Earnings Call: Q3 2026

Nov 12, 2026

Summary

Net sales grew more than 30% YoY, with EBITDA positive for a second consecutive quarter; FY guidance moved to the lower end due mainly to supplier and project delays. Investment is focused on maritime intelligence and constellation expansion.

Operator

[Foreign language] Luis, nice to see you again. How are things in Glasgow?

Luis Gomes
CEO, AAC Clyde Space

Good morning. Nice to see you again. Things are going well. Busy.

Operator

Busy.

Luis Gomes
CEO, AAC Clyde Space

But well.

Operator

Yeah, of course. There is a strong quarter in many respects, so please take it away.

Luis Gomes
CEO, AAC Clyde Space

Thank you. Thank you very much everyone. Could go on to the next slide. We have a strong report. We have grown quite substantially this year in relation to last year. Our net sales grew about 30%, more than 30%. We maintain a strong positive EBITDA. Although our cash flow from operations this quarter was negative, overall, that is in terms of the year performance, that is just what happens because we had lots of prepayments. Now for the quarter, we have a lot of payments to make from our suppliers. Overall, we still see the year as being good for our cash flow, operational cash flow, and we expect it to be positive. Now, in terms of our backlog, it has remained quite strong. Sterna, but we have got other things coming along.

It has been a strong year for us in terms of building our backlog. As we can see, our net sales continue to have a trend that is upwards, but our EBITDA is nicely positive now for two quarters in a row. That is something that we have, it has been an objective for the company for quite some time. We go on to the next slide, please. In terms of the full year guidance, our guidance now is for the lower end of the range that we gave. This comes down to mostly supplier issues. We have currently quite a big competition for boards, for instance, PCBs, printed circuit boards, and components from suppliers. There is a big explosion in demand, which means that some of the suppliers are having issues with delivery, and that has delayed us in some cases.

We have one project that continues to have some issues in terms of delivery, not related necessarily with us, but we suffer that from the delays on that project. We still keep on planning to have an EBITDA of approximately 10% for this year. As I say, we still expect operational cash flow to be positive and to remain positive this year. On to the next slide. In terms of what the third quarter has delivered to us, we have had the first deliveries of VIREON data to our customer. The data has actually proved to be quite good, and actually the customer was very happy with the results of what they saw. At the same time, we saw Bonnier Capital exercising their warrant for another SEK 40 million.

That is an important thing for us because it shows the confidence, the trust that Bonnier has built on the company and on our future plans. We also did secure financing facility, a drawdown facility, which will help us with some of the plans and give us some more flexibility in terms of some of our expansion and growth plans over the coming years. That is quite an important thing for us. We saw continued growth both on our Products & Missions and Data & Services. That is something that is very important for us, is to grow the business as a whole, not just as one part of the business growing more than others. This is quite good. As I say, we kept seeing some delays on major programs, mostly down to a shortage of components and parts.

These are things that we are managing. These are things that, although they delay us, they do not actually create major problems apart from the delays. That creates some slow recognition of revenue on some projects. It is something that we will do, if we do not do it this quarter, we will do it next quarter. It is something that we are just managing and it is part of the business. If we go on to the next slide. What we are seeing quite in terms of growth, and we announced recently, is that we are actually going to add two more satellites to our maritime intelligence constellation. We see continued demand for data and for information from space on the maritime domain. In anticipation of INFLECION later in this decade, we are actually building more satellites for our current constellation.

We have currently four satellites for maritime intelligence in build right now. Sedna three through to six. At the same time, we are starting to work the design and the plans for the manufacture of the 12 satellites for our INFLECION constellation. By 2028, our maritime constellation, we will have another 16 satellites either in orbit already or about to be launched, what will increase significantly our ability to deliver data to our customers. That, in terms of updates, that is where we are. I will open the floor for questions now.

Operator

Well, thank you for that, Luis. Let us look at the pros and cons of this report, the actual result, the current, and the forward-looking statement. To me, it is a strong quarter in several respects, net sales, EBITDA, and the positive result on tax. What is driving the improvement in the business?

Luis Gomes
CEO, AAC Clyde Space

It is a mixture of two things mostly. One is the fact that we got some very large contracts this year, big contracts that have been in the works for quite some time, things like Sterna and the contract on INFLECION. All of those are helping to improve our numbers. It is also a result of the work that we have done over the last few years to become more efficient to actually be able to deliver better. Those two things are actually driving very much the improvement of our operational results.

Operator

Yeah. Let's just jump into a couple of questions here. We have one impatient viewer who is waiting for new data orders. When do you expect that to start happening?

Luis Gomes
CEO, AAC Clyde Space

Those data orders are continuing to work. There are several smaller orders that we are working on. There are some larger ones. But in the case of VIREON, for instance, we have been working through the quality of the data, improving our data delivery. That's work that has been going on, and of course, customers want to see all those things in place before they actually commit. But we get quite strong interest, and we are in discussions with several potential customers right now on VIREON. We expect to see those orders coming in very soon.

Operator

Mm-hmm. How do you view the possibility for orders in the near term, is a viewer question, so maybe that's connected to the data orders. But let's make that a wider question. New orders in the near term.

Luis Gomes
CEO, AAC Clyde Space

We don't usually discuss, we don't give a forecast on orders that we have, but I can assure you that we are in several conversations, several discussions for several projects and new orders. We are seeing quite a lot of demand, for instance, on our products. We are seeing quite big demand from people that are building their own constellations. There are big opportunities. Our pipeline is very robust and healthy right now, so I would say stay tuned. It's the only thing I can say to that.

Operator

Yeah. Are you satisfied with the compositions here of, let's say, sales and the earnings?

Luis Gomes
CEO, AAC Clyde Space

I would have wanted a little bit more of data sales, since we mentioned that. VIREON has taken us longer to actually commission and to start operational delivery service. In that sense, if we had done it earlier, I would expect to have more revenue coming from that constellation right now. That has actually delayed us. But in general, yes, I see both segments are growing. We continue to see both our Data & Services and our hardware sides growing, so that's good. But yes, our expectation is that we would have grown a little bit quicker on the data this year. We are focusing very much on doing that right now.

Operator

Mm-hmm. If we look at the current situation, the Q3, then the forward-looking statement here, you're expecting full-year net sales to be towards the lower end of the guidance.

Could you just, well, give us a feel for why you're looking at the lower end and not the higher end?

Luis Gomes
CEO, AAC Clyde Space

In our business, we are very much dependent on third parties for delivery of parts, so we have many suppliers. We also have customers that have their own timings and that they have their own schedules. We are somehow dependent on them. Particularly this year, what we have seen is, as I said, we have one project where the customer has some issues in terms of their schedule, and they are not pushing so hard for some solutions that are needed, some information we need before that we can actually progress. In other case, we actually have issues with suppliers. This is across the board. It is not just specific to us as a company. It is actually sector-wide, and actually, anyone that is doing electronics these days is facing issues with components, printed circuit boards.

There are delays because there is so much demand and there is not enough capacity around the world. What that means is that we have seen some delays on some of the projects.

Those are things that we are working, we are managing, but nevertheless, they will have an impact on our revenue recognition this year. As such, we are giving our guidance towards the lower end of the spectrum of our interval, just to recognize that there are those delays that have been affecting us.

Operator

Mm-hmm. I interpret you correct here if I would say that it is more a question on, let us say, supply rather than demand-

Luis Gomes
CEO, AAC Clyde Space

Yes

Operator

because it's sub-suppliers, and it's not clients that are walking away.

Luis Gomes
CEO, AAC Clyde Space

Yes, it's supplier-led. It's a supplier-led issue. This is all about us not being able to get the suppliers to deliver things when they are supposed to deliver. This is something that we are having to manage, we are having to do, for instance, in some cases, dual supply rather than single, because we are trying to cover the risks. There are many techniques and many things we are doing to improve that. But this year has been a little bit more demanding on our procurement teams in terms of finding suppliers for many of the things we need.

Operator

I'll tie in a viewer question here. What are the risk of additional delays related to supply chain, and how can you manage this going forward?

Luis Gomes
CEO, AAC Clyde Space

I already mentioned one of the ways we are doing. In some cases, we are doing dual supply. We are looking for dual suppliers for the same products if we see that there is a risk that the main supplier can't do it in time. In other cases, we have looked to other suppliers that we know have capacity, even if in some cases they are not our normal suppliers of a certain equipment. We are working with others, but requires a little bit more work from our teams in terms of establishing the supply chain and understanding how good they are. At the same time, we are, of course, pushing the teams, very focused on the suppliers that we know are at risk, working with them, incentivizing them, making sure that they will supply what we need when we need it.

This is an ongoing work. There is quite a lot of work ongoing in the offices to actually deliver these things on time. There is quite a lot of work from, as I said, from our procurement teams and subcontract managers with the suppliers and the subcontractors to ensure that we get things we need when we need them.

Operator

Can you give some indication of the size of own investments into Data & Services ahead?

Luis Gomes
CEO, AAC Clyde Space

I can tell you that a lot of the investments, so in terms of Data & Services, the biggest investment is on INFLECION. As we said, it is a PPP with the European Space Agency with support from the U.K. government. So, roughly half of the investment is actually paid by the U.K. government, and half is paid by us. So that gives you an idea of the level of investment that we are doing. Then we have the VIREONs, so that gives you an idea of the level of investment that is needed. As we mentioned with capital raises, a large part of that goes into that investment.

Operator

Continuing on the investment side here, you are expanding facilities in Glasgow, Gothenburg, London, and Fairfax. What concrete demand are you seeing that gave you the confidence to increase capacity and fix cost at this particular point? Or were they indeed a long-term planning?

Luis Gomes
CEO, AAC Clyde Space

Some of them were long-term planning. For instance, the investment in Gothenburg is required to actually deliver the Sterna instruments for the constellation. Others are actually because we are seeing increased demand, our investments in Fairfax and in Glasgow, we are seeing increased demand for satellites and for products for other customers. We have an opportunity to actually grow without expanding too much our fixed cost. We actually took that opportunity. It's good timing. In Glasgow, we need to build more satellites for INFLECION and for other future opportunities. We actually saw that opportunity and decided to take it. As I said, in Fairfax, we have prospective customers that are looking for more capacity from our side. Then, of course, in London, the expansion follows the expansion of our data business.

As we are selling more, as we are engaging more with customers and growing our offering of products, we needed to grow that office that very much focuses on Data & Services.

Operator

Looking back or coming back to one of your slides here on the maritime side, you had two major developments. One is the building more Sedna satellites, and then the other is the INFLECION program, adding 12 satellites to 2028. Are these separate offerings, or should they be understood as part of the same future maritime intelligence businesses?

Luis Gomes
CEO, AAC Clyde Space

They are part of the same offering, so they are effectively an incremental improvement of our maritime intelligence business. The Sedna 3 to 6, sorry, are actually satellites that very much extend the current existing constellation and existing capabilities, and very much focused on expanding the business as it is. INFLECION will add new capabilities. We add new facilities to our maritime intelligence business. They are part of the same story. They are part of the same constellation. It just means that by 2028, we will have another 16 satellites either launched or about to be launched. That just shows that our maritime intelligence business is growing, is expanding, as we see more and more demand for it.

Operator

Here is a question regarding the opportunistic vibe in AAC Clyde. Could you elaborate on how much of the additional capacity is supported by existing customers' demand or contracts versus capacity being built in anticipation of future demands?

Luis Gomes
CEO, AAC Clyde Space

I am not sure that I can easily answer that question.

The capacity, as always, we are not growing capacity dramatically. We are not actually building large factories, but we are building capacity that is expandable. If we want to expand, we have that opportunity. We have always been very careful with that.

Operator

Yeah.

Luis Gomes
CEO, AAC Clyde Space

What we are building now is very much focusing on either contracts we already have or things that are very strong in our pipeline, things that we are very confident. We are not doing an expansion based on a dream that something very large will come. But it gives us that opportunity. By using our experience and by using our methods of production, we have shown to customers that we could increase production quite easily in our current facilities. With these new facilities, we will be able to do that even better if we need to. That is not actually the driving case. The driving case is pretty much what we already have on the pipeline, what we already have on the books, and what we have on the pipeline, on the high-probability pipeline. That is what is driving us at this stage for expansion.

Operator

Prudence is a virtue here, if I interpret you correctly. Over this year, you have secured additional equity and a new credit facility, while announcing investments, of course, here. How would you prioritize those if we look at the different areas where you operate in?

Luis Gomes
CEO, AAC Clyde Space

Very much our priority right now at this stage is maritime intelligence. We are growing that. That's where we are focusing. For instance, in the case of Earth Observation, we've got now the VIREONs, the next two ones going up. Now we have to actually Our focus on that side of the business is very much in monetize the investment. Our investment going forward in the next three years is very much driven around maritime intelligence. That's where we are focusing.

Operator

Mm-hmm. I have a sent-in question here, but I think you already answered that, because basically, if you are coming to the market or expanding a credit facility and so on, it's because you have a new opportunity rather than just seeking a new opportunity. Is that a way to interpret it?

Luis Gomes
CEO, AAC Clyde Space

Yes. We're always actually looking at opportunities. Even in the maritime intelligence side, there are other things we can do and that we want to do. There are more investments we want to do, for instance, in AI and the processing of the data, so that we can offer new products to our customers and to different customers that currently we are not addressing. There are investments we want to do on that. That's just expanding the existing business. Of course, we are looking at other opportunities. We have said for a long time, for instance, we are looking at larger satellites. We are looking at opportunities around the weather market, for instance. All of those are things that we remain interested and we keep a close eye on.

If we identify opportunities, yes, that credit facility gives us the flexibility to move quite quickly to occupy that opportunity or to take advantage of that opportunity. That, I think, is the strength of having a credit facility like that.

Operator

Mm-hmm. If we move into certain projects here, the EPS Sterna, you are now moving into delivery. What should investors expect to see during 2027 and 2028 as production ramps up? Should one expect follow-up orders in this program?

Luis Gomes
CEO, AAC Clyde Space

In this program, I do not expect any major follow-up orders. It is quite a large one. It is quite a large program. It is designed to deliver over a few years. I do not expect. Our focus very much now is in delivering the EPS Sterna instrument, is something, a hardware that we are also contracted to deliver. That is very much the focus of the company when it comes to EPS Sterna. Now, I see opportunities, and we have quite a lot of inquiries about that same technology now. We have a few developments and a few projects ongoing already, smaller projects to develop around the technology. Not part of that program, but using that technology for other opportunities. That we see quite a lot of interest right now. I would not be surprised if there are some opportunities coming up on that in the next couple of years.

Operator

Rounding off here, VIREON 1 and VIREON 2, we will watch end March. When should we expect the satellites to become fully operational? I think the key word here is fully.

Luis Gomes
CEO, AAC Clyde Space

We are expecting to launch them next year, in the beginning of the year. But we are dependent on the launch company. We will make our best efforts to launch them as early as possible. But I would expect them to be much quicker to commission than the VIREON 1 and 2, by the simple reason that a lot of the processing chains are already established. That's what has taken us so long on VIREON 1 and 2, is that we are actually seeing quite a lot of work on the ground. Not on the satellite so much, but on the ground processing. That's where it takes longer. That will already be done for VIREON 3 and 4. I expect a much quicker commissioning and a much quicker start of delivery.

Operator

Mm-hmm. Looking into the next quarter, what would be the main tasks that you will be focusing on, and what would you like the market to be focusing on?

Luis Gomes
CEO, AAC Clyde Space

Delivery. Next quarter is very much about delivery. We have deliveries on big programs like Sterna and INFLECION. We have the VIREON satellites that have to be delivered. They have to be ready to launch. Our focus is very much right now in delivering over the next quarter.

Operator

Mm-hmm. Right, Luis, thank you.

Luis Gomes
CEO, AAC Clyde Space

Thank you.

Operator

A very active quarter, and I believe a very active quarter ahead. Thank you for that. It's been an absolute pleasure. We thank everyone who has asked questions ahead and during this broadcast. With that, Luis, thank you and see you next time.

Luis Gomes
CEO, AAC Clyde Space

Thank you very much. Thank you.