Investor update

Nov 23, 2026

Summary

Richmond Hill’s PFS indicates a $2.0bn after-tax NPV and 71% IRR at $3,500/oz, with 171koz annual production and $1,289/oz after-tax AISC. Drilling, throughput flexibility and a 2027 feasibility study support upside toward targeted late-2029 first gold.

Operator

Thank you for standing by. This is the conference operator. Welcome to Dakota Gold's Richmond Hill Pre-Feasibility Study Call and Webcast. As a reminder, all participants are in listen-only mode, and the conference is being recorded. After the presentation, there will be an opportunity to ask questions. To join the question queue, you may press star then one on your telephone keypad. Should you need assistance during the conference call, you may reach an operator by pressing star then 0. If you are participating through the webcast, you can submit a question in writing by using the form in the lower section of the webcast frame. I would now like to turn the conference over to Jack Henris, Chief Executive Officer, President, and Director. Please go ahead.

Jack Henris
CEO, President, and Director, Dakota Gold

Thank you, operator, and good afternoon, everyone. Welcome to our webcast on the positive outcomes of the Pre-Feasibility Study for the Richmond Hill Gold Project. Earlier this afternoon, we released the results of the extensive study, and the S-K 1300 technical report summary has been filed. Joining me are three members of our management team. Lindsay Chasten, our Senior Exploration Manager, will recap the heap leach resource and our exploration potential. Mike Eiselein, Vice President, Project Development, will walk you through the engineering behind the study. Shawn Campbell, our Chief Financial and Development Officer, will take you through the project economics. I will finalize our presentation by summarizing the value creation opportunity ahead of us. We will then open the line for questions. Before we discuss the PFS results, I also want to say a word about safety.

Year to date, our employees and contractors have recorded zero reportable or lost time injuries and had no notices of environmental violations. Our safety performance reflects our continued commitment to being responsible operators. During the presentation today, we will be making some forward-looking statements, and we caution the audience to read the disclaimer on the presentation and our company website. Today is an important milestone for Dakota Gold. The Pre-Feasibility Study establishes Richmond Hill's first mineral reserves and supports an efficient open pit heap leach project on private land in an established mining district. Our PFS supports an efficient, low-cost, three-stage crush and truck and stack operation that provides strong economics and significant leverage to the gold price.

At our base case gold price of $3,500 per ounce, the study shows an after-tax net present value at a 5% discount rate of $2 billion and an after-tax internal rate of return of about 71%. Initial capital of $538 million, including an $83 million contingency based on a 41,000 metric ton per day stacking rate with an after-tax payback of 1.4 years. Gold production averaging 171,000 ounces per year, which makes this a meaningful gold producer with approximately 1.6 million ounces over a nine-year mine life. Life of mine all-in sustaining cost of $1,289 per ounce, which is in the bottom quartile of all producers. Importantly for shareholders is production. At our base case gold price, the project will generate over $350 million in after-tax free cash flow to reinvest in our other Homestake District opportunities.

The second row on this slide shows the same project at a gold price of $4,250 as a sensitivity. Net present value rises to $2.7 billion, the internal rate of return to 94%, and the payback shortens to 1.1 years. All-in sustaining costs move up to $1,357 per ounce, primarily because of higher royalties. The PFS mine plan has been designed with robust crushing capacity and infrastructure to accommodate expansion and a long mine life. The deposit at Richmond Hill is open in multiple directions, and with current drilling targeting the additional resource beyond the reserve, we see significant potential upside to what is presented here today. Richmond Hill's growth potential starts from a deliberately conservative foundation. Our pits are optimized for oxide material only, and recoveries are assigned by rock type, cyanide soluble content, and sulfur content.

First, our 2026-2027 definition drilling program is targeting the higher recovery breccia zone to convert inferred material. There is 90 million tons of leachable inferred material across the project that is not included in the PFS. Second, we see further upside in optimizing the pit design and processing plan in the feasibility study. As a reminder, the current plan focused solely on oxide for pit design and optimization. Finally, we have designed a plant and heap infrastructure that allows us to evaluate increases in both throughput and placement rates. Overall, we are very pleased with the quality of our pre-feasibility study, which we see as an interim step towards the feasibility study in 2027. I'd now like to pass the presentation over to Lindsay Chasten, our Senior Exploration Manager.

Lindsay Chasten
Senior Exploration Manager, Dakota Gold

Thanks, Jack. The heap leachable totals 2.2 million ounces of proven and probable gold reserves, an additional 0.4 million ounces of measured and indicated gold resources, and 1.1 million ounces of inferred gold resources. There are 25.4 million ounces of proven and probable silver, 5.2 million ounces of additional measured and indicated silver resources, and 8 million ounces of inferred silver resources. Mill material, while not part of the heap leach case, provides long-term optionality. Since the initial assessment, we've drilled about 30% more footage than went into the prior model. This footage also contributed geochemical data used to develop the metallurgical model, which is refined over the initial assessment. Independent of the metallurgical results, the updated mineralization model is very similar to that of the initial assessment.

Blocks above internal cutoff that were inferred in the initial assessment, but are now measured and indicated in the pre-feasibility study, had an average grade of 0.36 grams per ton and now have a grade of 0.41 grams per ton, as the inferred model proved to be accurate, along with new ore trends being intercepted. As expected with the pre-feasibility study level resource, factors differ from those used for the initial assessment resource. There is now a more specific oxide definition, additional new metallurgical and geochemical data, and further established constraints. The result is a well-defined resource with confidence in leachability. We've given the highlights in the previous slide. Slide eight provides the detail. The additional resource outside the reserve domain, currently being targeted by our drilling, demonstrates the upside beyond the pre-feasibility study, and that the mine life has the potential to be extended.

Slide nine provides a section view of the northwest part of our deposit, comparing the initial assessment model with the pre-feasibility model. The blocks shown are measured and indicated, with color representing grade. In the initial assessment model section at the top, you can see gaps, areas where classification was inferred, but still inside the previous shell. The 2025- 2026 infill drilling filled those gaps to decrease spacing and move material into the measured and indicated categories, and ultimately support the reserve, as shown in the pre-feasibility study model section below. Some gaps were filled in below the bottom of heap-leachable material as well, as defined by the current metallurgical thresholds informing the pre-feasibility study. Inferred was also converted at shell edges and within main pit areas. This section is in the northeast area of our deposit.

Here, the drilling was focused on expansion northwards and on the extension of several high-grade ore zones down dip, extending measured and indicated beyond the edge of the initial assessment model. The new model reflects what has been reported in the last year's results, with expansion holes intersecting mineralization over 360 meters north of the previous measured and indicated boundary, and the northeast remains open in all directions. Our current drill program focuses on inferred conversion and metallurgy, with an opportunity for quickly completing definition drilling within the central portion of the deposit. Breccia, fractured Precambrian rock, and tertiary intrusive are the dominant rock types. In the map view and section view, existing Dakota Gold holes are shown in green, historic traces in black, and planned holes in magenta. We have a significant amount of inferred material here, with colored blocks reflecting grade.

This program was developed to capitalize on good recovery numbers in the breccia and the potential for conversion of inferred mineralized blocks. The program will also improve confidence in metallurgical definition of this area by adding geochemical data in these new holes. We are drilling about 11,000 meters in 123 holes through early 2027 in this definition program, and this information will feed into the feasibility study in 2027. This drilling will also give us cyanide-soluble gold data and multi-element geochemistry data. We can use these metrics to determine metallurgical domains precisely as we convert this material. Mike Eiselein, our Vice President, Project Development, will now take you through the engineering. Mike.

Mike Eiselein
VP of Project Development, Dakota Gold

Thank you, Lindsay. This PFS was led by a very seasoned Dakota Gold team with extensive industry experience, directly supported by M3, with specialists across mining, metallurgy, heap leach design, and environmental engineering. The combined team has accumulated hundreds of thousands of hours designing and building similar projects all over the world. They provide the technical expertise and experience to carry us through the FS and ultimately to build this mine. Together, Dakota Gold and the team developed a nine-year plan producing roughly 1.6 million ounces by crushing and stacking 120 million tons life of mine from an optimized mine plan with an extremely low strip ratio of 1.18. In our plan, we were able to significantly improve the average grade to the pad, along with a higher target throughput over previous studies.

This results in a significant improvement to the ounce production profile, averaging 171,000 ounces annually for a total of 1.6 million ounces. The basis of the PFS plan is an eight-year mining sequence that brings higher value material forward to maximize ounce placement at the targeted tonnage rates. The low strip ratio and shallow pits make for simple and straightforward mining with a conventional truck and shovel fleet. Based on our experience, we can operate this mine with a hydraulic shovel and a couple loaders combined with 150-ton class trucks. This fleet gives us maximum operational flexibility with ease of operation and maintenance. As the pits develop, mining quickly reaches a steady rate while the transition material stockpiled throughout the plan for processing at the end of the mine schedule.

Once crushed ore reaches the pad, gold recovery benefits from short leach cycles averaging between 30 days and 45 days for most ore types. Significant expansion capacity is available by application of additional capital within the PFS design if deemed advantageous later in the plan. We designed this pad to be on-off in the upper pad phases, further allowing us a great deal of operational flexibility. To maintain simplicity and help control overall initial capital, we designed a conventional three-stage crushing circuit and a Merrill-Crowe recovery plant with an equipment profile selected that we know will provide a great deal of robust mechanical and operational reliability, excellent throughput flexibility, and low operating and maintenance costs. Jack and I, along with our project partners, have installed and operated similar gear previously, so we have a great deal of confidence in our fleet selection, sizing, and designs.

Our project capital spend supports a compact site layout, including a large 154 million ton consolidated heap leach pad design to provide maximum operational flexibility for the future. I want to emphasize that the plan laid out in this PFS can be fully executed within our existing footprint as shown. As we discussed, we kept to a conventional process that is simple and straightforward, three-stage crushing, including a gyratory crusher, truck stack heap leach pad with multiple pad expansion phases, Merrill-Crowe recovery process plant, and on-site production of a gold-silver doré product. This simple design drives our total operating cost to $978 per ounce, and our before-tax AISC is $1,066 per ounce. Our after-tax AISC rises to $1,289 per ounce, and this project will be a solid low-cost producer.

The low-cost nature of the project, of the production is driven by simple processing and a low strip ratio. For the PFS, we undertook a rigorous metallurgical variability testing campaign to fully establish confidence in the quality of the resource and ultimately the project we intend to build. Led by our partners at SLR, formerly Forte Dynamics, we produced a body of work that fully established excellent metallurgical performance characteristics in the four primary lithologies and geomet domains across our resource. In parallel, we undertook an extensive geochemical testing and modeling campaign to accurately characterize oxide ore from transition and sulfide ores. The result is the ability to characterize ore and leach with a great deal of precision to optimize recovery on the pad and reduce the risk of mishandling or misrouting non-heap leach materials.

Finally, Richmond Hill benefits from vibrant nearby communities with established mining infrastructure and with a skilled labor pool throughout the region. There are existing roads, power infrastructure, and mining service vendor supports within a 160 km radius of the site. I will now turn the presentation to Shawn Campbell, our Chief Financial and Development Officer.

Shawn Campbell
Chief Financial and Development Officer, Dakota Gold

Thank you, Mike. Now let's turn to the Pre-Feasibility Study economics, the sensitivities, and other metrics that demonstrate a robust project. As a reminder, the base case after-tax NPV is $2 billion. The after-tax IRR is 71%, with a 1.4-year after-tax payback. At $3,500 per ounce gold, Richmond Hill would generate over $350 million in annual after-tax free cash flow per year. Another exceptional point for this project is that even at a low gold price of $2,750 an ounce, it has an IRR of almost 50% and an approximate payback of two years. At a gold price of $4,250 an ounce, the NPV increases to $2.7 billion, and the after-tax payback is approximately one year. Due to the project's high margin, it is not sensitive to operating or capital cost. Even a 20% change in either metric drives less than a 10% change in NPV.

That gives it a very attractive, low-risk financial profile. The project remains sensitive to gold recovery. We are pleased our study assumptions are based on the 24 columns included in the significant amount of metallurgical work undertaken by SLR. On slide 27, the after-tax free cash flow chart shows both the base case and a $4,250 gold price. You can see the project has the ability to generate in excess of $350 million a year in after-tax free cash flow from years one through eight, thanks to its low operating cost. Slide 28 shows other key metrics for project evaluation. The ratio of net present value to initial capital is 3.7- 1. The initial capital is paid back 4.7 times over the life of mine, and the initial capital remains less than our market cap .

This high-return project should reasonably support better-than-average access to capital for development and construction purposes. Looking at enterprise value per ounce of resource, the company has a large global resource that is currently receiving a market value of only $63 an ounce. Per ounce of reserve, the company is sitting at $281 per ounce. We believe that as a high-margin project located in the U.S. at the pre-feasibility stage, with an executable plan to advance through feasibility and into production, Richmond Hill warrants a premium. We are excited about the potential re-rate that occurs as we execute our production strategy. With respect to the equivalent position of other mid-tier producers, 170,000 ounces per year of annual production equates to a market value of between $1.2 billion and $3.9 billion, or an average of $2.6 billion.

With that, I will now pass the presentation back to Jack.

Jack Henris
CEO, President, and Director, Dakota Gold

Thank you, Shawn, Mike, and Lindsay, for going over the strong foundation built at Richmond Hill with the PFS. Let me close by stepping back and talking about the value creation opportunity ahead of us. Through a disciplined, phased, and responsible development approach, we are advancing Richmond Hill toward our target of first gold production in late 2029. Over the next 12 months, we are looking forward to significant project milestones. We will be completing our Feasibility Study, where we are targeting reserve growth. We will also complete the remaining baseline studies and file our notice of intent, large-scale mining permit, and the Lawrence County conditional use permit. Following the anticipated receipt of permits in late 2028, we will begin construction. Our $92 million cash balance as of September 30th, 2026, allows us to fund all planned expenditures to being shovel-ready for construction in 2028.

In addition, we have sufficient capital to secure long lead items in advance of construction, helping to mitigate construction risks. Dakota Gold's project portfolio includes 50,000 mineral acres surrounding our headquarters in Lead, South Dakota, and the historic Homestake Mine, which produced 40 million ounces of gold continuously over 125 years. Dakota Gold's land package creates a diversified project development portfolio in one of America's most prolific gold districts. Building on the Richmond Hill PFS, we are currently drilling, targeting the additional resource beyond the reserve in our Feasibility Study for 2027. Once Richmond Hill is in production, its cash flow can be used to grow the company and create additional value. That may include advancing the high-grade underground gold mine target at Maitland, just 2 km from Richmond Hill, and continuing to explore our large land package.

To close, I want to thank our employees, our contractors, and our consultants, including M3 and the full study team, for their work on this study. I also want to thank the residents of Lead, Lawrence County, and the state of South Dakota for their continued support. Thank you for taking the time to join us today. We would now like to turn the presentation back to the operator and open the line to questions from the audience. Operator?

Operator

Certainly. To join the question queue, you may press star then one on your telephone keypad. You will hear a tone acknowledging your request. If you're using a speakerphone, please pick up your handset before pressing any keys. To withdraw your question, please press star then two. If you're participating through the webcast, you can submit a question in writing by using the form in the lower section of the webcast frame. We will wait a moment for callers to join the queue. The first question comes from Heiko Ihle with H.C. Wainwright. Please go ahead.

Heiko Ihle
Analyst, H.C. Wainwright

Hey, everybody. Congratulations on this release. Obviously, a long, long time in the making, lots of work and sweat gone into this, and I think it Haven't gone fully through the whole thing, but it reads itself quite well. Let's talk about your plans for the 2026, 2027 drilling program a bit, please. I mean, obviously, the focus is the resource conversion, as you mentioned earlier. Is there some color that maybe you can give us in ways that the ore body surprised you in past drilling, and where the drilling stands now location-wise compared to where it would have been maybe a year or two years ago? Is there maybe any areas that you think the analyst community and your investor base should particularly focus on in regards to favorable results that maybe were not quite as expected?

Lindsay Chasten
Senior Exploration Manager, Dakota Gold

Thanks, Heiko. We're planning to be drilling the central breccia area, which is one of our high recovery rock types so far in the metallurgical program we've been doing so far. That area is a bit of a new target for us compared to what we've drilled in the past, which was focused on Deadwood and intrusive. This area has a potential to convert quite a bit of our inferred material as well. In the past, I would say that our inferred conversion, the grade of the blocks that were previously inferred that has been converted to M&I in the last two years has actually increased. So our model has performed well year-over-year, and we've actually intercepted more high-grade zones than were previously modeled. So, we're hoping to find similar results with this program.

Of course, we can't commit to anything yet, but we're excited about the program that will be going forward here pretty shortly.

Heiko Ihle
Analyst, H.C. Wainwright

Fair enough. Walk me through scalability. I mean, you had the equipment breakdown on page 16 of the presentation. I mean, if gold prices were to rip, and we're back into $5,000 an ounce land or thereabouts, is there any indication of how long it would take to scale up ops at site? Also, just permitting-wise, what exactly would be needed to do so if pricing and conditions warrant?

Mike Eiselein
VP of Project Development, Dakota Gold

Hey, Heiko, Mike here. For scalability, the reason we chose the design we did is it gives us

a high margin of that flexibility, operability, optionality, excuse me, later on without a whole lot of downtime to the circuit at all, in fact, almost zero. Because we're leaving expandable slots open for additional crusher capacity, so it's essentially dropping in an additional crusher and proceeding that way. The gyro is kind of on the lower, middle-lower tier of sizing, 60 by 89, you know, Metso type Superior MKIII crusher. So, it's just simply changing concaves and a mantle to get that additional throughput. So, from a crusher material handling perspective, it's all there. It being truck stacked, you know, that also does not hamper you. You know, if it's an additional truck, that's pretty easy to turn on.

The rest of the constraint is, can you advance liner ahead of you fast enough to accommodate that increased throughput, plus, you know, being able to stack it and leach it and get through the leach cycle? So, the design that we have in there accounts for just about all of that. Obviously, as we fill the pad, it becomes a little bit tighter. But, you know, having run these before, we learned a long time ago that you don't want to hamstring yourself if that were to happen. This is a potential, this is a project that has the potential to really benefit from increased throughput, and we recognize that, and we want to have that to put in. As far as permitting goes, incrementally, it'll be pretty easy, I would imagine. Cam Trimburth is online for us on the permitting side as well.

But I don't suspect it will be. It's probably just a permit mod at that point to get the increased throughput. Everything else should be done, I would imagine.

Heiko Ihle
Analyst, H.C. Wainwright

That's very helpful. Thanks for the comprehensive answers, and congratulations. I'll get back in queue.

Mike Eiselein
VP of Project Development, Dakota Gold

Thank you.

Operator

The next question comes from Andrew Mikitchook with BMO Capital Markets. Please go ahead.

Andrew Mikitchook
Analyst, BMO Capital Markets

Hi, team. Congratulations on this important milestone. Just kind of forward-looking, what are the milestones that you guys have to meet to initiate permitting and complete permitting by, I guess, I think the wording was the end of 2028, from earlier comments on the call?

Jack Henris
CEO, President, and Director, Dakota Gold

Yeah, Andrew, this is Jack. Certainly, filing our notice of intent, a big milestone for us. Right on the heels of that, be the large-scale mining permit that will be filed later in 2027, you know, in conjunction with us working on the feasibility study as we pivot right to that, certainly, which is scheduled for next year as well. A number of milestones and key objectives that we need to complete to get us queued up for permitting in 2028, and then an investment decision, and then into construction after that.

Andrew Mikitchook
Analyst, BMO Capital Markets

Okay. Coming back to this expansion, the press release uses wording that you've got several million ounces in both categories of millable material. Is any of that, you know, maybe to pick up the wording from the previous analyst, you know, at higher gold prices, is that just join the heap leach, or is it really kind of segregated and outside of this potential heap leach plan?

Mike Eiselein
VP of Project Development, Dakota Gold

Yeah, so the millable category is a little bit of a misnomer. It is millable only in the fact that it's refractory, so it's sulfide and not heap leachable ore for all intents and purposes. It's just too high sulfide, too high risk to the pad, and just would not recover well anyway. So, it would be ultimately, you know, those ounces just shift from bucket to bucket and requires a different flow sheet is all for processing.

Andrew Mikitchook
Analyst, BMO Capital Markets

Right.

Operator

The next question comes from Eric Winmill with Scotiabank. Please go ahead.

Eric Winmill
Analyst, Scotiabank

Oh, hi, Jack and team. Thanks a lot for taking my question, and congrats on the study. Maybe just a question, if you wouldn't mind elaborating a bit on some of the different domains here. I know you did quite a bit of metallurgy work and drilling, obviously going into the study. Maybe any thoughts on how that's changed from what you'd seen previously?

Mike Eiselein
VP of Project Development, Dakota Gold

Well, yeah. So, historical work didn't really provide any clarity on really what the geomet domains were. They weren't defined really by rock type or lithology that I could find anyway, going back quite a few years. So, we took an inordinate amount of time on this one to really break that out. Really, everything flows out of the four lithologies that we have there and the rock types. Then the subcategories, the geomet domains below that, are segregated by sulfide, sulfur, and soluble gold, CN/FA ratio, and then grades. So, we were able to establish a pretty tight matrix. It's in the report that really defines those areas and is a great outline. I mean, that's why you do that work, so you can really get an understanding of how you characterize and categorize.

Oxides from transitions to transition material and sulfide material and waste to really optimize things to the pad and ensure that you're not putting the operation at risk. So, a tremendous amount of work went into that. Lots of bottle rolls to help break, establish those master composites and those shield net domains.

Eric Winmill
Analyst, Scotiabank

Okay, great. No, super helpful. Thank you very much. Maybe just one more on the long lead time items. Any sort of critical path items that you are worried about, or do you see tightness in the supply chain out there?

Mike Eiselein
VP of Project Development, Dakota Gold

The only thing that we were worried about was the power distribution equipment for the site, the substations and the switchgear for the coming off the main power line, the utility line. With all the data centers out there, you can imagine those were going from 18 months all of a sudden to three-plus years out. So, we secured that already because of that. The remainder of the long lead items, which is basically a crusher and material handling stuff, isn't that bad currently. It may change, but right now it's about 18 months, maybe pushing 20 months in some instances. But it's a 150-ton class truck. Those aren't long lead. Everything else is looking pretty reasonable, so not too worried about anything else other than what we've already secured with the power.

Eric Winmill
Analyst, Scotiabank

Okay, great. No, appreciate that. I'll hop back in the queue, but yeah, congrats to you on the study. Cheers.

Mike Eiselein
VP of Project Development, Dakota Gold

Thank you. Thanks, Eric.

Operator

The next question comes from Luke Bertozzi with CIBC. Please go ahead.

Luke Bertozzi
Analyst, CIBC

Thank you, operator, and good evening, Jack and team. Congrats on the solid PFS. I am just curious, you touched a little bit on the potential to actually increase the throughput here. What would it take to see that happen? Do you need to see just kind of a resource growth? I guess just curious on your thoughts on the trade-off of throughput and mine life there.

Mike Eiselein
VP of Project Development, Dakota Gold

Yeah, so really, it is crusher capacity and installed horsepower, right? We left that flexibility within the building design so we could just slot in additional crusher capacity really relatively easy. Because we are crushing to half an inch, you need the crushing power, you need the crushers. Everything upstream and downstream of that, we sized the gyratory crusher accordingly because of that, and it has got plenty of flexibility. Everything downstream, such as truck stack, is just additional trucks. We got a load-out hopper that is sufficiently sized as well, even at the higher rates. Mining rates would be, again, that is just the fleet. That is just additional equipment and coordination there. It is pretty easy to turn the dial there. Stacking in a valley fill or a hybrid becomes a little bit more orchestration at that point, but nothing we are not accustomed to, and plenty of flexibility there as well.

Yeah, this project lends itself easily to a potential throughput expansion if that really warrants itself in very short order without impact to the operation.

Luke Bertozzi
Analyst, CIBC

I see. Thanks. What would really help you make that decision to go with the higher throughput case?

Mike Eiselein
VP of Project Development, Dakota Gold

Yeah, good question. It just becomes how we are going to rely on Lindsay to keep us well-supplied in resource and reserve. Obviously, if we can grow the resource, we will be looking very closely then to advance that and get that on the pad and get ounces out to help that production curve, right?

Luke Bertozzi
Analyst, CIBC

Yeah, I see. Okay. Thanks, Mike. I think that is most of my other questions have been answered, so I will leave it there. Thanks, guys. Congratulations again.

Mike Eiselein
VP of Project Development, Dakota Gold

Thanks, Luke.

Operator

The next question comes from Jake Savage with Agentis Capital. Please go ahead.

Jake Savage
Analyst, Agentis Capital

Hi, good afternoon, everyone. I am wondering if you can provide a bit more color on the mining schedule and any changes that have been made with respect to the initial years versus the IACF, if there are any kind of starter pits that have been outlined, and then how the waste backfill schedule has changed as well.

Jack Henris
CEO, President, and Director, Dakota Gold

Yeah, so great question there. So, in the initial assessment, we envisioned kind of starting in the northeast part of the deposit, moving west, and then moving south. What I like to talk about with the results that the team has seen, we are certainly data-driven, and with the metallurgical results that Mike talked about in length, we start to see these four geometallurgical domains, and you start to see that if you want to optimize the pits, as we pivot from the initial assessment to the PFS, focus on NSR, which is a combination of strip grade and recovery, it changes the sequence a little bit for what that might look like.

I think that is one of the things that we are going to evaluate as we move forward from the PFS to the FS, as Mike stated. With the work that Lindsay is doing and the drilling, we saw that preferentially the breccias had higher recovery. So that is the area that we are drilling, and we will see what that sequence looks like. You could certainly see a potential change in sequence as we pivot from PFS to FS. Again, the company certainly being data-driven by the results of previous work. So that sequence could change a little bit as we move forward, but we will see what the results of the drilling tell us, and we will bake that into the FS going forward.

Jake Savage
Analyst, Agentis Capital

Excellent. Thanks again.

Jack Henris
CEO, President, and Director, Dakota Gold

Thanks, Jake.

Shawn Campbell
Chief Financial and Development Officer, Dakota Gold

All right. In addition to some of the questions we had from callers, there is still the opportunity to log another call. We had a number of questions come in through the webcast. I will read out the questions, then we will answer those. The first question we had from an investor was, "When will you exercise the option with Barrick?" To answer that, I will say that the option runs until December 31st, 2028. We have up until that time to exercise the option. We are looking at different trade-offs for early exercising earlier in 2028 or even 2027, just depending on the ability to bond it. As a reminder, the only remaining steps with that are the proper notification as well as assuming the approximate $40 million reclamation bond associated with the property.

The next question we had was, "What is the assumed recovery, and how confident are you on the met work that has been done so far?

Mike Eiselein
VP of Project Development, Dakota Gold

So, if you look back in this slide on the production profile for the pad, we are showing a life of mine recovery of 72.4%, and we have shown how that will vary over the years as we advance the mine plan. That is pretty typical what you see on a heap leach, is you get more ounces and a higher grade with different various levels of recovery. Recovery goes up and down based on all those factors, plus inventory that is retained on the pad and comes out at different times. We are highly confident in these results. Like I said, we undertook probably one of the better exercises in my career on trying to model these different ore types and lithologies because of some of the complexity and performance variances that we are seeing in different rock types and different mineralogy out there.

Not only that, but characterize from an oxide and transition perspective how they behave as well. We have documented that very, very well, and you will see that in the technical report as well. We have a high degree of confidence in the precision of that work and what it is going to mean to that long-term operation of the pad. As we do the FS, we will actually do mine-to-heap modeling on a month-by-month basis to show much more precision in predicting shorter-term recoveries on operational windows as the life of mine advances. This was a good body of work as far as that goes.

Shawn Campbell
Chief Financial and Development Officer, Dakota Gold

All right. The next question we had from online was, "What are the current status of the royalties payable by the project, and to whom are they payable to?" I will take that question. Right now in our PFS, the royalties work out to an NSR of 2.98%, or just below 3%. The main royalties are payable, 1% to Barrick on exercise of the option. As well, there was a royalty that Orion had that was sold to Elemental. There is one other royalty that is disclosed in the technical report, and then some very small minor ones. But overall, less than 3% NSR royalty on the project. Next question was, "What are the key risks and bottlenecks identified at this stage, and what is the plan to de-risk the project related to those key risks?

Mike Eiselein
VP of Project Development, Dakota Gold

The operational risks were typically what you see with the heap leach design. It is a hybrid valley fill, so the design, working with NewFields, who is very, very good at these, by the way. The reason I brought them in is because they have done a lot of valley fill, and this is no different, is making sure you are not constrained by pad construction in an operation. Same with the throughput to the plants, you are not bottlenecking yourself there. We have given ourselves quite a bit of upside potential and operational flexibility with that. As well as the mine, these are shallow pits, low strip ratio. We have a very nimble fleet. It is contemplated to be a hydraulic shovel and a couple loaders, so we can jump around to different areas to chase either grade and opportunities there very easily.

Having run these types of operations over the years, we did a very, very detailed risk assessment, and we've highlighted as well in great detail over 70 items that we've encountered in previous operations that we're addressing through our design and engineering. I guess environmental would be, is always an unknown, I suppose. Managing, we've got a good team with Cam heading that up to really define the process and coordinate with the state and local authorities to ensure that we're keeping them informed and advancing things along that timeline, critical timeline. I don't know, did I miss anything, Jack?

Jack Henris
CEO, President, and Director, Dakota Gold

Nope. No, I think that's great. Cam's been working closely, certainly with regulators. So, we're keeping the team informed and on track for the work that goes into doing that permitting. Quite a bit of legwork upfront to de-risk that as much as we can.

Shawn Campbell
Chief Financial and Development Officer, Dakota Gold

Thank you. The next question from online is, what do you expect the news flow to look like over the next 12 months? I can take first part of that, and maybe Jack or Mike, if you want to chime in. As we've talked about, we're currently drilling in that breccia area, so we do expect to start to have assays come in and press releases related to those shortly. Obviously, the major milestone is the feasibility study expected mid-2027. Depending on the progress and the key inputs to that study, we may or may not have a release similar to what we did with the PFS, where key metrics or trade-off studies that have been concluded could be press released early, but that's to be determined.

Jack or Mike, we had one question come in, and it said, "Curious about the main drivers for the higher initial CapEx. Is it largely due to throughput and inflation, or are there other notable drivers?

Mike Eiselein
VP of Project Development, Dakota Gold

Yeah. The more significant drivers there are, well, the two primary ones are the 50% increase in throughput, a lot bigger equipment with the gyratory crusher on the front end and MP1000 class crushers for secondary and tertiary crushing. Obviously, that's a significant impact. We're truck stacking, but that equipment didn't have as much impact as the heap leach design is a valley fill. The phase I construction of that pad is relatively large, and you need that to ensure that you can get production and advance production without hamstringing yourself there. Being a valley fill with steep sides, it tends to be a little bit more costly than a traditional heap leach pad that you would see in Northern Nevada, for example. Those were the significant drivers in the capital over what you saw from the IACF.

Shawn Campbell
Chief Financial and Development Officer, Dakota Gold

Thank you, Mike. Maybe somewhat related to that, we had a question about why did the sustaining capital and closure cost decline from the IACF?

Mike Eiselein
VP of Project Development, Dakota Gold

Yeah. The sustaining costs dropped from the There was a large portion of the heap leach in the IACF that was pushed into sustaining costs. Well, we had to do the kind of the reverse there with the large upfront initial capital for the phase I of the pad that wasn't contemplated, because it really didn't have Those were conceptual designs in the IA. With really the detailed designs we have now, that drove a significantly higher initial capital and moved that out of sustaining. The closure reclamation cost dropped between the IACF and the PFS. Again, a little bit more rigor around the detail that went into that, and it'll be even another higher order of magnitude into the FS as we really drill down into the detail of closure and reclamation.

I think there was some re-handling material that isn't required just due to the change of the operation and the stacking, the heap leach operation. Those costs were reversed out too.

Shawn Campbell
Chief Financial and Development Officer, Dakota Gold

Well, we do, just being conscious of the time, it is 5:30 P.M. Eastern. We do have a few more questions that have been submitted, but we will answer those questions directly by getting back to the investors that have asked those questions. With that, we will conclude the question and answer session. I will pass it back to the operator.

Operator

I would like to turn the conference back over to Jack Henris for any closing remarks. Please go ahead.

Jack Henris
CEO, President, and Director, Dakota Gold

Thank you for taking the time to join us today for the conference call and webcast. We look forward to providing updates as we continue to advance work at Richmond Hill.

Operator

This concludes today's conference call. You may disconnect your line. Thank you for participating, and have a pleasant day.