Good evening, depending on where in the world you are logging in from today. Very, very pleased to have with me on the line from Asante Gold, three executives, Campbell Baird, Glenn Baldwin, and Morgan Carroll. They will be running through a presentation today, and then after that, we have a couple of questions that I will have for the executives on the line. This is also an open forum, so there is a chat button at the bottom of your screen.
Please do use that at any point during today's event to log questions. While this is only an hour event, it is unlikely we will get to every question. With that being said, I will make sure that the team on Asante's end gets the entire transcript of the chat, so they will be able to answer you either on the phone number or email that you gave upon registration.
The other thing I will say is this event is being recorded and will be available for replay likely as early as 11:00 A.M. or noon Eastern Time, so midday for those of us here in North America, and just towards the end of your day for those of us joining in Europe and in Africa. The only other thing that I will say is, once the presentation is complete, we will be able to share that with you for those that are in the room. Otherwise, I am going to throw it to Morgan to get us started today with the beginning of the presentation.
Thank you, Romeo, and good morning and good afternoon to everybody. Thank you for joining us for this session on Asante's turnaround plans, and very pleased to be kicking things off. I am here with Campbell online and Glenn, who is at Bibiani at the moment. Just by way of introduction, I am sure I know many of you online, but probably others that I have not met yet.
I am Morgan Carroll. I am the incoming President and CFO of Asante, and the lawyers tell me it is important that I note for everybody that I am still a consultant and not fully in my role at the moment, but that is an admin matter. I have been working with the team for the last several months as they have been getting to grips themselves with some of the headwinds at Bibiani and Chirano, and that is what we are here to talk to you about today.
I wanted to take a few minutes to just set the stage before we get into things. You will see the forward-looking statements slide as usual with the normal caveats and disclaimers. The presentation that we are about to give you is limited to the matters of the turnaround, so it is very focused on matters that touch technical operations, engineering. It is not a discussion of the sort of wider business asset profile, exploration, or anything else like that. It does aim to give you a very solid sense of what this team has in mind in terms of how to do things differently to provoke a different outcome from the one that investors have been experiencing over the last couple of years. So to show you the future opportunity that we believe is embedded in the assets.
Obviously, if you have seen the press releases over the past week or so, there are things that we will not be commenting on. Particularly, we wanted to point out the strategic review that was mentioned in the press release of Wednesday. For obvious reasons, we will not be able to comment on that. I think it is a good use of time to stick to the matters regarding the actual turnaround itself. The share price evolution over the past week, and I know this has been exceptionally painful for investors, that has obviously also been the catalyst for us to bring forward this presentation. If you read the Q3 press release, it suggested we were going to do this presentation for the market and for the wider world in January, but it is very obvious that we should bring that forward.
As such, quite a bit of what you hear is a little preliminary in nature. We want to bring you inside the tent, as it were, and have a frank and open discussion with you and offer you the opportunity to discuss and ask questions. But some of the information is still being cooked and being baked, so please bear with us to that extent. Other points that I should make before handing over to Campbell, the presentation itself is quite dense, so a lot of the slides that you are about to see are technical, a little bit operationally focused. For those of you who have been following with a mining hat on, a lot of it will be familiar to you.
We thought it certainly looked like a reasonably rigorous exercise for us to show you the bottom-up kind of approach that we have taken to looking at the assets and to seeing how we can map out the better future that we believe exists within them. There are several slides towards the back of the deck, which we will not get to, but they have even more detail or even more color. Please do take your time with those and have a read of them when the webinar finishes. With that, I think I will hand over to Campbell to dive straight into the content.
Thanks. Thanks, Morgan. Look, before I go into the turnaround plan, I want to briefly introduce the leadership team. Particularly, as you know, with me, culture is important, delivery is important, so we have been assembling a team who are going to be responsible for delivering this plan. Do not want to go through their biographies, but look, Asante Gold's challenges are not confined to one part of the business. We need to address the operations, the balance sheet, capital allocation, mine planning, organizational discipline, and the way the two mines work together. That requires a combination of operational, technical, financial, legal, and Ghanaian leadership expertise. Malik Easah, our Executive Chairman, he brings extensive experience in Ghanaian gold, exploration, project development, and capital markets. He is basically our company superpower.
His work with Cardinal Resources and Namdini, it is particularly relevant to the mineral potential and the outcomes within Asante Gold's portfolio. Morgan Carroll, as you just met, is joining as our President and Chief Financial Officer. He brings more than 20 years of experience across mining, finance, strategy, transactions, and governance. Glenn Baldwin, also on the screen, he has moved his family to Ghana, and he is our Chief Development Officer, currently sitting up there at Bibiani. He has got more than 30 years of experience, operation, and corporate development experience. Look, it is a pleasure to be working with Glenn, literally like we are at the moment, joined at the hip. Fred Attakumah provides deep operating, corporate, and stakeholder experience within Ghana. He is a great mentor and a great guide to me in particular.
Look, he has held senior roles in Asanko, AngloGold Ashanti, and is currently President of the Ghana Chamber of Mines here in Ghana. Dindiok Chialin is our Interim Chief Financial Officer. Dindiok has been a rock to all of us. Detailed knowledge of the business. He has worked across finance, audit, and supply chain here at Asante Gold, and particularly starting at Chirano. He has been here for over 10 years. Juliet Manteaw-Kutin, our General Counsel, she brings over 20 years of Ghanaian legal governance and corporate affairs experience to the business. I joined Asante Gold in April, and I have got over 30 years of international experience across operations, technical functions, and mine turnarounds. The important feature of this team is the combination of the new perspective and the institutional knowledge that it brings.
Look, ultimately, this is the team that is now responsible for converting the potential of these assets into operating and financial performance that we all know that can be achieved from them. Next slide. Thanks. Thanks, Morgan. Our operating turnaround is built around four connected pillars. They are deliberately very practical. They are going to address how we mine, how we process, what the business costs, and whether the mine plans themselves represent the best economic use of the assets.
At Bibiani, the immediate requirement is to restore reliable access to the main pit ore and to execute the mining schedule consistently. That means having sufficient mining capacity, managing contractor performance, controlling waste movement, and measuring actual delivery against the mine plan. There is an expression we are increasingly using internally, short-term interval control and control the variance. Every mining operation experiences variance. We all know that.
But the important question is whether the variance is visible early enough for management to understand it and correct it. If we planned to move a certain quantity of waste yesterday, what did we actually move? If we missed the plan, has the cause, availability, utilization, drill and blast, contractor performance, planning, or supervisor been considered and worked on? Most importantly, what are we doing differently today, and what are we thinking about for tomorrow? That discipline, repeated daily, is what ultimately determines whether the monthly and annual mine plans are delivered. I pretty much like to call this the hamster wheel of production. On plant stability and reliability, at Bibiani, we are increasingly approaching the plant as a recommissioning exercise. We have issues around feed size, grinding, classification, instrumentation, automation, flotation, recovery, power, maintenance, and critical spares. They are not independent problems.
If the feed entering the mill is inconsistent, grinding and classification becomes unstable. That instability then affects flotation, regrind, and downstream recovery. If the instruments are unreliable, the operators cannot control the process consistently. If the metallurgical accounting is weak, we cannot determine whether an intervention has actually produced more recovered gold. Our systems and processes matter, not just at the mill, but from the mine office into the mine and then into the mill. We need to stabilize the feed. We need to stabilize the grinding and the classification. We need to repair and calibrate the instruments. We need to automate the critical control loops. We then stabilize flotation, regrind, leach, and carbon performance. Look, ultimately, we are not just going to be doing automation for automation's sake.
We are going to be doing all of this to create operating conditions that are measurable, repeatable, and sustainable across every shift. Our third pillar is going to be to simplify and lower the cost base. Improved production has limited value if it is absorbed by excessive operating costs or CapEx. Our objective is not to simplify or to cut budgets. It is to remove complexity and expenditure that do not create an adequate return. This is particularly important at Chirano. If we concentrate the mine plan around fewer, higher value mining areas, we should ultimately require fewer trucks, fewer loaders, less maintenance, fewer spares, and less capital development. That is structural cost improvement rather than a short-term reduction in expenditure. Our fourth pillar is going to be that we reshape our mine plans. We have to challenge the mine plans themselves.
Our objective is not to simply become better at executing the plans that we have inherited. Where exploration resource conversion or technical work identifies a better option, we will change the plan. That is going to allow us to bring better, higher value tons forward, extend the mine life, simplify the operation, and/or defer capital that would have otherwise been required. That is what we call value beyond recovery. Underneath all of our pillars, the new Asante operating system: plan, execute, measure, challenge the variance, correct, verify, repeat, the hamster wheel. Life of mine planning has to connect to the annual plan. The annual plan has to connect to the monthly and the weekly schedules. Those schedules have to connect to short-term interval control, production, and cost KPIs, accountable owners, and disciplined capital allocation. Ultimately, it is all very simple.
The correct tons multiplied by grade, recovery, and reliability must produce gold, and that gold must produce cash after operating costs and capital. Next slide, please, Morgan. This slide and the next one, they are the key important ones from our perspective because it sets out how you, the investors, should be able to judge whether, first Bibiani, then Chirano, whether the recovery is actually working. You as investors should not have to rely only on us as management saying that conditions are improving. We need to demonstrate improvement through our operating evidence. The first constraint has been restricted access to main pit ore following the January wall pit failure. Our immediate activity in this quarter is to complete the clearance of the required waste and move the pit crest back approximately 60 m to support the revised geotechnical design.
The current target is to complete the in-pit waste clearance by the end of December. A second constraint has been inadequate contractor capacity and inconsistent execution. We have commenced mobilizing the second contractor fleet and are introducing much tighter measurement of availability, utilization, productivity, and surveyed tons. Our initial target is to deliver tons within 15% of the mine plan. While it's very early days, I will say I've been up on site this week and last week, and I'm already seeing the team starting to work very, very effectively together. I attended a number of daily plans and weekly plans, and it's really pleasing to see the team striving to ensure that on a day-by-day basis, they are meeting the plan.
Look, as I just said, we're going to do that through the execution of short-term interval control planning and day-to-day management of ourselves and our contractors, and this is the only way to success. This is something that's very dear to my heart, and I have been and will remain very closely involved in the coaching and the introduction of this with our teams. Our third constraint has been the extent to which the plant has been operating significantly in a very manual way. We are basically looking at this as we are recommissioning the mill and the plant controls. We're having to repair and calibrate instruments and automating the critical control loops. What this is going to give us, reliable information, stable set points, and effective control tools, reducing the shift-to-shift variability that has continuously affected plant performance.
The fourth constraint has been mill feed, critical spares, and then matching that to a stable throughput. Our working target is a stable mill feed rate of approximately 425-450 tons per hour. Towards the end of last quarter, due to a number of missing critical spares, the mill throughput has been and remains throttled back to around 6,000 tons per day. As we build up our internal maintenance planning team and critical spares inventory, we will be able to move our throughput back to over 10,000 tons per day. We're targeting this outcome through into Q1 2027. The flotation target is to move mass pull from approximately 2% towards a controlled operating range of around 8%-8.5%. This is not the final outcome. The real outcome is the whole plant recovery.
Our objective in the next six months is to move the metallurgical recovery from last quarter's levels towards more than 80%. I want to be careful with that number. That's a number, there have been lots of recovery numbers bandied around over the past 24 months or so. It is a target, but it's not a result that we're claiming today. With the past couple of months' work, we are confident that what we're dealing with is plant mechanical issues, not chemistry issues. But before we claim improvements, we're going to need reliable power, better metallurgical accounting and reconciliation, and a rebuilt plant control system, all of which that are underway, and we're already seeing the benefits of this across the plant. As well as the wall slip, the key constraint at Bibiani has been the outstanding phase one relocation program.
I could go on at length about the success of the company's village construction and relocation program, but that's not for today. We are at about 75% moved. We are just working through the final programs with the community. These are not simple matters that we're dealing with. This is a community program sitting alongside a mine plan. It is directly connected to mining access. Until the relevant areas are safely released, blasting and pit advance remain constrained.
Our immediate requirement is therefore to complete the phase one commitments and release the plan areas for mining. We are expecting to complete this by the end of the year. All groups are committed to this timetable, and we are all moving in unison to achieve it. Finally, there is power reliability. The instability of the national grid that feeds into Bibiani has been our ultimate Achilles heel through 2026.
The interim measures that we are working on include diesel generation redundancy and assistance from GRIDCo with new and boosted hardware in the town of Bibiani. The structural solution is the planned private independent power connection from Chirano. Construction for this is planned for as soon as possible, which will see us starting it, we believe, as soon as possible in 2027. But seriously, we are. We're working on that. We're very, very close to getting it going. The target is to provide power stability at greater than 98%, which will be like a dream come true for the team at Bibiani. Putting all of these things together is forecast to increase metallurgical recovery from current levels, like we had in the last quarter, to 80% by Q1, Q2 in 2027.
We're already seeing a lift in the levels on a shift-by-shift basis, and it's going to be about tying all of that together to get us past just a single shift. Thanks, Morgan. On to Chirano and the group. At Chirano, the fundamental question is not simply whether we can mine more tons. It's, are we mining the right tons with the right amount of fleet and development capital to maximize our cash generation from the asset? We are rebuilding the operating plan around the cash contribution of each mining area. That means using achievable grades and recoveries and including mining, haulage, processing, and capital development in the assessment. That does not mean selecting individual high-grade stopes or high-grading an open pit in the short run without regard to sequencing or mine life.
It means ensuring that the mine plan, taken as a whole, directs scarce equipment, capital, and management attention towards areas that can pay for their development and operating costs. The second measure is underground development. Chirano's ability to establish new production areas has been affected by its development rates. The target shown is to increase development toward approximately 180 m per month, supported by a specialist underground contractor. That's not development for its own sake.
The purpose is to shorten the time between production levels, improve access to ore, and provide greater flexibility in the underground schedule. Third, the measure is capital discipline. Development should not proceed automatically because it appeared in an inherited plan. Before capital is committed, the development alternatives need to be ranked according to the ore they unlock, the expected cash contribution, the timing of that contribution, and the available alternatives.
The intended endpoint is that development capital is transparently connected to ranked ore sources. How do you bring all of that together? Across the group, our mine schedules, our operating budgets, capital plans, working capital forecasts, cash forecasts need to become one integrated operating model. It sounds obvious, but it has been a key challenge for the business. We should not discover the cash consequences of operating in variance only after the month has closed. If grade changes, if tons are delayed, or if capital moves, the management at all levels need to understand the liquidity impact while there is still time to respond. The group is also targeting more than 450,000 ounces of resource additions, equivalent to approximately 7% of the current 6.5 million ounce resource base. These are targeted additions, not reserves or approved mine plan outcomes.
At Bibiani, near-mine drilling may extend surface mining, improve sequencing, and defer underground capital. At Chirano, resource conversion and exploration may extend priority underground areas or support larger and more efficient surface configuration. Exploration creates value when it gives us a better mine plan, not simply a larger resource statement. Finally, we are bringing the two sites into a more consistent Asante operating system. Bibiani and Chirano have different origins and have historically used different technical practices, systems, and standards. We will be applying a common risk-based decision process, shared standards, and selected group services while preserving clear site-level accountability. The purpose is not centralization for its own sake. It is to use scarce specialist capability more effectively, remove unnecessary duplication, and make the basis for operational and capital decisions more consistent across the company.
I would now like to hand over to Glenn to talk you through one of our evolving scenarios that we've been working through as exploration results have poured in, parallel with all the review work that we've been undertaking. Thanks, Glenn.
Thanks, Campbell. Just firstly, to finish off quickly on the Chirano side of things. The slide that you see in front of you has a number of numbers in it. I'll point you to the two which I know everyone is most interested in to start with, which is the gold sold in a range and the AISC in a range. Chirano is an underground and an open-pit mine, and relies on a split of between 50/50 and 60/40 as underground to open-pit ratio in order to achieve the head grades which are there and the indicative recoveries as well. The tons milled, though, are flat-lined all the way through, are purely a function of the maintenance activities and the availability of the plant. The plant is in very good shape.
We have been through the reconstruction of the crusher and the feeder, which took almost three weeks out of production last month, and we managed to work our way through the production quite well because of stockpiles which we had built up. It's those stockpiles built up, which, unfortunately, most of it came from open pit, not from the underground. When the declines will reach their development targets that are required, we will have additional levels underground being produced at the same time, and that is going to enable us to reach more of the 60/40% split, and that is where those head grades come from. We are moving towards those high-grade areas underground, and for those of you who have been involved with Asante for long enough, you've seen the long sections, you've seen the big red blobs on all of the pictures.
That is effectively where we are heading in 2027, 2028, and 2029. Beyond that becomes the exploration story and joining this all together, as Campbell Baird was just alluding to. That gold sold range is very important because at the lower end of 155,000 ounces next year, you can be looking at still sub $3,000 an ounce, which is obviously better than everyone has seen in the last few quarters. The reason for that is because we are changing our maintenance philosophy so that we can make sure we achieve the tons milled. We have introduced a mining contractor underground so that we can improve our development rates, share resources, and improve the activities safely that we do underground.
I guess that leads me to the very simple saying that we're living by now, which is, "Produce profitable gold safely." Chirano is in the right space with the right development rates to generate sufficient stocks of stoping underground over the next year or two, because it takes a year to build it up, that we will then have that steady state and the opportunity to start increasing the production to the 180,000 ounces a year plus, which is what you see in 2028 and 2029. I think that Chirano is a pretty reasonable story compared to what you've seen in 2025 and 2026. It has a fantastic opportunity, and if we do what we say we're going to do, those numbers that you see on the screen are reasonable and achievable.
The reason that I didn't start with Bibiani is because there's a slide coming after this with a picture, but Bibiani really is a grade story. The reason that we have not achieved what we wanted to achieve in the last couple of years is that we have under-mined the waste at Bibiani. We have had a couple of wall failures, as people should be familiar with, and that has impacted on our ability to access the high-grade ore at the bottom of the pit. Because of that, our rates of mining from main pit have been lower, and the supplemental ore that we have had from the other sources are typically running at a gram or less.
Although that gives you good ounces and a good cash cost, if you combine that with the high- grade, not combining it with the high- grade ends up where we are right now. But I think what Campbell Baird just said was the consistency of approach between the two operations. Chirano's maintenance has been run at a much higher standard with a much better level of spares compared to Bibiani. What we are doing at the moment is making sure that we have fully assessed all of the critical spares, and we are aligning everything that we do in the group. That is why we are implementing our new ERP system, which goes live in Q1 of 2027, which includes finance, supply chain, projects, and of course, maintenance and engineering.
That will be a fundamental change for this business to be able to plan, because as we know, prior planning prevents poor performance. With respect to Bibiani, you can see the numbers there, which I think people have probably seen historically of up to 180,000-200,000 ounces, and why can't we get there right now? Well, we focused on underground mining over the last year or two because there is a massive resource sitting underneath the existing main pit. Ultimately, underground mining is where we see Bibiani moving to in a couple of years.
However, in order to move there, you need to ensure that Chirano is extremely efficient, and then you take the learnings and the best people from Chirano, and you put that into Bibiani, and you make Bibiani a success from an underground development and production perspective from day one. That is how you deliver numbers into the marketplace consistently. What we are doing with Bibiani is we have had a look, and I will move to the next slide if we can, please. But what we have done is we have had a look at the pit itself. Just to look at this picture, you see the really big picture in the middle, that is main pit. There is a little white dot up the top in the middle, which is what they call Cut 5, which I know you will see when you get the slides.
Up between the two, it says the Let's put it on this one. Up between the two, it says the bridge potential to increase product life, production life in the open pit. That is the area where we identified a couple of months ago, so very recently, that the level of information was insufficient, and we had focused on moving that level of information up to an inferred and an indicated resource over the next couple of years, and to be mining it from underground. However, upon investigation, we identified that if we could put some holes in there very quickly, define a resource, and then hopefully define a reserve, and I say the word hopefully because we have not completed that, and we are in the process of doing that work at the moment.
It obviously takes a little bit more than a couple of weeks to get it into a compliance status. The drill holes which have been completed, which are, generally speaking, and we have successfully proven over the years, we do things to NI 43-101 compliance with respect to our resources. That work that has been done has given some of the best resource grades and intercepts that we have seen at this mine for quite some time. They are in the bottom left-hand box, including 60 m at 3.1 g a ton. I like the 25 m at 4.95 g a ton. This then talks directly to the head grades in the previous slide.
The reason is that we have identified an opportunity to move the main pit northern wall, and north is up the page, about 150- 200 m into what we call that bridge area where the arrow is pointing. If we are able to do that, the current strip ratio for the mine is around about 13. Indicatively, we are looking at 13.5- 14.5 when we start looking at mining that bridge. We also add another couple of years of life with respect to production before we have to fully transition to underground.
That allows us to, A, look at how our balance sheet is structured at the moment, because we are able to push out specific underground development, which is around about $132 million worth of capital planned, which was planned over the next couple of years, so we can defer that. That $132 is actually a larger number for underground mining, but we have accounted for the additional waste that we need, hence the increase from 13 to 13.5- 14.5 with respect to a strip ratio. So the numbers in the previous slide actually account for the work which we have done at the moment, reinforcing it is preliminary, but we do have real drill results. We do have spatial compliance with respect to those. We have put a shell around them, and we are now doing the detailed work.
What this basically means for us is, from a risk perspective, we have de-risked Bibiani because we do not have to move underground immediately in the next couple of years, which is what everyone has been focused on. Open pit mining means that we can work more closely with our mining contractors and improve our drilling and blasting and all of the things that we always talk about with respect to operational excellence. We have looked at the blended CapEx profiles, and we have been able to reduce them. We have looked at the cost discipline that we need to ensure we improve upon by implementing our ERP system. The fifth element of an ERP is human resource systems, and they will be integrated into our ERP, either in somewhere around the middle of 2027, something which we are working on.
Where that leaves us is that both Chirano and Bibiani as a combined entity are looking at ramping up their production, not because we need to ramp up production and say, "We're ramping up and it's a new story," but because we have done the work so far that gives us the confidence to say, "Indicatively, this is the tons, the grade, and the ounces that we will be producing over the next three years.
This is what we expect the CapEx to be." This is, in the next few slides, exactly what we're going to be focusing on over the next six to nine months in order to ensure that we reach these levels of production with the cost profiles. We have a number of consultants very specifically chosen for their areas of expertise to assist us in doing that, and we will put in that discipline.
We are putting in that discipline, which leads us to a successful outcome. If you just go to the next slide for me, I'd just like to show you in a cross-section, you can see what says the current ultimate pit, ULT is ultimate, which is that dark pink color. You can see where it says $2,500 with an arrow. Do not worry about the one that says 0.5 cutoff grade, because if we mine that, we have to do more relocations, which we have not put into any of our models. The reason I left it in there was because some people think that the ultimate pit we're going to show you at the moment, the $2,500 one, is as big as Bibiani can be, and the answer is, it is not.
We could actually move this open pit hundreds of meters to the south and do another relocation. Instead of doing that is why we now dovetail the underground and the open pit so well over the next few years, because we've given ourselves time to do some more drilling, to do bankable feasibility studies, and to ensure that we take the market on the journey with us. The $2,500 shell you can see on the northern side, which is the left-hand to the right-hand side of the screen, you can see that lighter pink color. That's around 150- 200 m. We expect it may even be a little bit further, and that gives us that extra one to two years, maybe a bit more of life, which allows us to have all of this additional time. That time brings us down the cost curve.
That time allows us to be more productive and more efficient. With that one, I'll leave it with you, Campbell, and thank you very much.
I'll just briefly interject to say to the folks waiting in the chat, the presentation will be over shortly, and we'll get to as many questions as we can. Thank you.
Thanks, Glenn. Absolutely. Just as Romeo just said, there are a number of other slides there, mine initiatives, but we've gone through a lot of those, so I'm going to skip over those and just close so we can move to questions. Look, I acknowledge on the surface, Asante has not been an easy investment story. The recent operating performance has been inadequate, costs have been too high, capital requirements have repeatedly exceeded expectations, and the balance sheet has constrained the company's ability to respond effectively. I do not think we create credibility by avoiding those facts, but that's not the story for today. Asante owns two significant gold operations, substantial infrastructure, and a considerable mineral endowment across one of Ghana's most prospective gold districts.
The problem has been that we have not consistently converted those strengths into reliable production, controlled costs, and sustainable cash generation. That's the work that's now in front of us. At Bibiani, it's increasingly clear where we have to go. We need to restore reliable access to the main pit ore. We need to establish sufficient mining capacity. We need to recommission the plant, rebuild its control systems, stabilize the throughput and recovery, improve power reliability and plant availability, and demonstrate that the resulting production improvement converts into cash. At Chirano, we need to focus on the mine plan, on the areas that generate cash. Obra and Suraw are going to be fantastic operations for us in particular going forward, two of our better performing underground operations. We need to increase our development productivity. We need to resize the plant and the fleet around that plan.
We need to reduce the complexity that we found ourselves having at Chirano. Across both operations, we are building a common operating system and applying much greater discipline to planning, cost, capital, and accountability. We have also presented a preliminary pathway towards materially higher production and lower unit costs between 2027 and 2029. But I want to be very clear, none of the outcomes we've discussed today are guaranteed. We have to earn them through execution, and what I believe has changed is our understanding of the problem. We can now explain with considerably greater clarity what went wrong, what needs to change, what we're doing about it, and how investors should be able to measure whether the plan is working. The last point is particularly important. We are not asking investors to believe us in the potential of these assets.
We will demonstrate that potential through our operating results and ultimately through the sustainable cash generation of the business. Our measure of success will be repeatable mine plan delivery, improving plant stability and recovery, declining unit costs, disciplined deployment of capital, and cash generation that is sustainable after both operating and CapEx. That is the standard that I would like the investors to judge against us. There is a great deal of work to do. There is a lot of work ahead of us, but it is a real clear opportunity. If we execute this plan with discipline, Asante can be a simpler, more reliable, and more financially sustainable gold producer while retaining the considerable longer-term value within its mineral endowment. That is the turnaround we are now working to deliver. Thank you very much.
Awesome. Thank you so much, gentlemen. Really appreciate you running through that presentation. I would usually jump into a bunch of questions of my own, but I know there are so many good questions in the chat. I am just going to go through one or two quite quickly. The first one, Campbell, is this for you. I know 2026 guidance was withdrawn last week, and the audience here has just seen a plan with new timelines in it. My only real question is, what is different about how the numbers in this plan were built?
Romeo, look, the big difference is how we built the plan. We withdrew guidance because a number of Bibiani constraints came together in Q3. Restricted main pit access, poor contractor performance, relocation delays, plant instability, and increasingly unreliable power. We understand those problems considerably better, and the new plan has been built from those physical constraints upward, and how we are going to execute, fix them, and get on with them.
Each one has a defined intervention and an operating measure against which we can judge whether it is actually working. Rather than starting with an ounce target and working backwards, we are starting with the tons, grade, recovery, and reliability that we have to produce those ounces. That is why I have been talking about controlling the variance, and it is also why the numbers we have shown you are still a management scenario, not guidance. We will earn those numbers through execution.
Great. Appreciate that, Campbell. Morgan, I have one for you, and then I will get into the audience questions. I know the Q3 filings include a going concern language and a November 30th date for $100 million in new funding. For a shareholder, for the folks in the room reading those words or hearing them for the first time today, what do they mean and where do things stand?
The company's been carrying a going concern for several quarters, obviously, due to the high-pressure liquidity situation and the solvency concerns, et cetera. It's something that's visited all the time with the auditors, and it's something that is obviously preoccupying us in terms of the future outlook. Clearly, the need to fund a turnaround plan, because that matter is going to be on everybody's mind as well. How do we get from point A to point B? What is that amount? What is the company's planning around that? That's a matter that's coming together at the moment. It's absolutely front of mind. It's the kind of thing that we are spending a lot of time with advisors at the moment. We have an ongoing monthly waiver situation with our lending group, who have been exceptionally supportive, I have to say.
We are planning around that, obviously, with them on a daily basis. I'm sorry I've been a bit elliptical about that, but I hope that kind of gives a decent perspective.
Great. No, appreciate that. I'm going to jump into the audience Q&A now. I'm obviously not going to get to all of them today, just for the folks in the room, as we only have 15 minutes left. But I will send the full transcript to the team. Right at the beginning of the hour, someone noted that Asante Gold reported $421 million in trade and other payables, including approximately $270 million in trade payables. They want to know how much of this balance is currently overdue, and what would management consider a normalized payables balance once the mines are operating sustainably?
Yeah, great question. Yes, there are quite a few aged payables, and of that total amount, approximately 50% or a little more are past due at the end of quarter. So, a little bit north of $200 million of past due. In terms of the ongoing target or the normalized payables balance in a business like this, it's something that has been modeled quite heavily with our debt advisors over the last months. We think that the right range for people to think about is between $150 million- $200 million of normalized payables.
Great. No, appreciate that. Byron from the chat asks, "How much flexibility does the company have to materially revise its operating strategy, particularly at Bibiani, without securing any additional consent from lenders?
I can take that. Look, we've got all the support in the world from the lenders. One of the first things I did on joining was to meet our senior lender, RMB. We have three local banks also who are incredibly supportive, Absa, Fidelity, and I apologize. And then also Appian, who are our mezzanine and ECG lender. All of them are quarterly reviews with us. We have constant ongoing technical contact, and they're very much across what's happening on a week-to-week basis. So, we have all the flexibility in the world, and they're a great team to be working with.
Appreciate that. Direct question from Terry in the chat, also towards the beginning of the hour, "Who owns the first position on company assets, and what is that dollar number?
Who owns the first position on company assets? Maybe it means who's got the first ranking security, I think.
That's what it is.
Yeah, which is the senior lenders, obviously, led by RMB, but also with Appian Capital Advisory, and with the local lenders in Ghana who are Fidelity Bank Ghana Limited, as Campbell Baird said, and Ecobank Ghana Plc, and-
Ecobank Ghana Plc.
GCB Bank Plc. Sorry, I've lost my thread, I'm afraid. Sorry. What was the question?
The final question with that is just what's the dollar number that they have?
Yeah, it's approximately $180 million of senior.
Great. Thank you. Ernest from the chat asked, "What accounts for the contractor underperformance?" They want to know if it's financial, contractual, perhaps a lack of expertise. They're looking for your perspective.
Look, it was material movement. We were consistently 20%-30% behind in waste movement in the past 12 months on a month-by-month basis. That has been the challenge that we have found ourselves in. We were expecting to have moved a lot of the material and be in the bottom of main pit by Q3, and frustratingly, we weren't. One of the things, all of this compounds from that slip happening in January. There's about 40,000 ounces sitting underneath that slip, which were going to be in the schedule in 2026. They haven't been. They've been sitting outside of the schedule. It's $160 million-$170 million worth of recovered gold, depending on how you calculate gold price.
But yeah, so material waste movement, not being able to get down in the bottom of the pit has sort of kept that 40,000 ounces out of the schedule, which has been our challenge through 2026.
Appreciate that perspective. Joel from the chat notes, there's a couple of questions about AISC, but I'll kind of combine them into this one. They note that Chirano's AISC rose year-on-year on higher royalties linked to gold price and sustaining CapEx. They want to know how you intend to control that moving forward.
Look, like we went through the past 30 minutes, controlling your costs isn't just cutting your budget and saying, "We're not going to buy that new widget." It's about really sort of staying focused, working on your budget. An annual budget, what is that annual budget going to deliver? How are we going to deliver that budget? And then from day one, staying focused on delivering that annual budget. Short-term interval control, it is all about what you do today, what you think about today. What are you thinking about today to ensure that you meet on Friday, next Friday? What have you got to do to ensure you meet the plan next Friday? And then ultimately, that's about mining, the way you budgeted, spending the money that you said you were going to spend, working with your contractors, working with your suppliers.
It's all integrated through an ERP, all the way up to board level. It's the process of running your mine. And being on top of your cost, being on top of your production, doing it, controlling that variance, basically ultimately means that you are able to just work through and you slowly bring down your all-in sustaining cost. It is also significantly, as Glenn Baldwin mentioned, affected by grade. It's the gold that you produce, and there's so many variables that come into the gold that you produce, but ultimately, it is grade-related. Very, very confident that we're going to see an increase, particularly at Obra and Suraw. If you go back and have a look at a number of our presentations, you will see the grade profile that we're heading towards at Obra and Suraw. Fantastic sort of profile coming there through 2027 and 2028.
And then also Bibiani, the Bibiani main pit, as we get that cleared, there is a really great level of gold production there, particularly in Bibiani South. But then also some of these new drilling results, seeing 60 m at 3 g, et cetera, great.
Oh, certainly appreciate that. Morgan, I know you already touched on this, but somebody in the chat describes this as the elephant in the room, and I always like to acknowledge elephants. They ask, "What is the plan to tackle the financing issue?
Yeah. I mean, I know it is at the front of my mind, as it would be, I think, on all shareholders. Unfortunately, we cannot say very much about that at the moment. There are a limited number of levers that you have, if you look at our balance sheet, that are available in order to resolve some of the challenges on the balance sheet. And so we have to bottom out all of the possible solutions, which we are doing.
I think people should expect that we will run that to ground in the short term, because it has to be. I mean, it is not something that can persist forever and ever. The company has been carrying around this obligation to raise $100 million since the beginning of the summer. I believe it was before when I was involved, but I remember it back then even.
And it was a lender-imposed condition. And so, the lenders, again, been extremely accommodating while the company is trying to overcome the operating challenges and get things back on the feet at both of the assets. But it is difficult to be more specific on the financing at the moment. I think we do not want to go back to the old days of lots of gold forward financing. There is a place sometimes for short-term instruments like gold forwards, but I think they have been heavily overused, and they have been robbing the company of liquidity that it has badly needed at the expense of having more permanent capital, or longer-term capital, which it should have had.
Great. Certainly appreciate that. I had one question that came in relatively early. That's that the independent plant review pointed to the crushing and grinding circuit as the main constraint at Bibiani. They'd like to know, what does fixing that look like on the ground, and when should recoveries reflect that change?
I'm happy to take it. Do you want to go with that one, Glenn?
Yeah, I probably should answer that one. Look, the issues at the plant are broader than just crushing and grinding. I think what happened was we lost our gyratory crusher. We didn't obviously have a spare one on site, which is normal, but we also didn't have the planning in place to make sure that we had a spare one on site, because it was probably pretty obvious that there was going to be a problem at a point in time. What the team was able to do was to move to mobile crushers very, very quickly. But obviously, that's got a different profile going into your mill than a gyratory crusher. More importantly, it also has a different cost profile associated with managing your ROM pad or your run-of-mine pad, where everyone tips their material and blends it. We stop direct tipping.
That automatically increased your cost up on that part of the circuit. Our plan is we have already ordered a new gyratory crusher. It sounds a bit strange, but half of it is on site, and the other half is yet to arrive. We expect that to be arriving during the course of Q1, and then we will put the plans in place to install that during Q2, maybe it stretches into Q3. We'll just see what we can do to do that as quickly as humanly possible, because it will impact, and the guys are doing the designs on the feeder underneath the crusher and all sorts of things that we have to play with. That's the plan for the crushing. That will then give us a gyratory crusher. We can direct tip into it. That sorts out our crushing for the life of mine.
We'll then use the mobile crushers as our backup secondary circuit, and we need that because the mine has never had a crushed ore stockpile. That's the reason why we need to maintain a certain level of mobile crushing on site.
Great. Appreciate that, Glenn. As we're near the end of the hour, I'm going to close with one of the last questions in the chat, actually. They describe it as another elephant to consider. Campbell, I assume we'll start with you, but eager to hear anybody's opinion. They note that strategic alternatives and outside interests could play a part in what comes next. They'd love if you could unpack that for us.
I think from an investor's point of view, you've got a pretty good team sitting here, the six, seven people that are on that slide. We're all here because we believe quite passionately about the assets of Chirano and Bibiani and the opportunity that it presents. It's not often that somebody hands you the opportunity to work with two existing plants, 2.5 million tons per annum each capable of, as you've sort of seen in our numbers there, the gold production potential that they can possibly do. Each one, seven, 10+ year mine life. These are stunning assets. They're a little bit weak at the moment, but we really do believe that we can turn them around and drive them forward and really create significant value for them. We're not the only ones who believe that, I guess, Romeo?
Well, fair enough. I'll say, Morgan, Glenn, Campbell, thanks so much for running through a presentation, but also taking questions directly from shareholders and also a couple from me. For those in the chat whose questions I didn't get to, there were a couple, not too many, I think I got to most of them, but I'll be passing those directly through to the Asante team afterwards, and they'll be able to get back to you individually. The replay will be available in a few hours. I hope you're able to watch it and share it along. For those who are watching it on replay, if you have questions, please reach out either directly to the Asante team or in response to the email I give you the replay. I'll pass those questions along. Morgan, Glenn, Campbell, thank you so much.
I really appreciate your time today and appreciate everybody who's in the room.
Thank you.
Thank you.