Hello, everyone, and welcome to the ACWA Power financial results conference call for the nine-month period ended September 30, 2026. My name is Carla, and I will be your Moderator today. If you would like to ask a question during the session, please use the raise hand button if you have joined us here on Zoom. Alternatively, you can submit written questions by using the Q&A chat box. If you have joined us on the phone lines, please press star followed by one on your telephone keypad. I would now like to hand the call over to Ozgur Serin , the VP Investor Relations and Corporate Strategy, to begin. Please go ahead when you are ready.
Thank you very much, Carla. Good morning, good afternoon, and a very warm welcome, everyone. Thank you for joining us in another quarterly earnings call for ACWA Power. Today, we are here for discussing and sharing with you ACWA Power's financial results, business results as of and for the period ended September 30, 2026. Before we start, I would like to have a few words on our logistics and introduction. Carla has already introduced me, so I am going to skip myself. Together with me in Dubai, next to me is sitting Dr. Samir Serhan, who is our CEO. In Riyadh, we have our CFO, Mr. Abdulhameed Al Muhaidib. So three of us will be your hosts today. As far as the logistics are concerned, we have prepared remarks and a material. It is relatively shorter because this is an interim period, and you will immediately notice that.
Following that, we are going to move on to Q&A to answer your questions. Another logistics, which is very classic, is all our materials, including our financial statements, as well as a management discussion and analysis in the form of an investor report and Dr. Samir's address to shareholders and stakeholders, are all available on our website in addition to Tadawul's ACWA Power page. The last thing, but not least, obviously, we are going to be using forward-looking statements in this call, and therefore, there is a disclaimer in all the materials that you are going to be reviewing and for all the forward-looking statements that we are going to be using today. Without further ado, let me just hand the word over to Dr. Samir. It is all yours, sir.
Thank you. Thank you for joining us today. I would like to begin by providing an update on ACWA Power business performance for the first nine months of 2026. Despite a challenging external environment, our business has continued to demonstrate resilience, supported by the strength of our contracted portfolio, our diversified geographic footprint, and our ability to develop, finance, and operate essential infrastructure at scale. Our priorities remain clear: maintaining safe and reliable operations, converting our development pipeline into long-term contracted assets, and delivering sustainable value to our shareholders. Let me begin with the key highlights of the period. On the development front, we have signed new offtake agreements covering more than 5 GW of power, 6 GWh of battery energy storage, and 600,000 cubic meters per day of water capacity. We also achieved four financial closes, representing SAR 19.2 billion in total investment costs.
These milestones are important because they demonstrate our ability to translate development opportunities into bankable, long-term infrastructure investments. Operationally, we continue to bring new capacity online. We have added 3 GW of power, 2 GWh of battery storage, and 1.2 million cubic meters per day of water capacity. Our operating portfolio continues to perform strong. Power availability, 94%. This includes 98% availability for renewables and an impressive water availability of more than 98%. Safety remains our highest priority. During the period, we recorded 58 million safe hours with a lost time injury rate of 0.012. This is really made up of 97 operating assets and around 29 projects under construction. These results reflect our continued commitment to operation discipline and well-being of our people. We also completed the refinancing of Noor Energy 1, which demonstrated the continued confidence of financial partners in the quality of our assets.
At the same time, we recognize the challenges facing our business. The evolving regional security situation has affected certain facilities in the Middle East, and we continue to assess the operational, contractual, and financial implications of these incidents. Near-term earnings recognition was affected by delays in project milestones, operational disruptions, and timing of acquisitions, divestments, and financial closes. While these factors affect the timing of earnings recognition, our focus remains on the underlying strength of our business and our ability to generate sustainable long-term returns. We are responding with a clear emphasis on safety, operational safety, development portfolio conversion, and organizational effectiveness. High-Performance Organization initiative is also strengthening accountability, cost efficiency, and performance management across our business. Importantly, our growth momentum has continued beyond the reporting period.
In October, we have signed a joint venture agreement with EIG to establish a strategic partnership focused on opportunities in the U.S., opening a significant new avenue for our international expansion. We have also signed in October a water purchase agreement for the Hassyan IWP expansion in Dubai. We are adding approximately 273,000 cubic meters per day of water capacity.
Together, these developments reinforce our confidence in ACWA Power's long-term growth trajectory. Turning to our portfolio, both the scale and the diversification of our business continue to grow. By the end of September, ACWA Power's portfolio comprising 112 assets across 16 countries, with a total asset under management reaching SAR 478 billion . Our contracted power capacity increased to more than 98 GW. Our water portfolio expanded to 9.7 million cubic meters per day. One of the most significant developments has been the rapid expansion of our battery energy storage portfolio.
Our contracted storage capacity has more than doubled from 5.5 GWh to more than 11.5 GWh. This is really important strategically. As renewable energy penetration increases globally, storage will play an increasing critical role in ensuring grid stability, grid flexibility, and reliability. Our growing capabilities in this segment position ACWA Power to address this demand and deliver integrated power solutions at scale worldwide. Renewables today is around 53% of our gross power capacity. Let's look at the maturity of our assets. We now have more than 44 GW of power in operation, 46 GW under construction, and nearly 8 GW in advanced development. In water, 6.9 million cubic meters per day are operational, another 2 million under construction, and 800,000 cubic meters per day in advanced development. Very impressive numbers.
These figures are significant because they illustrate not only the size of our portfolio, but also the substantial capacity that is progressing toward commercial operation. Our priority is not growth for the sake of growth. It is to convert this expanding asset base into reliable, recurring cash flows and substantial sustainable shareholder returns. That remains central to our investment and execution strategy moving forward. Looking ahead, our development pipeline provides strong visibility into future growth. Across our core segments, we continue to see substantial opportunities supported by structural demand for reliable electricity, energy storage, water security, and low-carbon energy solutions. If you recall, we said 98 GW of power asset under management. You can see here that our current active pipeline stands at more than 96 GW of power. We are talking about a huge pipeline of opportunities ahead of us.
Almost 70 GWh of battery storage in the pipeline, more than 5 million cubic meter per day of water in the pipeline, and 1.3 million tons per year of green hydrogen. These figures demonstrate the many opportunities available to ACWA across its markets. However, what is particularly important is our near-term conversion pipeline. Let me tell you a little bit about that. In power, we have close to 7 GW of submitted bids and close to 3 GW of awarded projects pending contract signing. In battery storage, we have 8.5 GWh of submitted bids and more than 1.2 GWh awarded. On the water, it is equally encouraging. Close to 1.5 million cubic meter per day submitted bid and 600,000 cubic meter per day awarded. These expected milestones provide a clear indication of the momentum we are working to sustain. Our approach remains disciplined.
We will continue to focus on the projects that offer attractive long-term fundamentals, strong contractual frameworks, and the potential to generate substantial returns. As we look ahead, three priorities will guide our execution. First, protecting the performance of our operating assets. Second, accelerating the conversion of our development pipeline. Third, maintaining capital discipline as we expand into new markets. With that, I will hand over to Abdulhameed, who will take us through our financial results. Abdulhameed?
Thank you, Dr. Samir. Assalamualaikum, everyone. Good afternoon, good evening. It is a great pleasure to be here with you for the third quarter of the year, and we tried as much as possible this time to make it an efficient and a limited number of slides when it comes to the discussion of the financial performance, where we have included most of the details in the investors report, where we have also shared it in the website, and we are more than happy to take questions in both sections right after this financial update. We will start with the key figures. We had a quite strong operating income for the full nine months of this year with around SAR 2.55 billion .
This is almost 9% lower than the same period of last year, whereas we are almost at par when it comes to the net income for the same period. We are at SAR 1.288 billion. When it comes to during this quarter also, we have been able to complete the dividend distribution for the period of 2025, which is equivalent to SAR 0.46 per share. What we have seen contributing positively to the operating income this period is the acquisitions that we have completed toward the end of last year and beginning of this year. These are mainly the assets that has been acquired in Bahrain, Kuwait, Saudi Arabia. Also, we have seen some of the assets that we have shared with you, the update that they have moved from construction to operation, that they have started contributing positively to the operating income.
In line with what we have mentioned in the beginning and the intro of this session, the geopolitical escalation remains disrupting multiple areas of our basically business streams, including the business development and a bit of the construction and operational assets. As we look forward for the end of the year, we see and we witness pressure on the interest rate increase of rates. We have seen also the impact of slow development to continue toward the end of the year. Most of these opportunities we are looking at, they are actually moving toward 2027. The next quarter, which is actually quarter four, is expected to be slow when it comes to business development. As we look at our full capital allocation, we expect also to be below our expected equity investment for target of this year.
We don't see ourselves investing the full $2 billion-$2.5 billion this year, whereas as mentioned and highlighted by Dr. Samir earlier, the pipeline remain very active and solid, and we are pretty confident that this slowdown and the development today will give us more optionalities, better assets to look at and to explore for the growth in the coming years. When you look at our business model, where it emphasizes the four main pillars, I would like to take a snapshot of the fourth pillar, which is the optimization, and focus on Noor Energy refinancing happening this quarter, or quarter three. This is a SAR 9.7 billion refinancing that the first time in the history of the CSP technology, you achieve a refinancing for a successful project.
Yes, there has been in the past a refinancing of a CSP, but all of them are actually in a challenging position. This is the first time we see a successful CSP technology refinancing, and that comes in a place where the geopolitical escalation is at its highest, and the asset has performed fantastically well as it moved to operation last year. What we have witnessed also that significant amount of this refinancing comes from a cash inflow. It's coming from outside of the region to the region, which is another testimony to not only the long-term and resilience of the region expected for the long term, but also the belief in ACWA Power business model and ability to deliver this project with the 35 years of PPA.
When you look at the bigger picture, actually, we have been able to raise more than SAR 30 billion year-to-date on both financing and refinancing. SAR 10 billion of that basically funding came from inflow outside of the GCC to the GCC. This is definitely a positive view of the international lenders to the region, despite the short-term headwinds that we are facing. Moving quickly to the operating income, we have built up a waterfall to show you the bridge of the same period of last year to this year. If I take you through the details, the first item, which is the SAR 344 million, is specifically to capture the contribution from these existing and new assets that have moved from construction to operation.
Whereas the block number two, it's the acquisitions that we had in the three countries, mainly the Shuaibah IWPP, KSA, and basically the portfolio we acquired between Bahrain and Kuwait. The similar period of last year, we had quite basically the settlements for Noor III Morocco project, and that settlement has impacted us negatively here when you compare it for the same period, which is the item number four here, which is around SAR 326 million. Whereas we see item number three is linked to the low development progress and low construction management fees that has been captured this year compared to the similar period of last year. Again, a big part of that, we believe it's a timing impact that we believe that we can capture this project as they are still alive and active and in discussion with the different off-takers we are working with.
The last item is around SAR 88 million. It's mainly related to some additional provision we took this year compared to the same period of last year. Moving quickly to the net income waterfall. Again, when you compare it to the same period of last year, we witnessed there were impairment losses that was recognized of around SAR 230 million last year that has been considered one-off, and this is not included this period. When it comes to the SAR 92 million, it's mainly basically a non-controlling interest and contribution of the insurance settlement that has been recorded for the same period of 2025. We have witnessed higher exchange rate losses. This is mainly a P&L loss, not a cash loss for the assets in Morocco.
We have also witnessed a lower operating income as described in the previous slide of around SAR 245 million. This brings us to around SAR 1.2 billion of net income, and there was just a small adjustment for this period, and brings the adjusted net income to SAR 1.29 billion. we have included in the investors report a detailed table showing the adjustment that has arrived to the SAR 1.297 billion. We will pause here, and we welcome any question related to the financials, the investors report, and the presentation. Over to you, Ozgur. Thank you.
Thank you, Abdulhameed, and Dr. Samir as well. I think Carla is going to now manage all of us for the Q&A. Carla, it is over to you, please.
Thank you. We will now begin the Q&A session. If you would like to ask a question and have joined the call via Zoom, please press the raise hand button on your screen. Alternatively, you can use the Q&A chat box that is available on your screen. If you are joining us on the phone lines, please press star followed by one on your telephone keypad. When preparing to ask your question, please ensure that your line is unmuted locally. We will take our first question from the phone lines from Julia Faro with Morgan Stanley. Julia, please go ahead.
It is related to the announcement for the U.S. How do you see potential returns there, and what is the expected ramp-up on the announced value? Thank you.
Thank you for the question. Listen, you are probably familiar, we are not talking about specific returns of our projects or market, let alone U.S. spec- talking for returns in the U.S. is too early. However, I would like to assure you that we have very stringent investment policies and principles, and U.S.A. is not going to be different when it comes to evaluation of specific opportunities that we are going to be bringing as and when we are ready in front of the market.
Thank you.
Thank you.
Thank you. The next question comes here from Zoom from Prateek Bhatnagar. Please state your company name and proceed with your question.
Thanks. Prateek from Jefferies. I have a couple of questions. The first question is on capital recycling. Could you let us know the status on that? You said you are planning to group some of the projects and then do capital recycling for them together. Could you give some color on that? That is number one. The second question is on the power prices. The power prices globally are set to kind of expected to increase because of higher demand from AI and data centers. Is ACWA planning to take higher exposure to merchant power prices so that it can benefit from that? Thanks.
Yeah. Anna, I can take the first question, and maybe part of the second, and feel free also from Dubai if you would like to complement. When it comes to the capital recycling, you are absolutely right. We are progressing well on these capital recyclings. We are actually in active recycling of one portfolio, small portfolio of three assets, and another basically one on a single asset. We were expecting, to be honest, that we will close them toward the end of the year, but now I think with the current market environment, it will be basically shifted to early 2027. That is one part of the capital recycling.
Having said that, given the size of the portfolio, and today you are talking about 112 assets, we are embedding even a bigger recycling program over the next five years, and we are definitely going to see that more and more active as we shift these assets from construction to operation. We have witnessed actually and learned from the past that usually investors are very interested to enter these assets either before financial close, which is like at early development stage, or one year almost after the operation. Whereas that period of basically construction period, nobody is looking at these assets. So if you look at our portfolio next year, you are talking about almost 50 assets out of the 112 will be under construction during this period.
But that is just to give you kind of an outlook on, yes, maybe it is, we are slowly engaged in the capital recycling, but we do believe that over the long term, you will see us more and more active. Similar to the refinancings, it starts one every two to three years. Today, we are doing three to four refinancings every year. For example, this month, we finished the third refinancing, and you have seen on average we are doing three to four refinancings. For the power, maybe I will start with an answer from my side. If you have seen the Saudi market, just to pick up an example, there was an announcement on increasing the tariffs on the power and water, and you have seen that ACWA Power did not announce any material impact to ACWA Power because of the increase of these prices.
The reason is that most of our assets are actually built and designed on a contracted capacity for a long-term contracts. Except for any one asset in Turkey and maybe a few assets in China subject to short-term renewal contracts, the rest are very much fixed contracted capacity. That is why the impact on the increase of the power price is not significant for us when it comes to the existing portfolio. Maybe for the future, and specifically you touched upon AI, this is mainly in the U.S., so I will really hand it over to maybe Dr. Samir or Ozgur from Dubai if you would like to add anything to this specific answer.
Thanks, Abdulhameed. Definitely still our strategy really to rely heavily on the long-term supply agreements with limited exposure to the merchant volume. There is really no doubt about it, as you mentioned, the world, the power market in the whole world is at an inflection point with the accelerating demand coming from data centers, from AI, from electrification, industrial growth. We are definitely looking into the opportunities, especially now with the entering the U.S. market. Can we really participate in some of that upside? Not just supplying, really getting tariff on the power we supply, maybe on the final product. Can we really have some of that upside? We are looking into this, especially in the U.S. market.
Thank you. Just as a reminder that if you would like to ask a question, you can use the raise hand button if you are on Zoom. Alternatively, you can utilize the Q&A chat box to submit a written question, and if you are on the phone lines, it is star one on your telephone keypad. Our next question is from the phone lines from Anna Antonova with JPM organ.
Yes. Good afternoon, gentlemen. Thank you for the presentation. Anna Antonova from JP Morgan. Just two questions from our side. First, with the current geopolitical developments, could you please comment what is the status of the NEOM green hydrogen project? Are you expecting any delays to the commissioning, or is it still on line to start commercial operations early next year? That is my first question.
Okay.
Okay. I will take the first question, if you allow me. When it comes to NEOM, basically we are currently at 97% project completion. Commissioning is going on. The expectation, basically energization and production ramp-up will be happening throughout 2027, next year. Around 8,000- 9,000 people currently at the job site. Very, very exciting. I was there recently, and it is just a very impressive facility when you really see 4 GW of renewable power. You see the power island, the ammonia, the jetty. It is coming together, and we are excited to get the production ramped up in 2027.
Understood. Thank you so much. My second question is maybe for Abdulhameed. Could you please comment on the following? In the investor reporting, I see that you had two financial closes during Q3, and one of them is Rabigh 2 expansion. Could you please comment whether in Q3 results there was a contribution from some of the fees associated with this financial close in Q3 results?
Thank you, Anna. Yes, there was. Not significant, very small, but yes, there was for Rabigh.
Okay, understood. Because based on your disclosure to Tadawul, the financial close for this project was on October 1st. Do we understand correctly that means you have some flexibility in front-loading some of the fees associated with financial closes of projects?
Correct. We disclosed, and you are actually thanks very much for highlighting the details. You are right that the disclosure came into Tadawul on the 1st of October, but we have received the certificate of completion of the financial close a few days ahead. There is a bit of administrative kind of slowdown by the time you get the certificate from the agent that the financial close has been achieved to the project company, disclosing the full financial close to Tadawul. Our announcement is correct on the 1st of October, but the effective date actually was a few days before that. That is where we were able to book very small portion of actually the development income of specifically this project on the third quarter. We usually don't disclose the numbers, but I can tell you much less than even SAR 50 million.
That is very clear.
Sorry?
Anna has just disconnected, so I will go to the next question. The next question is a written question from Anup Fernandez. The first question is, could you please talk a bit about the major challenges in executing projects in this region? Where are the biggest constraints today?
I think we mentioned maybe we have 46 GW of power basically under construction today. Definitely a good part of that is also happening in the region that is really impacted with the regional conflict. Definitely there are challenges that we are dealing with, but I can really tell you that there are lots of positive energy now in basically coordinating between the OEMs, the EPC contractors, ACWA Power, and the other investors basically on these projects with the off-takers in the region basically. Now we see positive momentum where some are acknowledging the force majeure, acknowledging the challenges to the cost and the schedule, and we are trying to really resolve this to the best of all parties involved. The major impact really definitely supply chain is definitely getting a lot more expensive than used to because of the regional conflict.
But again, we really have high-quality EPC contracts, and we are trying to mitigate the majority of this risk without impacting too much the schedule and the overall cost of the project.
Thank you. The second question is, how have capital costs changed in the solar PV space over the past year or so? In the past, we have seen very low levelized tariffs on PV projects. Are those levels behind us with the rise in commodity prices and cost of capital? If yes, by what magnitude has the LCOE moved up?
I do not want to be really too. Abdulhameed, you want to take that?
No, no, please go ahead. I can complement.
I mean, I do not really want to be specific and say what is the increase in the tariff like for PV, but definitely the supply chain, the cost of material like the PV modules, they did go up. So definitely the tariff today, that mean it is at a higher percentage than the projects that were a year or two years ago. Again, we are talking to the off-takers, and that is basically being reflected in our contractual arrangements between, for these projects.
Thank you.
Yes. Maybe I would like to complement as well. On top of the logistics, also the finance costs have significantly increased, and specifically in the project related to the GCC, we have seen insurance cost, transportation cost has increased. Actually, if you reflect on all of that, this is one of the main reasons why there has been a slowdown in development, because as these tariffs come into a new reality of adjusting up, some of these off-takers, some of these developers will slow down their development. They will be slowing down in terms of awarding or submitting these projects for a period of between 6 to 12 months or 6 to 18 months. Once the prices neutralize, the geopolitical escalations go down, and basically the cycles go down, that is where you see a more active pipeline of projects come into the market. It is a cycle.
We have seen both the upside of the cycle and the downside of the cycle. But we believe, and for ACWA Power, we have been able to continue progressing in both cycles, ups and downs.
Thank you. Just as a final reminder that to ask a question, please use the raise hand button if you have joined us here on Zoom. You can also use the Q&A chat box to submit your written question. If you have joined us on the phone, please press star followed by one on your telephone keypad. We have a follow-up from Prateek. Please go ahead.
Thanks. Prateek again from Jefferies. I have a follow-up. Your parent net debt by parent operating cash flows, that increased slightly in the first half. Internally, when you look at the metric, is there a ceiling there that you would not like to breach and you will look for alternate sources of funding? Thanks.
Sorry, the line was not very clear. You are saying which ceiling you are talking about? What was dropping or increasing?
Leverage. Parent net debt to parent operating cash flow, that leverage increased to 6.6 times in the first half. Is there an internal ceiling you have which you do not want to breach?
Yeah. There is maybe two components to the way that we monitor leverage. One component is mainly related to our financial institution, which is the lenders, that basically these covenants are not being shared or presented here. The second key metrics for us to monitor is the, as you rightly highlighted, net debt to POCF. When it comes to our long-term target, we are always trying as much as possible to keep it below the 6x, 7x multiplier. Definitely, as we are working in multiple fronts with different stakeholders, including credit rating agencies, where we would like to make sure that in case such a ceiling or such a ratio goes above that, let's say, threshold, we activate certain mechanisms to go below that again in a specific period of time.
That could include additional divestments, issuance of hybrid or perpetual bonds, slowing down on equity deployment, which is mainly through leverage, and other activities as well. Yes, we have definitely that metrics. We continue to monitor it, and that is why actually, maybe not in the quarterly report we are sharing it in the presentation, but every six months, which is the half year and the full year, we are showing the leverage ratio, and we are trying to give an update on how we are trying to reduce it below the threshold desired.
Thank you. As we have no further questions in the queue, I will hand back over to Ozgur for any final comments.
Thank you, Carla. Thank you everyone who is at the other end of the lines and their computers. It was a pleasure to be with you again. Thanks for the questions. Thanks for listening. As usual, if you have any further questions, please, you know where to find us. As usual, we are going to get back to you as soon as possible. Thank you once again. Have a good day, have a good evening, wherever you are.
Thank you.
Thank you, everyone. This concludes today's call. You may now disconnect. Have a good rest of your day.