Status update

Nov 17, 2026

Summary

Construction is progressing across the camp, access route, power line and process plant, while the EXIM loan is targeted for Q1 2027. A $111 million tungsten program and 2026 drilling results add critical-mineral and resource-growth opportunities.

Operator

Hello, and welcome to today's webinar, Perpetua Resources Advancing the Stibnite Gold Project. Leading the call today is Jon Cherry, President and CEO, and Mark Murchison, CFO. I will now hand the call over to Mr. Cherry.

Jon Cherry
President and CEO, Perpetua Resources

Morning, everyone. Hello, and thank you for joining us today. My name is Jon Cherry, and I am the President and CEO of Perpetua Resources. Joining me on today's call is our CFO, Mark Murchison. The purpose of this webinar is to provide an update on Perpetua Resources, including progress on Stibnite Gold Project construction and procurement, an exciting new tungsten program, and a summary of exploration activities. Following the presentation, we will have a question-and-answer session. You may submit questions at any point during the call by using the Q&A function at the bottom of your screen. Before I hand it over to Mark, I want to remind everyone that today will include forward-looking statements and to please read our disclaimers on slides two and three. Mark, over to you.

Mark Murchison
CFO, Perpetua Resources

Thanks, Jon. I would like to start by recognizing the hard work of the Perpetua team and our partners. Construction on the Stibnite Gold Project is ramping up, and we have made significant progress on several work fronts. Before we get into the slides, just a note on financing. We continue to execute on our comprehensive plan. The senior secured loan through the U.S. Export-Import Bank is progressing through diligence and documentation. We anticipate the loan will be available upon completion of definitive documentation and satisfaction of customary conditions in the first quarter of next year. At the end of the third quarter, we had $504 million of cash, of which $443 million is unrestricted. Now, anticipated expenditures for the fourth quarter are approximately $198 million. Based on current plans, cash on hand is anticipated to fund expenditures through Q1.

Moving to the slides, we will provide an update on the Stibnite Gold Project construction progress, the exciting new tungsten program, and exploration activities. There we are. The worker housing facility. Following the completion of civil works in late August, the foundation was installed for the kitchen, dining, and recreation facility, the Arctic corridor, and the dormitory wings. Placement and installation of phase one of the camp dormitory modules is complete. This included placement of 178 modules of the total 357 modules to be installed. The remaining modules will be installed in the spring. Mechanical work to support the camp is ongoing, and the facility fit-out is also progressing with furniture and equipment being installed. When fully complete, the camp will support our peak construction workforce. The Burnt Log Route.

The Burnt Log Route will serve as the primary access road to the mine site and will offer year-round access. The route originates from the intersection of Highway 55 and Warm Lake Road at the town of Cascade. From Cascade, there will be 34 miles of existing highway to where the Burnt Log Route commences. From this intersection to Stibnite, we will upgrade 23 miles of existing road and pioneer 14 miles of new road. To-date, rough pioneering has been completed on 5.4 miles of road. Burnt Log Route is critical to provide access for materials into site for the construction of the process plant and the large mining equipment. Work on the route ramped up over the summer, with crews focused on alignment, clearing of timber, geotechnical work, and installing temporary bridges.

All of the geotechnical investigations have been completed, and we're on track to have the route active in late 2027 to begin deliveries of large items like the autoclaves and mining equipment. We expect to have the Burnt Log Route fully completed in 2028. The power line. We're working closely with Idaho Power to upgrade and install new power lines to site that will support the project. Overall, the construction will include 62 miles of existing power lines that will be upgraded from 69 kV to 138 kV.

There will be approximately nine miles of new power lines in the final section of the line into the Stibnite mine, which will also be constructed. The resulting line will deliver 65 MW of capacity to the site for the operations. In late September, work began on the installation of new power poles to support the project.

The new high-standing steel poles is a significant upgrade to the existing low-standing wood poles. The process plant. Another area of focus and activity is the site for the project's process plant. A lot of the process plant site has been cleared in preparation for civil grading. Pre-mobilization and spot grading is underway, which will ensure construction readiness for the civil contractor. The location of the process plant is a key factor for Stibnite. It will be centrally located, being less than one mile from the Yellow Pine Pit and approximately half a mile from the Hangar Flats Pit. Water treatment plants. We're advancing work on the important water treatment plants. There will be three plants installed: the fresh water treatment plant, the sanitary water treatment plant, and the contact water treatment plant. The latest technologies will be used in these plants.

For example, the contact water treatment plant will employ state-of-the-art, two-stage precipitation and two-pass reverse osmosis. Deliveries of equipment associated with these plants has begun, and we will soon begin concrete foundation. Engineering and procurement. Engineering work for the project is advancing, with over 68 engineering packages active and progressing. The current focus has been on long lead items such as autoclaves, mills, crushers, and screens. Important autoclaves. They've been fabricated off-site in Europe. Four of the six autoclave shell sections are complete. Overall, fabrication for both autoclaves is approximately 43%. In addition, work on the process flow diagrams is well progressed, with PFDs complete for the crushing, the grinding, the flotation, and the pressure oxidation circuits. The piping and instrumentation PFDs for the same areas are nearing completion. Now turning to another exciting development for Perpetua.

We are advancing a second critical mineral opportunity in addition to antimony: tungsten. Tungsten is another critical mineral essential for military and industrial uses. The production of tungsten at Stibnite dates back to 1942, where during World War II, tungsten mined at Stibnite accounted for approximately 50% of the demand for the allied war effort in the production of ammunition and other military items. Like antimony, tungsten production has largely been controlled by China, and recent export restrictions from this country have caused turbulent market pricing. Accordingly, a reliable, stable tungsten supply remains crucial for both domestic manufacturing and military applications. Perpetua has designed a multi-phase $111 million industrial tungsten program to evaluate the technical and economic feasibility of producing tungsten concentrate at Stibnite. Funding for the program is anticipated from several sources.

We announced this morning a memorandum of understanding with a major U.S. aerospace and defense contractor for up to $55 million. We announced a couple of weeks ago a new $40 million grant from the government, and discussions are ongoing with leading-edge U.S. high-technology companies. The tungsten program will consist of two phases over 36 months. Phase one, the first 18 months, activities will include exploration drilling, definition of a potential tungsten mineral resource, collection of samples for laboratory and bench-scale metallurgical testing, permitting, and engineering of an exploration decline to access areas of known tungsten mineralization. We anticipate phase one expenditures will be approximately $20 million.

In phase two, the second 18 months, activities will include progressing the work started in phase one, development of a decline to access areas of known mineralization, underground exploration and development, pilot-scale processing, an assessment of recovery circuits, and developing a commercial production plan. Phase two expenditures are estimated to be approximately $90 million. It is important to note that any future tungsten development would be separate from the approved gold antimony mine plan for the Stibnite Gold Project and would require additional environmental review and permitting. I'll now turn the session over to Jon to cover a bit more detail on the tungsten program and exploration activities.

Jon Cherry
President and CEO, Perpetua Resources

All right. Thank you, Mark. Exploration potential for tungsten at our site is high, and we announced some very encouraging tungsten results in our August exploration release. This included a new tungsten discovery on the flanks of our Yellow Pine pit, as well as some impressive tungsten intercepts beneath our Hangar Flats pit, ranging from 1.2% to upwards of 4.6% tungsten. A proposed exploration decline at Hangar Flats is expected to provide access to tungsten and antimony mineralization, which is not included in our current mine plan. With 4.8 million ounces in reserves, Stibnite is the largest gold reserve in the lower 48 states, outside of the Barrick and Newmont Nevada joint venture, and that is gold only. We also have 148 million pounds of antimony in reserves.

What is interesting is that the last time we calculated reserves was almost a decade ago, using $1,600 per ounce gold price assumptions. On top of our 4.8 million ounces of gold reserves, we have 1.5 million ounces in measured and indicated, and 1.6 million ounces in inferred, both of which were calculated at $1,500 per ounce gold pricing. With 4.8 million ounces of reserves defined at that time, Perpetua focused on permitting rather than additional exploration. But with construction permits for our Stibnite Gold Project and a significantly higher gold price, we kicked off our first major exploration program in over a decade. Our new exploration program is focused on converting gold and antimony resources, finding higher-grade sources of feed to supplement our base case mine plan, and testing our best prospects.

Over 16,000 m of drilling was completed in 2026, focused on targets including the Clark Tunnel fault zone, Fiddle, Scout, and Hangar Flats. We found compelling new mineralization, including multiple high-grade gold intervals and a new gold-tungsten discovery at Fiddle. We upgraded on-site core cutting and preparation facilities to support an expanded drill program and set us up for years to come. In total, 72 holes were drilled in 2026, including 44 at and around Yellow Pine, 20 at Scout, and eight at other targets. Clark Tunnel was one of our first targets this season. Located on the edge of our permitted Yellow Pine pit, drilling showcased high-grade results, including 21.3 m of 3.2 grams per ton gold with 0.9% tungsten from 24 m below surface, and 6.4 m of 16.2 grams per ton gold with 1.7% antimony from surface.

In addition to gold, our program also identified significant new tungsten along with antimony mineralization. The cross-section on this slide depicts Clark Tunnel in more detail and from another angle, looking to the northeast. As we highlighted in our November 4th press release, recent drilling showcased high-grade results, including 25.4 m of 4.5 grams per ton gold from 13 meters below surface, and 25 m of 2.3 grams per ton gold from 18 m below surface. These intercepts demonstrate new mineralization that is near surface, within the permitted pit footprint, and at grades that are multiples of our reserve grade. At the Hangar Flats deposit, drilling continued to focus on high-grade gold, antimony, and tungsten, either in or in close proximity to our permitted pit. Drilling beneath the reserve pit was particularly exciting, where we encountered both high-grade antimony and tungsten.

Assays included 22.9 m of 3.2% antimony with 1.2% tungsten, and 9.8 m of 8.3% antimony with 4.6% tungsten. Importantly, Hangar Flats remains open at depth and along strike. The new Fiddle prospect, located approximately 750 meters south of the permitted Yellow Pine pit, includes some of the most significant mineralized material encountered at Stibnite Gold Project to-date. Located along the Meadow Creek fault zone, drilling has traced the mineralized structure along approximately 600 m of strike length and across more than 300 m of vertical extent, north and south and beneath Fiddle.

Discovery hole SB633 returned 109.7 m of 3.2 grams per ton gold and 1.1% antimony, beginning at 189 m below surface. Fiddle adds a new target area with potential to expand the project's in-pit and near-pit resource base. We have since completed significant additional drilling at Fiddle, with assay results expected in the coming months.

Overall, we are very pleased with the results from our recent drilling, which align with our objectives of expanding our currently defined resource base and extending our compelling production profile. Our focus has been on areas that align with our currently planned mining sequence with potential to directly add value. Our priority has been testing higher-grade gold and antimony targets within our three permitted pits that could supplement our existing Stibnite Gold Project mine plan, with the aim of sustaining or exceeding our estimated annual production level of 463,000 gold ounces per year beyond our first four years of production. Looking at the results from Clark Tunnel and other targets, we can see potential for additional mineralization with significantly higher grades than our current mine plan.

We have also identified gold and antimony exploration targets with the potential to allow for extensions of the existing permitted pits within the project and are evaluating opportunities to expand our overall resource base beyond the existing project scope. This includes identifying potential sources of tungsten that could enhance the value of Perpetua's broader land package. It is important to note, however, that any activity outside the scope of our currently permitted project will require additional regulatory review. With significant drilling completed this season, our staff continues to process log core ahead of assaying, with significant quantities and new results expected over the coming months.

With that, we will conclude the formal presentation, and we will now open it up and take a few questions here. All right, it looks like we have a couple of questions. I will go ahead and moderate that as we go through these.

The first question that has come in is, "Why was the closing of the EXIM loan changed from Q4 2026 to Q1 2027?" I will go ahead and hand that one over to Mark to talk about EXIM.

Mark Murchison
CFO, Perpetua Resources

Thanks, Jon. Yeah, the process is taking a little longer than what we perhaps anticipated. But I think in context of what we are doing here, it is obviously a large facility. For EXIM, this is a new tool in their toolbox for providing financing for domestic projects and project financing facilities. It is a new process for them, and it is important that we obviously get the process and procedures right. We are working very closely with EXIM and their advisors to make sure we cover off everything so we have success of the facility going forward. It is really just a process of getting through everything to be lined up, and we expect that we will have that closed in Q1.

Jon Cherry
President and CEO, Perpetua Resources

All right, thank you, Mark. We have another question here. This question, "Do you anticipate updating your reserves and/or resources based on the recent drill results? If so, when?" I will go ahead and take that one. Our resource models are currently being updated with the exploration results as they are coming in, which is pretty exciting for us. We still have a lot of additional data that is going to be coming in throughout the rest of this year and into early next year. This is really kind of a work in progress, but we will continue to progress. It will look kind of hand-in-hand with the strategic mine planning and scenario analysis that will follow all of that. But we cannot necessarily confirm or provide specific timing at this moment, as we are waiting for more data to come in.

All right, it looks like we have another question here, again, more on the exploration side. "How many samples are currently awaiting assay results versus samples completed?" I will take this one again here, Mark. We have sent in approximately 1,500 samples, plus or minus, to this point, and we have received about approximately 1,000 gold assays back, maybe about another 400 that are pending for the gold right now. But we are still estimating that we will be sending in approximately 10,000 additional samples. Back to the prior question, there is still a lot of assays that are pending and still a lot of data that is going to be coming in, but that is just a reflection of all the work that we did over this year with our exploration program. All right, got another question here. Let us see.

"When do you anticipate first gold from the project?" Mark, do you want to take that one?

Mark Murchison
CFO, Perpetua Resources

Yeah, thanks, Jon. We are still on track with the process of the project and the financing package for production in second half of 2029.

Jon Cherry
President and CEO, Perpetua Resources

All right, very good. Look, out of respect for everyone's time and appreciation for your attention and participation in listening to the webinar today, we will give you back a couple of minutes. We really appreciate your participation listening to the webinar. If you do have any additional questions, please do not hesitate to email or reach out to Joe Fazzini, who is in charge of our Investor Relations, and we can get back with you on that. Again, thank you for your time today, and appreciate your attention. Thank you.