Thank you for standing by. This is the conference operator. Welcome to the Endeavour Silver conference call and webcast to discuss the Pitarrilla feasibility study. As a reminder, all participants are in listen-only mode, and the conference is being recorded. After the presentation, there will be an opportunity to ask questions. To join the question queue, you may press star then one on your telephone keypad. Should you need assistance during the conference call, you may reach an operator by pressing star then zero. I would now like to turn the conference over to Allison Pettit, Vice President, Investor Relations. Please go ahead.
Thank you, Ashia, and good morning, everyone. Joining me on the call today is Dan Dickson, Endeavour Silver's Chief Executive Officer. Dan will walk us through the results of the feasibility study, and then the rest of our management team will join us for the Q&A. With us today are Elizabeth Senez, our Chief Financial Officer, Luis Castro, our Chief Operating Officer, Dale Mah, our Vice President of Corporate Development, and Gord Bussieres, our Vice President of Projects. Before we get started, I ask that you view the cautionary language regarding forward-looking statements and the risk factors pertaining to these statements in both the news release and the presentation, along with our MD&A and financial statements, which are available on our website at edrsilver.com. Following Dan's formal remarks, we will open the call for questions. Now, over to Dan.
Thank you, Allison, and good morning, everyone. Thank you for joining us today. Yesterday marked another important milestone for Endeavour Silver with the release of the Pitarrilla feasibility study. Over the past several years, we've been focusing on transforming Endeavour from a producer operating relatively short-life mines into a company with large-scale, longer-life, and lower-cost assets. Terronera was an important first step in that transformation.
The acquisition of Kolpa was another step, and Pitarrilla represents the next major opportunity. The feasibility study outlines an 18-year underground mine with a processing capacity of 4,000 tons per day, producing silver-bearing lead and zinc concentrates. Located in Durango, Mexico, Pitarrilla benefits from an established mining jurisdiction, existing infrastructure, and a substantial mineral resource that provides opportunities well beyond the current mine plan. What excites us most is the combination of mine life, operating costs, and significant exposure to silver.
We believe Pitarrilla has the potential to become another cornerstone asset for Endeavour, an important driver of the long-term production and cash flow. Turning to slide five, let's look at the key economic results from the feasibility study. All figures here are in U.S. dollars, and our base case uses a silver price of $50 per ounce, with lead and zinc prices of approximately $2,028 and $2,734 per ton, respectively. At these prices, Pitarrilla generates an after-tax NPV of $736 million, using a 5% discount rate and an after-tax IRR of 16.4%. The initial capital estimate is $585 million. Over the 18-year mine life, the project's expected to generate approximately $2.4 billion in operating cash flow and $1.7 billion in free cash flow. Perhaps most importantly, silver accounts for approximately 73% of the project's revenue.
Producing both lead and zinc concentrates, Pitarrilla is fundamentally a silver project, providing shareholders with substantial exposure to silver price over a long mine life. While these results are attractive on their own, the feasibility study only considers a portion of Pitarrilla's broader mineral resource. We see significant opportunities to further enhance the value and potentially extend the life of the operation.
Slide six here summarizes the study. The mine is designed to process approximately 4,000 tons per day, producing an average of 5.4 million ounces of silver annually, together with about 13,000 tons of lead and 29,000 tons of zinc. With the initial capital estimate of $585 million, which includes $65 million of contingency, with an additional $119 million of sustaining capital over the life of the mine. One of the attractive features of Pitarrilla is the efficiency of the underground mine design.
The geometry of the deposit allows us to access a substantial amount of ore with relatively limited underground development, helping to both manage capital requirements and operating costs. The project also benefits from an established infrastructure footprint, including multiple year-round access roads, existing power infrastructure, access to water, and established camp facilities. Together, these advantages provide a strong foundation for project development and help minimize the infrastructure investment required to bring Pitarrilla into production.
Moving to slide seven, one of the most attractive characteristics of Pitarrilla is the geometry of the deposit and the resulting efficiencies of the mine design. The feasibility study contemplates 16.7 km of primary underground development over the mine life, providing access to more than 25 million tons of ore. To put that in perspective, that is approximately 1,500 tons of ore for every meter of primary development. This is a significant advantage for an underground mine.
The mineralization is relatively concentrated and accessible through a common ramp system, limiting the amount of infrastructure required to access the deposit. The initial development requirements are all relatively modest, with approximately 5.4 km planned during the initial years. The balance of the development is spread over the remaining mine life, allowing future development to be supported by operating cash flow.
The mining method is primarily transverse and longitudinal long-hole stoping, a well-established underground mining approach. The combination of this mining method, the deposit geometry, and the ability to phase development throughout the mine life contributes to the project's capital efficiency and provides flexibility in mine sequencing. Slide eight illustrates the geology supporting the underground mine design. The primary focus of the feasibility mine plan is the sulfide mineralization within Pitarrilla's manto and its associated feeder structures.
Existing underground development is situated above the manto, providing a foundation for future mine access and additional exploration. Importantly, these feeder structures extend to depth and remain prospective beyond the current mine plan. This gives us confidence in the underground mine development strategy while preserving opportunities to expand the resource and potentially extend the mine life through additional drilling.
Turning to the production profile on slide nine, the feasibility study outlines approximately 25 million tons of ore processed over an 18-year mine life, generating an estimated 135 million silver equivalent ounces. Average annual production is 7.5 million silver equivalent ounces, with production reaching as high as 8.7 million ounces. What we particularly like about this profile is its consistency. Following the initial ramp-up, the mine is designed to operate at approximately 4,000 tons per day, supporting a relatively stable production profile over the majority of the project life.
Life of mine grades average 133 g per ton silver, 0.96% lead, and 2.27% zinc. This combination of scale, mine life, and relative consistent production profile gives us a strong foundation for a long-term operating and financial planning. Moving to the processing flow sheet on slide 10, the feasibility study incorporates conventional crushing, grinding, and flotation circuit, similar to our build at Terronera. Ore will be crushed and then processed through the SAG and ball milling, followed by flotation to produce separate silver-bearing lead and zinc concentrates. The feasibility study estimates life of mine recoveries of approximately 91% for silver, 96% for lead, and 91% for zinc. These are attractive recoveries and contribute significantly to the project's operating margins. The design also incorporates concentrate thickening and filtration, along with filtered tailings and dry stack storage.
Overall, we believe the conventional processing approach provides a sound technical foundation for the project and for operations. Slide 11 provides a breakdown of the project's operating cost structure. Total life of mine operating costs are estimated at $109 per ton of ore processed. Mining and processing account for the largest components of these costs at approximately $44 for mining and $31 per ton for processing. The remaining costs include G&A expenditures, treatment and refining charges, royalties, and special mining duty. Importantly, the lead and zinc byproducts provide meaningful revenue credits, bringing life of mine cash costs to $12.66 per payable ounce of silver, with mine site all-in sustaining costs being $15.06 per ounce of silver.
These costs position Pitarrilla to generate attractive margins under the feasibility study base case price assumptions while providing a measure of resiliency during weaker silver price environments. Slide 12 demonstrates what we believe is one of Pitarrilla's most attractive characteristics, its economic resilience across a wide range of silver prices. At our base case silver price of $50, the project generates a net after-tax NPV of $736 million and an internal rate of 16.4%. For every $5 per ounce increase in silver price, the project's net present value increases by roughly $157 million. At $65 silver, that translates into an after-tax NPV of approximately $1.2 billion and an IRR north of 22%. But equally important is what happens at lower silver prices. Even at $30 per ounce, the study generates a positive NPV of approximately $109 million and a 7% IRR.
That is particularly meaningful for a project with an 18-year mine life. We know commodity prices fluctuate over time, and we want assets that can withstand weaker markets while providing substantial exposure to stronger ones. Pitarrilla offers that combination of resiliency and leverage to silver price. Turning to slide 13, I'll provide an update on permitting, engineering, and the work currently underway to advance Pitarrilla.
One of the advantages of this project is that a number of the important permits are already in place, including approvals related to the build of the process plant, underground mine development, explosives, water use and discharge, and land use changes. The principal outstanding approval is the tailings storage facility, together with certain amendments and extensions necessary to reflect the final project design.
While that permitting process advances, we're continuing to work on areas that can improve the project readiness and reduce execution risk ahead of a future construction decision. We've engaged an engineering firm and progressing basic and detailed engineering. We're also working with Mexican Federal Electricity Commission, CFE, on the required power line upgrades and substation engineering. Power infrastructure represents $77 million in initial capital estimate. So this is an important component of the overall development plan currently scheduled to be operational when construction is complete. Our objective is to continue advancing engineering, procurement planning, and project preparation while the remaining permits are being secured. Ultimately, the timing of a full construction decision will be linked to obtaining the necessary tailings storage facility approval, expected sometime in 2027.
We're fortunate to be advancing Pitarrilla from a position of financial strength, and our current expectation is to fund the majority of the construction through existing cash resources on hand and cash flow from our operating mines. We'll provide additional detail on planned 2027 activities and expenditures when we release our annual guidance in January of 2027. Moving to slide 14, I want to spend a moment discussing what we believe is one of the most exciting aspects of Pitarrilla, the opportunities that extend beyond the current feasibility study. While the study outlines an 18-year mine life, it only incorporates a portion of the broader mineral resource, and we see several opportunities to potentially extend mine life and enhance the project economics. The first is resource conversion and mine life extension.
The current mine plan is based off 150 gram per ton silver equivalent cutoff grade, effectively $36 of silver. With sustained higher metal prices, we see opportunities to evaluate lower cutoff grades and potentially incorporate additional material into future mine plans. Targeted drilling could also support conversion of additional inferred mineral resources into higher confidence categories, providing further opportunities to extend the production profile.
The second is metallurgical evaluation of the transition zone. There are approximately 18.4 million tons of transition zone material resources that have been excluded from the current feasibility study mine plan. Further metallurgical work may identify opportunities to economically recover metals from this material and potentially incorporate a portion into future mine plans. What's particularly attractive is that some of this material may be accessible using infrastructure contemplated in the current development plan, potentially eliminating the additional underground development required.
A third opportunity is exploration. The feeder structures remain open at depth, and we have additional exploration targets across the property. There is potential to identify additional mineralization that could either extend mine life or improve the overall production profile. And finally, there is the longer-term open pit opportunity. By initially developing the underground sulfide resources, we're preserving the option to evaluate the broader mineral resource, including the potential for future open pit development of the oxides. None of these opportunities are assumed in the current feasibility study, but collectively, they demonstrate why we believe Pitarrilla has the potential to be a much longer asset life than the 18 years currently outlined. When we look at the scale of the broader resource and the opportunities still available to us, we believe there is a potential for Pitarrilla to operate well beyond the current mine plan.
Our long-term vision is to continue evaluating opportunities that could ultimately support a 30 or even a 40-year underground operation. Before we open up to Q&A, photos on this slide, on slide 17, give you a sense of the property today, along with a vision of what it would look like in the future. They show the plant site on the left and the future tailings site on the right, set in the terrain of the Sierra Madre foothills. Over the past several years, we've been focused on building a company with larger scale, longer life, and lower-cost operations. Terronera was an important step in that transformation, and we believe Pitarrilla represents the next opportunity. Again, the feasibility study outlines an 18-year mine life with attractive operating costs, substantial silver exposure, and the potential to generate significant cash flow over its operating life.
Equally important, we're advancing a project with existing infrastructure, several key permits in place, and substantial opportunities to extend beyond the current mine plan. Our immediate focus is on advancing engineering, progressing the outstanding approvals, and preparing the project for the next stage of development. We believe Pitarrilla has the potential to become our next cornerstone asset for Endeavour Silver, strengthen our production profile, and create meaningful long-term value for our shareholders. Thank you again for joining us today, and with that, operator, we're ready to take questions.
To join the question queue, you may press star then one on your telephone keypad. You will hear a tone acknowledging your request. If you are using a speakerphone, please pick up your handset before pressing any keys. To withdraw your question, please press star then two. The first question comes from Kevin O'Halloran with BMO Capital Markets. Please go ahead.
Hey, Dan and team. Congrats on the good study here. Can you maybe to start just remind us of the work you've done so far, like the infrastructure currently on site and the degree of development work that you've done to date? And then maybe roughly how much capital has gone into that infrastructure?
Yeah, very good question. Thanks, Kevin O'Halloran. Ultimately, we acquired this project May of 2022, and there was an existing adit in place that was about 1 km, almost one and a third in place, and it needed a little bit of work and cleanup and support. Ultimately now, we've pushed that out at about 2.5 km. We have a vent raise in. We're sitting right on top of the manto. The plan this year was to continue to push that ramp and ultimately down. For next year, we ultimately want to test that manto and ultimately go right through it, and then start going below and go through some of the feeder structures.
We've already gone through the feeder structures on top of the manto, which has given us a lot of information and understanding kind of the complexity of those veins and ultimately how the feeder structures characteristics and how they work with the manto. So it gave us a lot of valuable information and obviously gives us one of our key ramps for the mine plan that currently exists. We have an operating fleet on site, which is about $7 million worth of equipment. We've accumulated that over the last three years. Then ultimately, when we bought Pitarrilla, there was $145 million already invested in the project. A lot of that was obviously exploration work and evaluation work done by SSR, including the permitting of the plant and the underground.
From our standpoint, we've cleared the area where the camp's going to go and the plant's going to go, and that was all part of our budget this year, which was approximately $65 million that we were going to spend. We're not going to be close to that. We're spending probably closer to $40 million this year in 2026. Again, we've done a lot of engineering work on the camp. We expect to start that camp relatively shortly and improve that. Currently, we have about 80 beds at site. The camp that we need for construction is upwards of 500. I think we have space to go up to 800 beds in our current design. We'll continue pushing on that. Obviously, over the last year, we've done a lot of work with CFE and evaluated power opportunities, whether that's self-generation or coming off the grid.
Obviously, there's a lot of advantage of coming off the grid, and there's a lot of potential there to continue to reduce that cost, $77 million that you'll see in that news release. But we have advanced this relatively strong. It's just coming down to that tailings permit that we've done work on for the last year and continue to have good dialogue with the state of Durango and trying to push that through, and as I say, get it sometime in 2027.
Great. Appreciate that. That's really helpful. In terms of the construction, the tailings permit was going to be my next question. Anything outstanding there that you're seeing, or is it just waiting for that to make its way through the permitting process with the government? Once you get that, what would be that construction timeline that you'd be looking to start construction, and then how long is that construction period?
Yeah, I mean, ultimately, it's been back and forth. Again, we're at the state level for that tailings dam. It's a dry stack tailings facility, so it's not as environmentally sensitive as what a conventional tailings would be. We feel, and I think really across the industry, dry stack's much easier to permit. We've had great dialogue with the state of Durango. As I say, it's really a waiting period for us, ultimately answering questions when the state comes back with further questions. Again, we've got a team that's got a very good relationship with the state of Durango, SEMARNAT. Again, done everything we can to put ourselves in a strong position for receiving that permit sometime in 2027.
As far as the build period, in the feasibility study, there's a three-year period for the build. Our expectation, hopefully we can do that better, but we did just go through a build at Terronera that took longer than the two and a half years that we had originally contemplated. So we feel like we have sufficient contingency in our build time, and we've built that into our schedule. But it's currently a three-year period, and if we can get our permit in 2027, we can have production from Pitarrilla in 2030.
Got it. Thanks. Just last question from me. Looks like the grade is quite consistent, which gives you a nice consistent production profile over the years. Is there any potential to adjust sequencing to maybe bring forward some higher grades, or is it really just consistent grade across the deposit that's driving that?
Yeah, the manto's very consistent, and ultimately, half our production's coming out of that manto and half's coming from the veins. So the ability to kind of go high grade and improve project economics at the front end of the mine plan proves to be difficult because of the characteristics of the manto and where we sit on those veins. Ultimately, there's very little development into that manto. As I say, we're sitting right on top of it. So, with the transverse long-hole stoping, it doesn't give us as much flexibility to go after high-grade portions. It's really been, it's a volume story and trying to get those tons out as efficiently as possible. There's not enough variation in that manto to selectively then go back to other areas. It's just not efficient.
Got it. That makes sense. That's it for me. Appreciate it, Dan, and congrats again.
Thanks for the questions, Kevin.
The next question comes from Alex Terentiew with National Bank. Please go ahead.
Hey, guys. Yeah, congrats on a good study here. Couple questions from me. Apologies, you may have kind of alluded to some of this already, but just between now and when you do get the tailings storage facility permit, which, from what I understand here, seems to be the kind of the key thing you're waiting for, can you just maybe walk me through the investments and what you're going to be doing at the project and where you're spending the money, the rest of this year and into next year as you wait for that permit?
Yeah. I won't get into huge detail on exact dollars because we're going to finalize that. Obviously, we've seen the price environment and cash flows from existing operations change drastically here over the last two weeks. But there's some very key things that we can do to continue to drive this forward. First and foremost is the power line and CFE. Ultimately, we're coming through a town called Rodeo, and I think it's about 87 km, and there's an existing power line there already, Alex, that comes up through site. Ultimately, we need to upgrade that to have sufficient power for the project. We're working closely with CFE. We're working closely with other groups in Mexico that also require that power. Something that we feel like we can execute. We've given a nice contingency that it won't be operational until we complete construction.
So ultimately, during construction, we'd be on diesel gen sets. So that's first and foremost. We have our construction camp that we've engineered and we've gone out for procurement. We can execute that and hopefully have that ready for next year. Road access. There's multiple accesses into Pitarrilla. One of the key items for larger equipment, ball mills, SAG mills, et cetera, is a river that we've got to pass. Inside our feasibility study, there's a small bridge, and we've been working on permits for those bridges, and I believe we have those permits, so it'd be starting on that and just moving that engineering forward.
Then obviously, there's the completing basic engineering and detail engineering with the engineering firm that we've engaged. So there's lots that we can do between now and effectively mid-year next year for when we expect to get that permit. Additionally, with the fleet that we have on site, continue to push down that mine development. So we've got to go through as a management team of where our cash flows are, what we're willing to spend, and we'll come out with that in January of 2027, what our expenditures plan will be for next year.
All right. No, that sounds good. On the build, I mean, you guys, as you say, you're just kind of coming off Terronera. Plan to use a lot of the same guys. Maybe just remind me too, kind of your own project team. If most of those people stuck around with you, or how are you looking about lining up people to build this one?
Yeah. Don Gray, who is very important to us, was our COO and built mines all over the world. He retired. We brought in Gord, who's on this call, sitting down in Mexico right now, Gord Bussieres. He's got 40 years of experience building mines. Then below Don, there's a number of people that were with our company at the end of the build of Terronera, over two-year part of that build. I wouldn't say we have all of them. We have some of them.
I couldn't even tell you a percentage. But we have a team that's been very integrated with the actual feasibility study. So we have a study that we feel like we can actually execute. Now we need to refine it and ultimately optimize it. So Gord and his team have been very involved with it. We learned a lot from building Terronera as an institutional group through procurement, logistics, et cetera, that I feel like we're in a lot better position building Pitarrilla than we were at Terronera. So we're very excited and really trying to get that permit so we can make a decision on Pitarrilla.
Okay, great. Kind of what I wanted to hear. Last question, metallurgy. Numbers in report actually looked pretty good, better than I was expecting. Any more work to be done there on that end or any risks that you need to Any more tests you need to do to confirm the numbers?
No, we feel very good about the metallurgy on the sulfides. There's been a lot of work that's been done on oxides. I touched on a bit the transition zone from the oxides down to the sulfides. Like I say, there's 18 million tons of mineralization in the transition zone. Of course, some of that's going to be more oxide, some of that's going to be more sulfide. Our plan would be to start working on that and continue metallurgical work on that transition zone. Obviously, we have no intention immediately to go after the oxides. A lot of people are familiar with Pitarrilla and talked about the metallurgical challenges with regards to the oxide portion of Pitarrilla. Again, that's an open pit story.
SSR did a lot of metallurgical work and unlocked a lot of that, but we always felt there was more work needed. Again, our focus will be on that transition zone and seeing how much of that 18 million tons can come into our mine plan. If we can get recoveries of 75%-80% from areas in the transition zone, we fully expect to try to bring that in to the underground mine because it sits right above the manto. So you've got development that goes to the manto. Rather than just spiraling down, now you're spiraling up, and you access a lot of ore for very little development.
Good. All right, that's it for me, guys. Thank you.
Thanks for the questions, Alex.
The next question comes from Larry Liu with CIBC. Please go ahead.
Hi, Dan, Libby, Allison. Thanks for taking my question today. I guess, Kevin and Alex in front of me asked a lot of great questions. I will start with a more general one. Can you remind us, what is the reason that drove the change from more of an open pit scenario in the 2012 feasibility study to today's more underground sulfide development strategy? What kind of benefit does it provide Endeavour Silver from this change?
Yeah, sure. I think if we step back at it and when we bought Pitarrilla, silver price was in the teens. A lot of people were familiar as the open pit from SSR, which was an $800 million build at $25 silver back in, like I say, 2012. It had an NPV value 1.2, and ultimately, it supported the 600 million ounces of silver plus lead and zinc in that resource. It is not that we do not believe in that open-pit project. I think we do. Ultimately, it takes a lot more work, a lot of metallurgical work, as I just talked on from the oxide standpoint. And us as a company, us as Endeavour, our expertise is in underground mining. We have knowledge there. It is something we can execute. From a capital standpoint, we feel like we can execute a $585 million project.
It would be very difficult for us to execute a $2 billion open-pit project of that scale. Not saying we take away that optionality, but at the end of the day, we want to focus on something that we think we can execute. And again, starting in 2022 when we acquired it, we had always focused on the underground sulfides, much more easily to manage from, obviously, operational standpoint. The sulfides are a lot easier to float. We get great recoveries on those sulfides, and it is a project that lends itself to positive economics.
So always our thought pattern was always going to be around the underground operation when we acquired it. Obviously, when prices run up to $120 silver, you still think beyond what the underground would be. But I think today, we are showing an 18-year mine life. We envision a 40-year mine life from an underground standpoint without sterilizing the open pit. Again, it's something that we can, as Endeavour, can execute, and it fits very well with our portfolio.
Yeah. Dan, that makes a lot of sense, that's for sure. It's good to see it's very underground-focused right now. But like you talked about earlier, it feeds well to my next question. You talked about the open-pit optionality. How should we look at it? It's more of a further term kind of consideration, or how can we add value to our model if we want to at this point?
Yeah. I mean, obviously, our focus will be getting the underground operation built, and then obviously operating to capacity or nameplate capacity. Once we get into operations and getting steady cash flow, then you take that opportunity and try to extend mine life with further drilling underground, regional exploration to extend that life. But you also have a team start looking at the broader picture and seeing if we can bring the oxides into a mine plan or ultimately into an open pit. That's all There's so many variables that will go into that, Larry. So really, the oxide portion is something that comes in, and the studies start happening after 2031. So 10 years from now is really when you start looking at that broader long-term oxide portion of Pitarrilla.
Got you. Sounds good. Thanks, Dan. I just have one last question. I know earlier you were talking about the timeline, you were talking about investment decision. So, can I ask what type of metrics do you look at when you consider your investment decision? We've seen a lot of volatility within the silver price or within the commodity prices in general. I know you highlighted at today's spot price, about $40 an ounce, you still generate a 12% IRR. What are some metrics you look at that will help you make your investment decisions?
Yeah, there's a lot of metrics. Obviously, NPV, IRR, payback period are your standard ones that we see across the mining space. With a long-lived asset, when you're talking about assets that are going to operate 30, 40 years, those metrics aren't near as important as it would be when we had Terronera and we had a 10-year mine life. There's a lot that goes into it. There's a lot that's beyond the current feasibility study that management takes into consideration to make that decision. Obviously, silver price and metal prices are a key component to that, and the ability to make sure that we can fund the project is also part of all that. I'm not going to box myself into, hey, what type of IRR do we need to see to actually execute this project?
Because again, we're thinking about this from a long-term standpoint and where we see silver and metal prices 10 years from now, 15 years from now, 30 years from now. Again, we see Pitarrilla as a project that we can execute and provide it when we get that tailings dam permit, and there's timelines around permits that you have to make a decision around as well. Again, if we see an environment that we're at today, I think we have a project that we can execute on and that we'll look to construct.
Got you. Yeah, and that makes a lot of sense, Dan. Thanks again for taking my question. Excited to see what's more to come. Thank you.
Thanks, Larry.
Once again, if you have a question, please press star then one. The next question comes from John Tumazos with John Tumazos Independent Research. Please go ahead.
Thank you for taking my question. When the permits and details are all finalized, do you expect to have a military garrison at your site? Some of the other companies ask for that at their sites.
Yeah. John, thanks for the question. I mean, this state of Durango, we operate Guanaceví in Durango. We have an office, our exploration office and support office in Durango, the city. For Pitarrilla, we're about three and a half, four hours north of Durango, a little bit to the east. There's very little violence in that area, if any, at this point in time. Our preference would not to be having a military presence. We don't think we need one. Currently, we have close to 80 people on site. We've had anywhere from 20 to 80 people for the last three years with no incidents. So our expectation is no.
Super. Thank you.
Thanks for the question, John.
This concludes the question and answer session. I would like to turn the conference back over to Dan Dickson for any closing remarks. Please go ahead.
Thanks, operator. I want to thank everybody for joining today. Endeavour is very excited about the feasibility study and what's to come. We're very proud of how we've executed on Terronera in 2026. We've executed very well on Kolpa with the expansion there this year and executing on our operating standpoint. We feel Pitarrilla is the next evolution of our company to long-lived, low-cost assets that really repositions ourselves in the silver space. Again, thanks a lot for listening today, and have a good day.
This brings to an end today's conference call. You may disconnect your lines. Thank you for participating, and have a great weekend.