Aris Mining Corporation (TSX:ARIS)
Canada flag Canada · Delayed Price · Currency is CAD
24.95
+0.36 (1.46%)
Oct 2, 2026, 4:00 PM EST
← View all transcripts

Mining Forum Americas 2026

Sep 28, 2026

Summary

Four gold projects are advancing, with Segovia and Marmato ramping up to 500,000 ounces annual production and Toroparu and Soto Norte progressing toward development. Strong community integration and new government support in Colombia are driving growth and reducing risk.

Neil Woodyer
Chair and CEO, Aris Mining

Okay. Thanks very much, John. Good morning, ladies and gentlemen. A quick overview of Aris Mining as we are today after about five years. We are two operating mines in Colombia, Segovia and Marmato. We have the pre-feasibility finished on the project, Soto Norte, getting ourselves ready to submit for environmental approval. In Guyana, we have Toroparu, where we should complete the pre-feasibility this quarter. In total, our reserves are 9.3 million ounces, and that, of course, does not include Toroparu yet. Our resources are nearly 22 million ounces. Gold production in 2006 was 257,000. This year, we're guiding it forward. When we have Segovia and Marmato both expanded, we should have a steady state production of about 500,000 ounces a year. Of course, if we brought the other two online, we'd be up to approximately 1 million.

When we look at these four assets, we can see the two, Segovia and Marmato, who are now in the process. Segovia, we've already expanded it. We're ramping it up. Ramp-up should be complete during the course of next year, hopefully by the half year. It takes time to do the underground development, but it also takes longer to bring our small miners along in parallel with us. We should be there by about halfway through next year. Marmato is scheduled for its first gold pour the last quarter of this year. We will have it fully operational by about February, March, and then it'll be able to ramp up to its 200,000 ounces. As I say, those bring us to 500,000 ounces. Toroparu, pre-feasibility complete. We're in the licensing process now with the government.

Hopefully, in the early part of next year, we can make a construction decision there. Soto Norte, the famous or infamous Soto Norte, we have completely redesigned. We have the pre-feasibility study for it, and we have finished all the work we have to do on environmental measurement and recording, and we're about to be in a position now, particularly with the change of government in Colombia, to be able to submit that fairly shortly. One of the interesting things about these assets is that Segovia, which has been operating for about 120 years. Marmato has a mine life of over 20 years. Toroparu has mine life of over 20 years, as does Soto Norte. I think I'm the only asset around here in Aris who has a mine life of less than 20 years.

We have fairly good grade assets, and we have long life assets, two in operation and two we're putting together over the next few years to bring us up to the infamous and famous 1 million ounces. Looking a little bit more at Segovia. Proven and probable reserves of 1.5, but as I say, it's been operating for about 120 years. Also, about 30%-35% of mining comes from our small mining partners, which I'll discuss later. They are not included in our reserve base. Resources, 3.6 million. Production, up towards 300,000 ounces, and a steady state will be 300,000 ounces. All-in Sustaining Cost margin over the last 12 months of just over $600 million. Excitingly, the expansion of Marmato. Marmato Historic was a small flotation plant of about 20,000-25,000 ounces a year.

In our tenement above it, there were a lot of small illegal miners. Below it, there's a large industrial deposit. We're now building the CIP plant. That plant should be ready for its first gold pour later this year, before the end of the year. We have already got the ramp down to it, so we have access to ore, and we are stockpiling ore ready for that. It'll take us a couple of months into next year to get it fully operational, and then I would hope by the latter part of the year, we're up to about 200,000 ounces from Marmato at the flotation plant and the CIP plant. Additionally, through an arbitration that we solved last year with the government, we also are working with the mining agency to formalize miners above us.

If we can bring that material down to Marmato as well, we have a flotation capability of dealing with it. That may give us, over a couple of years' time, another 30,000- 50,000 ounces. So we'll have over 200,000 ounces from Marmato in a year or so's time. Stepping outside Colombia, we have the Toroparu project, which we acquired, which was part of the acquisition of Gran Colombia. When we acquired it, the first thing we did was we stopped production, construction at that time. We weren't sure of the numbers. We weren't sure of the resources. We redid the resources at, I think, about half of them. We are finishing now. Before Christmas, we will have finished a PEA. Sorry, pre-feasibility. The PEA which we finished was 5 million ounces, 235,000 ounces a year, over 20-year mine life.

Initial capital of about $820 million, which I suspect may have gone up a little bit as things do since the last couple of years. We'll find out in a week or so's time. It had at $3,000, I think it was, gold, an NPV of 25%. That project will be finished and ready to go. From a licensing point of view, we already have the environment license. We have applied for the construction license, and we are partway through the discussions with the government. They have reviewed everything. I would hope by about the same time we finish the pre-feasibility, we also get the approvals from the government, which should put us in a position to make a construction decision early next year. The fourth project, Soto Norte. I don't know if people know the history of this.

This was a very large gold project that Eike Batista put together many years ago. Mubadala lent them about $1.2 billion. Spent goodness knows what on it. We acquired a 25% interest three or four years ago and took over the management of the project. We rapidly came to the conclusion that the project that was being built was just too large, too big, too risky, too big a footprint, and quite honestly, too expensive for anybody to handle. It included such things as a 7.5 km between tunnels in the Andes, and the anticipation was a tunnel boring machine would be taken up there and would be quite a nightmare. We just came to the conclusion it wasn't a practical project. We reduced its scale to about the scale that we're operating now at Segovia.

We reshaped its mine plan, so we weren't taking every ounce out. We had a sensible mine plan in terms of cash generation. In fact, our model showed that we would be generating more cash in the first five years than the large project. Very importantly, the project had been rejected by the communities. A great deal of protest against it. In preparation for this, what we did is we set about taking the mayors and community leaders from Soto Norte area to Segovia to sit them down with our small miners who operate in partnership with us, and we help as to how it would work, the project. So we now have community support rather than community opposition.

As I say, the other thing we did, we changed the whole footprint of the project and are now in a position to be able to submit that shortly. We are also planning to build 120% of the capacity that we need for the project. The extra 20% we're building to allow the small miners to have a clean processing facility. So we're working with our local communities, we're working the way the government wants us to work. It's a project now that is getting a great deal of acceptance. Hopefully, as I say, the approval process can start, and we can then look to see about construction. A well-defined project. I spoke previously about our contracting miner partners. This is a model we built up over the last few years, starting at Segovia, picking up for where Gran Colombia Gold Corp. had started.

We've now formalized in total about 4,000 miners to work with us. I'm not sure you know the background. Very briefly. In Colombia, 85% of the gold is produced by small miners, most of which are old families, old traditional miners, some are the bad guys. 85%, this is 350,000 small informal miners in the country. We have formalized about 4,000 so far, and if you follow our plans through, which we're working through with the Ministry of Labour, if we include Soto Norte, we can get to about 8,000 formalized miners. This not only means that they have social security, they pay their taxes, but they now have a great deal of protection from society as to how they operate. They do work with us as businessmen. We help them design their mine plans. We help them form their legal structures.

We help them in health and safety. Sometimes we lend them money. We pay them cash when they deliver the material based upon the tons, the grade, and the gold price. So this gives us a tremendous community support. It's this process that we followed at Segovia, we've introduced to Marmato very successfully, and we carry on doing so, which is why we got the arbitration with the government. We'll also carry on doing it at Soto Norte, which is why the climate has now changed to support us. So we have a clear path from our two mines now to 500,000 ounces, followed by a clear path to potentially 1 million ounces. I think there's one thing to say when you look at the Aris stock. We are significantly discounted, I think primarily for two reasons.

The first is the stage of development, which to some extent is inevitable. The second is undoubtedly risk associated with Colombia. Colombia has not been a mining-friendly country. When exploration development was advancing in Chile and Peru, we had all the bad guys and all the bad movies going on in Colombia. After that, the environmentalists took over. After that, the left wing took over. It has been a progressive series of steps like that. Therefore, the opportunity is quite extraordinary. The present government has stated and has demonstrated that they now support mining. Since the election in the middle of August, we have had the Minister of Mines, the Minister of Environment, the Minister of Labor, and their vice ministers all visit Segovia and Marmato.

We are getting tremendous support, and I think the industry will be getting tremendous support to such an extent I start to worry about how difficult it is going to be to get geologists, because all the big guys are going to fly in there and do a lot of exploration. The market is getting tighter for us in that point of view. The government is certainly supporting us and I think will also support us in Soto Norte. They take the attitude, mining is one of the things they have to put right in the country from a social, small miner point of view, and also economically. It will continue to get a very big push. I think over time, that will not only give us the assets we want. That Colombian discount will disappear as the other discount disappears. That is where we stand today.

I know I have run out too quickly, but nevertheless, that is the story. That is the company as is today.

Moderator

Thank you very much, Neil. We do have time for a few questions. Okay, Neil, thank you for the update on Toroparu. It looks like it is moving along nicely. As you approach a construction decision next year, waiting for some milestones from the government, how is the workforce in Guyana, and would you expect a ramp-up of labor to be somewhat uneventful, or any comments on that? Thank you.

Neil Woodyer
Chair and CEO, Aris Mining

It's not going to be easy. It is not a mining country. It's a country that's seen huge investment in oil and gas recently. It's a country that lacks infrastructure, and we are out there. We're about 180 km away. We have to build a long road. We will be doing two things. We've already started putting a management team together. We've already started talking to EPCM potential construction help. Some of the other mining companies have brought labor in from other countries. We could perhaps bring labor in from Colombia. We have enough guys who can drive trucks around Colombia. It is going to be one of the bigger issues to handle. If we plan now, we're in a good position to do it. But yes, it is an issue.

Moderator

Okay. Thank you. Looking at Marmato, you're coming up to a key milestone at year-end, declaring commercial production, then you've got a steady ramp-up through next year. Investors are always thinking, well, what's next? Is there any scope to potentially maybe increase the mill throughput even further than you already have done, or any other levers that you can pull to enhance the economics, say, in 2028 and beyond?

Neil Woodyer
Chair and CEO, Aris Mining

Well, we've got some amazing milestones between now and the end of the year. We've got, I think, proving that Toroparu has got its license. We've got the pre-feasibility in Toroparu. We've got, I think, seeing the government taking Soto Norte seriously. We have the first gold pour. We have Segovia ramp up. All those things between now and the end of the year, and there's only three months. But we are calmly confident that we'll achieve this year's milestones. When we look forward to next year, we see the ramp-up of Segovia. Again, Marmato. Hopefully, we've started Toroparu and hopefully, not long afterwards, we're in a position where Soto Norte can be taken forward as well.

Moderator

Okay.

Neil Woodyer
Chair and CEO, Aris Mining

That'll keep us quite busy for a little bit of time, I think.

Moderator

Very catalyst rich. I'll just poll the audience again. We have a new administration in Colombia as of this summer. I'm wondering if you've had a chance to meet with them or what the read-through might be on your operations in Soto Norte with this new administration.

Neil Woodyer
Chair and CEO, Aris Mining

Last week, I met three ministers, three vice ministers, and three heads of agencies. I think that gives a very clear indication of their intent. Now let's see if they are capable. They have obviously decided what they were doing when they were in opposition. They are not working things out now. They have a very clear plan, and they would appear to be implementing it. I can't say more than that.

Moderator

Okay.

Neil Woodyer
Chair and CEO, Aris Mining

They're very determined people.

Moderator

Okay. What would the read-through be to Soto Norte? Maybe if you could just talk about a potential timeline for the next milestones at Soto Norte. Is there the potential that you might even be developing two projects at once?

Neil Woodyer
Chair and CEO, Aris Mining

I honestly don't know the timeline with Soto Norte. We have to go through the six-week consultation progress. Maybe the soonest we put it is three or four months, but roundabout give or take at the end of the year. How long does it take? A project normally takes 18 months in Colombia. Soto Norte has been at it for 10 years, on the other extreme. These people will not take 18 months.

Moderator

Okay.

Neil Woodyer
Chair and CEO, Aris Mining

Okay? If all being well, yes, we would be in a situation, if we were able to do so, of building two at the same time. Let me just address that, if I may. We do actually have the financial resources to do that, but today we do not have the human resources to do that. If it was coming nearby and it was looking serious, we would have a lot of work to do organizing ourselves to do it.

Moderator

Okay.

Neil Woodyer
Chair and CEO, Aris Mining

Honest answer.

Moderator

Okay. Thank you very much. Thank you, Neil Woodyer, Chair and Chief Executive Officer of Aris Mining. Thank you.