Vision 2035 prioritizes disciplined, high-return investment, with BRL 21bn planned over five years and a minimum 75% dividend payout subject to leverage. Growth options center on hydro capacity and a 9.1 GW pumped-storage pipeline.

Rafael Bosio
Head of Investor Relations, Copel

Good morning, everyone, and welcome to the 2026 edition of the Copel Day here at the New York Stock Exchange. I'm Rafael Bosio, Head of Investor Relations, and on behalf of the entire team, thank you. Thank you for joining us today, both those of you here in New York and those watching online. By the way, this webcast is being recorded. Before I continue, I would like to remind everyone that today's presentations contains forward-looking statements that are subject to risks and uncertainties. The full safe harbor disclaimer is on the screen now, and we encourage you to review it. Now, a brief safe announcement to those present here. In case of an emergency, please note the exits on the front side and on the back of the room. If the fire alarm sounds, NYSE's security staff will guide us through the evacuation. Finally, let's go through the agenda.

Marcel Malczewski, our Chairman, will officially open the event, followed by the thematic presentations prepared by our C-level executives. Then we will open the floor for the Q&A and closing remarks. For those of you here, we will be serving lunch in this room, and we really hope that you take this opportunity to talk, to discuss, and to interact with our executives. Now that I have delivered all the disclaimers and announcements, I leave the stage to Daniel Slaviero, our CEO. Daniel.

Daniel Slaviero
CEO, Copel

Thank you, Rafael. Good morning. It's a pleasure to welcome everyone here. In 1997, Copel became the first Brazilian power company to ring the bell on the New York Stock Exchange. Next year, we celebrate three decades of that milestone, and we are back here on a defining moment in our history. Last year, we presented our strategic Vision 2035, and one thing I can tell you for sure, our moat is wider today than it was ever before. This morning, I am going to show you why. To start and share the board's perspective, please welcome our Chairman, Marcel Malczewski. Marcel.

Marcel Malczewski
Chairman, Copel

Thank you, Daniel. Good morning. Beautiful day in New York City, beautiful day to be here. Full house at New York Stock Exchange. Thank you for receiving us in the house. Well, 2023 was the year of a fundamental turning point for Copel. Transformation into a true corporation has changed the way we govern the company and the way we create value. Today, every capital allocation decision, every investment, and every dividend must serve one goal: sustainable long-term value creation for all of the shareholders. I joined Copel's board in 2019. Over these seven and a half years, I have witnessed an evolution that goes far beyond what most companies achieve in decades. Copel is now ready for its next chapter, its growth that lasts.

So, we asked the management for a plan that works across different scenarios and builds on Copel's real competitive advantages. That became the foundation of our Vision 2035 strategic plan. We, the board, challenged the company to develop a bold plan. What you will see today is the result of that process, a strategy built around financial discipline, clear strategic choices, a long-term perspective on the evolution of Brazil's power sector. The results so far speak to the progress we've made. Copel has demonstrated agility and resilience in a challenging environment, exceeded key performance targets, and delivered meaningful returns to the shareholders, to you guys. But what gives me confidence is not simply what Copel has achieved so far. It is the governance we built to sustain the performance. As we look towards 2035, one principle will continue to guide the board. Growth is a choice.

Value creation is the discipline behind that choice. That's the standard with which we will measure Copel's decisions and our own performance as an efficient board of directors. Welcome, everyone. Thank you for being here with us, and enjoy the morning.

Daniel Slaviero
CEO, Copel

Thank you, Marcel.

Marcel Malczewski
Chairman, Copel

Thank you.

Daniel Slaviero
CEO, Copel

As our Chairman, the guardian of our governance, especially in a true corporation. Now, let me show you who we are.

Speaker 4

[Presentation]

[Presentation]

Daniel Slaviero
CEO, Copel

What you just saw, it is a work of outstanding people. It is a privilege to lead them and to lead this company. What we have achieved so far was built with discipline and a clear ambition: be the leading value creator in the Brazilian power sector. This ambition has guided us to every major decision we have made in the past eight years since I joined the company. Since then, we sold non-core assets, focused on distribution and generation business, and became a true corporation. Every move made Copel more valuable to our shareholders and a better service provider to our clients. But we are winning. We focus on one metric above all: total shareholder return. That is the only metric driving the long-term incentives to our management. Now look at the numbers. 10 years, five years since the privatization. Across any horizon, Copel is number one value creator.

It is almost a 25% annualized return over 10 years. Now see the orange line. See how the curves bent in 2023. Let's look at deep dive on this period. Every check mark here is a commitment we made during the privatization process. 12 commitments, all of them delivered. All of them delivered. I will mention three recent milestones with a huge value creation to Copel. On generation, the capacity auction, securing long-term and predictable revenues. On the distribution, the tariff review, the largest asset base nowadays in Brazil. In governance, our migration to Novo Mercado. What all of them have in common? Not only those three, but all of those 12. What do they have in common? We create our own opportunities. That's our philosophy. It doesn't depend on any given cycle. It depends on us.

There are many things we do not control, but there are two things that are entirely in our hands: how we run our business and where we put our money. This is a flywheel. This is our flywheel. One circle is feeding the next. It starts with operation excellency, how we manage our assets, how we manage our people, and how we serve our clients. An efficient operation generates cash, and cash moves the wheel forward. Second stage is how we get more value from the assets we already own, and this is where we differentiate ourselves. First, because we invest where we already have a match. Our DISCO is clear as the case. Sharp investments, tariff review recognition, and there's expertise and room for more investment cycles ahead. The same logic applies to our trading business.

We are building the best team to have a proprietary view and to stay one step ahead of the market. Second, and this is where it truly defines us, we build opportunities before the market sees them. You will remember a few years ago when Copel started talking about hydropower plants competing in capacity auctions. There was no regulation, no business model, and very few believers. We built it together with the regulator, with our suppliers. We built it, and it paid it off in the 2026 capacity auction. None of this is luck. It comes from competitive advantages that are hard to copy. Our integrated business with renewal concession, our position in Paraná State, our technical expertise, and the quality of our assets. That's what creating our own opportunity means.

When you combine those competitive advantages with a deep knowledge of the regulatory framework, we are able to see value before it's priced. Once again, that's what creating our own opportunity means. Then we go to the third circle, which is a very strong circle, optionalities. The beauty of Copel case is you can do both, pay strong dividends and be selective to be ready to selective M&As. Remember, we have the highest payout policy in our sector and be ready to selective M&As. Selective means selective. Small assets and thin returns are not our game. This only works with discipline and execution. That is how value compounds. Now, let's talk about the Brazilian power load. This is the EPE estimates that we are going to growth by over 20% by 2032.

We are going to grow by 20% by 2032, driven by almost 20 giga, driven by data centers, electrical vehicles, and GDP growth itself. But the challenge here is not just adding power, it is adding the right kind of power. This is an interesting slide. This shows how power supplies has increased in the past 20 years. For more than a decade, most of the expansions came from intermittent sources. You can see here on the orange bars. Starting in 2010 with wind and solar farms, and more recently with distribution generation, which itself has reached more than 50 giga. You can see here on the dotted line how it shows how demand for firm and dispatchable power has continued to grow. Here, 2011, peak demand overtakes firm power. What does that mean? It means that we are over 10 years consuming surplus power.

You are going to see on Diogo's slide, the balance is getting smaller. It is getting smaller. Brazil has reached an inflection point. This gap became a structural challenge for the system. Brazil responded with capacity auctions to secure additional firm power. That is important because reliability always comes first. But there is another side of this equation. How much will it cost? This is the bill of subsidies in Brazil. Starting 2005, it is around BRL 2 billion. Over 20 years, has reached more than BRL 70 billion. By 2031, according to our estimates, it will reach an incredible BRL 140 billion. This cost is not only affecting the expansion of the system, but the economy itself. Brazil has the resource to meet its power needs. There is no doubt about it. But the cost issue will remain relevant, no matter how much quickly the market evolves.

When we say about market development, Brazil in the next few years has two choices. It can keep in path A, keep today's model, an energy market, increasing capacity markets whenever firm energy is needed, and where spot prices are not given by bids, but by computer models, mathematical models. Or we can go to B, an energy only, where price are not set by bids, but generators give on-day-ahead tenders. This models is used in development countries like U.S., Europe, and Australia. At Copel, we are committed to the long term, so we think, we strongly believe that right price signals can support a more sustainable and a better expansion for the Brazilian power system. This discussion is especially important because it will affect the attractiveness of the opening of the market scheduled to November 27 and November 28.

The choice of market design and the pace of any transitions belongs to the authorities. But the main point here is for us, regardless each path it takes, our hydro portfolio, which is renewable, flexible, and dispatchable, will be needed, and we will generate value under both model and in the path. You have seen what make Copel different. We have the assets, we have the people, and we know how to turn opportunities into value. When it comes to Brazil, either on the power sector or on the economic landscape, we know the challenges, the opportunities, the risks, and where the value is. That is why I can say, we are built to win in any environment. Thank you very much. Please, André, join the stage.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Thank you. Okay. Thank you, Daniel. Good morning, everyone.

Daniel Slaviero
CEO, Copel

Good morning.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Morning. First, let me introduce myself. I have been working in Brazilian power sector for almost 26 years. Private companies, the regulator, and for the last three years, here at Copel. Years ago, I worked for an American company, and my boss used to ask me, "André, with so many rules, how do we make money in Brazil?" Today, I will answer that question. I will start with the one thing I learned in 26 years. In regulation, I do not do opinions, I do math. Let us start with the rules of the game. Here is my first answer. In Brazil, rules are bankable. In Brazil, rules are bankable. You can build a business on the rules for decades. First, we have an independent regulator. ANEEL is 30 years old. 30 years of independent and transparent decisions. In 2021, the OECD recognized ANEEL's credibility. Second, we have clear responsibilities.

Who plans, who operates, who regulates, who invests. The responsibilities are clearly defined in Brazil. Third, and above all, the contracts are honored. In Brazil, a concession contract is a contract. In our case, we have almost 30 years of visibility. 30 years of visibility in Copel's case. In transmission, 16 more years. In distribution, 19 more years. In our largest hydro plants, 28 more years. Stable rules are only the starting point. Our edge is how we play them. Let us start where we play the game. Paraná is our home, and Paraná grows faster than Brazil. Last year, Paraná GDP was 2.8%, and Brazil GDP was 2.3%. Paraná has strong economic fundamentals, and when the economy grows, energy grows. Look at the chart. We have a solid market growth year after year. What are the drivers in Copel market? Industry, a strong industrial base connected to agribusiness.

In homes, an income above Brazilian average. In commerce, a strong local economy. Now, let's do the math. In our case, the 2026 tariff review set a new baseline for Copel. Every five years, the regulator resets the DISCO revenue, and our tariff review was a success. First, our regulatory asset base, almost BRL 20 billion, one of the largest in Brazil, and with a value creation of 11% when compared to the book value. Why? Because the CapEx efficiency. We still have BRL 11.5 billion in fully depreciated assets. Second, our regulatory OpEx. For every BRL 100 we actually spent, the tariff pays BRL 124. Why? Because the regulator compares all the distribution companies in Brazil, and Copel is at the efficiency frontier today, among the most efficient. Third, bad debt and energy loss recognized above our actual levels. Why?

The state of Paraná, a strong income where the clients pay their bills. This is our distribution today. What about the future of our distribution? Let me show. Look at the map. This is the state of Paraná. Each orange point is distributed generation. The distributed generation is increasing, has increasing in recent years. Almost 9% of Brazil installed capacity. Think about it. Brazil has 27 states, and one of them has 9% of installed capacity. By 2031, we expect 6.31 GW in the state of Paraná. But why is this related to the future of distribution? With a lot of distributed generation, as you just saw, 9% of Brazil's total capacity is already in our grids. Plus, market opening from November 2027, small business and homes can choose who sells them energy, combining them.

We have the future of distribution, the DSO, the distribution system operator. The discussion is just starting in Brazil. Just starting. But we can learn it from regulatory frameworks in markets as Europe, U.S. Their experience show that the DSO can be remunerated by performance-based incentives, by additional revenues for the new service. For Copel, keep in mind three points. One, protection. Our distribution revenue is protected even in market opening because the demand charge. Second, an upside. We can have stronger economic signals in tariffs and upside in the future with new products and services. Third, our edge, 40% of smart meter penetration, and smart meter giving us data. I talked about the rules of the game, the state of Paraná, the distribution market, the distribution today and tomorrow. Now, let's go to the business where the change is even bigger, generation.

What's the challenge in generation? Today, Brazil needs more capacity and flexibility in the system, and it's not come fast enough. Let me show the challenge. Look at the orange line. It's the net load ramp in Brazil. In the last five years, we're talking about an increase of 109% of the net load ramp, from 23 GW to 48 GW. Who can give the flexibility that the system needs? Not solar, no. Not wind, no. Hydro can, in minutes. The good news, Brazil pays for this. Two ways. First, capacity reserve auctions. More capacity for existing plants. Two, pumped storage hydropower auctions. New flexible capacity. The new frontier for Copel and for Brazil. Diogo will show you our plants here in pumped storage. Why is flexibility so important? Why? To answer that, let's go to Texas, Australia, and Germany.

These markets are similar to Brazil in size, and they look alike in one key point, high penetration of renewables. Look at this. The storage includes pumped storage. Brazil has almost zero, 0.01%. In other words, zero. On the other hand, look here, the solar capture price, the highest when compared with the other markets. Brazil needs flexibility and capacity, and the pumped storage hydropower can deliver it. What about the future of generation? In our view, the generation is moving to market-based dispatch. This is our view. As Daniel told you, in Brazil today, a computer model runs the plants and sets the price. Market-based dispatch is different. The plants make offers. The market decides. It is totally different than what we have today. Totally different. Remember what we saw? Distributed generation, renewables penetration, market opening, the necessity of flexibility and capacity.

With so much volatile supply, in our view, competitive price can reflect better the scarcity and the opportunity costs. Let me be very clear. This will take time. Again, let me be very clear. This will take time. The contracts will be respected, the existing contracts. We can grow under today rules. We can grow under today rules, as Daniel told you. If markets change, we are prepared. There is one more opportunity for hydro. One more. By 2032, 16% of Brazil's hydro fleet will expire. 16% of Brazil's hydro fleet will expire. More than 15 GW. Today, the government is running a public consultation. The big question is, to renew these concessions or rebid? An easy big question. These are big plants, already running. Our call?

Auction should be the rule, because we defend the public interest, the competition among investors, and lower rates for the customers. This is a real debate in Brazil. If these plants go to auction, we will compete. If not, our plans stay exactly the same. We do not depend on this, but we are ready. Let me recap. Three key messages. One, Brazil's rules are bankable, and they support value creation. Two, the distribution company has a new baseline, resilience, and built to grow. Three, we have a hydro portfolio providing the capacity and flexibility that the market needs. Remember how I started? In regulation, I do not do opinions, I do math. To my former American bosses, this is how we make money in Brazil, and this is how my team delivers.

We are pragmatic, we anticipate what comes next, and we are measured by one thing, Copel's bottom line. Thank you.

Daniel Slaviero
CEO, Copel

Just before you go, you mentioned here about the market-based dispatch, which we see from the medium to long term. We have to move to this direction. That is our opinion. If you can give us more detail or elements, why do you think it is going to be inevitable, in our opinion, in any point of time, we move to this direction?

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Okay, Daniel. If you just seen, Daniel, and as you told too, the challenges Brazil are facing now are very clear. More renewables penetration, more distributed generation, not coming market opening. There are several regulations and public policies to address this, but individual regulation, individual discussions about renewables, about distributed generation. The point is, we understand that we do not have the price signal in the market. The model do not give us the signal. So, only with the signal, we understand that we will have the correct signal to the expansion of the system, the energy, the power, and the costs for the system too. My point of view and our point of view, we understand that we need to start now with the goal that we want in the future, with a detailed plan to achieve this.

This will take time, we know, but we need to start now.

Daniel Slaviero
CEO, Copel

Perfect. The point is, right price signals are fundamental to sustain the expansion of the system. I think that is the main point of André, of myself. Thank you, André. Congratulations. Now let us invite Diogo Mac Cord. Please, Diogo, welcome to the stage.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Thank you, Daniel. I am very, very happy to be here today with you all. After Daniel and André, my mission here is to put everything together from a strategy point of view, and the way I will do it is by organizing our framework, our mental framework in three questions. First, what will Brazil run out of first? In other words, what are the restrictions that we have to face in the coming years? Is it electricity, or is it electricity at the time that we want? That is the traditional dilemma between energy and power. Second, how much time is left? This is an important question because prices go up whenever we have a bottleneck. Keep in mind that a greenfield hydropower plant or thermal plant, so a greenfield non-intermittent source of power, takes up to six years to be done.

It means that whatever we decide today will deliver results only from 2032 on. That is the relevant horizon that we should look for, six years. That is why in the power sector, timing matters a lot. Finally, why Copel? Follow me on that. Daniel just told us how intermittent sources of power have dominated the Brazilian expansion in the past 15 years. What is the impact of that? Let us start with wind. We all know that wind installed capacity in Brazil is as big as 35 GW. The question is, can we count on it? Take a look to this example. Within 24 hours, in one day, from August 20th to August 21st, we lost 13 GW. Within 24 hours, we lost 13 GW of power.

Since 2023, some days when the wind is just not blowing, the wind portfolio combined delivered to the system as few as 10% of its installed capacity. It has happened 678 times since 2023. So, can we count on it? At the same time, solar capacity is growing fast, and it is reaching 43 GW of peak delivery. Not installed capacity, delivery, real delivery. 43 GW that just disappears every day as the night arrives. The question is, can we count on wind and solar? If the answer is no, if we cannot rely on either, what are the consequences of that? Wherever you have this huge capacity of intermittent sources of power, the system is just less reliable.

In Spain, last year, it took to the government, in fact, several days for them to realize that the true cause of a huge blackout was that wind and solar were delivering as much as 80% of the load at that time, just before the blackout. It has driven the insufficient voltage control that causes the blackout. The same thing happened here in Brazil three years ago. Solar and wind were delivering 86% of the load just before the blackout. Because of that, ONS constrained the Northeast transmission lines thereafter. As we all know, that is one of the main reasons why the curtailment is growing. In both cases, who restored the system after the blackout? Hydro and thermal. This is not a conjunctural problem. This is a structural problem that is getting worse. We are here today. We still have 18 GW of power surplus

But if nothing is done, by 2032, this power surplus will be over. At that time, we will be accessing thermal power plants that will cost us as much as BRL 2,000 per megawatt hour. It happens because a simple principle of physics, power should be produced at the same time of the consumption. In the past 15 years, the world tried to fool itself by looking only for energy, megawatts average, which by the way, is also shrinking, but it is not as urgent as power supply. That is why we do believe that a new capacity auction should be organized next year. Apart from herd mentality, we understand that the Brazilian system inevitably has a rendezvous with the same technology that saved our system in the past decades, which is hydro. This is no longer a promise.

Copel was the main winner of the last capacity auction, and we are building just now 2 GW of brand-new hydro turbines to deliver clean, reliable, and cheap power to the Brazilian system. This is huge. It is equivalent to a greenfield Hoover Dam that we are putting together as we speak. For the next year's capacity auction, we already have Salto Caxias project, very competitive, very similar to Segredo, that has 900 MW of capacity. Very competitive to next year's auction. This is not enough, and our vision is much greater than this.

Speaker 4

[Presentation]

[Presentation]

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

That's an announcement. 10 GW of pipeline that we have, 900 MW of Salto Caxias, plus 9.1 GW in pumped hydro. The technical advantages of pumped hydro are huge. First, we are talking about more than 100 years of asset lifetime. 100 years. That's five times greater than a chemical battery. That's a legacy to the future generations. With a pumped hydro, we can spend the whole weekend pumping water up. That's when the curtailment problem is worse, right? We can spend the whole weekend pumping water up and give this power back to the system along the week to meet peak demands. That's why pumped hydro is the ultimate solution for energy storage worldwide. The U.S., Europe, Japan, even China. That's the ultimate solution for energy storage.

Copel is the company that is most prepared to lead this technology in Brazil, as we have a fantastic group of engineers, and we have a fantastic endowment. Endowment of topography, up to 450 meters high, and geology, with rocks as strong as basalt, makes our life easier to excavate. Our pipeline is ready to be part of next year's auction, along with all the existing infrastructure that we have. We are talking about projects around the existing reservoirs that Copel has. Changing now the subject to transmission lines. As we know, this is a very important asset to drive energy transition, and Copel has more than 10,000 km of transmission lines. We were selected by ONS two years in a row as the best transmission line operator in Brazil. However, the reality is that today, we don't see a fair angle to invest.

As we can see here, from 2018 on, the discounts are too high in the auctions. As a consequence, the expected returns are below what we consider to be our opportunity cost. That's why our decision today is to focus on our existing lines, reinforcements, and improvements that still present very good margins. One day, if this 2016 window of opportunity comes back, we will be ready, but not for now. On the other hand, our DISCO. Copel is the fourth-largest distribution company in Brazil by consumers, but we have the largest RAB, the remuneration asset base in country. Why is that? What's the story here? Copel has an area equivalent to England and Ireland combined, a huge area to be covered. Among the largest distribution companies in Brazil, only Minas Gerais and Bahia could be compared. There is one big difference.

When we look to the per capita GDP of Paraná, we see that we have a 25% larger per capita GDP than Minas Gerais, and we have two times the double of the per capita GDP of Bahia. It gives us, at the same time, the opportunity to have a large area, large grid with sophisticated equipments in it. At the same time, we also have BRL 11 billion of totally depreciated assets that opens another avenue of investments. When we remember, as André just told us, that we have a reimbursement coefficient of 1.11, meaning that for every real that we invest in the past tariff reset process, we had 1.11 back, it means that we have at the same time a great space to invest and great returns for investment. It's a great place to be when we talk about DISCO.

And let me give you a flavor of what we are doing with that. We already have 2 million, I would say, digital meters, 2 million digital meters here, and more than 15,000 automated reclosers. But when we put together a proprietary communications network, all of that becomes a smart grid. So the difference between a just electronic device to a smart device is a communication network, and Copel has one of the largest proprietary communications networks in the country. And that is why we have the largest smart grid in Brazil. And what are we doing with that? So we are collecting more than 80 GB of information every day, data that arrives in our headquarters every day, 80 GB. And when we combine it with an AI engine, we can understand what is happening in our area. We can optimize our field crew. We can maximize our CapEx investment.

And this is fantastic for our customers. Yes, it increases dramatically our quality, but more importantly, it gives to our clients a unique experience. We have the best app in Brazil. Copel has the best app among all the utilities companies in Brazil. We have the best rate in both Play Store and App Store. You can do through our app everything in only four clicks, like organizing your bill installments, overdue bill installments in only four clicks, and having many other easy experiences. But if you have a smart meter, your experience is even better because you can see through this app in the palm of your hand how much electricity did you consume today, real time. You can compare with your last month's consumption, last year's. You can compare with the neighbor's average consumption.

And from next year on, you will be able to see in our app how much electricity your air conditioning has consumed, your fridge, your electric shower, and maybe you will be able to buy something from our app. Why not? Only Copel has it in Brazil. Again, this is a unique experience that only our customers have access to. And our app is a fantastic tool to improve customer loyalty when the market opens. And this experience is already paying off. I told you last year that we started to sell insurances. Well, after one year, we reached 3,000 policies per month. That is an average monthly growth of 20%. And many other services are following the same path. We have just started microcredit operations. More than 10,000 contracts are being signed every day, sorry, every month, powered by AI, and it gives us a margin as high as 90%.

So in other hands, we have, through our app, the opportunity to launch new services that are at the same time asset-light, scalable, and with great margins, and that is a great deal, and we are growing really fast. So finally, our power trade. By 2032 on, Copel will have up to 1.4 GW average of uncontracted power. And by our calculations, the DISCOs will need as much as 6,000 MW average of power, meaning that we will be able to meet up to 23% of the market. When we consider that both modulation and sub-market risk will have to be assumed by the seller, we understand that Copel has a unique position to offer power to the southern market. As we saw before, demand is rising, but supply is not. Prices will go up, and Copel will be ready for that moment.

Going back to our first slide, what will Brazil run out of first? Power first. In one word, power. Power first. But don't be mistaken, energy shortage is just around the corner. Two, how much time is left? I would say less than the time of a greenfield power plant. Six years, remember? Within six years, everything will change. If nothing is done now, everything will change in six years. Clock is ticking. And finally, why Copel? The answer is because our strategy has anticipated all of that. We are ready to be part of next year's capacity auction and existing energy auction, both. It was never luck. It is the result of a well-designed strategy, long-term vision, and of course, great professionals working together. Thank you very much. Daniel, back to you.

Daniel Slaviero
CEO, Copel

Diogo, challenging landscape, but we see opportunities. Big announcement that you made, 9 GW in pipeline for pumped storage hydro. That's the, as you mentioned, the new frontier of growth of Copel, and same playbook as capacity auction, same story, pumped hydro. The pumped storage is next. But you mentioned here about the disclosed contracts. It happened one last week in Brazil.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Last week, yeah.

Daniel Slaviero
CEO, Copel

And we have a lot of uncontracted energy from 2028, 2029, and beyond. If you can explain a little bit more that, what opportunities that we see here. You mentioned a little bit, just more details.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Last week, the government organized an existing energy auction. Copel was one of the three largest winners. We offered 80 average megawatts of power. There were three products, 2027, 2028, and 2029. The first product, 2027, is the one that Copel was part of, and it had 2.5 GW average of contracted power. But on the other hand, the products 2028 and 2029 had very little offerings. It goes to our point that prices are rising. It goes to our point that prices are rising. Next year, the government will have to come back and do it again, offering higher prices.

Daniel Slaviero
CEO, Copel

We will be ready to capture that. Thank you, Diogo.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Thank you.

Daniel Slaviero
CEO, Copel

After we come back to our Q&A, please welcome our CFO, Felipe Gutterres. Felipe, the stage is yours.

Felipe Gutterres
CFO, Copel

Thank you, Daniel. Good morning, everyone. With you all at the first Copel Day in New York. As you know, I joined Copel three years ago, and since then, my mandate has been focused on strong balance sheet, capital discipline, and full transparency with our shareholders. Today, I will show you how we do that with numbers and why we believe this is the path to close Copel's valuation gap in comparison to its peers. We have followed a clear strategy sequence each year built on the previous one. In 2024, we started with a capital allocation manifesto when we put an end on the growth for the sake of volume. Balance sheet discipline came first. In 2025, we started building a compounder. We defined our optimal capital structure and our minimum rate of return.

In 2026, it all comes together with another lever, our compounding engine, as we call, our ACE compounding engine. That's how we compound value from 2026 onwards. The discipline of 2024 made us able to define the optimal capital structure, and the optimal capital structure makes us able to compound from 2026 onwards. It's about strategy, discipline, and execution, and you can track our progress quarter after quarter. Now, the ACE engine. How do we leverage our consistent returns? Through ACE, three letters, three levers. A stands for assets and digital operations. We use technology and automation to improve our productivity, increase our asset availability, and level our service quality up. C stands for capital and cash discipline. We only invest when the project's IRR is above our minimum rate of returns. We are managing our working capital in a tightly fashion.

By doing that, we also increase our asset turnover. That's how we increase our capital and cash discipline. E stands for efficiency, tax efficiency, and governance. We optimize our effective tax rate, increase our after-tax results, including the full use of our tax-deductible interest on equity. These are three initiatives that work together, and they serve only one purpose, maximizing ROIC, maximizing our return on invested capital, getting higher returns, and widening the spread over our cost of capital. Now let me show you how the math works. First, the numerator. We increase our operating profit through efficiency gains from scale, asset availability, service quality, but also we improve our after-tax results through a lower effective tax rate. Again, taking advantage of the optimization of our tax, effective tax rate, and also using in full our historical tax-deductible interest on equity. Now, the denominator.

Turnover of our capital employed, reducing our working capital, increasing our asset turnover, and making the investments that have returns higher than our minimum rate of return. Every investment has to meet this minimum return. So, higher results on top, more efficient capital employed on the bottom. This is how we increase our results, but it's much more than a formula on a slide. Our operational targets are linked to that. So when our teams are working in the field, we are generating value to you, our shareholders. Let's put Copel next to its peers. Many utilities struggle in the growth dilemma quadrant or in the capital efficiency quadrant, and they have difficulties to keep returns sustainably above their cost of capital. Now find Copel and follow the arrow.

In the next five years, we will move towards the value elite quadrant using the lever that I just showed you. One additional lever, our proprietary ACE engine, that help us to move the needle to the value elite quadrant. Higher operating margins. This is a matrix where we plot the return on invested capital and also the NOPAT margin. So higher operating profits, higher return on invested capital is how we deliver sustainable value. How do we define our investment analysis framework? Every project at Copel goes through a simple test. They have to meet our minimum rate of return. We come first from the cost of our capital, then we look at our implied IRR of our share price, and we consider project-specific risks and opportunity costs to define the spread over the implicit rate of return to define our minimum rate of return.

Here, the test is simple. Every project has to meet at least our minimum rate of return. If not, we don't invest. We keep the capital for other investment opportunities, or we return capital back to you, our shareholders. As I just showed you, we screen our investments through this framework, but over the next five years, we'll invest BRL 21 billion. Out of this BRL 21 billion, BRL 5.5 billion will be invested in 2027. From 2028 to 2030, we will invest BRL 15.6 billion. 71% will be invested in our DISCO. We are building a new DISCO within our DISCO business. Smart grids, high voltage, remote-controlled substations, sensors. They help us to reduce operating costs, our availability, and level up our service quality.

22% will be invested in our generation business for the expansion of Foz do Areia and Segredo, and to modernize our hydro plants to keep our availability above 98%, which increases dramatically our cash operation after 2030, when we deliver these expansions. The remaining balance, 6%, will invest in transmission lines, improvements, and reinforcements. Projects with low execution risk, predictable regulated revenues. We are talking about, in this time horizon, something around 78% of regulated revenues and attractive returns. Three investment priorities, but only one rule: CapEx IRR has to be higher than our minimum rate of return. That's how we turn expenditure into value. When we go for our capital allocation, I have to point out that our cash flows are predictable. If you take our latest tariff revision, we came from a regulatory EBITDA from BRL 1.9 billion to BRL 3.5 billion.

If you consider our secure net revenue from 2026 to 2031, it will increase 155% by 2031. That's why we can have the boldest dividend policy in our segment in Brazil, minimum of 75% of net income, provided that we keep our leverage within 2.6 and 3.2, with a target of 2.9 times net EBITDA, which is the target that optimizes our equity value. Predictable cash flows, optimal capital structure, consistent dividends. This is how we deliver returns to our shareholders. How will we finance all of this? What happens after? The answer starts with our strong core business. We count on a natural hedge. When hydrology is unfavorable, our distribution and transmission cash flows offset the impact. More than that, we count on the commercial arbitrage.

Strategically, we keep part of our energy portfolio uncontracted in the long term to take advantage of pricing arbitrage, benefit for hourly pricing, and leverage, yes, leverage our southern sub-market position. We also have reduced earnings volatility, stable cash flows, lower cost of equity, higher valuation multiples. That is how we create the strength, the financial strength to support our investment plan, and no additional follow-ons needed. Yes, we will have a strong investment cycle till 2030, but what happens after 2030 is that with higher cash generation from the expansion projects, CapEx winding down, we deleverage the company naturally, and this creates more room for dividends, for other investment opportunities. We are building tomorrow's capacity, but financing it today. But what makes all this possible? We have a strong business platform. Sorry. We have a strong business platform that count on four competitive advantages.

We have integrated business model that creates a natural hedge for regulatory risks and hydrology risks. We are based in a very attractive region in Brazil. We are in the south of Brazil, so we have a geographic advantage. We count on superior technical skills. That is why we have 9 GW of pumped storage hydro projects in our pipelines. We have an outstanding asset quality. Together, we have a solid cash generation foundation, and a solid cash generation foundation to make us able to explore new opportunities and future opportunities, new concessions, capacity reserve auctions, pumped storage auctions, and selective, very selective M&As. We do not need to chase growth at any cost. We have a strong business today and plenty of opportunities tomorrow. Let me leave you with the reasons we believe that Copel stands out as a very compelling investment opportunity in Latin America.

One, low structural risk. An integrated portfolio gives us the hedge that we need against volatility. Protection today and upside tomorrow. A strong business under today's rules, but flexibility to capture value as the market evolves. Three, compounding engine, proprietary compounding engine that depends on us. We do not need to wait for the new market cycle. It is all about our own execution. A resilient business, disciplined capital allocation, high return investments, a sustainable dividend policy. We have the assets, we have the strategy, and we have shown that we can deliver. We are very determined to have our share price reflecting all of that. Thank you very much.

Daniel Slaviero
CEO, Copel

Felipe.

Felipe Gutterres
CFO, Copel

Sure.

Daniel Slaviero
CEO, Copel

Strong balance sheet has always been one of our strengths, even more in challenging times. We have a solid investment plan for 2030, as you mentioned. Is there anything change for this investment cycle in our payout policy?

Felipe Gutterres
CFO, Copel

No, nothing. We have all of our dividend policy secured. We have, as you mentioned, a solid balance sheet and space to do both investments and continue being a strong dividend payer. So I think this is one of the beauties of our thesis, Daniel.

Daniel Slaviero
CEO, Copel

Thank you.

Felipe Gutterres
CFO, Copel

Thank you.

Daniel Slaviero
CEO, Copel

You can stay here.

Felipe Gutterres
CFO, Copel

Sure.

Daniel Slaviero
CEO, Copel

Let's just, we're going to start the Q&A session and just putting the chairs here, and then invite Diogo and André, please.

Felipe, here.

Felipe Gutterres
CFO, Copel

Yeah, go there.

Daniel Slaviero
CEO, Copel

Please. Diogo there, and then we can already start the questions, the Q&A questions. Thank you so much. The questions can be taken from our guests here or our online guests also.

Felipe Gutterres
CFO, Copel

Maybe for some-

Daniel Slaviero
CEO, Copel

30 seconds here. Thank you very much. Felipe, your mic.

Felipe Gutterres
CFO, Copel

All right.

Daniel Slaviero
CEO, Copel

Thank you very much. Let's organize here. Let me get my pens. We have quite a few time, plenty of time here to talk and discuss. Please, all of you are more than welcome to do any questions. The gentleman will take you the microphone, then we can do, if you can please introduce yourself quick, very briefly, then me and my partners here, we're going to answer all of the questions. Thank you.

Bruno Amorim
Analyst, Goldman Sachs

Thank you. Hi, good morning. Bruno Amorim from Goldman Sachs. Congratulations for the presentation. I have a few follow-ups on the PSH opportunity you have mentioned. I know it is too early days, but any idea of timing you can provide in terms of how long does it take Assuming the regulatory agenda moves in a reasonable pace, how long does it take for those auctions to take place and for the investments to start? Any ballpark idea of CapEx per gigawatts you can provide so we can kind of have an idea of the size of the opportunity from a capital deployment perspective? And finally, again, I know it is too early stage, but any color you can provide in terms of your competitive advantage on top of the topography that you have mentioned.

It is fair to say that regardless of the regulation to be applied, it is kind of a given that no third party could use the topography or the areas that you have described that are within your influence area, or if there is still a chance that, depending on the regulatory outcome here, a third party might be authorized to build an asset within your concession area. Thank you so much.

Daniel Slaviero
CEO, Copel

Thank you. Diogo.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

So-

Daniel Slaviero
CEO, Copel

There are few parts of the question.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Yeah. Tell me if I forget something, right? But

Daniel Slaviero
CEO, Copel

Yeah

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

First, about the time, about timing, right? The government has announced an auction for next year. So, if we are talking about the second half of 2027, we will need something around five years to build the plant, right? So that's the time horizon. About the CapEx. So, that's a hydropower plant, right? So we are talking about very similar equipment. In fact, a little bit more expensive than a traditional turbine. But on the other hand, we have much less environmental impact. I would say almost none, right? So, it will cost you much less than a greenfield hydropower plant, and maybe a little bit more than the announced CapEx that we had in Segredo, for instance, per gigawatt, installed gigawatt. About the topography and the possible uses by third parties, we understand that you have different kinds, different types of pumped hydro.

You have the open cycle, which is just pumping water up from the lower reservoir to the highest. But you have the closed system, right? So, two concrete buckets. And you have the semi-open system that we understand that only the current concessionaire can use it because you are accessing the lower reservoir, the existing reservoir, and you are building this new concrete bucket upper. And then we understand that only the concessionaire that is already operating the dam could be allowed to use it because of operational issues. So, no.

Bruno Amorim
Analyst, Goldman Sachs

Thank you. Very clear.

Lucas Andrade
Analyst, Itaú BBA

Good morning. Lucas Andrade from Itaú BBA. If I could stay on the pumped storage topic. You shared with us a very interesting slide in which you can see that basically the firm capacity is available at the demand hours is shrinking over time. In a portfolio standpoint, you are benefiting from that in the population, again, that the hydropower plants that Copel has on its portfolio. But how do you usually cite the uncontracted volume precisely to unlock the most of your portfolio, considering that within a few years we will likely see an increase in storage either through BESS or through pumped storage hydro?

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Mm-hmm. Okay, so in our first graph that shows the power shrinking, right? So the power surplus shrinking. What we do is, we know because of the lead time of non-intermittent plants, we understand that from 2027 to 2032, it's a given information, right? Even when we consider, how can I say, the demand growth, a conservative demand growth, we understand that this power supply is shrinking, and that's a more or less easy calculation because, as I said, the power, the supply is given, right? So that's only an estimative about the demand. But when we go to the DISCO and we see the 6 GW average, maybe that's what we are talking about, we see that the existing contracts, they are expiring, right?

Next year, in the next three years, we will see a huge amount of existing contracts that will be expiring, and the DISCOs will have to call this energy back. When we put this conservative estimates of demand growth, that's the result. That's not a difficult calculation to be done, and that's why it is so important, because something needs to be done now, and that's why we believe that the government will have to organize a huge capacity auction next year, because otherwise, we are going to have problems from 2031.

Daniel Slaviero
CEO, Copel

You. Here.

Speaker 10

Hello, Matheus [audio distortion]

Daniel Slaviero
CEO, Copel

Hello.

Speaker 10

I have two questions. The first one regarding the cost of the battery auction is being discussed, if it will be paid by customers or by generation companies. I would like to understand how you see this, because this could, in a couple of years, be a really big cost and could damage the customer's price or damage the economics of non-dispatchable, non-flexible generators. My second question, I would like to understand how you see the pumped hydro storage competing with batteries and with thermal, because everybody wants to grab a bit of the auction. But as we see of EPE's numbers, you only have a necessity of 4 GW, 5 GW per year on the next year, starting 2031. We are discussing 4 or 5 GW of battery auction, and there is not space for everyone because the bills will go a lot up.

I would like to understand how you see pump storage in terms of competing with batteries and thermal. Thank you.

Daniel Slaviero
CEO, Copel

Thank you, Matheus. Let us split the question in two. See if you can start with you, André, about the cost being appropriated to the developers, the generators, or to the customers. The second part here, it is a very good question also, about the PSH times or against BESS and thermal, how we are going to compete and what kind of auctions we see in this case. André, please.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

I think that today, we do not have this balance about customers and generators here. It is a huge discussion in Brazil about who pays, so generator or customer. Because of that, we are talking about the signal price. Only with the signal price, we understand that we will have the correct allocation of the costs, because today we are talking about it. We are trying to solve individually the things in Brazil. Sometimes you put in generators, sometimes you put in the customers, and you are not looking for what is the challenge in Brazil and who should pay for that. In my point of view, only of the signal price, only with public policy that look for this, we will solve. Today, we have an imbalance here between costs and the opportunity to the generators.

Daniel Slaviero
CEO, Copel

To add that, I mean, the generator pays the entire bill from themselves. It is a thin line. But at least up to the benefit that each generator has is something that we think should be fair on this. So that is a discussion, and this is giving some uncertainty of the BESS, which is two to three weeks. Yeah, two to three weeks. But I mean, generators pay at least up to the benefit they have, it seems to us quite fairly. So that is the first part. And second part, Diogo.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Okay. Matheus, let me split in two points, right? First about the quantity that should be hired by the government every year. You are right that we have to have something around 4 to 6 GW per year. But do not forget that we have to have a surplus, like a security surplus, right? If you put to auction only 5 GW to 2032, power surplus is shrinking. So we understand that you have to keep something around 15%-20% of surplus all the time. So that is why we believe that next year's auction, because do not forget that this year's capacity auction, from the 19 GW, 17 facts, right? And 10 GW was existing power plants. So we have to hire a huge volume next year in order to keep this power surplus.

From 2028 on, you can go back to 5 to 6 GW, right? So that is about quantity. About competitiveness, we understand that BESS have a great space into distributed storage, but not for huge storages. When we consider that the average quantity of energy storage around the world per gigawatt of BESS is three hours and pumped hydro is 20 hours, it is very clear the difference between appliances, right? Considering that our biggest problem about curtailment and about operations is along the weekend, a BESS is very quickly saturated. So early Saturday, the battery space is over, but the pumped hydro could spend the entire weekend pumping water up. So very different appliances and the competitiveness of the pumped hydro after six hours of storage, we are much more competitive than BESS, and apart from the 100 years lifetime.

Felipe Gutterres
CFO, Copel

Yeah

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

We are really building today a legacy to next generation in Brazil.

Felipe Gutterres
CFO, Copel

Against 50 years for the BESS, right?

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Yeah.

Daniel Slaviero
CEO, Copel

I mean, by the power that is going to be needed in next years, both of those technologies, in our view, are complementary. We are going to see room for both, and we are putting a lot of knowledge and effort on the pumped-storage hydro because we invest where we already have an edge. That is the point. André, please.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Other complement to add in the first question, in the balance, we need to put the distributed generation. We talk about the generator, the customers, but what is causing the problems in Brazil now is distributed generation. We need to put in this equation, in this balance, the distributed generation.

Daniel Slaviero
CEO, Copel

Thank you.

Vladimir Pinto
Analyst, Bloomberg

Hello.

Vladimir Pinto, Bloomberg. I have two questions. The first one is regarding the pumped hydros. These 9 giga that you mentioned, they are already with the previous environmental license, or meaning that next year they would be available to participate in the auction? The second one, you also mentioned in the presentation about the there are a lot of other hydro generation concessions that are expiring, and we know that there is discussions or to renew it with the existing owners or to rebid it. We know that probably rebidding, the government will receive the cash fastly, let's say, and well, but the other, the competition choice would lead to more money to the government. So, how do you see this discussion going on inside the government?

Daniel Slaviero
CEO, Copel

Perfect. Thank you, Vladimir. André, if you can start with the renew-

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

The second?

Daniel Slaviero
CEO, Copel

Yeah, with the renew or rebid.

Then, okay, Diogo, pumped hydro, pumped storage, of course, 9 GW is more than double our capacity, so that's very nice.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

The public consultation is running now. The government is running now. We don't know the trends of the government. What we know is that the law do the allocation of this money to the customers by CDE. So, because of this, in our point of view, the lower rates to the customers and the competition will give to Brazil this amount of money to reduce the tariff of the customers.

Daniel Slaviero
CEO, Copel

Adding to that, Vladimir, it's a decision that belongs to the government.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Yeah.

Daniel Slaviero
CEO, Copel

Whatever they decide, of course, we respect, and it is their decision. But we think, as we have seen in another industry, rails, airports, the main point is to be into putting on the bid. If it puts, we intend to participate because it is the kind of asset of the size, of the sources, and it is something that we know a lot about. It is a decision that we are going to see in the next few months. But with the fiscal, we think probably there is a good chance that they could go to renew, but it is not our decision.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

To add, in our sector, in transmission, the rebid is the rule.

Okay? Since 2022. This is a

Daniel Slaviero
CEO, Copel

You have seen also in the GSF auction.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Yeah

Daniel Slaviero
CEO, Copel

which was in the renew-

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

It was a success.

Daniel Slaviero
CEO, Copel

Yeah, what was a success as well. Diogo, out of this 9.1 pipeline project, if you can divide with us what are the stages with them, and who's been presented already?

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Mm-hmm. Okay. Environmental license, right, was your direct question. For Salto Caxias, it's not pumped hydro, right? But increasing the capacity from Salto Caxias, is it easy, right? We will have the environmental license next year, no doubt about it. About the pumped hydro, that's something new. We are still learning how to do it, and along with the environmental agency. Last year, we had in Copel a great event along with directors from IBAMA, from IAT, which is the environmental agency in Paraná state.

Felipe Gutterres
CFO, Copel

Last week, you mean.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Last week.

Felipe Gutterres
CFO, Copel

Last week.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Yeah.

Felipe Gutterres
CFO, Copel

ANA.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Last week. ANA, yeah. All the agencies were there. We are learning with them how to do it, right? It will be the first. But considering everything that we discussed last week, I am pretty sure that we will have no problem about it because, as I said, we are putting our efforts much more on the projects that are semi-open, right? And when we talk about this kind of projects, we are talking about an additional powerhouse in an existing facility. So, it is much easier to go for it.

Daniel Slaviero
CEO, Copel

This is an interesting angle, I think, because we are educating the market and also developing the solutions together with the regulator.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Yeah.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Yeah. We filed the basic project for the first pumped storage at Samuel two months ago. So, it's the first one and the first to analyze, to study, to give us the regulation. We are moving-

Daniel Slaviero
CEO, Copel

Yeah

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

this issue.

Daniel Slaviero
CEO, Copel

The same as what happened with the capacity auction. You remember in 2021? This one only thermal, and we built it with the regulators, we built it with the suppliers, we built it with the environmental areas. This path, we are doing, it is the same playbook, and we hope to have the same story. We are very confident with the knowledge that we have on those business.

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Important to say that the pumped hydro, this new upper reservoir is very, very small.

Right? The environmental impact-

is very, very low. Very, very low. We are talking about 0.7 square kilometers-

of area, right?

Daniel Slaviero
CEO, Copel

Thank you.

Victor Swishchuk
Analyst, Letko Brosseau

Hi, Victor Swishchuk with Letko Brosseau in Montreal, Canada. I wanted to ask you about EBITDA and EPS guidance forecasts between now and 2031, 2032. As I understand on the distribution side, your trajectory is locked in because the next reset period is in mid-2031. That number will grow by rate of inflation, so correct me if I am wrong. On the generation side, you are completing the two brownfield expansions, and that will basically set your EBITDA higher, but just 2030, 2031, and then transmission, as you said, you are not seeing competitive IRRs, so you are staying away from those options. Just maybe if you can map out the path of your EBITDA and EPS over the next five to six years. Thank you.

Daniel Slaviero
CEO, Copel

Thank you, Victor. Felipe.

Felipe Gutterres
CFO, Copel

Yeah. As you know, Victor, we don't give guidance, but we can guide you through what we will generate from the businesses that you mentioned, right? The tariff revision was really strong, as you saw. In 2026, we only had half a year of this new DISCO EBITDA. So, full year from 2027 onwards. If you take the expansions for Foz do Areia and Segredo, one point that we are working hard on is to have Foz do Areia delivered by 2029, so we can capture one year in advance. From 2030 onwards, we are talking about something around BRL 2.6 billion in addition to our current EBITDA of our business platform that we will add with this expansion of Foz do Areia and Segredo in full, if you take 2031 full, because as you know, we have to deliver the expansion by August 2030.

I think this gives you a sense on how we will perform.

Daniel Slaviero
CEO, Copel

We have online questions. They are putting on the screen here. Let me read it. "You mentioned there are several gigawatts of hydro concession agreements ending near term. Government and regulator are already discussing if renewal is an option. When should we have news on this topic?" I think it is very linked to Vladimir Pinto's questions. André, timeframe of these discussions?

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

The government said until the end of the year, because some of the concessions will expire next year, in the next two years. We are expecting by this year, yeah.

Daniel Slaviero
CEO, Copel

Yeah, but this is what they say.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Yeah.

Daniel Slaviero
CEO, Copel

But what we truly believe is by first semester of 2027-

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Yeah

Daniel Slaviero
CEO, Copel

I think it's a good timeframe. Then we can expect a decision on this matter.

André Luiz Gomes da Silva
VP of Regulatory and Market, Copel

Yeah.

Daniel Slaviero
CEO, Copel

I think that's a reasonable period to expect a decision about this. Two. It's question number two here from online. "Capital allocation. So many opportunities, what we can expect in terms of order of presence or progress? How can we think about the dividends, assuming some of the opportunities materialize?" And third question, "What the minimum reasonable level that you would consider to remunerate your shareholders?" Felipe.

Felipe Gutterres
CFO, Copel

In terms of capital allocation, we are agnostic, right? We like the projects that deserve the best return. Obviously, based on our core businesses and the businesses that we are focused on. When we talk about dividend payout and dividend payments, you have to, in our view, consider a multi-year projection. We normally look forward, we look five years ahead and consider the predictability and sustainability of our dividend payments to define the payout ratio that we will basically execute. Obviously, we have our minimum dividend payout, but if we go to something higher than that, what I'm saying to you is that we will define that in a way that it will be predictable year after year, considering that we have this strong capital investment plan already. We have space in our balance sheet.

You know that we can work within this 2.6-3.2 net debt EBITDA leverage ratio. Obviously, if we, as I mentioned, anticipate the delivery of Jorge Lacerda, we start deleveraging the company earlier, which gives us room for more dividends, and also for new investment opportunities as well.

Daniel Slaviero
CEO, Copel

On the order of preferencing, as Felipe mentioned, we are agnostic within the electrical sector. So generation, distribution, transmission, and trading, and it has to be 100% clean energy. We did our decarbonization process, so it is something that we do not want to go back again. We do not intend to go in another industries. We want to stay where we have an edge and where we think scale is a competitive advantage also. When we mean we are capital allocators, I think on the track record, we just sold a small HPP, Dona Francisca, because it is not in our strategic minimum size. You will remember last year, we bought and sold Baixo Iguaçu in 15 days because we thought this was a good opportunity to generate value. So that is how we think as a capital allocator within our electrical business.

Question number 3 here, "Your updated 2027-2030 DISCO CapEx plan is up to BRL 2.3 billion over the last year guidance. What is driving the increase and how much justify the higher capital allocation given declining regulatory WACC and ANEEL's unwillingness to visit the current methodologies?" Our business, our CapEx investments, especially on the distribution, they have a framework analysis of how we can spend every dollar, every real. It has to meet our internal rate of return. First, this increase on this CapEx 2027-2030 has to meet the grid resilience needs that we see and the opportunities that we see in our DISCO concession. Number two is investing now technological and smart grids, something that will help us return a very great amount of return on those kind of technology. It help us also to keep the OpEx very tight, this kind of investments.

The third reason of the CapEx is the growth of itself of our state, especially the demand growth that we have been seeing over the past few years. So this is to expand capacity with substations and other elements of the grid. Of course, all of this has the purpose to remunerate, and so is a good capital allocation for the company, low-risk execution, and of course, gives our clients a better service quality to our clients. This is the mindset of our CapEx investments plan until 2030.

Felipe Gutterres
CFO, Copel

If I can add.

Daniel Slaviero
CEO, Copel

Sure.

Felipe Gutterres
CFO, Copel

Obviously, considering our investment framework that we approved this investment in our DISCO business, we also make sensitivities to consider the new WACC from the information that we have so far.

Daniel Slaviero
CEO, Copel

Look at the post-election landscape, what concrete governance structure or legal framework does Copel have in place to insulate the company from political interference at both the state and federal levels?" Our true corporation model, our governance was built to face any environment, either in the state local or in the federal government. We are protected to any kind of interferes. Our bylaws is very restricted with the 10% voting share, and we are very confident that we will not have any issue on those. The company, it's a true corporation, a private company. It will be run like this, and we don't see any risks in the interference either of the federal government or in the local government.

We are very not worried about this issue, and we are very confident that our bylaws and our chairman mentioned here, the board is the guardian of the governance, and it was designed and prepared to see any possible try of interference. But truly, I don't think it's going to be the case. Neither in the federal government, neither in the local Paraná state government, I don't think there is going to be trying to interfere. But if it happens, we don't know yet, but if it happens, our bylaws, our governance, our board is protected for to be continue as Copel true corporation. This is our model, this is our style, is how it was designed to face any challenges. New strategies or execution over promise. What are the two or three hard milestones over the next 12 to 14 months we should hold you accountable for?

That's a very good question. First, execute this solid CapEx investment, especially on the capacity auction. We are trying to anticipate, and we will anticipate to 2029, and we have this big 2030 Segredo. We have the DISCO also. This is number one priority. Number two is good quality service to our clients, to our customers, especially when we see these several climates that we'll be seeing over this year. This is, in our opinion, is something is happening very more frequently. Third, it's find always good opportunities of investments that meets our internal rates of return. If it doesn't, since the company is a strong, solid, mature company, we will give back to dividends or buybacks. Of course, we have our operation excellency within year-over-year. That's, of course, one of our priorities because everything starts with operation excellency.

I mean, after that, those three, I would say, are strong challenge and our priorities here. One thing I would add, since the landscape have been more challenge, keeping a solid balance sheet, as Felipe mentioned, is one of our competitive advantages. It's key. It's balance sheet, it's a competitive advantage. I'm at Copel eight years. Since I've been there, I've seen interest rates in 2%, 15%. I've been seeing right-wings politics, left-wing politics, and Copel always outperform because of our resilient business model, our integrated company, and our people, the people who manage the company. We are very confident that we still going to be for the long term. One last thing, it's important. We are here thinking on the long term. When we discuss any market design, it's not something going to change.

We mentioned this a lot throughout the presentation. It's not something that we think is going to change in a year soon. The system can go this way. We are able to compete because of our business, resilient business model. Copel is, I think, is one of the most protected company, low risk, as Felipe mentioned, within the utility sector in Brazil. I think one last question here. You secured significant capacity expansion at Foz do Areia and Segredo, have registered Salto Caxias for the next auction. What are the expected returns profile for these projects, and how do you protect your returns if auctions prices compress?

Diogo Mac Cord
VP of Strategy, New Business, and Digital Transformation, Copel

Well, about Foz do Areia and Segredo, after the auction that was in March, we published the predicted CapEx. You all know the revenue, so I think it's pretty easy to do the math. About Salto Caxias and other projects, pumped hydro in special, we understand that the trade-offs should be the other options that we have. We have to compare different technologies that will help the system to meet some specific demand. We don't like this segregation of technologies. We understand that the government should define one problem that has to be solved, and the market should be able to present different technologies to meet this problem. That's the market who has the best capacity to choose the best technology.

That said, it is public, the price, the ceiling price that the government published for the BESS auction that will happen next month. We understand that it should be a good target to keep in mind for any storage technologies that might be auctioned in the coming years.

Daniel Slaviero
CEO, Copel

No further questions. I do not know if in the room there is any final question. If not, I would like to thank you all for being here. I am going to invite the President, the guests here. But one final word. I mentioned our competitive advantage, our moat. I mentioned our strength. You have seen our partners representing more than 5,000 people in Copel, and we are obsessed with discipline and execution. This is one of our trademarks, and we are going to keep it like this. Thank you so much for being here. We are excited, conservative, but excited what we have ahead, and we will see Copel keep growing and keep delivering fantastic and good results. Thank you very much. Thank you all who are online here.