Nov 11, 2026

Summary

9M revenue rose 70% YoY to €410m, with almost €18m EBITDA and guidance reaffirmed. A near-€2bn backlog and rising U.S. and European demand support upside, while capacity, execution and funding remain key constraints.

Operator

Welcome, and thank you for joining the Avio nine months 2026 results web call. All participants are in listen-only mode, and after the presentation, there will be a Q&A session. At this time, I would like to turn the conference over to Mr. Nevio Quattrin, Head of Investor Relations. Please go ahead, sir.

Nevio Quattrin
Head of Investor Relations, Avio

Good afternoon, everyone, and welcome to nine months 2026 results conference call of Avio. I am here with Mr. Giulio Ranzo, Chief Executive Officer of Avio, and Mr. Roberto Carassai, Chief Financial Officer. In a moment, we will go through the presentation we have uploaded on our website, and then at the end, we will more than welcome your questions. At this time, I hand the conversation over to Giulio. Please go ahead.

Giulio Ranzo
CEO, Avio

Thank you, Nevio. I welcome you all to the presentation of the results. I hope you have the presentation in front of you. I am moving to page four with the highlights. Once again, also in this quarter, we continue our double-digit growth path all along the revenue, the profits, and so on. As you know, we have completed successfully our last Vega C mission with Sentinel-3C and FLEX. Also, one more Ariane 6 was successfully launched with MTG-I2. Launch activity is progressing as expected. We have made some new progress on our U.S. project in that we have started the construction of the plant.

We have recently conducted our groundbreaking ceremony and started works, but also signed a strategic cooperation binding agreement with Lockheed Martin in the form of a framework agreement, so to speak, for future long-term production of ER GMLRS and PrSM missiles or rocket motors. That is a very important achievement. Then we have received additional orders from MBDA for ASTER 30, probably more to come in the future. As I expected, the flow of orders continues to arrive regularly, not with much of an ability for us to predict, but they continue to arrive regularly. The order backlog as a result of that stands again at a couple of billion euros, and it is converting into revenues quite fast, given that the revenues are growing at some 20%, and therefore, we are obviously on one side adding more backlog, on the other side consuming what we have.

EBITDA also growing in the high teens region, so I would say in line with what we expected. As a result of that, we confirm the guidance for 2026. Moving to page five, the last launch of Vega C was quite important for us. It was almost at the top of our performance, launching two satellites together, Sentinel-3C and FLEX, so leveraging the full capacity of the rocket. As you can see in the picture, we completely filled the fairing. It was also a very complex mission in terms of how to position these two satellites in orbit, and therefore, we are quite happy that the mission was completed flawlessly with full satisfaction of the customers. It's never trivial to say this is the core of what we need to do to satisfy the customers. So, I would say in this case, we did a great job.

Also good to know that Ariane 6 on page six successfully launched MTG-I2. Ariane six is continuing to ramp up very fast. I would say almost surprisingly fast. This was a Meteosat of the third generation imaging satellite, what is traditionally been done by Ariane. What is impressive to me is the rate at which they are successfully delivering flight cadence growth. So this year, they expected to do eight launches. Maybe they will not do eight, they will do seven, I don't know. If not, the following launch would be soon after year-end. So they really are ramping up fast, and that is crucially important for us to feed our booster production activity. On page seven, as a matter of fact, as I told you, the launch manifest becomes busy. On the side of Vega, we will have a third launch before Christmas. We're targeting that.

The satellites from the customers are a little bit late, so we are waiting for the last few of them to arrive. It's an interesting mission, six different satellites. They're coming in a little bit late, so we are coming very close to Christmas Day, but okay, we do the best we can from that point of view. The rocket is being assembled on the pad. There's one more Ariane rocket in November, potentially one in December. We will see what their schedule looks like, but it looks like a very successful year overall. On page eight, this was a picture taken from our U.S. factory groundbreaking ceremony. It was a very interesting event because it was quite well participated by very relevant U.S. institutions, including the Virginia Governor. The Secretary of the U.S. Navy and key people from the core customers, Lockheed Martin and Raytheon.

As a result of the agreements we recently signed, we'll be basically the core customers feeding pretty much all of the capacity we have. So we have high expectations on this, and I think we did a great job. I have to say, the presence of all these parties at the groundbreaking ceremony was telling because they all expressed gratitude for what we are doing in the U.S. and reliance. So, the Secretary of the Navy expressed very clearly that what we do is highly needed for the U.S. Navy, and they rely on our project and so on, and so did Raytheon and Lockheed. Also, very strong words of encouragement from the governor. The governor, as you may recall, is supporting us with up to $97 million worth of state funds to release expenses on, to tax benefits and stuff like that.

We really have a great team to succeed. Yet, we have to do it, but the overall context is very much progressing as we expected. What is new, and on page 10, we have communicated to the market a few days ago, is that our business plan that we communicated a year ago to the market, especially for the U.S. business, is now being populated with new relevant facts. In particular, between August and October, so to speak, the core customers, Lockheed Martin, Raytheon, and U.S. Army, signed their own contracts with the U.S. government and customers. Namely, with the U.S. Army, the U.S. Navy, the government in general. On the very products in which we are involved, on PrSM and ER GMLRS for Lockheed Martin, on SM-6 and SM-3 and Tomahawk for Raytheon, and on multiple programs for the U.S. Army.

This means that now our own customers, meaning the prime contractors, have in their hands sufficient business to flow down to us work for the future to come. It is not very surprising that Lockheed Martin then signed an agreement with us to book essentially capacity in the plant for the entire duration of these programs. Raytheon will probably do very soon for the MK 104 and for the Tomahawk missile. Similarly for the U.S. Army, which has a couple of programs with us that are already in production. Overall, I would say this news allowed us also to realize that there is probably more business that we had anticipated with these customers. Volumes may be higher than we had incorporated in our original business plan.

We are not exactly in the possibility to estimate by how much, but it is quite evident to us that there is now an upside opportunity that also may stretch beyond the six programs you see in this page. Two with Lockheed, two with Raytheon, two with the U.S. Army. There may be more programs coming from each of these customers and more volumes than anticipated for each of these programs. Overall, we passed the message through a document we published on the website a few days ago that we now expect volumes may be higher than we had anticipated. Similarly, on page 11, on the European space business, space and defense business, we are seeing clear evidences of the system willing to move to a different scale.

The European Space Agency is contemplating to request the European member states to support a substantial increase in Ariane 6 and Vega C launch cadence, all the way up to 15 Ariane 6 per year and all the way up to nine Vega C launches per year, as it was communicated by the European Space Agency Director for Space Transportation. Similarly, in defense, MBDA, as you can see from their press releases, is issuing orders, new orders continuously because there is more demand, internal demand from European customers, and more stuff that is going to Ukraine through the refinancing of the Ukraine support. Overall, the reading of this, as I said a couple of minutes ago, is that anywhere across our business plan, there appears to be more upside potential than we had incorporated in the plan.

That is not firm enough yet for us to be able to say that we have to update our business plan or anything like that. But, it is important that we signal that we do see more upside and that we follow through the news flow if there are any other evident signs of this upside actually materializing in practice. With this introduction, I would then leave you to Roberto to go over the financials.

Roberto Carassai
CFO, Avio

Okay. Good afternoon, everybody. If we move to slide 13, then we can comment on the backlog. As Giulio was saying, we are still around EUR 2 billion of backlog, despite quite, again, significant increase in the revenue side that we will comment in a while. In the nine months, we have booked EUR 240 million of orders, 50% in the space domain, 50% in the defense business segment. In terms of composition of the backlog, you can appreciate that the production stake of the backlog has achieved 70% of the total backlog compared to the development part that is obviously the 30%. If we move to the next slide 14, we can comment on the revenue growth a bit. We have achieved EUR 410 million in the nine months period, with a 70% increase compared to last year.

I think it is worth noticing that all the three business segments contributed to this growth, so the launch system, the space propulsion, and defense propulsion as well. Now the defense portion of the revenue has achieved 70% of the total revenue. Obviously, the largest bulk of the revenues are still related to the launch system business segment for more than 60%. In terms of composition of the revenues, again, similarly with the comment we have done on the backlog, we can appreciate that the production stake of our revenue is raising compared to last year, achieving 67% in the nine months 2026. If we move to the slide 15, here we have the main figures, main economics and financial figures of the company. I think overall we can appreciate that figures are improving compared to last year in all the lines.

It particularly would mention that the revenue growth keeps a double-digit pace for the third consecutive nine months period, similarly on the EBITDA side.

Giulio Ranzo
CEO, Avio

Quarters, yes.

Roberto Carassai
CFO, Avio

And in terms of EBITDA, we have achieved almost EUR 18 million. In terms of EBIT reported, we have EUR 1.7 million of positive result compared to almost nil last year. The net financial position is quite significantly high at more than EUR 600 million, EUR 614 million. You need to consider that this amount benefits from the capital increase that was subscribed by Advent late in September. So net of this capital increase, the company has experienced a cash absorption of almost EUR 80 million in the period due to the CapEx acquisition in the period and the flow down of the advance payment to suppliers previously, let's say, collected. Moving to slide 16, here you can appreciate the quarterly evolution of the EBITDA.

You can, I think, realize that there is this constant growth in the first nine months, and then as usual for this company, with the seasonality that is typical of our business, we should expect to have a more significant growth in the last quarter of the year. We have already commented the net financial position, so we can go to the last slide of the presentation, basically confirming the guidance for year-end at this stage. Thank you very much for the time being.

Nevio Quattrin
Head of Investor Relations, Avio

Thank you, Giulio. Thank you, Roberto. We can now open up the Q&A session.

Operator

Thank you, sir. Thank you, gentlemen. We will now begin the question- and- answer session. To enter the queue for questions, please click on the Q&A icon on the left side of your screen. When announced, please click continue on the pop-up window. If you are connecting in audio today, please press star and one on your telephone. The first question comes from Alessandro Pozzi of Mediobanca.

Alessandro Pozzi
Analyst, Mediobanca

Good afternoon. Thank you for taking my two questions. The first one is going back to the opening remarks about volumes in the U.S. potentially being higher than expected. Also, I have seen some press comments suggesting that the Lockheed Martin volumes are underpinning half of the volume of the new plant, with most of the rest from RTX. Then there is a little bit of maybe volumes left, but not much. I was wondering, now you are building the new plant as well, what is the best time to make a decision on how to size the new plant, whether to go for the 700 tons per year or adding more mixer to the plant? That is the first question. The second question is, also you mentioned, we all know that there is a big push from ESA to increase the number of launches.

How should we think about the production volumes for Avio from here to 2030? Is it going to be a linear, steady increase next year, 2028, 2029, or is that more of a step change as you go towards the ambitions of ESA? Thank you.

Giulio Ranzo
CEO, Avio

Thank you very much. Let us first talk about the U.S. volumes. When is a good time to decide for the plant size? First of all, you know that we have been designing with our engineering firm a scalable plant that can be put in place with a capacity that can be up to 3x the baseline capacity. Anywhere from 700 tons capacity all the way up to 2,100 tons capacity. When it is a good time to make a decision? That is one hell of a question because I presume in the course of 2027, because at the end of the day, you would want to wait a little bit more to see if these upside volumes really materialize. At the same time, you cannot let the construction of the company, of the factory last six or seven years.

We need at some point to force the customers to be a bit more specific into their expectation for volumes in a way that we can more properly concentrate production over a certain period of time and make sure it does not take too long if we defer decisions on a potential plant size growth. In fact, the dilemma here is the following. If you invest more for a bigger plant, you end up having a better return because you do not spend much more, but you get more volumes, you get more profit. Definitely it will increase the return. But you are not yet completely sure about the upside. We will have to make a decision to answer your question in the course of 2027.

Regarding the ESA volume growth, as it stands right now, we have a fairly linear growth rate in the boosters for Ariane, which has been very fast so far, because if you compare what we did last year, or this year with respect to last year, we increased the number of boosters delivered by 50%. Next year, we will increase the number of boosters delivered by another 50%. Then we would be very close to capacity. We would be at 90% of the capacity.

In terms of the growth on the Vega launches, we should be climbing to four and then to five as quickly as possible if the customers maintain their deadlines, because even in the case of this last flight, the customer was a little bit late, so we end up slipping about one month, and that's not because of our production capability, but it's because we had to accommodate a need from the customer. So even on Vega, I would say if you grow by one launch per year, it's like growing 25%-30% per year, which on the launch service side is not a trivial exercise. On the solid rocket motor side on the European part, we are probably growing some 35%-40% a year in terms of volumes, steadily, and we will have to continue to do that.

Unlike the U.S., for example, for Aster 30, we are very well covered by orders all the way to 2034. So, it's more a question of execution than it is a question of market. So it's a more plannable type of growth.

Alessandro Pozzi
Analyst, Mediobanca

All right. Just going back to the U.S., we've seen the results of the midterms. Do you think it's going to change in the calculus for the defense budget going forward and allocation to munitions in the defense?

Giulio Ranzo
CEO, Avio

There is in fact a page that we published on the website, I believe the one we downloaded from a third party with the estimates of the various programs funding at government level, including Tomahawk, including SM-3, SM-6, and so on. In that picture, if you go back to our website, you see what was the funding in fiscal year 2025, fiscal year 2026, and fiscal year 2027. That is as far as the U.S. government approved congressional budget goes, right? You evidently see in fiscal year 2027 a very steep increase in budget allocation. We don't know yet whether that is also going to happen in 2028, 2029, 2030, et cetera, because the U.S. Congress has not yet approved that. There is a clear tendency not for a linear growth, but also for a vertical step change in volumes.

Is this trend set to continue? Is this trend going to change because of the change in Congress that has already happened? This, quite frankly, we don't know. But one thing is for sure, that the U.S. inventory for solid rocket motors is down to the minimum, okay? So, whether the Congress is Democrat or Republican, or whether they believe or not in this, there is a clear need to accelerate the production volume very substantially.

Alessandro Pozzi
Analyst, Mediobanca

Understood. Thank you very much.

Operator

The next question is from Martino De Ambroggi of EQUITA.

Martino De Ambroggi
Analyst, EQUITA

Thank you. Good evening, everybody. The first question is, once again, on the announcement date. I clearly understand it's next year for the decision on the doubling or maybe multiply by three the production, but can we consider the Tomahawk signature, the Tomahawk order formalized and so on, the milestone that makes this 100% clear that there is a need for an upward revision? Am I right in assuming that if you need to double capacity in the U.S., your financial structure is able to self-finance the investment that I estimate in the region of EUR 150+ million just for doubling the capacity? On the additional programs you are currently negotiating, I clearly understand it's secret, so you cannot disclose, but are they potentially smaller in size or similar as a potential upside compared to what you already announced so far? Thank you.

Giulio Ranzo
CEO, Avio

The announcement of Tomahawk itself, it's a very strong indicator, but we do not have yet the precise volumes of the Tomahawk. Everywhere you go, if you look at the size of the orders for the Tomahawk that Raytheon has received, this is over $24 billion, if I recall correctly. It's $23 billion they received in orders. In line of principle, there is a lot of volume there. We don't know what share of production they would want to award to us yet, and it will take some time to discover. I don't think there is a core milestone that makes or breaks our plan whether we go for a bigger plant or not, because this is very gradual. We could start with two mixers. We could add another mixer to go in three, then later in time, we could add a fourth one.

There's not a critical decision milestone whereby you have to decide whether you double or not. You can go progressively, right? What I said before, though, is that you cannot slice this in a different decision every month, because otherwise, or every year, because otherwise, the commissioning of the plant will take a decade, right? I would say that we start with the baseline assumption. Then in the course of 2027, if we have sufficient reasons and visibility to believe that we can do more, maybe we will upgrade by one mixer, and then we would see. Obviously, to increase capacity, every time you add a mixer is a few tens of millions of dollars, and we don't have this money yet.

For this very purpose, and not only for this purpose, we have requested additional money to the U.S. government in the form of a soft loan, and partly, hopefully, in the form of a small grant. We will see if we get awarded additional money at a cost of capital that should be lower than what we have today as the equity cost of capital. If we succeed in doing that, obviously, it would be a much easier decision to go for a slightly larger plant or even a doubling of that. We have to somehow put all this decision-making in parallel. In fact, yesterday, I was discussing with the team that we need to monitor where the customers stand with their ability to flow down orders to us.

We have to check where the government stands in terms of awarding financing to us, and then we need to see where we stand with the plant construction, and we will try to align these dates. Obviously, it would be nice to have that they get all of the decisions upfront and all we have to do is execute the plan. But unfortunately, life is not perfect.

Martino De Ambroggi
Analyst, EQUITA

Yeah. On the ongoing negotiations for new programs, just to have an idea if they are similar?

Giulio Ranzo
CEO, Avio

I think there is a complete discussion on another program for Raytheon. There should be another discussion for another product with Lockheed. I honestly don't know how much time these things will take. For example, the discussion on Tomahawk has been way faster than I ever thought, whereas the discussion on MK 104 has taken a long time. Every product has its own history, and also, we do not have the full visibility of how easy or how difficult it is for the customer to receive the product funding from their customer. As a supplier, we have limited visibility of their contracts with their government. But I think, on a couple of programs, the discussion is complete. Let's see where we stand, but I hope in the course of the next couple of quarters to be able to say something about it.

Martino De Ambroggi
Analyst, EQUITA

Thank you, Giulio.

Operator

The next question is from Gabriele Gambarova of Intesa Sanpaolo.

Gabriele Gambarova
Analyst, Intesa Sanpaolo

Yes, thank you and good evening. The first question is again on soft loans. From your October presentation, I understood that you could ask up to a couple hundred million dollars. Is it correct, this understanding? This is question number one. The second one is on the level of costs connected with the U.S. initiative of EUR 4.8 million in the nine months 2026. I was wondering what could be the level for 2026, the whole year, and the coming years, if anything has changed. The third one is on inflation. Do you see any disruption, any impact, considering that the cost of gas went up significantly? Thank you.

Giulio Ranzo
CEO, Avio

Gabriele, I will answer the first question, and I will ask Roberto to answer the following ones. On the soft loans, we don't know what we will get approved. Yes, we can ask for a few hundred millions. It's not so difficult to ask. You can ask as much as you want, even billions. You have to see what is the feedback. We are having a very constructive discussion because I think also the concurrent need from our customer, which became evident at the occasion of the groundbreaking ceremony with the U.S. Navy speaking very highly of what we are doing and so on, is forming a sufficient consensus in the government that what we are doing has a merit. A soft loan would be a soft loan, so it should be cheap.

I don't know exactly what are the precise conditions that will come along with such a type of funding, so we will see. The discussion is continuing, and we will keep you posted as soon as we have more quantitative details around what we can get. Roberto.

Roberto Carassai
CFO, Avio

Okay. On the second question, Gabriele, in the nine months, we have incurred costs for almost EUR 5 million, and we are in line with our budgeted profile, and we expect to close the year with something in the range of EUR 8 million-EUR 9 million, as expected.

Operator

As a reminder, if you wish to register for a question, please press star and one on your telephone or click on the Q&A icon on the left side of your screen. The next question is from Michael Filatov of Berenberg.

Michael Filatov
Analyst, Berenberg

Hi, guys. Thanks for taking my question. Apologies if I missed this earlier. It's been a bit hard to hear sometimes. Just quickly on order intake, Q4 needs about EUR 200 million to reach that guidance of yours. What's in the pipeline beyond the EUR 55 million Aster order? I guess, could you give us some sort of idea of the split of that for the remainder of the year? The second question is just around the timing of the agreements with Lockheed Martin and Raytheon. I guess, the slides say now that Raytheon is potentially partnering on the SM-2, SM-3, SM-6, and the Tomahawk. So I guess, what is the path and timing to a binding agreement and something that looks similar to what you've announced with Lockheed Martin? I'll just leave it there and maybe follow up.

Giulio Ranzo
CEO, Avio

First of all, on the order intake this year, couple of considerations. First of all, between now and year-end, we should receive more orders from the space side. We have a few space launch services that we shall contractualize between now and year-end, and then a few orders from the European Space Agency. The last quarter will be still more towards space new orders than defense orders, okay? Keep in mind that by virtue of how the business works, we tend to have more orders on the Vega side, I mean, continuously, because we sell new launch services and things, and we sign new contracts with ESA, and similarly with defense, every now and then we get an order. Whereas for what we call space propulsion, meaning the boosters that we deliver to Ariane, we don't get an order every quarter.

We get an order maybe every three years, because we do get a large batch and we work on the batch. Now we will be consuming that batch with ArianeGroup, and then at some point it will go to zero, and before it goes to zero, we will get another big batch. To answer your question, between now and year-end, it will mostly be space-related, the order intake. Then you had a question on the agreement with Raytheon. It is in the making, it is being discussed. I hope we can get it done by end of the year. It will be similar to that of Lockheed, not identical, but most probably similar. It will have pretty much the same effect. That will be another important part of the puzzle, so to speak.

Michael Filatov
Analyst, Berenberg

Understand. Just one quick follow-up on the guidance. I know if I just take sort of nine months seasonality, it points towards above the top end of the revenue guidance. I guess I am just wondering why a raise is not in the picture. Then you spoke earlier about sort of the business plan in sort of the mid to long term potentially being up for revision because things are looking good, so that is a positive thing. I guess, what signs do you need to see to feel confident about that potentially around the end of the year results or, I do not know, whenever you feel comfortable?

Giulio Ranzo
CEO, Avio

Look, on the revenue side, as always, we are not particularly concerned that we will not make the figure or be on the upper part of the guidance potentially. On the profit, it is a little bit more complex because as you know from our chart number 16 where we show the quarterly progression of profits, most of the profit, meaning half of the profit, is accumulated in the fourth quarter. So, it is a little bit gambling to know what we do between now and year-end to recognize every cost and therefore accrue what type of profit we can bring within the year and such. Therefore, we have more ability to predict revenues than we have ability to predict profits until really the last day in the year. Therefore, I would say overall, we think we can hit the guidance.

Now, on some of the lines of the guidance, we may be on the upper part. On some others, we may be in the center line. As of today, it is difficult to say because of this concentration of activities in the fourth quarter, which is not something new of 2026. It actually happens every year.

Michael Filatov
Analyst, Berenberg

Understood. Thank you.

Operator

As a reminder, if you wish to ask a question, please click on the Q&A icon on the left side of your screen or press star and one on your telephone. For any further questions, please click on the Q&A icon on the left part of your screen. Gentlemen, at this time, there are no questions registered.

Giulio Ranzo
CEO, Avio

Thank you, everyone, for joining.

Operator

Oh, excuse me, sir. We do have a follow-up question from Mr. Andrea Bonfà, if I may.

Giulio Ranzo
CEO, Avio

Okay.

Operator

Mr. Bonfà, your line is open, sir. Mr. Bonfà, do you have your line on mute?

Speaker 9

No.

Operator

Okay. I could hear you now if you have a question.

Speaker 9

Okay. Can you hear me now?

Operator

Yes, sir.

Giulio Ranzo
CEO, Avio

Yes, Andrea. Yes, Andrea.

Speaker 9

Okay. Hi. Good evening to everybody. Very quickly, I got, let's say, one curiosity. When are we going to see, let's say, a stronger acceleration in defense sales? Is it going to be next year? Because at the end of the day, in 2026, we are, let's say, seeing still a kind of pedestrian growth rate for the sales in defense compared with the, of course, huge potential that we are assuming in due course. I am wondering when we are going to see the +50%, +100% increase in sales in defense. The second one is, your business plan kind of assumed, at the time, used to assume, let's say, a European Union defense business not far away from the U.S. one. But for what we are seeing, the size of the U.S. is by far much larger at the moment.

Is it something going on in Europe that allow us to understand what is the actual size of the potential European defense business, or what is your thought about it? Thank you.

Giulio Ranzo
CEO, Avio

First of all, on the increase of defense revenues, I really hope we should see something more significant in 2027. Now, we are more execution constrained than order constrained because we have so much in order for defense, even in Europe, I mean, for the federal, that it is just our ability to manufacture. The speed at which we increase defense revenues only depends on our ability to manufacture, which is not only an ability of Avio to manufacture in Colleferro, it is also the ability of the suppliers to supply the things in time. Because if you think about it, for example, in these nine months, our growth on the defense revenues was something like, let me do this calculation real quick for you, in absolute terms, was 22%, okay, year-on-year. This is value of production. It is not sales, it is value of production.

It is the value of what we manufacture. It grew 22%. Can we get maybe to a growth rate of 30% or 35%? Probably yes. We will try. It is industrially complex because now we are no longer manufacturing one or two programs as we used to do, meaning Aster and CAMM-ER. Now we are working in parallel on 14 different programs across production programs and development programs. The level of complexity is definitely higher. I think in 2027, we should see quite some growth because we will overlap the growth of the U.S. programs, processing Colleferro, the growth of Aster, the growth of CAMM-ER, and so on. We should see a faster revenue growth in 2027. Overall, regarding the defense growth in Europe, what can I say? There is plenty of demand signals that suggest a continuous growth.

As I told you, we are a supplier, so we do not have the full visibility of when one order really comes and when not. We have multiple signals because we have more and more frequent visits, for example, from military parties in our plant. We have confidence from MBDA, and overall in Europe, we have this need to catch up with a higher ratio of defense expenditure versus GDP. The reality of what the governments have in hand, though, is that several governments are at the end of their terms. As you can very well see in Italy, they struggle to close the budget, and they have to save money for other purposes. The right answer is I do not know, Andrea, because the long-term trend is that this shall increase.

The speed at which they do it and when they do it is still a little bit obscure to me. Every other month, we do see another order from Aster for EUR 55 million, EUR 60 million, EUR 70 million coming. This is piling up on an order backlog that is already more than we need, how can I say? It could not be any better than this because now we are not depending on how many orders we get. We are dependent on how fast we can ramp up in production without making quality mistakes. You can try to double the number of products you do from one year to the other, but then the risk of making production mistakes is high.

Speaker 9

Thank you very much.

Operator

Gentlemen, at this time, there are no more questions.

Giulio Ranzo
CEO, Avio

Thanks, everyone, for joining, and goodbye.

Operator

Ladies and gentlemen, thank you for joining. You may disconnect your devices.