Ladies and gentlemen, good day, and welcome to the Larsen & Toubro Limited Q3 FY25 earnings conference call. As a reminder, all participant lines will be in the listen-only mode, and there will be an opportunity for you to ask questions after the presentation concludes. Should you need assistance during the conference call, please signal an operator by pressing star then zero on your touch-tone phone. Please note that this conference is being recorded. Today, we have with us on the call Mr. Subramanian Sarma, whole-time director and president of the Energy division, and Mr. P. Ramakrishnan, Head, Investor Relations, of Larsen & Toubro Limited. I now hand the conference over to Mr. P. Ramakrishnan. Thank you, and over to you, sir.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Thank you, Sagar. Good evening, ladies and gentlemen. This is P.R., P. Ramakrishnan. A very warm welcome to all of you to the Q3 FY25 earnings call of Larsen & Toubro. The earnings presentation was uploaded on the stock exchange and on our website at around 6:30 P.M. Hope you have had a chance to have a review, a quick review of the same. As usual, instead of going through the entire presentation, I will summarize the highlights for the quarter, followed by the financial performance summary in the next 30 minutes or so, and after which, myself and Mr. Subramanian Sarma, we will take the questions. Before I begin the overview, a brief disclaimer.

The presentation that we have uploaded on the stock exchange and our website today, including the discussions we may have on the call today, may contain certain forward-looking statements concerning the group's performance, business prospects, and profitability. This would be subject to several risks and uncertainties, and actual results could materially differ from those in such forward-looking statements. I would request you to go through the detailed disclaimer, which is available in slide two of the earnings presentation that we have uploaded just now. The growth momentum of the Indian economy has waned a bit in the recent quarters. The urban consumption has tapered off as the excess savings from the pandemic have been exhausted, formal sector wages have slowed down, and the consumption lending norms have also been tightened. Rural consumption, on the other hand, has continued at a healthy clip on the back of robust agricultural activity.

Public investments have also slowed down due to the recent central and state elections in the country, whereas private investments have been episodic at best. Nevertheless, the recent pickup in the various high-performance, high-frequency economic indicators suggests that the slowdown in economic activity has possibly bottomed out and could recover on the back of improved government spends in the near term. Moving on to the international landscape, the global situation continues to be marked by military conflicts, the changes in the political landscape across several countries, and trade wars, which is threatening to reignite inflation and minimal policy choices available to central banks. Similarly, the government across countries with elevated Debt-to-GDP ratios are finding it difficult to impact fiscal impulses at will. On the positive side, though, the ceasefire between Hamas and Israel is expected to bring the much-needed stability in the GCC region.

The GCC region, led by Saudi Arabia, is continuing to strengthen its physical and digital infrastructure besides monetizing its oil and gas assets. Coincidentally, multiple GCC countries are also embarking upon the energy transition journey with utmost seriousness. Having covered the macro landscape, let me share a few important highlights of the company for the quarter. The company posted or reported the highest-ever order inflow growth in the history. This was received during the quarter for INR 1.16 trillion. The growth of 53% on a Y-on-Y basis was backed by a strong ordering momentum in the infrastructure, hydrocarbon, CarbonLite Solutions, and Precision Engineering Systems businesses. Despite the lackluster economic activity in India in Q3, we have secured INR 987 billion, which is 64% Y-on-Y basis, of orders in the Projects and Manufacturing business portfolio during Q3, with domestic and international contributing about 48% and 52%, respectively.

Moving on, L&T Energy Green Tech Limited has won 90,000 MTPA green hydrogen capacity in the Tranche II of the green hydrogen production PLI at an average incentive of INR 11.11 per kg, INR 11.11 per kg of hydrogen. This incentive, to be distributed over a period of three years, will aggregate to a total benefit of around INR 300 crores. Thirdly, LTIMindtree recorded its highest-ever deal wins in Q3 FY25 at $1.68 billion. Similarly, LTTS, L&T Technology Services, also witnessed its highest-ever large deal bookings during the quarter, aided by eight large deals across segments, which includes one $500 million deal, two $35 million deal, two $25 million deal, and three $10 million deals. LTTS signed a definitive agreement on November 11, 2024, to acquire a 100% stake in Silicon Valley-based Intelliswift and its subsidiaries for a consideration of $110 million.

The objective of this acquisition was to deepen the company's offerings across software product development, platform engineering, digital integration, data, and AI. Intelliswift has 25 plus Fortune 500 globals, including five of the top ER&D spenders in software and technology, and it is also associated with four of the top five hyperscalers. This acquisition got fully closed this month. Moving on to financial services, L&T Finance Limited achieved a portfolio utilization of 97% in Q3 FY25, a milestone this business has achieved way ahead of its Lakshya 2026 targets. Lastly, the data center business has entered into a strategic business partnership with E2E Networks, an Indian cloud and AI cloud provider, towards the adoption of GenAI solutions in India to foster a fundamental shift in the way accelerated computing on cloud is used by Indian corporates.

Further, an investment agreement was signed on November 5, 2024, for the acquisition of 21% stake in E2E Networks, of which 15% stake has been acquired through a preferential allotment of equity shares on December 4 for an aggregate consideration of INR 10.79 billion. The secondary acquisition of 6% is expected to be completed before May 30, 2025. Now, let me cover the various financial performance parameters for Q3 FY25. This quarter was a quarter of robust performance across the various financial parameters. Our group ordering flows for Q3 registered a Y-on-Y growth of 53%. On the back of a strong ordering momentum, our order book is at INR 5.64 trillion on December 24. This has registered a growth of 20% on a Y-on-Y basis.

Aided by a strong execution momentum from several businesses within the Projects and Manufacturing portfolio, our group revenues for the quarter registered a growth of 17% on a Y-on-Y basis. Our margins of the Projects and Manufacturing portfolio at 7.6% is in line with the corresponding period of the previous year. Our net working capital to revenue is at 12.7% as on 21st December 2024. This improvement of almost 390 basis points on a Y-on-Y basis. Our return on equity on a trailing 12-month basis as on December 2024 is at 16.1%, improving by 90 basis points on a Y-on-Y basis. I now move on to the individual performance parameters. As said earlier, our group order inflows for Q3 FY25 at INR 1160 billion registered a Y-on-Y growth of 53%.

Within the group ordering flows, our Projects and Manufacturing businesses secured ordering flows of INR 987 billion for Q3, reporting a robust growth of 64% over the corresponding period of the previous year. Our Q3 ordering flows in the P&M portfolio are mainly from infrastructure, CarbonLite Solutions, hydrocarbon, and the precision engineering and systems businesses. During the current quarter, the share of international orders in the P&M portfolio is at 52%, vis-à-vis 67% in Q3 of last year. Moving on to the order prospects pipeline, we have a total order prospects pipeline of INR 5.51 trillion for the remaining three months of FY25, vis-à-vis INR 6.27 trillion at the same time last year. This represents a drop of 12% when compared to December 2023 order prospects pipeline. This decrease is primarily due to the fall in the hydrocarbon and CarbonLite prospects.

The broad breakup of the overall prospects pipeline for the remaining three months would be as follows. The share of infrastructure is INR 4.00 trillion, vis-à-vis INR 4.01 trillion last year. The hydrocarbon prospects pipeline is at INR 1.44 trillion as of December 24 when compared to INR 1.71 trillion as of December 23. The Heavy Engineering and the Precision Engineering Systems business, which caters to what we call the Hi-Tech Manufacturing segment, the order prospects pipeline is at INR 0.06 trillion, vis-à-vis INR 0.16 trillion last year. Moving on to the order book, our order book is at INR 5.64 trillion as on December 24, which is up 20% vis-à-vis December 23 last year. As the Projects and Manufacturing business is largely India-centric, 58% of this order book is domestic and 42% international.

Of the international order book of INR 2.37 trillion, around 84% is from the Middle East and 3% from Africa, and the remaining 13% comprised from other countries of the world. Like I said earlier, the various countries in the Middle East are continuing to focus on investments in oil and gas, infrastructure, industrialization, and energy transition. The breakdown of the domestic order book of INR 3.27 trillion, which I said is 58% of the overall order book as of December, comprises of central government order book orders at 15%, state government orders at 26%, orders from public sector corporations or state-owned enterprises, the share being 39%, and the private sector contributing to 20% of the domestic order book. Approximately around 15% of the total order book of INR 5.64 trillion is funded by bilateral and multilateral funding agencies.

Once again, that 90% of this total order book comprises orders from infrastructure and energy. You may refer to the presentation slides for further details. During the nine-month period FY25, we have deleted orders of INR 6 billion from the order book. There has been no deletion of orders from the order book in the current quarter, which is Q3 FY25. As of December 24, our slow-moving orders are around 0.5% of the order book. Coming to revenues, our group revenues for Q3 FY25 at INR 647 billion registered a strong Y-on-Y growth of 17%. International revenues constitute 51% of the revenues during the quarter. The strong execution momentum in infrastructure, hydrocarbon, and the Precision Engineering Systems businesses within the P&M portfolio drove the overall group revenues for the quarter.

Within the group revenues, the revenues for the Products and Manufacturing businesses for Q3 FY25 is INR 473 billion, up by 20% over the corresponding quarter of the previous year. Moving on to EBITDA margin, our group level EBITDA margin without other income for Q3 FY25 is 9.7%, vis-à-vis 10.4% in Q3 of the previous year. This EBITDA margin variance is mainly due to the revenue mix favoring the Products and Manufacturing segment and also lower operating margin in the LTTS segment. The detailed breakup of the EBITDA margin business-wise, including other income, is given in the annexes to the earnings presentation. You would also notice that the EBITDA margin in the Products and Manufacturing portfolio for Q3 FY25 is at 7.6% in line with the corresponding quarter of the previous year.

I will cover the details a little later when I talk about the performance of each of the segments. Our consolidated PAT for Q3 FY25 at INR 33.6 billion is up 14% over Q3 of the previous year. This PAT growth is reflective of increased activity levels and improved treasury operations. The primary reason behind group PAT growth of 14%, despite group revenues growing at 17% for the quarter, is the lower operating leverage in the LTTS portfolio and slightly higher credit costs in our financial services business. The group performance P&L construct, along with the reasons for major variances under the respective function heads, is provided in the earnings presentation. You may go through the same for further details.

Coming to working capital, our net working capital to sales ratio has improved from 16.6% in December 2023 to 12.7% in December 2024, mainly due to an improvement in the gross working capital to sales ratio backed by strong customer collections during the quarter. Our group level collections, excluding the financial services segment, for Q3 FY25 is INR 591 billion, vis-à-vis INR 494 billion in Q3 FY24, registering an increase of 20% on a Y-on-Y basis. You may also like to go through the cash flow statement as part of the annexes to the earnings presentation. Finally, the trailing 12-month return on equity for Q3 FY25 is 16.1%, vis-à-vis 15.2% in Q3 FY24, an improvement of 90 basis points for the year.

Very briefly, I will now comment on the performance of each business segment before we give our final comments on our outlook for the remaining period of current year. First, infrastructure. Coming to ordering flows, this segment secured orders for INR 491 billion for Q3 FY25, registering a robust growth of 14% on a Y-on-Y basis. International orders constitute 74% of the total ordering flows. During the current quarter, the orders were mainly received in renewables, power transmission distribution, water, buildings and factories, and minerals and metals sectors. Our order prospects pipeline in infrastructure segment for the remaining three months is around INR 4 trillion, vis-à-vis INR 4.01 trillion during the same time last year. This infra prospects pipeline of INR 4 trillion comprises domestic prospects of INR 3.15 trillion and international prospects of INR 0.85 trillion.

The subsegment breakup of this total order prospects in infra would be as follows. Transportation Infra share is 35%, Heavy Civil Infrastructure at 18%, water also at 18%, buildings and factories at 14%, minerals and metals at 6%, power distribution at 6%, and renewables at 3%. The order book for this segment is at INR 3.61 trillion as of December 2024. The book-to-bill for infra is around three years. The Q3 revenues at INR 321 billion registered a healthy growth of 15% over the comparable quarter of the previous year, largely aided by execution across multiple jobs from a large opening order book. Our EBITDA margin in this segment for Q3 FY25 is at 5.5% in line with the corresponding quarter of the previous year. Moving on to the next segment, that is energy products. This comprises hydrocarbon and CarbonLite Solutions.

The receipt of two ultra-supercritical thermal power plant orders helped the CarbonLite Solutions order book, whereas hydrocarbon benefited from the receipt of a mega international onshore order. We have a strong order prospects pipeline of INR 1.44 trillion for this energy segment for the balance three months, comprising of entirely hydrocarbon prospects. The order book of this energy segment is at INR 1.46 trillion as of December 24, with the hydrocarbon order book at INR 1.1 trillion and CarbonLite Solutions at INR 0.27 trillion. The Q3 FY25 revenues for the segment at INR 111 billion registers a strong growth of 41%, driven mainly by the execution ramp-up in domestic and international products of hydrocarbon, whereas lower revenues in CarbonLite Solutions are reflective of a depleting opening order book. The energy segment margin in Q3 FY25 is at 8.3%, vis-à-vis 9.7% in Q3 FY24.

The negative variation in hydrocarbon margin over the previous year is largely reflective of the state of execution of the various jobs in the portfolio, whereas CarbonLite Solutions margin improved due to a favorable claim settlement. We will now move on to Hi-Tech Manufacturing segment, which comprises of the Precision Engineering Systems and the Heavy Engineering businesses. The precision engineering and systems business benefits from the receipt of the K9 Vajra repeat order, and multiple international orders help the Heavy Engineering order book. The order book for this segment is at INR 418 billion as of December 24. The order prospects pipeline for the remaining three months in this segment is around INR 65 billion for the next three months. The strong execution momentum continues in the precision engineering and systems, whereas muted revenues in Heavy Engineering are reflective of jobs in the early stages of its progress.

The execution cost savings in Heavy Engineering business aid segment margin improvement at the overall segment level. Moving on to the next segment, which is the IT and the technology services portfolio. This comprises of the two listed subsidiaries, which are LTIMindtree and LTTS. The revenues of this segment are at INR 121 billion in Q3 FY25, registered a modest growth of 8%, largely reflective of the present market conditions. Despite the ongoing macroeconomic concerns, and as I mentioned earlier, both these companies recorded very strong big wins in the quarter. The segment margin decline during the quarter is mainly due to wage hikes and forex losses in both these companies. I will not dwell too much on this segment, as both the companies in this segment are listed entities, and the detailed fact sheets are already available in the public domain. Next, we move on to L&T Finance.

Here again, the detailed results are available in the public domain, but very briefly, I will summarize. The Q3 results show around healthy credit calibrated growth in the disbursements. The credit cost during the quarter was largely in check despite the ongoing headwinds in the microfinance portfolio, and the balance sheet is strong on the back of built-in macro prudential buffers. The company expects credit costs in Rural Group and the microfinance loans to peak in Q4 FY25 and some normalization from Q1 FY26 onwards. The financial services business has achieved 97% utilization of its loan book in December 2024, well ahead of the Lakshya 2026 targets. The return on assets remains healthy at 2.27% despite the sectoral headwinds, and finally, adequate capital in the balance sheet is available to pursue growth in the medium term.

Moving on to the development project segment, this segment includes the power development business comprising of Nabha Power and Hyderabad Metro. Most of the revenues in this segment are contributed by Nabha Power. A combination of improved PLF and higher energy charges in the Nabha Power drives the segment revenue growth. At this juncture, let me give you some ridership statistics from the Hyderabad Metro. The average Metro ridership was 4.32 lakh passengers a day in Q1 FY25, 4.68 lakh passengers per day in Q2 FY25, and remains around 4.45 lakh passengers a day in Q3 FY25. The sequential decline in ridership was mainly due to the festive season holidays during the quarter. Our ridership in Q3 FY24 was 4.44 lakh passengers a day, so on a Y-on-Y basis, it's largely the same.

The Metro at a PAT level posted a loss of INR 2.03 billion in Q3 FY25, as against a loss of INR 2.54 billion in Q3 of the previous year. The improvement is largely on account of lower interest costs consequent upon reduction in debt. Moving on to the other segment, this segment comprises realty, construction equipment and machinery, rubber processing machinery, and industrial valves, and to some extent, the residual portion of the Smart World & Communication business. The Q3 revenue at 9% growth over the corresponding quarter of the previous year was mainly contributed by a higher handover of residential units in the realty business and improved sales in the industrial machinery and the products business. The segment margin improvement is mainly due to a favorable revenue mix in industrial machinery and product business.

Coming to the last part of my presentation, the outlook for the year, the revised outlook for the current year FY25, taking into account how we see Q4. Despite the initial hiccups, the Indian economy is poised for steady growth, with projections indicating a GDP growth of 6.5%-6.8% for the fiscal year FY25. The rural consumption has remained encouraging, supported by strong agricultural performance due to a favorable monsoon. The services sector continues to be a key driver of growth. There are initial signs of a pickup in government spending post the center and various state elections, which will give the necessary impetus to the infrastructure CapEx spend in the near term. As the country strives to achieve the vision of a Viksit Bharat by 2047, the government is expected to maintain its strong commitment to infrastructure investment, recognizing it as a key driver of broader economic growth.

The forthcoming union budget is likely to strike a balance between policy continuity and fiscal discipline. The country would still be one of the fastest growing economies in the world, although the pace and sustainability of the growth trend would be shaped by how the country navigates challenges around global and financial market volatility, potential implications of intensified trade wars, domestic inflationary impulses, the compulsions around a coalition-led government, and finally, a trade-off between social spends and pursuing long-term development goals. The global economy at the current juncture is at a crossroad, whereas policy changes by the USA could result in another bout of tariff wars. On the other hand, the ceasefire between Hamas and Israel should improve the situation in the GCC region. The European economies continue to move sideways, while questions over the Chinese economy further cloud the growth picture and put global economies towards fragmentation and localization.

Further, we expect multiple countries to enhance their defense outlays in an uncertain world. The consequences due to climate change are getting serious attention and are leading to substantial investment outlays into cleaner technologies. Lastly, artificial intelligence and all its attributes and variants are gaining faster acceptance and adoption across the world. On a positive note, the GCC region, led by Saudi Arabia, will continue to strengthen its physical and its digital infrastructure apart from monetizing its oil and gas assets. Coincidentally, multiple GCC countries have also embarked upon the energy expansion transition journey with relatively large investment outlays. In this economic backdrop, the company will continue to pursue its objective of a volume-led, profitable, and rhythmic accretive growth. The company has robust order prospects for the near term and is confident of maintaining its growth momentum by leveraging the emerging opportunities and maximizing shareholder value on a sustainable basis.

Before we conclude, let me cover the guidance that we have given on the various parameters for the year FY25. First, order inflows. You will recall that we had given a guidance of 10% growth in order inflows for the year. For nine months FY25, our order inflows at INR 2,670 billion is up by 16% over the corresponding period of the previous year, and looking at a strong prospects pipeline of INR 5.51 trillion for Q4, we believe that we would be surpassing the 10% guidance on order inflows for FY25. With India expected to pick up in Q4, and since the international prospects pipeline also remains healthy, we feel confident of exceeding the guidance on order inflows. As we speak, we seem to be well placed in orders in the projects and manufacturing segment of almost INR 500 billion.

Coming to revenues, we had guided for a 15% growth in revenues for FY25. Since our group revenues for nine months FY25 have reported a growth of 18% and our order book remains strong, we do believe that there are potential upsides to the revenue guidance of 15% for the full year FY25. Moving on to the EBITDA margin, our guidance on EBITDA margin for the projects and manufacturing businesses remains at 8% that we guided at the start of the financial year. This 8.2% is for the full year FY25. On net working capital, we had earlier guided the NWC to revenue of 15% in March 2025. Since our NWC to revenue is at 12.7% as of December, we believe that our net working capital to revenue should be around the same levels that we have filtered for as of December 2024.

Lastly, as you're aware, our free cash flow generation has been robust in the last couple of years, and we are also stepping up our capital allocation into newer business areas like green energy, data centers, and semiconductor design. We do expect some of these investments to start contributing to group returns in the next Lakshya plan of the company, which will start from FY27 and end at FY31. With this, I conclude. Thank you, ladies and gentlemen, for the patient hearing. We will now begin the Q&A. My request to all the people who want to ask questions, in case you have any bookkeeping questions, please feel free to connect to me or Harish, my colleague, afterwards. We have with us also my senior colleague, Mr. Subramanian Sarma, who is the President and Head of the Energy Business. Over to you, Sagar.

Operator

Thank you very much. We will now begin the question and answer session. Anyone who wishes to ask a question may press star and one on the touch-tone phone. If you wish to withdraw yourself from the question queue, you may press star and two. Participants are requested to use handsets while asking a question. Ladies and gentlemen, we will wait for a moment while the question queue assembles. Our first question comes from Mohit Kumar from ICICI Securities. Please go ahead.

Mohit Kumar
Equity Research Analyst, ICICI Securities

Yeah, hi. Thanks for the opportunity, sir. My first question is on the, I think you mentioned that in projects and manufacturing, you are heavily placed in a INR 500 billion order. Does it mean that you are well in those orders? Is that the right understanding?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

I said we are well placed. It is just to give the comfort that while we get into Q4, since you all know that a 10% guidance for the full year also means that we need to print almost INR 650 billion of orders in Q4. So just to give the comfort that we seemingly are on track because we are well placed in four, five, very large orders. But there is always, since the orders are large, there can be always a slippage into subsequent quarters or not close the contract itself.

Mohit Kumar
Equity Research Analyst, ICICI Securities

Understood. My second question is that have you included the order for 5 gigawatts, 19 gigawatts, solar plus closed this quarter? And is it possible to lay out the scope and division of responsibility between you and China, and is it possible to also give a color on the order book size of the project?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So you are referring to the renewables press release that we had?

Mohit Kumar
Equity Research Analyst, ICICI Securities

Yes. Preferred EPC contractor for the Middle East, 5 gigawatts, 19 gigawatt hours.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So it is an ultra mega order, and that has been taken in the ordering flow for Q3. We received the client clearance sometime in January, and we have released the press release recently. It is, I would say, it is quite a very complex order and one of the largest renewable investments that UAE is embarked upon, and we feel, I mean, it's a prestigious ordering flow for us.

Mohit Kumar
Equity Research Analyst, ICICI Securities

What is the difference of responsibility between you and China?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Hello, Mr. Subramanian China has a separate contract?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

That is the total generation capacity and storage capacity is split into two contracts. Sorry, this is Sarma here. Those two contracts are independent contracts. What we announce is related to our part, and similar scope is being done by China Power. They are independent contracts, mutually exclusive, and directly with the customer. We have no relationship with China Power on this contract.

Mohit Kumar
Equity Research Analyst, ICICI Securities

Understood. That's so detailed. My last question is that is the development of Green Hydrogen project, which have run in the last quarter, is it a contingent of finding the market for Green Hydrogen in the advanced, let's say, developed markets? Is that right understanding?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Yeah, yeah. I mean, we applied this. What we announced was this PLI scheme, and under that PLI scheme, we have been successful, and we secured the INR 300 crores incentive, which is subject to setting up that capacity. I mean, it is linear. I mean, if we set up the full capacity, then we will be entitled for that full incentive. Otherwise, it will get discounted based on the capacity we set up within that timeline. Now, of course, our decision will also depend upon how the market evolves and the economics related to that investment decision. We are very actively pursuing many opportunities within India as well as outside, and we are quite confident that some of those will materialize now. To what extent and when is something a little bit uncertain now, but we are very hopeful.

Mohit Kumar
Equity Research Analyst, ICICI Securities

Understood. Thank you, Mr. P. Ramakrishnan. Thank you.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Thank you, Mohit.

Operator

Thank you. The next question comes from Amit Anwani from PL Capital. Please go ahead.

Amit Anwani
VP and Lead Analyst for Capital Goods, Industrials, and Defence, PL Capital Group

Thanks for taking my question. My first question is on the execution in the sector this time. We can see domestic infrastructure business revenue was kind of moderate, saw a moderate growth. So any challenges we faced this quarter with respect to project execution and domestic market in any of the projects which are there?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

No, so let me answer that, Amit. The execution of our, especially of the projects in the domestic sector with respect to infrastructure segment, I think it is continuing as per plan. There have been some isolated cases where we had to bring down the execution because of delayed payments, but otherwise, the execution momentum is in line with our budgets that we have done and in line with our guidance itself.

Amit Anwani
VP and Lead Analyst for Capital Goods, Industrials, and Defence, PL Capital Group

Yeah. Second question on the prospects in the energy business. You said the INR 1.44 trillion pertains to only hydrocarbon, and there's, I think, I guess, no thermal order prospect which you're accounting now. Is it that the prospects have kind of deteriorated in the market, or we have been selective and now not taking orders in thermal in upcoming quarters?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

No, I think thermal, there are the INR 1.44 trillion has got several components. One is thermal power plants in India. Then we have hydrocarbon projects both in India as well as in West Asia. And then we also have some gas-to-power opportunities. I think between the three, we believe that we have a very good bid slate and we should be able to secure a reasonable size of that prospect. Now, thermal power plant in India, we have made a strategy to bid for BTG, that is the boiler, turbine, and generator, and we'll continue to pursue those. And yeah, to some extent, we'll be selective from a point of view of our manufacturing capacity and our ability to execute those jobs, provided, of course, the location and the situation conditions are favorable for us to execute in an efficient manner.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So, Amit, just to add to what Mr. Subramanian Sarma told is the order prospects that I have articulated in the call. They are all further what we believe are tenders which are going to come, which are addressable. Not necessarily the order prospects will be the order that is getting tender could be larger, but it's all what we call the addressable L&T universe for the three months. So to that extent, some of the thermal power plant opportunities may be coming in the next year, but not in the next three months.

Amit Anwani
VP and Lead Analyst for Capital Goods, Industrials, and Defence, PL Capital Group

Yeah. Just to clarify, so orders we just won in thermal are only catering to BTG, which we won in three Qs?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Yes. What we have printed or what we have disclosed in Q3 FY25 relates to the BTG orders of NTPC.

Amit Anwani
VP and Lead Analyst for Capital Goods, Industrials, and Defence, PL Capital Group

Sir, thanks a lot. Thank you so much.

Operator

Thank you. The next question comes from Aditya Bhartia from Investec. Please go ahead.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

Hi, good evening, sir.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Good evening.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

So my first question is on the status of the submarine tender that we wanted to participate in. There have been some media articles around that, so if you could just let us know about what's really happening over there?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Okay. So there are media reports on this matter in the public domain. We cannot comment further as the matters pertaining to the bid are subject to an NDA. We have also sought out some clarification with the customer, but unfortunately, I'm not in a position to comment further on this particular matter because of non-disclosure agreement compliance.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

Sure, sir. Understood. So my second question is on margins in the intra-vertical. It has been a while since margins have been hovering around this range, and we have not really seen a big expansion. Do you think this is the new normal wherein we are looking at lower working capital, but that also kind of entails lower margins? Nothing wrong with the strategy. We're just trying to understand if this should be seen as the new normal.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Okay, so the infrastructure margins have been a little softer in the last two to three years. We do expect with the slow liquidation of the orders that we had taken prior to FY22-23, all of them tapering off in the last stages of execution, the new set of orders, which are large orders, subject to the fact that if we are able to complete them on schedule, we do expect some improvement in margins. But having said this, as a projects company, we have been given guidance only for the particular year under revenue. So in the month of May, after the internal budgets which we will be closing out in the next one month or so, I think we'll have a better visibility to comment as to how the margin trajectory for FY26 pans out across the projects and manufacturing portfolio.

Having said this, as you rightly mentioned, despite the fall in margins, the overall return on the investments, each of these businesses, each of the businesses under the projects and manufacturing portfolio, they have actually improved on the back of timely billing and faster collections.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

Sure, sir. Also, my last question is just wanted to understand if we are looking to get into some more stuff on the semiconductor side, maybe a foundry or maybe a display fab for electronics. Are we kind of thinking in that direction also, or would we be restricted to fabless?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So you have taken two questions on this. So the first point, as far as semiconductor is concerned, the current approach is to build up the semiconductor design, build up a good set of products, which will obviously have to be manufactured through other fabs before even exploring to decide whether we want to go on to investment in fab itself. The only thing I can talk about at the current juncture, our foray is in the semiconductor design, and I hope, I think it will pan out in the next two to three years when we build up the various products under using this, I would say, L&T IP-led design. And based on the success that we have, we will explore whether we go into the fab manner, but that is not in the near term.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

Sure, sir. And something else like display fab?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

At this juncture, I mean, there are various aspects we are looking at, but very difficult to comment on the progress or what is the final step will happen.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

Sarma, you would like to add on this electronics part?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

No, I think, like you said, it will evolve. I mean, these are all new arenas we are exploring, and we believe that long-term potential is quite good in this sector. That's why we are entering into this. But we'll keep the options open, and as it evolves, then we will pivot and implement appropriate strategies, but too premature to sort of articulate on the exact plan because we are still exploring that.

Aditya Bhartia
Co-Head of Research and a Lead Analyst, Investec

Perfect, sir. That's helpful. Thank you so much.

Operator

Thank you. The next question comes from Sumit Kishore from Axis Capital. Please go ahead.

Sumit Kishore
Executive Director, Axis Capital

Good evening. Thanks for the opportunity. My first question is in relation to [audio distortion]

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Voice is not clear.

Sumit Kishore
Executive Director, Axis Capital

Sorry to interrupt.

Speaker 14

Sumit, your voice is breaking.

Sumit Kishore
Executive Director, Axis Capital

Am I audible right now?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Perfect.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Loud and clear.

Sumit Kishore
Executive Director, Axis Capital

In case of hydrocarbons, the stage of execution of projects has been calculated in terms of the margin mix for the nine-month period. When can we expect the stage of execution, given the execution itself is going at a very swift pace? When does that cross the margin recognition thresholds? And the second part of this question is on the infra side, where could you give us some qualitative color on how the margin improvements that we have seen in the nine-month period, how is it sort of driven by domestic overseas? Because higher overseas in the mix might be depressing your headline margin, and how is domestic behaving in that margin mix?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So two parts to it. One is on the hydrocarbon margins, and the second is on the infra margins. So as far as hydrocarbon margins are concerned, I want to tell you that cumulative nine months or you take Q3, the margin accretion is over at the stage of completion of each of the businesses. The hydrocarbon margin is in line with our internal target benchmarks, and there are some large projects which will possibly cross the margin recognition threshold in the near term. Some of that could be in Q4, and some of that could be slipping into Q1. But as you are aware, we have given a full-year margin guidance of the P&M portfolio at 8.2%, and whereas nine months cumulative, it's 7.6% because all the three quarters, the margins have been at 7.6%.

So which means that the Q4 run rate for EBITDA margin is, of course, going to be very high, and that has been baked into our plan, execution momentum, and the stage of progress. Okay? So I don't think the hydrocarbon margin optically dropping is an assumption that has been baked in our nine-month trajectory itself. So I don't think we have any cause to worry. As far as infra margins are concerned, we are having a good portfolio of a decent mix of renewable projects, sorry, decent mix of renewable projects and overseas projects in the Middle East, and also quite a large substantial order book in the domestic side. Whereas the international projects can have optically lower margins, but I wish to tell you timely execution is enabling that we are able to print the margins that we have bid.

Whereas in domestic projects, as you know, there can be time and cost overruns for reasons possibly beyond our control. So in a way, both are offsetting each other. It is not necessary to conclude that a larger share of domestic project execution will be higher margins or a larger share of overseas projects in the international can possibly drop the margins. So I think the mix is good, and we should be on track to meet the margin guidance for the entire P&M portfolio at 8.2% for the full year.

Sumit Kishore
Executive Director, Axis Capital

Sure. And one thing, hydrocarbons are crossing margin recognition threshold. Next year, the base will become favorable for hydrocarbons. Is that the right understanding?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

It can happen in two more and subsequent quarters. So Sumit , please understand, it's not that we are executing hydrocarbon projects what we secured one and a half years back. Some of those projects may have already crossed the margin recognition. Hydrocarbon business has also secured ultra mega and mega orders in FY24 and even in the current year. So all these jobs also will get into execution over a period of time.

Sumit Kishore
Executive Director, Axis Capital

Sure. Sure. The four large contracts that you mentioned here favorably, please, are India contracts or overseas contracts?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

I will just stay put here. I will say it is four or five large contracts. Let's not get into whether domestic or international.

Sumit Kishore
Executive Director, Axis Capital

Yeah. Just one second. The second question is on L&T, as pictured for.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

It's a decent mix. It's a good mix, I said.

Sumit Kishore
Executive Director, Axis Capital

[audio distortion] L&T has picked up a significant stake in E2E Networks. How are you thinking about the capital allocation, the future roadmap for E2E and this area it will present?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So, Sumit , it is a collaborative acquisition. We have taken a 15% stake at almost INR 1,080 crores. Another 6% stake is due for transfer sometime in May 2025. Okay? With this, it is being considered as an associate from an accounting perspective, it's an associate, but essentially from a business perspective, we thought, and as I mentioned, it is a collaborative partnership where we will leverage, Larsen & Toubro will leverage E2E's scope of offerings on the AI side, especially on the cloud data center, while we pitch our offerings. Because as you may be aware, L&T is also investing into data centers, and we get into the higher-end or more margin-led. We have to blend the offerings into giving cloud data services for our data center customers. We will leverage that.

And similarly, E2E also will leverage our data center infrastructure to strengthen their scope of offerings. So that way, it is a collaborative partnership with a strategic investment also.

Sumit Kishore
Executive Director, Axis Capital

Those were my questions. Thank you.

Operator

Thank you. The next question comes from Priyankar Biswas from BNP Paribas. Please go ahead.

Priyankar Biswas
Associate Director, BNP Paribas

Thanks, sir, for the opportunity. My first question is on the domestic infra. What we are witnessing is that a lot of CPSUs and those things in the state budgets particularly. Can you please elaborate what are the areas in the domestic CapEx where you specifically see that you can break down from central, state, CPSUs, things like that? Which areas we should see coming from?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

In terms of, okay, as I talked about the total order prospects of INR 4 trillion of infrastructure, a major part is coming out in domestic itself. So we have actually, it's a that way a wide, I would say, canvas of opportunities across various segments. It can be to keep it simple. Let me talk about the buildings, both led private sector and also at the central level. There are various opportunities for public health, which means I'm talking of hospitals. There are opportunities on some large projects on the hydel side. I also want to tell you that there is a major set of urban infrastructure connecting between two cities, not necessarily and not as of railways. I'm talking of road networks, elevated corridors that are expected to get tendered out in the near term.

So it's a combination of state and central-led projects, largely states, I would say, and the share of the government prospects would be almost 75%, whereas private sector prospects, which covers the typical real estate and other kind of data centers and so on, that is almost 25% of the overall prospect share.

Priyankar Biswas
Associate Director, BNP Paribas

Sorry, may I just add in? So how do you -

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

It doesn't appeal to any specific sector. I think it's a decent mix of energy, of urban infrastructure, of, I would say, also water-related investments. [cross-talk] That comes in and even metals, but that comes under the 25% share, private sector. Yeah, go ahead, Priyankar.

Priyankar Biswas
Associate Director, BNP Paribas

Yes, sir. Just adding on to this, so what is your outlook for the defense space? Because see the prospect that you gave for high tech, it seems to be quite low. So aren't you really constructive on the defense CapEx? That's my question.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So we are very much constructive on the defense CapEx, Priyankar, but I am going as the order prospects, what we believe is going to get tendered out in the next three months. So defense prospects doesn't mean that defense prospects that are addressable defense prospects in the country is coming down. Incidentally, as I told you, the Q3, we had the benefit of very large that Vajra repeat order is almost INR 6,500 crores. So this year, we have always managed to get a print of INR 12,000 crores of orders in the nine months for the PES business, which is the defense part of the business. We don't see any immediate prospects for the next three months.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Generally, it takes time. The defense orders take time to conclude.

Priyankar Biswas
Associate Director, BNP Paribas

Okay. And actually, if I can squeeze just one more in. So what I see is you have a heavy order book in the building. So going forward, I guess the international share in the revenues will also rise up as we go into the subsequent quarters. So what should be the general direction we can give the margin and the working capital trajectory from here on?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So Priyankar, I think I have answered this kind of a question for the previous people who were asked. Let me tell you, the margins what we are giving is for the current year update. Okay? As we get into next year, in the month of May, we will be giving you the outlook of margins of the P&M portfolio after we complete this year and the budgets for the next year.

Priyankar Biswas
Associate Director, BNP Paribas

Okay. That's all from my side.

Operator

Thank you. The next question comes from Atul Tiwari from J.P. Morgan. Please go ahead.

Atul Tiwari
Executive Director and Lead Analyst, J.P. Morgan

Yes. Thanks, sir. Just one question on the pace of execution in deals. So lately, we have seen some top-down reports about budget constraints in Saudi Arabia and some of the projects being deferred. So for your projects, have you seen any discussion on the customer's part about deferral, delays, delays in payment, or anything of that sort?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

You're referring to only Middle East, no?

Atul Tiwari
Executive Director and Lead Analyst, J.P. Morgan

Yeah, only Saudi Arabia.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Yeah. I mean, no, we have not seen actually. In fact, we continue to see a good pipeline. There have been some slowdown in maybe non-priority projects. And I think there is some amount of reprioritization of capital allocation. But in the sectors we are in, which is oil and gas and carbon capture and petrochemicals, I mean, those continue to remain top priority. And we have a pretty large presence in gas development, which is the highest priority for the country, for the Kingdom. So we are not seeing slowdown. In fact, we are not seeing any slowdown in payments. I mean, I was going to comment on the previous question that the difference in the international and domestic is that the payments are much more prompt and working capital is generally better compared to domestic. But we are not seeing any slowdown on those.

Atul Tiwari
Executive Director and Lead Analyst, J.P. Morgan

Yes. Good to know. Thank you.

Operator

Thank you. The next question comes from Srinidhi Karlekar from HSBC. Please go ahead.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Hi. Thank you for the opportunity and congratulations on strong performance. Sir, my first question is on the Power business. Here we see that order inflow for the segment is about INR 234 billion. Does that include entire 4 gigawatt of ultra mega plants that you book, or there's some portion that's not included in that?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

It includes everything.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Right. So in that case, is that right that ordering per megawatt is about INR 5.5 crores, which looks quite aggressive?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

No, I don't think so. Your calculation is right. It is higher than that. When the results have been declared, I think it was.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

It is in the public domain.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Public domain. It is upwards of six. I mean, I don't remember the exact number, but you can check that.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

This is for the two projects, sir.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

This is only for four gigawatts. Yeah.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

The 4 gigawatt and the order book shows is INR 23,000 crore, right, in the segment?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Yeah.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

So, some of the portion that boiler's JVs.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

But this is only for the BTG, right? I mean, this is only for BTG. You have to see this. This is not full EPC. Normally, maybe you are used to using entire EPC because the balance of the plants is still not included in this.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Right. Right. So it's just the BTG part, right?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Correct.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Okay. Okay. Understood, and sir, in the same order, how should one think about the EBITDA that will be captured in the consolidated business, considering that some of the EBITDA will be captured in the JVs as well?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

These orders have been procured by Larsen & Toubro Limited as the BTG EPC contractor and insourced to the boiler and the turbine JVs.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Right. Large part of the margin will come to the group level only. It is, I mean, it will accumulate later. I mean, now this jobs have just been awarded, so it will take some time for it to reach the threshold.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Understood. And sir, one question on the Middle East. Would it be possible to comment on what are typical retention money clauses are there in the oil and gas order that the company is running?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Typically, I think the retention is not much. I mean, I think we have been negotiating all our commercial terms in such a manner that we maintain either neutral or slightly positive cash flow across the board. And we have been quite successful in doing that. But sometimes you have maybe 2.5%-5% of the contract linked to certain end milestone. But overall, the cash flow situation is pretty good. I mean, I think most of them we are running at positive cash flow.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

This is the contract that we have got, no? Shrinidhi, I want to tell you that we don't expect as and when the projects get complete, in the balance sheet, there will be a large amount of retention. It is not the case like in any other segment, possibly in India or any other country. So the payment terms are favorable.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Right. And the stocks are definitely favorable. They're also favorable at the end as well, right?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Yeah. Yes. Generally, I mean, across the project timeline.

Shrinidhi Karlekar
Equity Research Analyst, HSBC

Understood. Nice to know that, sir. And thank you and all the very best.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Thank you.

Operator

Thank you. The next question comes from Parikshit Kandpal from HDFC Securities. Please go ahead.

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

Yeah. Hi, sir. Congratulations on a good quarter. So earlier in the call, you mentioned there are some slow-moving orders where there was an execution issue because of collection. So in which segment are you facing these challenges, and how much would have been the revenue impact of this?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Okay. So in the infrastructure segment, we have had, I mean, there has been because of the funds that had been stopped for some time with respect to water projects funded under the Jal Jeevan Mission. So there was some amount of stoppages. But now we expect the fund flow momentum to start through from, I think it has already started from December onwards, and we'd expect a revival in momentum to happen. It would be very difficult to compute how much, because of delay in payments, how much of revenues we have lost. That won't be an accurate answer to put it across like that.

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

Okay. And sir, in this quarter, were there any one-offs in the EBITDA line because we have seen declining margins both quarterly, sequential, as well as YoY? So I know you touched upon some NPAs and something on IT. So if you can give some more color like why there was a drop.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So there is no one-off in the entire P&M portfolio as far as Q3 margins are concerned. It is normally as what is in any project part of the business in terms of stages of execution. We have not had any one-offs.

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

So what explains the decline in the EBITDA margins Q1, Q1, YoY?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

No. On a YoY basis at the P&L level, we have kept it at 7.6, 7.6.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Okay. At the group level, I think I did cover when you talked about the EBITDA margin at the group level. The drop is because of two reasons. The one is the revenue is tilted. The composition of revenue is tilted towards a lower margin P&M portfolio as compared to, in the previous year, a higher margin LTTS portfolio. So that is one. That is contributing to almost 30 basis points in the drop of the group operating margin. And the second one is the operating leverage of the LTTS company, that is, in terms of their margins, has come down. That has another 40 basis points impact. Am I clear, Parikshit?

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

Yes.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

The fall in the EBITDA margin at the group level is for two reasons: a larger share of revenue growth coming from a lower margin trajectory of the P&M portfolio, which is almost 30 basis points, and the lower margins in the LTTS portfolio, which is attributing to another 40 basis points.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Basically, the growth rate of LTTS has been less than the core business, and their margins are also some.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Our revenues for the quarter at the group level have grown by 17%. Okay? Whereas I did say that in the LTTS segment, the revenues have grown up to 8%. So there is a relative rebalancing there. That's the reason for the drop in the EBITDA margin at the group.

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

Right. Okay. Sir, the other thing is you mentioned the reducing losses in the metro. You attributed it to loan repayments. Did you receive any sort of support from the Telangana government? So what has been the quantum? Any change versus last quarter?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

So the last time we received was almost last year. So the cumulative support that we have received under the INR 3,000 crore loan support, which was approved by the government of Telangana, we have received INR 900 crores all in the last year. We do expect some things to come up in the near term, the balance portion of INR 2,100 crores. And the other part is that we also are looking at very, very aggressively a further amount of some transit-oriented development monetization. Hopefully, the approval should be coming up in the near term, possibly even in Q4. Let us do that wait and watch. So an aggregate of this INR 2,100 crore of additional loans, the soft loans from the government, and also TOD monetization will enable us to reduce the current debt levels. The third-party debt levels in the metro is almost INR 12,600 crores.

We do expect over a period of time that to come down to, say, 9,000 also, which will enable a further reduction in the interest cost.

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

Sir, the last question on the Real Estate business. How much has been the new sales booking or sales for nine months and for third quarter aside?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

The total nine months booking has been in the range of INR 2,500 crores of ordering flow and nine months revenue. Realty is almost 1,500.

Parikshit Kandpal
Senior VP, Research and Lead Analyst, HDFC Securities

Okay. Thank you.

Operator

Thank you. The next question comes from the line of Bharanidhar Vijayakumar from Avendus Spark. Please go ahead.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Yeah. Good evening. Sir, can you spell out what proportion of order book is fixed price in nature at this point in time?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

45% is fixed price. Balance is variable.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Okay. And some of these recent large orders, both in renewables or in the hydrocarbon or in the thermal coal, they would all be on a cost-plus basis?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Most of the orders in hydrocarbon and also in thermal are fixed price.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Okay. That is very technically specified. Okay.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

I mean, thermal is some price adjustment, but for a very selected commodity. I mean, hydrocarbon is all fixed price, and thermal, we have some price adjustment for a particular component.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Okay. Got it. Yes, sir, can I say on the EBITDA margin expectation for the full year FY26 in the core business or in the P&M business, that's 8.2 is what you mentioned, right?

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Correct. Correct.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Okay. My final question is on the Nabha Power. So what is the status of the asset monetization there?

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

The asset is doing well, so the asset is doing fairly well. It gives us almost INR 100-110 crores of profits every quarter, and it is one of the best-performing plants, and of course, we are looking at, but the point is it should be something which we believe should be a fair valuation. We can look at it. Otherwise, at this juncture, it is a part of our portfolio.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Okay. No, because it would be good to get the bids when it is doing well. So perhaps we had the idea of monetizing it that way.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

That is correct. So we are not saying that we are not looking at options, but we are looking at valuations which we feel should be appropriate, considering that it is one of the best-performing plants in the country and having some sort of a clear visibility on earnings and profitability.

Bharanidhar Vijayakumar
Director of Institutional Equities and Lead Research Analyst, Avendus Spark

Understood, sir. Thank you. All the best.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Thank you.

Operator

Thank you. The next question comes from Amit Mahawar from UBS. Please go ahead.

Amit Mahawar
Executive Director and Lead Analyst, UBS

Yeah. I have two quick questions for Mr. Sarma. Sir, on Middle East, particularly, we had a very strong ordering that we saw in the last two years. Incrementally, seemingly, infra is more a bigger pipeline than hydrocarbon for us, where a lot of Chinese and non-Korean, non-European competition comes for us. So do you think the incremental returns on capital employed in incremental Middle Eastern orders might be. I'm not saying not great, but relatively inferior to what we saw in the last two years? That's my first question, sir.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

No. I think we have not seen much change in terms of bidding pipeline or in terms of competition. Yes, of course, sometimes in certain infrastructure projects or even hydrocarbon projects, we see Chinese. But we are also quite selective. And those which we are targeting, I think we believe that we have a fair competition, and we are able to secure jobs at the levels what we would like to have. I mean, that's how we play it out. I mean, the addressable market is quite large for everyone to have their share. So I don't see that as a big issue.

Amit Mahawar
Executive Director and Lead Analyst, UBS

Sure. Very comforting. And second and last question is some of the Korean companies like Hyundai, Samsung. We talk to people in the market. Them taking 20%-30% more orders in the Middle East region on the current base that they're executing, you need man and material, and man is the most critical part in that region, right? Man and material is easy to get relatively. Do you think L&T in 26 can back 20%-30% higher orders in the Middle East in terms of—is it possible you have capacity to execute there in terms of if I go by the manpower availability? Because your execution run rate in 25 is very heavy. 26 even will be heavy, the book you have. So can we take 25%-30% more orders in the Middle East in FY 26? Thank you.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

I mean, we will decide that will be part of our budget planning exercise now. And when we are completed with this, and when we approach the first quarter, then we will share more details. But in principle, I think we are. These two markets are becoming our important market. So we look at each and every opportunity available to us very seriously, critically, our ability to execute. And we have also strategies in place. If there are constraints, we work continuously in overcoming those constraints. Maybe like manpower you spoke about, we also have a great relationship with some of the large subcontractors in our Ultra Mega project. One of the Ultra Mega projects, we have a very good subcontracting strategy. And we are working with one of the largest construction contractors. We have access to a large number of pools.

So we do a bit of a blend here, hybrid model we follow. So we generally see through these issues and work through those issues and prepare ourselves. But at the end of the day, I mean, we'll have to balance it, and we'll have to be selective. And at the same time, chase those opportunities which will provide us the required growth rate.

Amit Mahawar
Executive Director and Lead Analyst, UBS

Good luck, Mr. Subramanian.

Subramanian Sarma
Whole-time Director and President, Energy Division, Larsen & Toubro Limited

Thanks.

Operator

Thank you. Ladies and gentlemen, that will be the last question for today. I would now like to hand the conference over to Mr. P. Ramakrishnan for closing comments.

Parameswaran Ramakrishnan
Head of Investor Relations, Larsen & Toubro Limited

Thank you, everyone, for attending this call. It was a pleasure to interact with all of you. Good luck and wishing you all the very best. Thank you once again.

Operator

Thank you. On behalf of Larsen & Toubro Limited, that concludes this conference. Thank you for joining us. You may now disconnect your line.