Study update

Nov 10, 2026

Summary

The updated CV5 study adds tantalum, cuts OPEX by ~20% and sets AISC at $480/t, with underground-first mining lifting early concentrate output. FID is targeted by end-2027; a combined CV5/CV13 PEA was expected before year-end 2026.

Nicholas Read
Managing Director and Principal, Read Corporate

Well, a very good morning to everyone in Australia, and good evening to those who have joined us from the Northern Hemisphere. My name's Nicholas Read from Read Corporate, and on behalf of PMET Resources, a very warm welcome to this investor conference call and webcast on the updated CV5 feasibility study for the Shaakichiuwaanaan lithium project in Canada. Thank you very much for joining us at short notice. It's my great pleasure to introduce PMET's President, CEO, and Managing Director, Ken Brinsden, to lead this morning's call. He's joining us from Sydney. Joining him online are the company's Chief Operating Officer, Fred Mercier-Langevin, and the company's Head of Investor Relations, Olivier Caza-Lapointe, who are joining us from Canada. All participants are in a listen-only mode. There will be a presentation first, followed by a question and answer session.

First for teleconference participants, followed by online questions from those on the webcast. For those on the teleconference, if you wish to ask a question, you'll need to press the star key followed by the number one on your telephone keypad. In the interest of efficient time management, we ask that you restrict your questions to two at a time. If you do have follow-up questions, please press the star key again, followed by the number one to re-enter the question queue. For those on the webcast, if you would like to ask a question, please click the live Q&A tab located on the right-hand side of the webinar screen. Well, with that introduction out of the way, it's now my great pleasure to hand over to Ken Brinsden. Ken, congratulations on a fantastic result this morning. Please take us through the updated presentation and feasibility study.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Fantastic, Nick. Thank you. Much appreciated. Good morning, good day, good evening to everyone that's joining around the world. We're really happy to have you participate in the call and also pleased to be presenting what we think is another fantastic demonstration of the significance of the Shaakichiuwaanaan project and its importance for the critical minerals world. Joining me on the call, Frédéric Mercier-Langevin. Many of you will have met Fred. Between him and his team, they've used just over the last 12 months about as effectively as you could hope for to continue to optimize our Shaakichiuwaanaan project, and now with the updated feasibility study inclusive of lithium and tantalum.

The tantalum sub-component is, of course, something that we'll come back to in a lot more detail during the discussion this morning, and I hope you come to appreciate through that, and our look forward just how significant these co-products are to the future of the project. It really is a key point of difference as we deliver the Shaakichiuwaanaan journey. Let's get into it. There's a lot of materials. For those of you that might be coming to our project, relatively cold. We're in north-central Quebec. The Shaakichiuwaanaan project is in amongst key infrastructure, even though it's in a remote location. We're adjacent to the enormous La Grande 4 hydroelectric dam, a massive power station for renewable and low-cost power, and only approximately 40 km away as the crow flies.

It's just one of 11 dams of the significant infrastructure that exists in north-central Québec, and it makes for an enormous infrastructure base for our Shaakichiuwaanaan project to draw from. It's also important that you understand that we are not just a lithium project. The confluence of amazing geology, including lithium, caesium, and tantalum occurrence at Shaakichiuwaanaan, is a really important difference in the expectations around our Shaakichiuwaanaan project. It's just incredible geology. As such, it affords a huge opportunity to continue to add value to the project, and our updated feasibility study, in fact, will demonstrate that. If I leave nothing else with you today, that would be one of the keys. I'm going to slip through a few of the slides. The entire presentation materials are available online. They've been recently lodged.

We're going to focus on those areas where it's really key importance to share information but also to open up the lines to Q&A. I'm sure there's some fantastic questions to come. Amongst our team, there is incredible capability. People that have been involved in financing significant mines, people that have been involved in building and commissioning significant mines, and building supply chains. I'm really proud of being able to work with the team and will continue to do so, even though this morning we've announced a CEO and board succession plan. The board is intensely focused on what it's going to take to continue to deliver the Shaakichiuwaanaan project. Whilst I have an important part to play in both current activities and future activities, I'm not the key executive that's ultimately going to be cutting the ribbon upon commissioning at the project.

Of course, I'll continue to be involved, and it's absolutely my pleasure to be so, but there will be another key CEO in place. Today, we've announced that that recruitment process is underway. We look forward to being able to introduce another key executive who will take the project through the next phase, detailed engineering, the financing initiatives, the balance of the discussions with the Cree and mine authorization, and of course, the build and commissioning. I'm sure there are key executives out there who would continue to take pleasure in the delivery of the project as the key executive. For my part, I will still be involved, initially as executive chair and then ultimately as non-executive chair. I bet there's every chance there'll be more questions, and we'll come back to this subject, I'm sure, during the Q&A period.

Amongst the feasibility, key to understanding is the inclusion of tantalum. Tantalum is a very, very significant co-product amongst our Shaakichiuwaanaan production portfolio. Yes, it's a big lithium mine, but it's also a big tantalum mine. Fred and the team have done an amazing job optimizing the delivery strategy, and that starts with underground first. That's important because it delivers the higher grade and actually, ultimately, higher production first as compared to the October 2025 feasibility study. The outcome, amazing economics around our project, and even if you consider outside price increasing, it's still a vastly optimized project, and we've got a few slides that focus on that. Very, very low cost, another key.

In fact, approximately 20% of cost stripped out of the delivery inside the project from an OPEX point of view, with CAPEX being largely maintained and similar to the 2025 Feasibility Study in both stage one and stage two. What does that look like? Well, an incredible project delivering amazing returns, and a lot of which is contributed to by the introduction of the tantalite containing tantalum in the form of the co-product. The co-products we will come back to because they are a key point of difference, and it is one of the reasons why all-in sustaining costs are now only $480 a ton. In terms of the ability of the project to deliver cash flow, it is incredible, and in fact, incredible from the early years of the project, in part because of those key optimizations that we have delivered.

When you compare the prior Feasibility Study, the reference on this slide is the October 2025 Feasibility Study being compared on a like-for-like basis to the updated Feasibility Study. If the 2026 Feasibility Study was priced at the same price as 2025, it would still be a vastly improved product and project outcome, and that is because of significant study improvements. Fred will outline them shortly, and of course, coming back again to the introduction of the tantalite co-product credit that delivers substantial value. I think it is also worthwhile reminding everyone that whilst tantalite is already a very important co-product credit, it is priced at $120 per pound of contained tantalite on the long-run pricing outcome. Today's spot price is effectively double that at $240 per pound of contained tantalite as per Shanghai Metals Market in the last couple of days.

What that means is, if you ran the economics and you passed through the spot price, you would see even higher credit from the tantalite, in effect, double, with the price effectively doubling compared to the spot price. It really is an important contribution, and for that matter, there is more to come because our project will continue to grow economically with the introduction of the caesium co-product credit in the upcoming PEA. In the end, that creates a really competitive cost position. With all-in sustaining costs some $500 a ton, you are likely well down into the lowest cost quartile, and it is certainly where Shaakichiuwaanaan deserves to be. We make the point of showing how the project has changed in this slide from the 2025 Feasibility Study to the updated Feasibility Study, a big leap down the cost curve.

Our expectation is that it does not stop there, and that will become more obvious once we print the updated Preliminary Economic Assessment, the PEA, or scoping study for the broader project once we introduce the caesium co-product as well. And the tantalite, doubling down, we are going to be significant in scale. I will come back and discuss tantalite markets in a little bit more detail, but it is important that you understand that we are not only a large-scale and effectively high-grade project in lithium, we are very, very similar in the tantalite category. For the non-artisanal supply, that largely describes production from Central Africa, we will likely become, if not the largest, one of the largest non-artisanal suppliers, and of course, off a North American base.

There is a lot to appreciate about the contribution that the Shaakichiuwaanaan project will make to the tantalite world. That is it for introductory comments. I'm now going to hand over to Fred, who's done a power of work, he and his team, in delivering some massive optimizations for the project. So over to you, Fred.

Frédéric Mercier-Langevin
COO, PMET Resources

Good. Thank you, Ken. And yeah, very excited to be here to be able to share and give you a glimpse, I guess, into the hard work that went behind the numbers that we're seeing on the screen today. A lot of hard work that's been done by the team, and really commending the team on the work that's been done. So basically, the work that we've done over the last year or so really has been focusing on a few items. First one, tantalum, right out of the gate, we knew that there was potential there, so we investigated a bit more. That panned out to be above our expectations.

But really from the get-go, we really wanted to have another crack at trying to get the underground first, and have access to the Nova Zone to really leverage the higher grade that we see there, which is really a differentiating factor for Shaakichiuwaanaan. And we actually were able, through some clever redesigning, to access that ore faster and then make the underground first strategy possible. But we didn't stop there. With the DMS, we basically have an opportunity to redesign the whole DMS now that we were going with the underground first, have a re-look at it, both the quantities and the flow sheet itself of processing. So we ended up with a simplified flow sheet, better recovery, and a smaller footprint. Also looked at the mining parameters, which ultimately reduced our mining costs and reduced our dilution.

Again, I guess increasing the grade that the DMS is seeing and just making the outcome that much better. Also, with this, I guess, review from the ground up of our mining plan, we had the opportunity to firm up some of the assumptions that went behind some of the key project elements, and do some more work to try and de-risk those and understand better, and reduce the uncertainty. Concentrate transport certainly is one of those, and also the power line, where we validated a number of key assumptions and ultimately validated that the outcome was right. So next slide, please, Ken. So starting with the Nova Zone, Nova Zone really is a key differentiator for Shaakichiuwaanaan, and with 12.6 million tons at 2.04% lithium content as mined, so that's fully diluted. It really is a compelling, interesting story there.

You have also a, I guess, a close-up view of certain stopes that we have, like the top 10 stopes in the Nova zone, with a lot of those being above 2.5%, again, as mined. There is a number of compelling reasons to go after the underground first. Owing to that very high-grade value and nature and intrinsically higher margins, we really wanted to have another go at trying to go for it first. We went back to the drawing board on the underground design, actually redesigned the entire ramp and the mining sequence for the underground to be able to start the underground from the get-go, with the Nova zone contributing to production. Next slide, please. You can see a view here looking north of the ramp.

You can see the new design of the ramp that actually accesses some of the Nova zone in red, faster than the original design would have been able to do. Some clever redesign of that ramp allowed us to do that. A few key things that we have also done with the underground since we were re-looking at it is to challenge maybe some of the assumptions as well in the design, where we ended up recutting the level spacing in the whole mining sequence. That brought some added benefits where by standardizing the level spacing, we have ended up with overall less development for the same tonnage, so less cost, basically 16% less development. Overall, a lower cost of underground mining, for basically the same amount of tons mined, making our already good margins underground even that much better.

By recutting some of the assumptions as well, we were able to challenge some of the dilution assumptions that went into last year's design and were able to come up with mitigation plans for dilution and ended up reducing our dilution. That again increased the head grade and made the, I guess, the business case for going underground first that much more compelling. Next slide. That slide basically highlights what the key benefit here is, and ultimately it is more concentrate by front-loading the grade in the early years, even with the fact that we are actually processing less tons. We are actually processing 2.2 million tons per annum with a much tighter plant design, but still producing overall on a cumulative, I guess, number, 436,000 tons of spodumene concentrate, so 45% improvement over the previous plant over the first three years.

That with less tons processed, like I was mentioning earlier. That is an outstanding result. Just a bit of a note here, we also had to do a little bit of clever design with the starter pit to supplement the underground production. You see that orange bar on the first year of production of the updated FS. That is a starter pit that we basically just mine a few hundred thousand tons for, just to supplement the ramp-up of the DMS in year one. After that, we idle the operations for that open pit until the phase two development starts. That pit is located within the western extremity of the bigger pit, and it is respecting a 60-meter standoff distance from the lake. Basically, no lake disturbance involved with the excavation of that pit.

We can proceed with mining in the first year, supplement the mill feed, and then idle that pit for a couple of years thereafter. Next slide. On the processing side of things, going with the underground first also generated a few other opportunities that we were very keen to exploit. One of them was getting the paste fill plant from the get-go actually helped us rationalize the equipment within the plant and actually go with removing the regrind system and removing altogether the secondary DMS recovery system and going to a single-stage DMS now, which ended up reducing the plant footprint and a lower OPEX on the processing side. Just want to highlight as well the already extensive testwork that we had done, we validated further with the ApplePick results that we published earlier this year.

We were actually able to challenge some of our recovery assumptions in that updated FS and increased our overall life of mine recovery by about 0.8%, so close to 70% now. So very happy with that result. What that does as well is when you combine with the higher grades in the early years coming from the Nova Zone, it means that we're achieving pretty exceptional recovery in the first few years with an average of 74% lithia recovery for the first three years of operations, owing to the higher grade coming from the Nova Zone. This is also, I'd like to highlight, despite a conservative discount that was applied to our recovery curve versus what the actual testwork results are saying. Next slide. As Ken mentioned, tantalum has exceeded our expectations.

Due to a combination of the overall grade of the resource, plus the pretty good recoveries that we're able to achieve in the range of 51% in the first phase and 48% in the second phase, we actually generate a pretty good quantity of concentrate itself. But the fact that we're also able to upgrade that concentrate to a secondary con at 20% means that we're able to capture the full value of the contained Ta₂O₅ within a tantalite concentrate is valued as a function of that contained Ta₂O₅. So that ends up yielding a very, very significant credit of more than $100 per ton to our spodumene production. That's at half the spot price, as Ken was mentioning.

Just a key reminder here as well, PMET Resources owns 100% of our tantalum rights, so basically we're going to be benefiting from that tantalum credit to the fullest.

I guess the last point I would make on the technical side of things is throughout this whole optimization process, we were very mindful of the ongoing ESIA process around our project and being sure that all of our optimizations would either be neutral or positive to the project's environmental impacts, just to ensure that we would basically be able to integrate those changes seamlessly into our ESIA process, but also to have better outcomes to show to our partners, the Cree partners that are going to be helping us along the way here, that we have a massively improved project on the financial side of things, but we also have an overall better project for the community that's going to be hosting our project. That was front and center as we went through that work. Ken, back to you.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Thank you very much, Fred, and congratulations to you and the team for the effort that was put in in the last 12 months. That was clearly time well spent. The compliance feasibility study of October last year set the scene for a great lithium project, and now because of the work that you and the team have achieved, we now have an even better project inclusive of tantalum. Well done. Well done. Relatively speaking, I'll skip through the financial slides. I guess key points are to understand that in phase one project CAPEX, we're effectively the same result as we were in the prior feasibility study.

You should understand that that's no mean feat, and again, full credit to Fred and the BBA team, because of course there has been background inflationary pressure, and for that matter, that the underground first development strategy actually starts to throw the effect of more capital at you, including the tantalite process recovery circuit. Combination of those things and the further optimizations that have been achieved inside the project meant that we have held our CAPEX outcome. That is effectively the same and true for the second stage or phase two of the project, the stage two processing capacity to take us to 5.1 million tons per annum and 800,000 tons per annum of spodumene concentrate. Obviously, the stage two project will be subject to further discussion and/or optimization.

At this stage, we show the project being commissioned and ramping up in stage two during year four of the proposed project in this feasibility study. But as I said, it'll be subject to another round of customer engagement and demand condition assessment, and of course, price assessment at the time. What does it mean? It's quite similar through phase one and phase two. We have a competitive capital cost outcome. Sitting at around CAD 2,000 a ton in respect of a 5.5% concentrate and approximately 800,000 ton per annum of spodumene concentrate capacity. That's actually very similar on average to other projects under consideration, actually around the world, let alone Canada and Australia. We sit around the average, in which case there is really nothing to be feared in respect of actually both stages, whether it's stage one or stage two production capacity.

We've already touched on the all-in sustaining costs, but they now sit at $480 a ton, a really competitive position. That belies, I guess, a lot of work that's gone on inside the project because there has been cost escalation, especially in the area of logistics. I'll come back to discuss the logistics more fulsomely. But the competitive advantage, the real competitive advantage that Shaakichiuwaanaan has is at site. With site cash operating costs of $212 per ton of spodumene concentrate, if not the lowest, it would be very, very low on the cost curve for site costs. That's because we have relatively low-cost renewable power. We have the high grade from underground, and then longer term, lower strip ratio in open pit.

It's DMS-only processing, and you cannot discount how much it costs to grind your spodumene to bug dust and then recover it with reagents via a flotation methodology. Not only does that make your operation harder to achieve recovery of spodumene concentrate, I can tell you that from experience, it also costs a lot more money. DMS only is clearly the cheapest form of processing cost that you can achieve in a lithium operation. Lastly, the significant tantalum co-product credit. Over $100 a ton per ton of spodumene concentrate. But again, I'll just make the point, that's at $120 per pound of contained tantalite. The spot price today is double that, at over $240 per pound of contained tantalite. Where do we give some of that cost advantage back? Well, of course, it's in logistics.

We have an 830 km truck haul and nominally 1,000 km on rail. Yes, the logistics costs are higher, but because of the ultra-competitive site costs, the sum of the two in cash operating cost terms is very low. What's happened in logistics? Well, clearly the team has done a lot of work in the last 12 months, including a deep level of contractor engagement for providers of these types of services, whether it's haulage by truck, transshipping at Matagami to load rail. In that assessment and the effect of the diesel cost and contributing inflationary pressure, yes, there has been a cost escalation. It's come from different locations, but some of it's also to do with scope.

Slightly smaller trucks, slightly smaller rail cars, a little bit of additional cost in respect of transshipping, and the combination of all those things means we have seen an increase in the logistics cost. But clearly, that is more than offset by the time you think about the combination of all costs. Site costs, very low. Yes, slightly higher logistics costs, but the outcome, the net outcome, still very low cash costs, very low all-in sustaining costs. By the time you run all that through your models, you have an incredible project for a nominally $1,750 per ton of spodumene concentrate at 5.5%. You get an incredible project. Very, very fast paybacks, just over two and a half years, very high rates of return, and obviously very strong cash flow.

But that would be equally true even if you accepted that the broker consensus was right at approximately $1,400 a ton, or even if you took the spot price today, let's say approximately $1,100 a ton on an SC 5.5 basis. When it's all said and done, it is a very strong project, mainly because we've continued to optimize the site works and the site activity costs, but we've also delivered a strong tantalite byproduct credit. The project, like all projects in the mining world, is going to be sensitive to those things that impact revenue, exchange rate, product price, and then from a site-based point of view, feed grade and process recovery. As Fred outlined, we remain confident in each of those initiatives with plenty of flexibility at the site to deal with both contributing grade and strong recoveries from our DMS plant.

To see the project built, of course, we need to finance the mine. The team has been very, very busy. Natacha and the team have been deeply engaged with the key pools of capital that are ultimately going, we believe, likely to support our project. Of course, that includes government entities. I'm sure you appreciate that Canada is very interested in further diversifying its supply chains, and that leads to strong engagement with people like EDC in Canada, the Export Development Bank, the Canada Infrastructure Bank, the Canada Growth Fund, the subsets of those funds, the strategic minerals funds. We are getting very, very strong traction with government as we think about supporting our project financing. Secondly, we have deep engagement going on with strategics in the supply chain.

I think you're familiar with some of our existing relationships, Volkswagen Group, PowerCo, more recently, Mitsui and others are all key advocates and strongly supportive of our project. Ultimately, we think they'll be key contributors to the financing of our mine. In Canada, everyone is going to be focused on mine authorization, and that's true, but we are a long way down the process now. We're over four years in with, we think, approximately 12 months to go. To describe that process, we show on this slide the work that's already been undertaken. We're now in the Q&A period that exists both at a federal level and within the province of Québec and the engagement that occurs with the Cree.

That Q&A period, we hope, will be settled over approximately the next three or four months, in which case we're on track for the purpose of mine authorization by the end of 2027. We are getting good engagement in respect of the progress of our project approvals, and that's particularly true at the federal level, where Q&A, original submissions and then subsequent Q&A has been progressing in very, very good order. The team tells me that they've never seen the bureaucracy move as quickly as they are today, and I think that's a function of Canada's interest in key critical minerals projects, but also more broadly, building sovereign supply chains for critical minerals like that exist in our project. Clearly, the Cree, and especially the community at Chisasibi, are ultimately a very, very important stakeholder in the progress of our project.

During July this year, we signed a letter of intent with the Cree Nation of Chisasibi. The letter of intent was a plan, effectively, to work towards the execution of our IBA, and it established what we consider to be a really strong and innovative process for engagement, such that we have key participation in local procurement, training and skills development, the environment, and of course, discussion about transportation, with each of those work packs being jointly developed in consultation with the community in Chisasibi and the Cree Nation Government, working alongside PMET Resources. So, a sophisticated process in response to timely development of the IBA outcome. Ultimately, we would expect the IBA to be ready for execution at about the same time as our mine authorization, being late next year. But with Shaakichiuwaanaan, there is more to come.

We have not finished delivering on the value that we believe the Shaakichiuwaanaan project brings to the table. So we are very much looking forward to the upcoming CV13/CV5 Preliminary Economic Assessment, which we expect to have completed before the end of the year. And what it does is it brings on the discovery at CV13 and the very high-grade lithium, caesium, tantalum resource that exists there, and it effectively plugs it into what we have already described as the base case for the Feasibility Study at CV5. So it is the combination of the two, CV5 plus CV13, and it realizes the economic potential in lithium, tantalum, and caesium. We are very much looking forward to showing to people why this differentiates Shaakichiuwaanaan from just about every other lithium or hard rock lithium project globally.

It really is a key point of distinction, and we cannot wait to show people why that is so important to the future of our project, lithium, caesium, and tantalum. We are continuing to work on the bulk sample. Again, Fred and the team and the authorizations team are flat out seeing that one progress. We believe this is an important part of our project development because it will have the effect of bringing forward key infrastructure and a large sample to support all the work that we have underway in the supply chain, whether that is engagement with key customers and future customers and/or the chemical work that exists around lithium and tantalum, but maybe even also caesium, because we know there is some caesium in CV5.

We have already flagged that in the public domain, and the bulk sample can help us tease out that caesium occurrence in CV5 in more detail.

Lots of engagement going on within the supply chain, and that is true in lithium, caesium, and tantalum. I think you are familiar with our relationship with Koch in the caesium world. There is still a lot of discussion going on there. Same thing is true in lithium, and we are reasonably advanced now in tantalum because of the significance of our production capacity. We have key groups around the world that are watching very closely our development profile, and for that matter, the product profile of our tantalite concentrate. So we think we can make more of that over time, and it might yet be that both tantalum and caesium are ultimately part of securing financing in respect of our project. So more work to be done there, but nonetheless, the team deeply engaged with industry downstream.

Key partners are already participating in our project, and I would challenge anyone on the call to find a lithium project around the world that has that portfolio of partners that we have. They are all interested in our project, and there are others, because of its known significance to the future of the lithium, caesium, and tantalum world. We fully expect to be able to build on that consortium over time. Again, we have some longer-run projects that ultimately add to the value at Shaakichiuwaanaan. On-site conversion, in partnership with the, or potential partnership with Mitsui, the Microwave Chemical Co., Ltd. in Japan, and via Primero Group Engineers and their ALi process. We consider the future in electric calcination at site, creating a materially higher value product, in the case of the ALi process, a battery-grade lithium carbonate.

Once you have done that completely changes the game in respect of logistics, and of course, you are then hauling a materially smaller volume of higher value product. That is an important one to us that we keep working on. La Grande Alliance and the concept that there is more regional connectivity to come. Again, these are very important projects to us, and we keep an eye on their progress and, where required, support their progress. One of the more important ones there is the so-called Renard Extension Road, which would connect the Trans-Taiga Highway and cut approximately 300 km off our truck haul. Those projects are equally important to us. Then another one that Fred and I hold dear is the potential in plant modularization being part of the future delivery strategy.

We have some early contractor engagement underway, considering a modularization model with a view to lowering the cost of the facilities, but also potentially partially accelerating their construction timeframe. These are all important projects. Now, on the lithium market, I am not going to dwell on it too much. Suffice to say, this is a demand story, and everyone is underestimating demand. A lot of that is going to be motivated by energy storage, which is now a huge phenomenon, and in my view, will continue to get bigger. By the way, just as a little anecdote, when you are thinking about the price of spodumene concentrate, it is often healthy to remind yourself of history. When we delivered the Pilbara Minerals feasibility study in 2016, just 10 years ago, the long-run price that was put into that feasibility model was $537 a ton. Let that soak in.

$537 a ton. Here we are now, debating whether the long-run price should be between $1,500 and $2,000 a ton, pretty much 10 years later. I think that tells you a lot about how much is being underestimated in respect of demand, and the fact that there is every chance we are still underestimating demand, and therefore, the cost of supply that is required to support that demand growth. Again, it was only 10 years ago, the long-run price was considered $537 a ton. I know it sounds like a joke now, but that was real. Within those 10 years, we all got it wrong. Therefore, are we concerned about whether the long-run price is going to be between $1,500 and $2,000 or even higher? Well, I would argue nobody should be concerned about that.

That is what is going to be required to sustain the industry. Lastly, on tantalum. The tantalum price has been on an almighty run because of a big step-up in demand, and that demand is motivated by the AI build-out. AI is a significant consumer of tantalum products, and it finds its way into lots of things that are being rapidly built out in that area. Chip manufacturing, capacitor construction, thin film, heat distribution on chips is another example that is worth highlighting. That has meant there is a structural shift in demand, and that is why people are approaching PMET Resources about the potential to be part of our story. That is because demand, but especially stable Western supply that avoids all the challenges that exist in the artisanal world in Central Africa, that is a big deal.

That is why we are confident that Shaakichiuwaanaan will ultimately be a very important part of the tantalum story. I am going to leave our presentation materials there, but would really appreciate what I am sure are going to be some very, very good questions. Why do not I hand back to Nicholas, who can guide us through the Q&A period? Thank you. Nicholas, over to you.

Nicholas Read
Managing Director and Principal, Read Corporate

Thanks very much, Ken. A very comprehensive presentation. We will move into Q&A now. We are going to deal with teleconference questions first, and we have got three on there. I will just hand over to Ash from Chorus Call. Ash, could you please take us through the teleconference list?

Operator

Thank you. If you wish to ask a question, please press star one on your telephone and wait for your name to be announced. If you wish to cancel your request, please press star two. If you are on a speakerphone, please pick up the handset to ask your question. Your first question on the phones today comes from Austin Yun with Macquarie. Please go ahead.

Austin Yun
Analyst, Macquarie

Yeah. Morning, Ken. Thank you for the update. Just keen to understand, now given the updated feasibility study is released, what are the key milestones from now to the FID, which is targeted by end of calendar year 2027? Understanding you're still going through the environmental permitting process, but any other key events? I'll come back with a second one. Thanks.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yes. Thank you, Austin, and thanks very much for joining. Yeah, to be clear, we now move, having completed the updated feasibility study, we now move into detailed engineering, focusing on the stage one project. That's the first 2.2 million tons of processing capacity, the underground mine, and of course, the tantalite recovery circuit. There's a bit of a mixture of work that contributes there. There's more process testwork, and some of that will be intensely focused on tantalum as well. The detailed engineering supports the FID case, which is obviously what we'd be working through with financiers. We're going to deepen, it's already extensive, but we're going to deepen our engagement with industry downstream in everything, so in lithium, caesium, and tantalum, as we start to think about the balance of the financing initiatives.

In parallel, you're right in so much as mine authorization processes continue. We are quite a way through that process now, Austin, through one round of Q&A, which we expect to be probably the last round with the feds, and, let's say, halfway through round one with Quebec. That is also well advanced. I mentioned it in the presentation materials, we like the idea of the bulk sample being a key contributor to continuing to de-risk the project, so that's an important initiative for us.

Effectively, they all happen in parallel, the IBA development with the Cree and all the consultation that goes on there, the mine authorization process, and lastly, the financing such that we achieve an FID outcome with all three effectively coming together by the end of next year, which in turn would facilitate the commencement of construction and ultimately project commissioning in the second half of 2029. I hope that makes sense, Austin.

Austin Yun
Analyst, Macquarie

Thank you, Ken. You mentioned that you are going to be progressing with the engineering work. I am just keen to understand if you could provide some color on how many stopes are required and how should I think about the required production rate and the development rate to de-risk the phase one production and the production ramp-up? Thank you.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah. I will hand to Fred shortly. He can provide a little bit more detail there. Yeah, so underground first helps with the, obviously, the grade that gets delivered to the stage one processing facility. We target multiple fronts for ultimately what is a total of up to, not always, but up to 2 million tons per annum. Fred, do you want to offer a little bit more detail about the opening up of the underground mine and perhaps the ultimate production strategy?

Frédéric Mercier-Langevin
COO, PMET Resources

Yeah, of course. Ultimately, in the overall, over the entire life of mine, you could think of stoping as being the main contributor to production, of course, where about, I would say, an average of 5,300 tons per day will come from stoping itself, and then with the balance about a bit over 300 coming from development ore, coming from the development and ore. That is what the split looks like. The total output from the underground is going to be in the range of 6,000 tons per day. Albeit in that first year, again, the ramp-up of the underground has to be supplemented by about 700,000 tons of ore from that starter pit I just mentioned. Thereafter, the underground is able to fill that DMS1, so starting from year two, if you will.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, thanks, Fred. Because there is over, there is about 12.5 million tons at over 2%, as mined in the Nova zone. What- deliver to the plant, Austin. I do not know whether you noticed the detail there, but in year two, we are already at 1.7%, and then I think by year three, we are up to about 1.85% lithium being delivered to the stage one facility. We have a lot of flexibility with those high-grade and ultra-high-grade Nova zone stopes, as to what we can do to support and supplement production capacity. Because the grade is so high, it has the benefit of giving you a much higher yield to product, so you process less tons, and actually, your recovery rate is also higher.

On average, it is approximately 70% from DMS, as estimated by the feasibility study, but it is actually higher than that when you feed the higher-grade underground tons.

Austin Yun
Analyst, Macquarie

Thank you, Ken. That's very helpful. I'll pass it on.

Operator

Your next question comes from Zach Krysianowski with Canaccord. Please go ahead.

Zach Krysianowski
Analyst, Canaccord Genuity

Again, thanks for the presentation. Congratulations obviously on the release of your study. I just got two questions. The first one on the CV4, CV5. I noticed in your announcement a couple of days ago, you're talking about the infill drilling there. Could you maybe give a feel for, I guess, what a resource could look like for that and how that might integrate into today's plans and whatnot?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, thanks, Zach. The exploration potential, we've said in our public releases that we believe they're actually connected, so CV4 seems likely to be connected to CV5. We have done some more work in that area, albeit results are yet to come through our recent summer program. So yeah, I guess in general, every expectation that we will connect the two. We previously published an exploration target for the entire project portfolio. Our current resource is 140 million tons, but by the time you look at the entire exploration target, I think it's effectively double that, if not 300 million tons. So, things like the connection between CV4 and CV5, we would hope ultimately, add to that resource base, Zach.

Whether it is there, even out at CV12, and for that matter, the other 20 km kind of west of CV12, we just think this ground has so much more to offer. It is already a spectacular project, but we see surface expression in lots of other locations, in which case we think if you keep exploration drilling going, there is every chance you are going to continue to add to resource.

Zach Krysianowski
Analyst, Canaccord Genuity

Excellent. Yeah, thank you. Appreciate that. The next one, just on offtakes. Obviously, you have mentioned the high-quality suite of partners you have got there, and I see you have got, you said 700,000 ton per annum left uncommitted. Do you have a sort of, I guess, percent targeted for offtake or sort of any updates you can provide on that front?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, it is a key question, isn't it, Zach? Good on you. I think historically when financiers look at your project, they think about something like 70% of your offtake being committed. Now, we have not got to that level of detail in the financing discussion, but I would hazard a guess and say that is going to be roughly what the expectation of the financiers are. I definitely subscribe to the theory that you should leave some offtake free, and that is because, well, it is for a couple of reasons. I guess firstly, there might be leverage in spot pricing outcomes. That could very much be the case, and that was something that we took advantage of in the period of time with Pilbara Minerals and PLS.

But also, every once in a while, you have to test new customers, wherever they are around the world, in which case having some spot cargoes available to be engaging with the potential new customer base is also an important objective. The combination of those things means that I will be looking for the idea that we can keep some free, but in the end, the financiers also have a part to play in some of that discussion.

Zach Krysianowski
Analyst, Canaccord Genuity

Of course. Thank you. Appreciate the time.

Operator

Your next question comes from Max Yerrill with BMO Capital Markets. Please go ahead.

Max Yerrill
Analyst, BMO Capital Markets

Good evening, guys, and good morning. Thanks for taking my question. Understanding now that you are going underground first, you can delay that disturbing the Lake 001. Is there the potential that it is late enough in the mine life that you could supplement some of that open-pit ore with ore from one of the other deposits on the property?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Good on you, Max. Great question. Yeah, absolutely. Fred, over to you. You might want to just offer a few more pieces of context there.

Frédéric Mercier-Langevin
COO, PMET Resources

Yeah, that's for sure that we see CV13 as a key contributor to the next phases of development of the project, and the upcoming PEA will flesh that out. So yeah, as we look to delay some of the open-pit impacts and so on, ultimately what slotting in CV13, say, as a phase two development scenario would do is further delay that and extend the mine life. That's the way that we kind of see it right now.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

It's a great question.

Frédéric Mercier-Langevin
COO, PMET Resources

Yeah, looking forward to it.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, exactly. And CV13 affords a great opportunity, not just because of the reason you've highlighted there about the potential in deferring Lake 1 impacts. It's also incredibly high grade. It's very high grade in everything, lithium, caesium, and tantalum. So, when we think about supplementing future production to the entire portfolio, including CV5 and CV13, it represents another important leap forward, which is why we're very much looking forward to the upcoming PEA later this year.

Max Yerrill
Analyst, BMO Capital Markets

Okay, great. Then maybe one more quick from me. For the tantalum, it is 20% concentrate grade targeted in the study. What is the grade that you need to achieve in order to be classified as a secondary concentrate, and then how does that line up with some of the testwork you guys have done on the tantalum front?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, spot on, Max. Prices quoted for tantalite around the world, it depends on where you are delivering as to how the price is quoted. You will see 25% quotes sometimes, for example, Argus in Western Europe would be one example. Then on Shanghai Metals Market, for common reference, people will quote a 30% headline price. To be in the secondary tantalite concentrate world, it is typically 20% plus. In our testwork to date, we achieved, I think from memory, Fred, about 21.4% for our site-based con, in which case it is definitely in the secondary con category. Once you are in the secondary con category, you effectively achieve the headline price, whether that is quoted at 25% or at 30%. Hence our ability to capture more value. Max, you have reminded me of a really important point that I think investors should also understand.

Because it is a secondary con, it is a very different proposition to what people might be used to in respect of tantalite from classic West Australian hard rock operations. They are not, well, typically, not secondary cons. They are primary cons. That very much narrows the buying pool and, of course, your ability to translate that to a decent headline price. They are primary cons, so typically in a range of, let us say, 5% or, if you are lucky, high single-digit percents. Other key point to reference here in respect of tantalite is we own 100% of the rights. So, they are unfettered rights for access to mine and sell our tantalite product, and that is not true for, by far, the majority of West Australian operations.

In fact, in some cases, the lithium miner does not even own the tantalite in the ground. It is owned by a third party. This is why when investors consider Shaakichiuwaanaan and our tantalite co-product credit, it has to be looked at through a completely different lens. We own it 100%. It is a secondary con, and it is a high grade in respect of head grade going into the processing facility. The combination of those things makes for a very powerful outcome in the credit itself to your spodumene concentrate costs of $108 per ton deduction.

Max Yerrill
Analyst, BMO Capital Markets

That is very helpful, color. Thank you, Ken and Fred. I will turn it back over to the queue.

Operator

Once again, if you wish to ask a question on the phone line, please press star one on your telephone. Your next question comes from Mohammed Sidibé with National Bank of Canada. Please go ahead.

Mohammed Sidibé
Analyst, National Bank of Canada

Hi, Ken and team, and thanks for taking my questions. Congrats on the release of your Feasibility Study. Just two questions from me here. The first one may be on the timing of the expected bulk sample and when we can see the results for that. If you expect to effectively get the sample result back before your FID in late 2027, I am guessing that is fairly important for the geotechnical work to give you more support around that 35-meter stope height that you highlighted in your underground optimization.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah. In fact, from a bulk sample timing point of view, the answer is no. It is not tied so much to the question of FID and/or mine authorization. It is definitely a de-risking event, but more in the category of the combination of industry engagement and the future of chemical initiatives around the Shaakichiuwaanaan project. So, when we think about the progress of the bulk sample, it is not tied to the effect of mine authorization. That is completely separate and not considered. But what it does do is effectively continue to de-risk the operation because it allows us to ultimately hand on more product to key partners that would be involved in next steps for the company. So, things like a chemical plant or a caesium sort of product flow, even a chemical plant in caesium.

Not so much chemical plant in tantalum, but certainly having more sample will help with our customer engagement. Yes, it is a de-risking tool, but no, not directly tied to the current mine authorization process for CV5.

Mohammed Sidibé
Analyst, National Bank of Canada

Thanks, Fred. I guess just in that same question, just for me to be clear on that. You do not really need the bulk sample results to validate any geotechnical work in the underground that kind of support your optimization? You are comfortable with what you have in the study at this point in time?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yes, exactly, Mohamed. There has been an extensive body of work that contributes to the feasibility study outcomes, which includes pretty much everything in addition to what you have described. Geotechnical inputs, whether that is underground or open pit, crown pillar assessment, dewatering, and/or hydrogeology. All these things are already advanced to a feasibility level of assessment. Hence, not required. The bulk sample is not required to continue to add to that. It helps, for sure, from a de-risking point of view overall in the project, and of course, we get the development in place earlier, but it is not required for the progress of the project to FID.

Mohammed Sidibé
Analyst, National Bank of Canada

Great. Second question from me, Ken, if I may. Congrats on the leadership succession. I just wanted to hear from you how you are thinking about the handover and the split of, I guess, responsibilities between a future incoming CEO and you as executive chair. Will you be more in charge of, call it, the offtaking, the government relationships, or how do you envision effectively that split between you and the incoming CEO when you take on the executive chair role? Thank you.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah. Thanks for the question, Mohamed. Yes, I think in effect, you are right, what you have just described. My expectation is that I can continue to help the company with the combination of strategy, in respect of critical mineral strategy more broadly, the combination of lithium, caesium, and tantalum as a function of the experience that I have had. But I do not need to be involved in the detail that ultimately delivers those outcomes. And the step into executive chair allows a new CEO to assume senior responsibility in the company, but principally off a Canada base or a Québec base, and working very closely with the senior executive team. And in so doing, having responsibility for key initiatives that deliver the project and deliver the outcome that we hope all of our stakeholders are looking for, whether that is customers, the Cree, governments in Québec and Canada.

My contribution would sit at a higher level in respect of strategy and the work that we are doing in the critical minerals world.

Mohammed Sidibé
Analyst, National Bank of Canada

Great. Thank you.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Thanks, Mo.

Operator

Your next question comes from Brian MacArthur with Raymond James. Please go ahead.

Brian MacArthur
Analyst, Raymond James

Good morning, and thank you for taking my question. I apologize, I haven't had a chance to go through everything yet. But as I look at the first three or four years of this, you give a lot of life of mine costs, but I presume with the much higher grade and the fact that the tantalum credits effectively, I would argue, linear, given the price is the same and the volumes are the same. Are the costs an awful lot better in the first three to four, five years? Because the reason I'm asking this is that if we go to stage two and we start to bring in CV13 and we move everything forward, one would assume then, as we look at the pro forma plan, you're going to have much better costs than what we see here for quite a few years at the front.

Is that a fair comment?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, Brian, I think the way to answer that question is, in fact, in two parts, not that dissimilar to what you've described. When we think about the stage one project has delivered, in the Feasibility Study, of course, it can stand alone. You don't have to develop stage two. In fact, stage two would be subject to its own set of FID criteria, market conditions, your ability to stabilize stage one operations, demand conditions, of course, price. Those things are yet to come. Can stage one stand on its own for the reason, broadly, for the reasons that you've described? Yes, absolutely. Very, very high grade from underground. In fact, you could choose to mine approximately 12.5 million tons at 2% lithium and be operating for seven years, at what you might consider to be, well, high rates of production, but probably very low cost.

Now, if there is a trade-off, and perhaps Fred could correct me if I am not quite on the money, is that in those first three years, you are still largely developing the underground mine. Practically, there is a lot of development that happens. Yeah. That is somewhat of an offset to the benefit that you have in the higher grade. Does that mean it is materially different to our projected life of mine cost? I do not think so, Brian. Second part. We, of course, are very much looking forward to demonstrating what happens with the introduction of CV13 via the PEA. In fact, for the very reason you have described, CV13 is an incredible resource. Whilst it is smaller than CV5, it is higher grade, and it is higher grade in everything. It is higher grade in lithium, it is higher grade in caesium, it is higher grade in tantalum.

The net benefit that we will achieve is being able to basically bring in that higher grade and supplement the overall plant feed, whether it was stage one, or additionally in the construction of stage two. Fred, is there anything else that you would like to add to that commentary?

Frédéric Mercier-Langevin
COO, PMET Resources

No, I think you hit all the keynotes, Ken. You are absolutely right. In the first few years of the underground, we are seeing a lot more concentrate, but we are also seeing the bulk of the development to establish the underground workings take place, so that kind of offsets some of the gains there. But right after that first phase is done, then we start raking in the money, if you will, or so to speak. Then, of course, if you were to add the high-grade CV13 to that profile, then that would make for a better outcome, we think.

Brian MacArthur
Analyst, Raymond James

Great. Thanks very much. That is very helpful color.

Operator

There are no further phone questions at this time. I will now hand over to Nicholas Read for any webcast questions.

Nicholas Read
Managing Director and Principal, Read Corporate

Yes, thanks very much, Ash. Ken, we do have a number of questions on the webcast, so we will try and scoot through these as quick as we can. First one is, are you expecting to have offtake in place for tantalum as well before you make a final investment decision?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yes, almost certainly, Nicholas. That is a good question, and the answer is a pretty unequivocal yes. That is principally because we are seeing strong demand. Those that participate in the tantalum world have noted that there has been a material step-up in demand, and they are very much looking for stable Western supply, such that Shaakichiuwaanaan can provide. So yeah, I am confident in that, achieving that outcome.

Nicholas Read
Managing Director and Principal, Read Corporate

Excellent. Thanks, Ken. The next question here is, what percentage of equity funding for phase one are you working towards? Given VW's cornerstone rights, could offtake prepayments on the uncommitted 700,000 tons per annum and the tantalum reduce your equity requirement below 20%?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, I very much appreciate the question, and there is definitely a bit of insight in it too. I have no doubt that the co-product opportunity in the form of tantalum and caesium has the potential to help us in respect of future financing around the project. Of course, not forgetting the lithium. We still have, in stage one, we still have another, effectively, 400,000 tons of spodumene concentrate to place, and that is one of the key levers that we have to support financing. The idea that there is a trade-off between financing and the ability to secure offtake from a project like Shaakichiuwaanaan, we think is attractive to strategic players in the industry. Whilst we are thinking about financing, I should also mention that we do believe that government ultimately will have a part to play here, and it is motivated by a couple of things.

Many people would understand that Canada itself is keen to open up new supply chains, but in particular where they have reference to sovereign supply chains for Western supply. With that as a backdrop, we believe government will ultimately be helping in support of the financing of the project. If you are after a reference, you have only got to look at a couple of projects in the last, let us say, the last four or five months. Two examples would be Generation Mining and Nouveau Monde Graphite, who were well-supported through government circles, effectively for similar reasons, or if not the same reason. Governments and their participation in the pool of financing, strategics in the supply chain, but including all three, lithium, caesium, and tantalum. The last cab off the rank, well, yes, that is the equity.

We would like to think that that is going to be a relatively small proportion of the project funding mix.

Nicholas Read
Managing Director and Principal, Read Corporate

Fantastic. Thanks, Ken. The next question is, will there be a pollucite recovery circuit included in the mill design in phase one and the underground development?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, also a good question. I think it is suffice to say that today, well, at least not yet. I referenced the fact that there is caesium occurrence in CV5. We have already flagged that in our public disclosure, and we are continuing to follow it up. Some of that would be best followed up via the underground development, and that is another reason why the bulk sample itself is helpful for the overall sort of bigger picture around CV5 and its ability to produce a caesium co-product. When we think about the caesium recovery plant, you will obviously have more insight once we publish the PEA, but effectively it is a mobile facility for the purpose of ore sorting.

Actually, from an addition to your facilities at site, it is a relatively simple tool to plug in, approximately the size of a sea container, and not difficult to put on the ground and kick off operations. It is also relatively small scale. The combination of those things helps in hopefully a bit of context. Once we have caesium in the ground and ready for production, it is actually really easy to bolt that on to our site-based operations.

Nicholas Read
Managing Director and Principal, Read Corporate

Fantastic. Thanks, Ken. The next question is, are there any other companies outside of Koch looking at your caesium concentrate? If so, could you provide any color around that?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, the buying pool for caesium concentrates is not huge, but there are some. I would not choose to go into them in detail other than to say that there are other key buyers who are equally interested in the potential of pollucite concentrate. Caesium markets are not. Well, some people might have argued in history that lithium markets are opaque. Well, I can assure you that caesium is more opaque, in which case buyers typically are not in the public domain and sit behind a corporate veil. But as soon as we made the discovery, I am going back, let us say 18 months ago, if not two years ago, the phone rang, and it was interested parties.

People are clearly paying attention to our caesium discovery, and we have almost no doubt that it will be very significant to the future of caesium supply, to the point where we're increasingly growing in confidence in our ability to grow the market through that supply base in one of our scale. Looking forward to that. More to come in the PEA a bit later this year.

Nicholas Read
Managing Director and Principal, Read Corporate

Fantastic. Thanks, Ken. Just two or three more to get through. Pretty basic factual question here, but I know people do sometimes get confused by this. Can you just confirm with all the company's issued capital across the two exchanges, how many shares are there actually on issue in PMET Resources, including options?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah. Using a normalized reference base, that would be the TSX, there's just over 190 million shares on issue, 195 million, I think, comes to mind. It's in our most recent presentation materials. Yeah, whilst there is CDIs, the CDIs are effectively a subdivided TSX share. If you sum through the effect of CDIs and the basic shares on TSX, you come up with about, let's say, 195 million shares.

Nicholas Read
Managing Director and Principal, Read Corporate

Fantastic. Thanks, Ken. And just another couple of quick ones. An investor has just asked if you have any idea about how long the suitable handover period might be before you go non-exec?

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Yeah, completely understand that question too. Look, I don't want to be definitive about it, but I certainly want to reassure, well, whether it's shareholders, of course, but also other stakeholders to the company. I am passionate about the Shaakichiuwaanaan project. It's just very difficult from a family point of view to continue to maintain effectively a full-time presence in Montreal, Québec, and Canada. As such, it makes sense to ensure in the first instance that we have the right CEO in place. As to the handover itself, well, again, I'm completely comfortable being deeply involved in that process to ensure that we have the right candidate in place and the right level of handover has occurred, that we can ensure transparency and continuity in the company's operations.

I don't know how long that process takes, but big picture view would be, well, I'm intensely interested in the continued success of our Shaakichiuwaanaan project. Of course, I'm a reasonably large shareholder and therefore keen to see the company as a whole succeed. Lastly, I really enjoy working with the team. They are very, very capable people and we have some fantastic talent on display in Shaakichiuwaanaan, those that can deliver the project, and that's a pretty rare thing. It doesn't happen that often in the mining world. You have the right confluence of project and people that will ultimately make for an outstanding development.

In this case, one that we think is going to be crucial for the future of the critical minerals world, and that's why I'm happy to maintain my involvement in the short to medium term, yes, in executive capacity, but equally in the longer term in non-executive capacity.

Nicholas Read
Managing Director and Principal, Read Corporate

Thanks very much, Ken. Look, I think I'm conscious of the fact that people need to get on with their days or their evenings as well. I might just ask you to wrap us up and I'll perhaps throw forward to the next big announcement, which will be the PEA coming out in December.

Ken Brinsden
President, CEO, and Managing Director, PMET Resources

Thanks for hosting, Nicholas. Fred, well done on both the project work in the last 12 months, but also in your contributions today. Fantastic as usual. We look forward to very much demonstrating the continued success of the Shaakichiuwaanaan project. Next step, the presentation of the PEA, which we would expect to have up in lights before the end of this year. We remain confident that that is going to continue to show why Shaakichiuwaanaan is a very, very important development for the future of the critical minerals world and the North American supply base. We look forward to showing you that in the coming weeks and month or so. I am sure we will touch base then. Thanks very much, ladies and gentlemen. Pleasure to be with you.