Probably the second question for me is how you think about funding the rest of the project from here. Obviously, you do not have to be pulling the trigger on that type of decision anytime soon, but how does debt, equity, and then a potential project sell-down factor into your thinking moving forward, just given today's raise?

Anna Sudlow
CFO, Paladin Energy

Yeah. We are progressing at the moment with a number of potential lenders, a project financing scope. The work that we have done today has been to bring in a number of parties. They have been through a phase one. We will take them into a phase two next year with the intent to get feedback around debt sizing, around ticket size from each of these counterparties, and also on kind of minimum revenue requirements.

What this raise does, though, is allows us to probably push out the drawdown of the debt and gives us more time to put in place potential offtake requirements for that debt. That is certainly on the list. I guess the reason we are really focused on project financing at the moment is the long lead time associated with that. I mean, there are obviously other debt options in the market which we will continue to consider.

They're all probably on a much shorter execution timeframe. I think we've got optionality around how we think of that. We could consider a corporate facility. I think, again, that's easier to execute potentially than a project finance. As you mentioned, we still have potentially a strategic partner option should we choose to go down that route. As you'd all be aware, we did enter into the purchase of Fission on the assumption we would progress this project ourselves, and we are happy to do that. I think what we're trying to do at the moment is maintain flexibility through into 2027 on what those pieces of funding are ultimately going to be.

Branko Skocic
Analyst, JPMorgan

I'd appreciate that color . I'll pass it on. Thank you.

Operator

Thank you. Your next question comes from Hugo Nicolaci with Goldman Sachs. Please go ahead.

Hugo Nicolaci
Analyst, Goldman Sachs

Oh, hi, guys. Again, thanks for the update this morning. Look, maybe just to build on Branko's question, and I note in your comments, a lot of what you talked to hasn't really changed in the last few months. Maybe sort of cynical question, but you had a hugely strong sentiment environment two to three months ago. Your share price was 50% higher, and even at that point in time, you probably knew that you'd need an equity component to fund PLS. What's changed in the last few months to now where you think you need to raise equity now? You touched on working capital. Is there some big swings that you need to manage from a corporate debt perspective? Is it CapEx at PLS that's starting to look a lot higher?

Is it a backlog of projects that might mean that you cannot execute on the timing that you are looking for? Can you sort of walk us through what has changed in the last couple of months?

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Well, look, one of the things I will say is that if we sort of reflect back, I don't know, 12, 18 months, we had quite a small team in Saskatchewan. As we built up the owners team, we brought on Santiago as our engineer for the plant design. One of the things you do realize as you get into the detail is that in order to preserve timing, you can benefit and reduce risk by bringing some of the acquisition of key items forward. This is not a spreadsheet project. We are building a mine, and there are some practical realities to doing that.

Although, as you rightly said, nothing is really changed in the broader environment, but we think that through this raise, we can considerably de-risk the pathway to first production through the early acquisition of key equipment items, through early works, as much as we can possibly do pre-permitting, to make sure that as soon as we get our licence to construct, we can very, very rapidly turn to building a plant. If we miss a production window, if we miss a or we have delays in construction of things like tunnel boring machines, then we can potentially delay the project entirely. Our goal is to deliver this project, deliver first production by 2031. In addition to that, what we have seen in the last six months is considerable exploration success. The Atlas discovery is arguably Paladin's best-ever uranium discovery. 28 holes, every single one of those with significant mineralization.

What we can do now is build on that success, punch more holes into the ground, and rapidly bring Atlas into the resource, which generates significant value, grows long-term life of mine, and I think that has the potential to be bigger than Triple R. So, like I said, nothing has changed, but what we are doing is de-risking this project and ensuring that 2031 production remains intact.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. Thanks. Look, maybe I will pick some of that offline then. Maybe moving to the Atlas piece, obviously significant spend there. You want to just walk us through the timing of that exploration spend and what you are aiming to achieve out of that? Are we looking at getting to a maiden resource from this spend? If so, when, what sort of timing can we expect some results out of that drilling?

Speaker 6

Yeah, so the seasonality in Saskatchewan, we have just wrapped up our summer program, and we released the results the beginning of September. We will start into the winter program shortly, drill that through to April-ish, and then as the assays come in, like we did last year, we will be able to release more results. We are planning about 30,000 m a year with two-thirds to three-quarters at Triple R. We really want to make sure that we firm up that resource and reserve. Knowing exactly where the ore body is and what we are going to get into when we get underground is really important, as well as extending that mine life. Atlas, as Paul just said, is hugely prospective. We have not found the extent in any direction just yet. As soon as the winter program kicks in, we will be back at Atlas full blast.

Hugo Nicolaci
Analyst, Goldman Sachs

Yeah. Okay. How do I reconcile then? You are spending in your sources and uses here $44 million at Triple R, but $58 million at Athabasca, but two-thirds to three-quarters of the drilling is at Triple R. How do I reconcile that?

Anna Sudlow
CFO, Paladin Energy

Yeah, so some of our existing budget is already allocated. This is just additional funds, not existing budget allocation.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. And so the timing, you said that Atlas is some of the highest grade and sort of best potential. So what is the timing then that that could start to firm up from this drilling? Are we another two or three seasons away of drilling before we start talking maiden resource?

Speaker 6

Yeah, it is really hard to tell just because we do not exactly know until we drill, but you are probably on track with, it will be a few seasons before we get a big enough resource that we can model it and add to the balance sheet.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. Thanks. I'm gonna pass it on.

Operator

Thank you. Your next question comes from Daniel Roden with Jefferies. Please go ahead.

Daniel Roden
Analyst, Jefferies

Hello, guys. Thanks for taking my question. Just wanted to, I guess, just get a bit of clarity around how the CapEx deployment that you're doing at the moment kind of correlates back to the, I guess, the quoted $1.226 billion CapEx for the PLS. How much of that is allocated within and outside of that budget, please?

Anna Sudlow
CFO, Paladin Energy

Yeah. Hi, Daniel. So, of the AUD 367 million allocated to PLS, probably about AUD 300 million of that is included in the $1.36 billion.

Daniel Roden
Analyst, Jefferies

Yeah. Okay. So that would imply that, I guess, the residual budget kind of outside of this, the residual funding stack is $926 million?

Anna Sudlow
CFO, Paladin Energy

Correct.

Daniel Roden
Analyst, Jefferies

Yeah. Okay. Thanks. And maybe can you, I know you kind of touched around it as well, but maybe can you provide a bit of commentary around, I guess, how the CNSC process is going, how the relationship with the MĂ©tis Nation–Saskatchewan, I guess, judicial review is, and yeah, probably just a bit more color around, I guess, the permitting and some of your TI relationships and actions there, please.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Thanks, Daniel. What's important to Paladin is that we have constructive, meaningful relationships with all of our stakeholders, whether it be suppliers, engineering partners, or local Indigenous people. What we've demonstrated in Namibia is that we value those relationships, and we employ 99% local people in Namibia. We spend most of our expenses is local, and we plan on doing the same thing in Canada at PLS. We have concluded three mutual benefit agreements, as I mentioned earlier. I think what we're doing with the fourth, with the Métis Nation, is just working constructively with them so that they feel comfortable with the benefits that their people will receive, including employment, access to contracts, et cetera. It's about building capacity and capability in their community and ensuring that their people benefit from our presence. We're fully supportive of creating that environment.

Métis Nation are very commercially savvy, and I think they're working incredibly hard for their constituents. As a consequence, it's a tough commercial negotiation. One of those points of leverage, of course, is something like an application for a judicial review. What we do know is that they haven't provided any affidavits to support their review, which means that can just sit out there. Our expectation is that when we reach conclusion to the MBA, that's one of those things that definitely comes off the table. Then we progress and build the relationship through partnering on construction projects, et cetera. I think that'll take its course. I feel like it's months away. It's not weeks away, it's months away. But that'll reach a natural conclusion when the commercial stack up for them and their people.

When it comes to CNSC, we have a very constructive relationship with CNSC. Our people have been working with them for a very long time. CNSC obviously finished NexGen and Denison's projects, and therefore have now experience in project review, technical review of projects, and they have people available to accelerate ours. NexGen took 30 months to get through the process. Denison took 13 months. We're targeting somewhere in the middle. At this point in time, we have the MoU with CNSC that commits to our timeline, and more specifically, a hearing date and a decision by the end of calendar year 2027 or very early 2028, and that remains on track. We're not seeing any risks to that at this time.

Daniel Roden
Analyst, Jefferies

Awesome. Thanks, Paul. I'll rejoin the queue. Thank you very much.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Thanks, Dan.

Operator

Thank you. Your next question comes from Glyn Lawcock with Barrenjoey. Please go ahead.

Glyn Lawcock
Analyst, Barrenjoey

Morning, Paul. I just wanted to make sure I fully understand the capital side. So, you said today the pre-FID spend is in addition to the $1.236 billion CapEx. Can we just work what is the pre-FID spend in total, and does that exclude all the spend you've identified today on resource growth, regional exploration? Thanks.

Anna Sudlow
CFO, Paladin Energy

No. Glyn, the PLS project development spend in the raise and the use of funds, it is deducted, AUD 300 million of it is deducted from the $1.36 billion . So it is not in addition to. Of that raise, probably half to two-thirds will be prior to FID. That is what this raise has allowed us to do, is move some of those post-FID activities and spend into calendar 2027.

Glyn Lawcock
Analyst, Barrenjoey

But sorry, then what you are saying is the pre-FID number is only AUD 67 million. Is that right?

Anna Sudlow
CFO, Paladin Energy

No, because we have got cash on the balance sheet from the previous raise. So essentially, we have got the residual pre-FID spend from the prior raise, and then we have got AUD 70 million in addition to that.

Glyn Lawcock
Analyst, Barrenjoey

Okay, so it is an extra AUD 70 million on top of what we thought we had pre-FID today, basically.

Anna Sudlow
CFO, Paladin Energy

Residual is deducted from the total CapEx.

Glyn Lawcock
Analyst, Barrenjoey

Okay, I think I understand. If we just think about, you've obviously said you'll have an update for us in Q1 as you've recut the numbers for CapEx, OpEx. I mean, is it looking like other projects where it's 20%-30% differential, or is it better than that? Any feel for how it's been coming together?

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Oh, look, Glyn, we'd be making it up if we gave you a number. I've said for a long time that I fully expect the capital cost to go up. If we go back to August, what we did through the engineering review was upscale the project, increase the footprint, increase tank capacity, increase surge capability. We priced the project at $1.226 billion on the basis of increased steel price, concrete costs, labor rates, and component costs, as best we knew in August 2025. What we're not doing through the FEED study is changing any of that. We're not increasing capacity, we're not increasing surge capacity, we're not increasing tank size or footprint.

My expectation is that the updated CapEx number is going to be as a consequence of refining the detail, but also of inflationary increases in key inputs, including things like cost of freight for large components. So, I'm thinking more inflationary levels of increase than significant movements as a consequence of scope change.

Glyn Lawcock
Analyst, Barrenjoey

Yeah. I mean, I don't know if you were surprised, Paul, but when I looked at NexGen's results and they said they've been able to continue putting contracts out at 2024 basis, seems like there's no inflation out there. I don't know if that shocked you as well.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Very shocked. Look, Glyn, even construction's an outdoor sport, and in the field, you get tired and things happen, you get tackled, and it's hard to imagine that things stay the same. My view is that if you're going to build a plant and you're going to have a certain output from that plant, and you want a certain level of functionality, then ultimately it costs what it costs. Our job is to make sure that we're not overcooking the plant, that it's fit for purpose, that it's maintainable in all seasons, and it delivers an annual production rate of 9 million pounds at least for 10 years. I think the capital estimate that we had in 2025 is good. Over this next, between now and Q1 next year, I think we'll be able to develop another reasonable base for an update.

I would be incredibly shocked if that number was exactly the same.

Glyn Lawcock
Analyst, Barrenjoey

Okay. No, understood. If I could squeeze one last one in, Paul. I think myself and maybe quite a few were disappointed by the September quarter result. I think you'd said back at the full-year result that the September quarter would look like the June quarter, yet it was 20% higher cost and 20% lower volume. At the same time, you'd also said Q2 would look like Q1 because you've got a one-week outage in both quarters. Is that still the case then? We still thinking while we were disappointed on Q1, Q2 still looks like Q1, so another quarter of a million pounds at $60 a pound cost?

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Yeah. So there's a couple of things there, Glyn. If we look at the actual result from Q1 FY 2027 and compare it to the previous quarter, then our total ore mined was similar. Our feed to the plant was about 20,000 lbs different. Our overall recovery rates was 5% difference, which resulted in 58,000 lbs less uranium into the system. So overall, that was about 70,000 lbs less actual production than the previous quarter. So virtually identical inputs. What was different though was a fairly significant inventory build in the first quarter of this year, but otherwise, production and accounting production was the same. What we didn't do was drum. We also lost a week for the shutdown, and so there's another 100,000 lbs, 120,000 lbs. We had the additional cost. So, the cost story was a function of 19%, 20% lower drummed production.

What you are seeing in the October result is that come back. We have seen our total movement increase. I think we were at about a 7.2 to 7.5 million tons total movement rate. Total movement in October, I think on an annualized basis, was more like 8.5 million tons. So we have seen that productivity gain there. We have seen our overall recovery sort of bounce back up to the high 80s, so well within the target range. We have seen grades up over the 500. So I think that October is probably better than I was expecting, to be honest. I expect this quarter to be, yeah, well and truly on track to meet our expectations, slightly better than Q1. And exiting at a run rate that delivers our second half uplift, as I said in the guidance.

Glyn Lawcock
Analyst, Barrenjoey

All right.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

[inaudible]

Glyn Lawcock
Analyst, Barrenjoey

Thanks.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Yeah. The only change, sorry, the only change, Glyn, overall is the timing of the second shut. The second shut is all about changing out our kiln. There is nothing wrong with the existing kiln. It has the capacity to deliver what we want. It is a maintainability issue. When we were commissioning that, I had many nights on the production floor there. The element arrangement in that kiln is horrible. It is difficult to maintain. The new kiln design is functionally better. It is bigger, higher surge capacity, easier to maintain, and so any shuts on that kiln are going to be much shorter in the future. Now, when the kiln outage is on, the rest of the plant keeps producing, and we produce in-process inventory, and we can come out of that with greater surge capacity.

The timing of that is mostly related to the shipping delays for the kiln, but otherwise, it is going to have no effect on our guidance.

Glyn Lawcock
Analyst, Barrenjoey

Yeah. Okay. We exited a rate that is probably going to be annualizing well above 6 million pounds, obviously, to get to the guidance.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Oh, I think it is not mission impossible, but that is mission difficult, but it will be something like that.

Glyn Lawcock
Analyst, Barrenjoey

All right. Thanks again. Appreciate it, Paul.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Thanks, Glyn.

Operator

Thank you. Your next question comes from Lachlan Shaw with UBS. Please go ahead.

Lachlan Shaw
Analyst, UBS

Morning, Paul and team. Thanks very much for your time. Just a couple from me. You did talk to, you're looking maybe at a project finance-type facility for the rest of the funding potentially. Just interested, what's your thinking in terms of how much you might need to sort of square away in terms of locking in terms for the syndicate, for the banks? Normally, they'd be seeking for some certainty on the revenue side there, so just interested in how that thinking is evolving, then I'll come back with my second.

Anna Sudlow
CFO, Paladin Energy

Okay. We're pretty early days with the banks. What I can say is that our existing lenders, Macquarie and Nedbank, who have backed us on the Langer facility, are pretty keen to be involved in this transaction. I guess the benefit that they bring is they understand the U market, they understand our ability to go contract. I think what we'll see from them is probably a drive to be giving us credit for uncontracted potentially, and spot-related contracts. I think the jury's out on how much that will be. The next scope of work that we're doing with the banks is aligning on what those minimum revenue requirements are. At the moment, they're all provided on a quite divergent way of describing basis, and we just really need to line everyone up and get on the same page as that then.

I mean, I think you can expect at FID, the board is probably going to want a de-risked position to some extent on offtake, so there will be some locked-in revenue at FID, I would expect. But what we actually need for the financing, we need to do a bit more work on.

Lachlan Shaw
Analyst, UBS

Yeah, great, Anna. Thank you. That's really helpful. Second question. Just again to come back to, I guess, timing, but also purpose of the raise. You've talked about de-risking long lead items, infrastructure, pre-FID works, et cetera. If you think about what comes next, what you need to get your head around, where do you see or where are you focused on in terms of the main pressure points to further de-risking? Is it contractor and labor capability and availability? Is it contractor performance? Is it permitting? What are the key sort of milestones and catalysts you're most focused on from here? Thank you.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

In an immediate sense, Lachlan, is the permitting process, so making sure we get through the CNSC process absolutely seamlessly. We'll do that by making sure the FEED project is executed extremely well, provide the best possible detail that we can into the CNSC process so that when we come out of permitting, we have as few conditions as possible on us. Then we can launch into the FID process, by which time I'd expect we'd have our funding stacks sort of narrowed down a bit. We'll have started to build the contract book, and we'll lock in the EPCM contract arrangements. We'll already have the long lead time items secured or production and slots secured, and then it just becomes about careful execution of the project.

I think it's a well-worn path for developers, and I think we understand the key risks and have management strategies in place for all of those risks.

Lachlan Shaw
Analyst, UBS

Great, Paul. Thank you. I'll pass it on.

Operator

Thank you. Your next question comes from Hugo Nicolaci with Goldman Sachs. Please go ahead.

Hugo Nicolaci
Analyst, Goldman Sachs

Hello, guys. Thanks for taking the follow-up. Firstly, just for PLS, can you just confirm if there is any outstanding permitting or maybe part of that mutual benefit agreement that you need in place before you can start doing any of these early site infrastructure works?

Paul Hemburrow
Managing Director and CEO, Paladin Energy

The only one outstanding is the MĂ©tis agreement. That is all. We have got three of the four concluded, Birch Narrows, Buffalo, and Clearwater River Dene Nation. We just now have MĂ©tis Nation–Saskatchewan to conclude. That is all we have from an MBA perspective. Other permitting, we are working towards an advanced exploration permit, which enables us to undertake clearing and grubbing on site, improve the quality of the road network, and constructing by gravel pits. That is pretty much it until we get our permit to construct.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. Thanks. Then maybe just coming back to Anna, you made comments about working capital earlier in terms of the timing of the equity raise. Can you just walk us through what you are seeing there in terms of working capital impacts this quarter?

Anna Sudlow
CFO, Paladin Energy

Oh, look, I think what you would appreciate having looked back at our previous quarters is, there is a big working capital movement at Langer quarter to quarter. That is really what I am alluding to. So we can see swings quarter to quarter, $30 million-$40 million . So that was really my reference, and I think that is always going to be the case at Langer because it is a function of the shipping schedules and the customer deliveries quarter to quarter. So, that was the reference there, really.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. Does that working capital mean that you maybe have less cash on hand than you are required to, and maybe that sort of leads into the timing of the raise now?

Anna Sudlow
CFO, Paladin Energy

Oh, I think it is just an acknowledgement that there is that volatility in the cash balance. So, I think we have got a big cap ticket. I think that volatility is probably not that helpful to us. So I think that does play into how we think about 2027.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. That minimum cash balance under your existing arrangements, is that $100 million, give or take?

Anna Sudlow
CFO, Paladin Energy

No, the current minimum cash balance under our existing debt facility is quite a bit lower than that, but our own internal threshold will not be that number.

Hugo Nicolaci
Analyst, Goldman Sachs

Got it. Thanks, guys. Thanks for taking the follow-up.

Operator

Thank you. That does conclude our question and answer session. I will now hand back to Paul for closing remarks.

Paul Hemburrow
Managing Director and CEO, Paladin Energy

Thank you once again for dialing in today, and appreciate your ongoing support. I think Paladin is really well positioned for this growing supply deficit heading into 2030. Langer as an operation is stable, business as usual, and I absolutely believe we are doing a great job running that asset. The PLS project is in the top three undeveloped uranium projects in the world. And with our exploration works, there is every potential to expand that current 10-year life at 9 million pounds per annum to something quite substantial. This raise, I think it is exciting for us. It continues to de-risk the project and grow value for the shareholders. Once again, thank you for your interest and thank you for your support. Have a great day.

Operator

Thank you. That does conclude our conference for today. Thank you for participating. You may now disconnect.