Q3 EBITDA was BRL 3.066bn, with concession-renewal accounting effects weighing on reported comparisons; net debt/EBITDA was 2.46x. Consumption and data-center demand grew, while delinquency, financing costs and wind curtailment remained pressures.

Gustavo Estrella
CEO, CPFL Energia

Thank you, Mariana. Well, good afternoon to everyone. Thank you for your presence in our call of results for the third quarter. I am going to start here. Just one minute. Well, I am going to start here on page three with our highlights. We were talking about our results. The EBITDA is BRL 3.066 billion, a drop of 3.1%. I think we have to remember when we talk about the results, the impact of the VNR after the concession renewal of distribution, and this brings a comparison of results, perhaps on non-comparable basis.

When we talk about this, the effect is zero impact on cash. It is just accounting numbers. The variation of EBITDA that goes to 0.5% . I think the correct variation and the correct reading to interpret the result 2026, 2024, the net income BRL 1,289 million. We go from a decrease of 6.4% to almost stability, 0.9%.

Our CAPEX relevant in the quarter, BRL 1,749 million. The accumulated BRL 4.5 billion. To close according to the guidance of the beginning of the year, the CAPEX of BRL 6.5 billion in the year. Some more highlights. Consumption of energy, an increase of 3.6% in relation to last year. We have an important effect of higher temperatures this year in the comparison to the previous year. Also, we have the effect on the right side, expressive moment in the consumption of data centers.

I am going to talk a bit more about this, affecting positively the results of the commercial side and also the total consumption of energy in our area of concession. It is increasing 41.7%. Valor 1000. We have been recognized, I think it is the sixth time, as the best in electric utility sector, the fourth consecutive time. So, an important reward, very expressive, recognizing CPFL Energia.

All this ABRADEE award, we were recognized in different categories, ESG, operational management, health and safety, and last, an international award, CPFL nos Hospitais, recognized by the OLACDE. It is also an important reward, recognizing the importance of this program and bringing a positive impact to the hospitals in our concession area. Now let us move to the next slide. This is slide number four. Here we are talking about energy consumption, 3.6%. We can see here in the residential class a growth of 2.6%, very much concentrated due to the increase of temperature, higher temperatures than the temperatures in 2025.

So this brought a positive impact in the residential market. The same thing happens in the commercial class, an impact of 3.2%, and what we call macro and others, a growth of 11.5%, closing this total growth of 14.3%.

When we see the commercial class, we see an expressive consumption in the consumption of data centers, 309 GWh. It is a growth of 41.7% in relation to 2025. If we compare to 2023, it is over 70% growth. The expectation is we are going to continue with increases in data center with the requests that have already been made and accepted by the company. This is important due to the connection restriction that we have.

We have several points of connection in our concession area, but even so, an important and positive perspective of growth in the consumption of data centers. In the industrial market, we have a growth here of 1.6%. The industrial part has a low growth, about 1.5%. So one more quarter with stable growth when we compare to what happened in the previous quarters. Now let us go to slide five, accumulated consumption.

The effects are more or less the same. The temperature has a positive impact, industry growing 0.3%, and the consumption of data centers 34% in relation to 2025. When we go back to 2020, 224% growth. A positive number moving forward given what has happened in our concession area in the previous years. Now let us go to slide number six. This is very important, and we find here a challenging situation, which is delinquency. Delinquency goes up to 1.16% in relation to last year, which was 0.91%.

The trend is to grow, whether it be because of the external environment, families are more indebted, a more challenging situation of controlling delinquency. But in this quarter, specifically a challenge, a rollout of our SAP system, which has made this program of cuts impossible. We have a relevant drop in the number.

Of power cuts, we can see the total volume, a drop of 12% in relation to last year, so 626. The reduction of the number, 100% concentrated in July. From August on, the numbers change, so the expectation is that up to the end of the year, these numbers will be better than the numbers that we showed in the third quarter. But even so, a challenging scenario, not only this year, but next year as well.

The scenario of losses, similar, but we still have some challenges, some internal challenges due to the rollout of SAP, but the loss then is a bit higher with 9.79%, and the highlight here is CPFL Santa Cruz that has lower losses than last year and also below the regulatory limit. Here in generation of slide seven, we see the PLD. There is an important drop of 48%, fruit of the hydrology.

This is a scenario of at least December, up to December this year, positive hydrology, especially in the south, but also in southeast. Expectation of maintaining the spot prices very close until December. GSF a bit this year with 77% in comparison to 65% of 2025. Here in wind, one more challenging quarter with a wind performance inferior to last year, so this brings a generation of 23.8%, but with a relevant impact of the curtailment. Curtailment reaches 47.7% in comparison with 39.4%.

The combination of winds below expected with the curtailment, which is higher of 2025, brings a reduction in the generation of the CPFL. The availability in line with 94%. We have the recovery here of some wind farms coming back into operation, so this brings an improvement in our availability of reaching 94% in this quarter.

Now, talking about results, I am going to give the floor to Ms. Ke Ji, and she is going to tell us about the results and the highlights of the quarter.

Ke Ji
CFO, CPFL Energia

Okay. Thank you, Gustavo, and good afternoon, everyone. Now let's look at the financial performance of result. In the third quarter of this year, the EBITDA was BRL 3.066 billion, which is BRL 98 million lower comparing to the same quarter of last year. Let's look at the performance of each section. In distribution, the EBITDA was BRL 1.704 billion, BRL 98 million lower than last year. The major reason was because, as mentioned, in the second quarter of the year, we finished the renewal for our distributions.

Therefore, we stopped recognize of the CFA profit, and also the net PMSO was higher in last quarter because one reason is the personal expenditure was higher related to some collective bargaining result, and also there was a legal provision related to social security changes. And also the D&A was BRL 25 million higher.

Some positive effects, including a better performance in the market and because of inflation and also higher consumption. Next, we talk about the generation. In generation, the EBITDA was BRL 999 million, which was about the same level of last quarter. Some positive effects, including we recognize a curtailment reimbursement, which was BRL 38 million in this quarter, and also there was some inflation adjustment for our energy contract.

On the other hand, the wind performance was weaker, so the revenue, the profit from wind section was BRL 43 million lower comparing to same quarter of last year, majorly because the wind was weak. Next, we talk about transmission. The IFRS result was BRL 291 million, while the regulatory result was BRL 280 million. The EBITDA of [IFRS] was BRL 43 million higher, majorly because a positive RAP adjustment related to recognize of some O&M RAP revenue from previous year.

For regulatory, the revenue was BRL 92 million higher because a positive RAP adjustment because of inflation and the RAP related to some new project. The PMSO was slightly higher comparing to same quarter of last year. Next one. In services and others, the result was BRL 72 million, which was BRL 7 million lower than last quarter. The major variance was in Alesta because of a lower installment, which was related to the SAP migration in third quarter. When we look at net revenue, we can see that the performance was BRL 88 million lower comparing to same quarter of last year.

Some positive contribution, including the UBP prepayment profit of BRL 42 million in the quarter, and also BRL 49 million related to adjustment of regulatory assets and liability. On the other hand, the financing expenditure was higher because of a higher balance in debt.

Also, the mark-to-market was lower comparing to last year because there was some new debt issuance in 2025, which contribute to this non-cash profit. When we look at the performance of nine months, we can see our result for the first nine months was about BRL 10.483 billion, which was BRL 439 million or 4.4% higher comparing to last year.

In distribution, we have a higher performance of BRL 40 million, majorly because of a better market performance. On the other hand, the PMSO was higher, and also a higher D&A and the stopped recognized profit of CFA was a negative aspect in distribution. In generation, the result was BRL 160 million higher comparing to nine months of last year.

The positive effects including, in 2025, we had an asset write-off related to EPASA discontinue operation. Also this year, we recognized curtailment reimbursement. Also there was some inflation contract adjustment, and we have received insurance recovery in our hydro dam. Negative aspect including a weaker performance in wind section and also in energy trading. In transmission, this year, for the nine months, we see the profit increased by 31.6% or BRL 246 million, which was related to higher regulatory RAB.

Also because last year, there was a RBSE one-off negative effect. In services and the other section, the performance were BRL 36 million better comparing to last year because of a better work performance in Transcos and Discos. When we look at the net income performance, the result was BRL 459 million better comparing to nine months of 2025.

In financial expenditure, there was a higher expenditure of BRL 162 million, majorly because of a higher balance in debt amount and also higher average CDI and IPCA. Also because of the positive contribution of mark-to-market in 2025. On the other hand, the adjustment of regulatory asset and liability offset the positive result from the section, offset some of the financial expenditure. Also we recognized UBP prepayment.

For tax, the result was, tax expenditure was BRL 274 million lower than last year because there was a deduction related to tax credit passed through to customers. Next section, we talk about financing activity and our debt portfolio. As you can see that by the end of the quarter, our total net debt reached BRL 33.6 billion, which brings the net debt to EBITDA covenant to 2.46x, which is still a pretty much controllable level.

In last quarter, we have finished the financing for BRL 4.877 billion in total amount through various of approaches, including debenture issuance, intercompany loans, 4131 loans, and proceed from some development banks. The average term of our new debt is two point zero four years, and the average cost is CDI - 0.04%. Now let's look at our debt portfolio. You can see regarding the cost of debt, there is a very clear declining trend.

The cost is lower for both nominal and real term for our net debt. Also another trend is, when you look at the maturity of our debt, the curve was very much flattened because we did intercompany loan, which will mature in the year 2029. So, by the end of the quarter, our average tenor increased to four point three nine years, among which 15% is short-term debt, which will mature in one year.

Regarding CAPEX performance, in the third quarter, we have finished a total CAPEX investment of BRL 1.749 million, and in the total of first nine months, it was BRL 4,538 million. So in last quarter, [79%] of the CAPEX goes to distribution. About 4% goes to generation, and 30.5% goes to transmission section, while the remaining 1% goes to services and others. Now, I'll give the floor back to Gustavo, please.

Gustavo Estrella
CEO, CPFL Energia

Well, going to our last slide, I think once more, I would like to talk about the CPFL nos Hospitais program, a lot of recognition, international relevance of the public hospitals in our area. The numbers are expressive, 640 hospitals, BRL 376 million invested, and we expect to continue investing about BRL 50 million per year, benefiting hospitals with different models. So, solar panels on the roofs, and the Santa Casa hospitals. Here we have an example of a project in a PCH of the company where we are using the floating plant.

These are models that we have been testing, GD, centralized, so that we really can optimize more and more this project, and so that we can attend more hospitals in our concession area. So it is a very successful project, and I hope that we will continue investing more and more during the next few years. Well, with this, we close our presentation.

I am going to give the floor back to you, Mariana, for us to move into questions and answers.

Operator

Thank you, Gustavo. Now we are going to start the session of questions and answers, remembering all you have to do is press raise hand to request your participation. We have a first question here, Guilherme Lima from Santander.

Good afternoon, Guilherme. We are opening your mic so that you can ask your question.

Guilherme Lima
Analyst, Santander

Hello?

Operator

We can hear you.

Guilherme Lima
Analyst, Santander

Good afternoon. I have two questions, two quick questions.

First of all, I would like to have an update about the self-dealing. Could you talk about this, about how the process is going, the next steps, what your expectations are? The second question, an update in relation to the vision of batteries due to the expectation of competition, how you are preparing yourselves, and your vision about the defined prices. I think that is it.

Thank you.

Gustavo Estrella
CEO, CPFL Energia

Thank you, Guilherme, for your questions. I think first of all about self-dealing, we are still waiting for a definition of the legal definition. So it is important to say the merit has already been judged since this is something without any defined value. The process is now to define the final value of this, and this discussion is on the table. We are still waiting for the judicial result of something that has already been judged, and the merit has already been defined. So this is a process, a long process, so we hope that we will have something new perhaps during the next few months, but we are still waiting for a legal decision.

Vitor Fagali
VP of Market Operations, CPFL Energia

I am Vitor Fagali. I am going to answer the second question about the battery auction. Well, the whole market, the competition will be high given the interest, the number of projects that have been registered.

Tomorrow, we will have the list of the projects that are going to dispute this auction. We have been preparing over two years. This was an auction that was announced a few years ago. So we continue ever since the beginning when the proposal started, the discussion of the auction and developing projects. So the company is working on this. We have an important CAPEX is going to be the main driver for this competition, and we are working hard with suppliers so that they can nationalize and they can have a higher be competitive.

Having the second auction on the fourth, which is going to be for imported equipment, we are also preparing ourselves. Well, I think as for the price, I think it is quite reasonable. It gives margin for everyone to be able to work and to have competitive projects.

I think that is a little bit of the vision. I think the project in two or three weeks, we will have the auction and we will have the response to your question in more detail.

Operator

Let us go to the next question, Ricardo Nascimento from Safra. Good afternoon, Ricardo. We are opening your microphone so that you can ask a question.

Ricardo Nascimento
Analyst, Safra

Thank you very much. I have two questions about the regulatory schedule for next year, how the discussions have advanced with ANEEL, and then the second question about your expectation about the discussion of the smart meters that should take place at the end of this month. I would also like to know a little bit of how the contribution has panned out and also the expectation of solutions. Thank you.

Gustavo Estrella
CEO, CPFL Energia

Hi, Ricardo. Well, at first for the regulatory agenda, our expectation is that the topics advance.

We have to wait for the regulation to see if this is going to come into ANEEL's discussion. We also have the regulatory process that was drawn today, in fact, and also other things that are in the process of ANEEL that have this process for next year. in relation to smart meters, we hope that there will be an evolution, and this will be for next year as well.

Operator

We have ended our questions and answers, and if there is any question or doubt, we from Investor Relations, we are at your disposal to respond. I am now going to give the floor to Gustavo Estrella for the final considerations and to end our presentation.

Gustavo Estrella
CEO, CPFL Energia

Well, once more, I thank you all for your participation in our call of results.

I think opening here a new era, especially with the renewal of the distribution concessions, a more positive perspective because we have a timeframe which is longer for our distribution activities. I think this is very relevant. What is our concern? Delinquency, as we mentioned here. I think we are going to continue with a scenario of long time with higher interest rates, and this, of course, pressures the budget of the families, and it also reflects in a higher challenge for the control and reduction of delinquency.

Also, the interest rate on the client side, but ours of an infrastructure company with the necessity of financing is a challenging scenario. In the future, 15% a year, so the high interest rates for a longer time. This is another challenge. On the other side, there is a positive number of the market.

The market continues responding positively, especially the topic of the data centers. We are going to continue with high growth rates and more consumption in data centers, a series of projects already ongoing, which will start operating up to 2028. Our CAPEX, we closed this year with a CAPEX once more over BRL 6 billion.

This is going to be a scenario for 2027. There is a base increase, a generation increase, and our businesses in our regulated business. An important number is the access that CPFL has to the capital market right now. This is extremely relevant and important. In this quarter, we got BRL 4.9 billion with an interest rate lower than the CDI. The important is also challenging, but even so, we are going to continue with the market with the best conditions possible compared to other companies.

And obviously, the support of State Grid, Ke Ji has mentioned this, with access to financial operations, which gives us other options for financing and the needs of the company. Last but not least, Vitor mentioned batteries. I think the expectation, perhaps not only this, but other auctions as well, and also possibly new opportunities in transmission. So we follow, we continue here very much focused on our activities and our current operations, but also looking at growth perspectives also with efficiency, with profit to our shareholders. I thank you all for the participation in our call of results, and we see you next time. Thank you very much.