First Solar, Inc. (FSLR)
NASDAQ: FSLR · Real-Time Price · USD
193.76
-2.43 (-1.24%)
At close: Apr 24, 2026, 4:00 PM EDT
193.68
-0.08 (-0.04%)
After-hours: Apr 24, 2026, 7:59 PM EDT
← View all transcripts

Earnings Call: Q4 2018

Feb 21, 2019

Speaker 1

Good afternoon, everyone, and welcome to First Solar's Q4 2018 Earnings Call. This call is being webcast live on the Investors section of the First Solar's website at firstsolar.com. At this time, all participants As a reminder, today's call is being recorded. I would now like to turn the call over to Steve Haymore, from First Solar Investor Relations. Mr.

Haymore, you may begin.

Speaker 2

Thank you. Good afternoon everyone and thank you for joining us. Today, the company issued a press release announcing its fourth quarter full year 2018 financial results.

Speaker 3

A copy of

Speaker 2

the press release and associated presentation are available on First Solar's website at investor. Firstsolar.com. With me today are Mark Widmar, Chief Executive Officer and Alex Bradley, Chief Financial Officer. Mark will begin by providing a business and technology update Alex will then discuss our financial results for the quarter and full year and provide the latest updates around 2019 guidance. Following their remarks, we will then have time for questions.

That could cause actual results to differ materially from management's current expectations. We encourage you to review release and presentation for a more complete description. It is now my pleasure to introduce Mark Widmar, Chief Executive Officer. Mark?

Speaker 4

Thanks, Steve. Good afternoon and thank you for joining us today. I would like to start by briefly discussing our EPS results for 2018. EPS of $1.36 came in slightly below the low end of the guidance range we provided at the time of our Q3 earnings call. While Alex will provide a more comprehensive overview, I wanted to highlight two items that had a material impact on the quarter.

Firstly, late in the year, we incurred increased EPC costs in order to meet deadlines for certain U. S. Projects. Climate weather and delayed shipments of materials to site adversely impacted plant construction and project commissioning schedules. The potential of project completion delay was particularly acute at one of our projects in California.

To ensure the project's cap structure proceeded as planned, we incurred significant acceleration costs to meet key scheduled milestones. While the project owner shared an enforcement of these costs, acceleration costs impacted Q4 results by more than $10,000,000. Maintaining a strong relationship with key priority and therefore, we made an investment in our partnership and long term relationship with this customer. Secondly, in Q4, continue to make at our 2nd Vietnam factory the 1st week of this year, 3 months ahead of our original plan and 45 days ahead of our latest expectation. The continued factory ramp across all sites combined with the earlier than planned startup of our 2nd Vietnam factory put pressure on our supply chain to support the accelerated schedule.

To maintain continuous operations across the entire fleet, we decided to airfreight certain raw materials to our factories. Which adversely impacted the 4th quarter by more than $10,000,000. Accelerating the Vietnam start date helped to provide resiliency to our 2019 Series 6 production plan. The production could lead to additional revenue, but more importantly, it creates optionality for downtime investments to increase throughput via tool upgrades or production buffers or to run engineering test articles to increase module efficiency. Turning to slide 4, I'll provide additional comments on 2018.

Despite the year where the solar market faced excess capacity and pressure on milder pricing, primarily as a result of policy changes in China, We were able to make steady progress and strengthen First Solar's competitive position. In 2018, we added to our contracted pipeline with strong net bookings of 5.6 Gigawatts DC, a greater than 2 to 1 book to ship ratio, which provides improved future visibility as we grow our Series 6 over the coming years. Systems projects were a significant portion of these bookings and we signed 1.3 Gigawatts DC of new PPAs last year. In addition, we added EPC scope to 500 megawatts of previously booked module sales, which combined with our development bookings positions us meet or exceed our targeted 1 gigawatt per year assistance business. Our 2018 bookings were also highlighted the strong demand for Utility Scale Solar from C and I customers.

Approximately 500 megawatts of our total 1.3 gigawatts of development project bookings, where PPA signed with utilities, where corporate customers are the intended consumers of the energy to be generated by these projects. Additionally, this trend has continued into 2019 with our recent booking of a nearly 150 Megawatt PPA with a corporate customer. We expect corporate demand for solar projects to continue to grow in coming years and we believe that our strong reputation and ability to offer turnkey solutions will position us to compete effectively for future opportunities. International wins were a meaningful portion of our 2018 bookings with more than 700 megawatts booked primarily in Europe. While strong domestic demand for our Series 6 product has limited our ability to support international market opportunity We expect international bookings to grow as we continue to invest in our regional sales team and add planned Series 6 capacity.

2018 was a record year for O and M bookings as we added nearly 3.5 gigawatts of new business, bringing our total O and M fleet under contract over 11 gigawatts at the end of the year. We remain encouraged by the opportunities to continue growing O and M and to leverage the fixed costs associated with this business. From a manufacturing perspective, we made progress starting in ramping Series 6 capacity over the course of 2018, During the year, we started production at 3 Series 6 factories, which collectively manufactured a combined 0.7 Gigawatt DC of modules. The production run rate of these factories at the end of 2018 was over 2 gigawatts, which is a significant achievement considering initial production did not begin until April. Construction of our 4 Series 6 factory was completed in late 2018 and recently started production.

Lastly, our 5th factory is under construction and progressing according to plan with an anticipated start of production in January 2020. To concurrently manage all the activities related to the construction, startup and ramp of the 5 different factories was a major undertaking that has positioned us to meet our strong demand for Series 6 in 2019. Also note in the late 2018, we reached the 20 gigawatts shipping milestone. This reflects cumulative shipments since the founding of First Solar highlights the extensive deployment of our CADTel Technology worldwide. Overall, our operational financial results 2018 have created a solid platform as we move into 2019.

Turning to slide 5. I'll next discuss our most recent bookings in greater detail. In total, our net bookings since the prior earnings call in late October were 1.6 gigawatts including 1.3 gigawatts, which were booked since the beginning of January. After accounting for shipments of approximately 900 megawatts during the fourth quarter, our future connected shipments, which now extends into 2023, are 12.1 gigawatts. Our most recent bookings include 2 PPAs that were signed totally more than 300 megawatts DC.

The first of these PPAs was signed with MC for the expansion of the Little Bear project in California. The second PPA was signed with a major utility customer the Western United States and the project will support a collaboration between the utility and its corporate buyers to meet their renewable energy objectives. Included in our new module bookings is a greater than 1 gigawatt agreement with a major customer in the United States for shipments in 2021 and beyond timeframe. This booking highlights the continued strong demand for Series 6 in the United States, particularly as certain customers look for opportunities to safe harbor modules to serve the higher ITC. While we are pleased with our 2018 bookings of 5.6 gigawatts and the greater than 2 to 1 book to ship ratio, It is important to put our 2019 bookings expectations into perspective.

Relative to our module competitors, we are in an extremely favorable position essentially being sold out over the next eight quarters. Generally, our customers, particularly in international markets, do not contract for module supply, multiple years in advance, given the project development cycle and the time horizon in which they have project certainty. While we are encouraged by our bookings year to date, and target a 1 to 1 book to ship ratio in 2019, our bookings may be more back end loaded given our available supply is 2018, we added nearly 3.5 gigawatts of new projects. A high percentage of these bookings was attributed to 3rd party wins defined as projects where are not the developer, but in which many cases include our module technology. 3rd party O and M not only expands our addressable market, but also helps to create economies of scale for our O and M business.

Some of the reasons for our continuing success in winning third party business are highlighted by an example of how we were able to leverage our O and M expertise to address the customer's need in a way our competition was not able. In 2018, we were approached by a customer seeking help with 2 large utility scale solar power plants in its portfolio that were under contract with a competing O and M provider and were underperforming. These projects utilized for competing module technology and were not constructed by 1st solar EPC.

Speaker 3

Based on

Speaker 4

the customer's experience with our O and M services, they asked us to investigate the cause of the underperformance. By leveraging our industry leading expertise, As our O and M team, we identified the root cause of the underperformance and created a detailed action plan to improve performance. The recommended corrective actions are expected to improve the annual energy output of the combined plans by approximately 3% which translates into more than $1,000,000 of annual revenue to the owner. As we continue to leverage our significant O and M experience to meet customer needs, We expect that 3rd party wins will continue to be a key part of our growing O and M fleet. Slide 6.

Provides an updated view of our mid to late stage bookings opportunity, which now totals 7.3 Gigawatts DC, a decrease of approximately 500 megawatts from the prior quarter, primarily as a result of our strong recent bookings. However, when factoring into bookings for the quarter, 1.4 gigawatts of which were included as opportunities in the prior quarter, our mid to late stage pipeline actually grew by approximately 900 megawatts DC. North America remains the region with the largest number of opportunities at 5.5 GigawattsDC. However, Europe has shown a meaningful increase since the prior quarter, driven by Resurgent Markets in France and Spain. Opportunities in Asia Pac Region have remained relatively stable.

Even with the more than 300 megawatts of recent systems bookings, our potential systems opportunities remain strong at 1.8 gigawatts DC. These potential system bookings are comprised of projects in the U. S. And over 300 megawatts in Japan. Continuing on to slide 7, I'll next provide an update on our Series 6 capacity rollout.

The most notable achievement to highlight since our prior earnings call is the start of Series 6 production at our 2nd Vietnam factory, our 4th Series 6 factory in total. As mentioned previously, production commenced in early January several weeks ahead of our targeted start date. Similar to our first Vietnam factory, the initial ramp has been accelerated relative to the previous facilities by applying accumulated learnings which including starting production with an improved module framing tool. Construction is continuing at our 2nd Series 6 factory in Ohio. Announced previously, we expect to start production in early 2020 and construction is on track to our schedule.

Once completed, we will have 5 factories with annual Series 6 capacity of 5.6 gigawatts, an impressive accomplishment since announcing the transition to Series 6 in November of 2016. Since the third quarter earnings call, we have seen steady improvement in our Series 6 throughput and wattage across our entire fleet. When comparing February's month to date performance to the month of October, you can see the significant improvements made. Note, our second Vietnam factory is excluded from this comparison as it was not operational in the base comparison period. Megawatts produced per day is up 65%.

Capacity utilization has increased 30 percentage points. The production yield is up 7 percentage points. And finally, the average watt per module has increased 2 bins or 10 watts. Since October, the percentage of modules with anti reflective coating has increased points. These significant accomplishments can be credited to the outstanding work of our engineering and manufacturing associates.

We are encouraged by the meaningful progress we have made over the last months of 2018 and how we started 2019. We continue to includes approximately 2 gigawatts of Series 4 modules. In order to meet these production commitments, we continue to roll out tool upgrades and optimize the production line throughput across the various sites. This is a dynamic process that continues to incorporate learnings from each of the factories as we have ramped and is moving according to schedule. I would like to make one final point before I hand the call over to Alex.

I mentioned in October, First Solar was a sponsor to an innovative study by E3, which highlighted the value of flexible solar to utilities in the form of expected reduce fuel and maintenance costs for conventional generation, reduce curtailment of solar output, and reduce air emissions. Since the study has been published, we have been pleased with the positive response and feedback from across the industry. For example, Public Utilities Fortnightly a leading industry publication recognized the study as 1 of their 2018 top innovators. Our efforts to demonstrate our thought leadership are not only limited to the United States. Recently, we supported this study by Solar Power Europe, that provides evidence to support the benefits of utilizing low cost utility scale solar to keep the European grid stable and reliable.

Efforts such as this will take on increasing importance in order for the European Union to meet its 2030 renewable energy targets and we look forward to remaining engaged in that process. Whether in the United States, Europe or other regions, we will continue to provide support and thought leadership advance the understanding of how utility scale solar enhances the reliability of power grids around the world. I'll now turn the call over to Alex who will provide more detail on our fourth quarter financial results and discuss updated guidance for 2019.

Speaker 3

Thanks, Mark. Before reviewing the financials for the quarter in detail, I'll first provide additional context around the factors that led the 2018 results falling below our guidance. There were 4 key issues that impacted our ability to meet earnings guidance. Firstly, 2018 net sales were $100,000,000 lower than the midpoint of our guidance due to the timing of module sales and delays in systems revenue recognition. The lower systems revenue is associated with inclement weather and also material delivery delays and projects.

Secondly and thirdly, as Mark mentioned earlier, we experienced increased EPC costs across several U. S. Projects, partially driven by scheduled acceleration to achieve year end customer milestones, and we experienced elevated inbound freight costs to expedite raw materials for Series 6 production. And fourthly, 2018 ramp and related costs $113,000,000 compared to our guidance of $100,000,000. So with that context in mind, I'll begin by discussing some of the income statement highlights for the fourth quarter and full year on Slide 9.

Net sales in the 4th quarter was $691,000,000, an increase of $15,000,000 compared to the prior quarter. The higher net sales were primarily a result of the sales of 2 projects in Japan. For full year 2018, net sales of 2,200,000,000 And as mentioned, relative to our guidance expectations, net sales were lower due to the timing of both module sales and delays in system revenue. As a percentage of total quarterly net sales, our systems revenue in Q4 was 83%, which was nearly flat compared to Q3. For the full year 2018, 78 percent of net sales came from our systems business compared to 73% in 2017.

Gross margin was 14% in the 4th quarter and was impacted by ramp charges of $44,000,000 as well as inbound freight costs and EPC acceleration costs. For the full year, gross margin was 18% and included $113,000,000 of ramp and related charges, which equates to a 5 percentage point impact. The system segment margin was 22% in the 4th quarter and the module segment margin was a negative 25%. It relates to the module segment gross margin, keep in mind that sales were composed almost entirely of Series 4 volume as Series 6 volume continues to be allocated almost entirely to our systems business. However, the module segment cost of sales is composed of both Series 4 cost of sales and Series 6 ramp related costs of 44,000,000.

Adjusted for the impact of ramp related costs, Series 4 module gross margin was in line with our expectations. Operating expenses were 87,000,000 in the 4th quarter, an increase of 17,000,000 compared to Q3. Q3 OpEx benefited from a reduction to our module collection and recycling liability, while Q4 was impacted by higher SG and A from project related expenses. For 2018, operating expenses were $352,000,000 near the midpoint of our guidance range. Highlighting our efficient management OpEx in 2018, combined SG and A and R and D expense decreased approximately $30,000,000 or 10% versus 2017.

Operating income was $11,000,000 in the 4th quarter $40,000,000 for the full year. Compared to our guidance for the year, op income was lower than planned as a result of the lower revenue and higher cost of sales discussed. Other income was $32,000,000 in the 4th quarter from the gain on sale of certain restricted investments. Investments sold associated with our module collection recycling program and was sold in part to reimburse overfunded amounts. Note that a smaller sale of restricted investments similar purposes was completed earlier this year in 2019 and we reflected in our first quarter results.

Recorded a tax benefit of 4,000,000 in the 4th quarter. For the full year, we recorded a tax expense of approximately 3,000,000 4th quarter earnings per share was $0.49 compared to $0.54 in the 3rd quarter. For the full year, earnings per share was $1.36. EPS was below the low end of our guidance range, due to the timing of revenue recognition for certain module and system sales and the higher EPC airfreight and ramp costs discussed earlier. I'll next turn to slide 10 to discuss select balance sheet items and summary cash flow information.

Cash and marketable securities balance at year end was $2,500,000,000, a decrease of approximately $183,000,000 from the prior quarter. Our net cash position decreased by a similar amount to $2,100,000,000 at the midpoint of our guidance range. Manufacturing capacity, factory ramp activities and the timing of cash receipts from certain systems project sales. Total debt at the end of the 4th quarter was $467,000,000, virtually unchanged from the prior quarter. Within the quarter, project debt issued to fund project construction in Japan and Australia was essentially offset by liabilities assumed by the buyers of 2 Japan projects sold.

Nearly all of our outstanding debt continues to be project related and will come off our balance sheet when the projects are sold. Net working capital in Q4, which includes the change in non current project assets and excludes cash and marketable securities, increased by 178,000,000 versus the prior quarter. The change was primarily due to an increase in module inventories, which is related to our capacity ramp and unbilled accounts receivable. Cash flows used in operations were $186,000,000 in the 4th quarter $327,000,000 for the full year. As a reminder, when we sell an asset with project level debt that is assumed by the buyer, the operating cash flow associated with the sale is less than if the buyer has not assumed the debt.

In Q4, Viator projects assumed 124,000,000 of liabilities related to these transactions. And for the full year, that total was 241,000,000 Capital expenditures were $129,000,000 in the 4th quarter compared to $238,000,000 in the prior quarter due to the timing of spending on Series 6 capacity. For the full year, capital expenses were $740,000,000 compared to $662,000,000 invested in Series 6 capacity expansion. Cumulatively Series 6 expenditures incurred at the end of 2018 were 1,100,000,000. Continuing on to slide 11, I'll next discuss the updated assumptions associated with our 2019 guidance.

We'll largely make our guidance ranges for the year with minor adjustments to ramp and startup costs, which have an offsetting impact on gross margin and operating expenses. While these changes are relatively small, there are a couple of important points to highlight. Firstly, there's been recently significant focus around the PG And E bankruptcy and impacts the companies that have contracted offtake agreements with PG And E. First of all, it has 175 Megawatt AC project PG And E is the contract loss taker. However, believe any risk associated with this asset is limited given the project size, total development capital invested to date and competitive PPA price.

Where First Solar could potentially have greater exposure is in several unsold projects where SCE is the contracted offtaker. We're currently in the process of marking some of these assets for sale and to the extent that buyers of these projects assume any increased risk premium associated with SCE as the offtaker, This could result in lower project value. So while we don't see this as a significant risk to the sale value of these projects, given their competitive PPA prices, and the key market interest for contracted solar assets that we've seen in recent capacity sale processes, it is an item we think should be highlighted. Secondly, we're lowering our gross margin guidance by 50 basis points to a revised range of 19.5% to 20.5% as a result of higher expected ramp costs. Offsetting the decrease in gross margin is a $15,000,000 reduction to startup costs within our operating expense guidance.

The increase in ramp costs and offsetting decrease in startup costs are a result of the earlier than planned startup production at our 2nd Vietnam factory. The revised range of ramp related charges is now $35,000,000 to $45,000,000 and plant starts at $75,000,000 to $85,000,000. Combined Raman product costs of 1000000 to 1000000 are unchanged from our prior forecast. Early, as we emphasized during our December outlook call, the profile of earnings is expected to be weighted towards the second half of the year. Slide 12 contains 2 charts, which illustrate from a revenue and cost perspective, some of the factors that are expected to impact the quarterly earnings distribution.

In both cases, we are The first chart shows Series 6 third module third party module sales by quarter. Notably, only 10% of the volume sold in the first and only 25% in the first half of the year. Not surprisingly as our supply increases over the course of the year, we expect to see the volumes of sales increase in Q3 and Q4. The second graphic shows the quarterly profile of our Series 6 module cost per watt produced relative to the 2019 full year average. The data illustrates the cost per watt for the first quarter of 2019, which has the lowest throughput and module wattage levels for the year, projected to be approximately 30% higher than the 2019 full year average.

Module cost forward is expected to improve in the second quarter, but will still be 5% higher than the average. The greatest benefit of our improved ramp and efficiency is anticipated to be in the second half of the year. In the third quarter, the cost forward is expected to be 5% below and the 4th quarter, 10% below the 2019 full year average. In addition to the Series 6 sales and cost water profile, there are 2 additional factors which we expect to contribute to lower earnings first half of the year. The first is the timing of ramp and startup charges, which are heavily weighted to Q1 and Q2.

Expect more than $40,000,000 of combined ramp and startup in the first quarter. The second factor is the timing of project development sales. Similar to our expectation at the time of our December outlook call, project development sales are expected to be weighted to the second half of the year. And we also expect to close the sale of our Ishikawa project in Japan in the 4th quarter. Taking all of these factors into account points to why we expect both a loss in the first quarter as well as low earnings in Q2 with the majority of coming in the second half of the year.

For the full year, we still see EPS guidance driven by Series 6 production ramp and cost forward improvements as the technology continues to scale. Finally, I'll summarize our fourth quarter 2018 progress on Slide 13. First, we had earnings per share of $1.36 and year end net cash of 2,100,000,000. Secondly, we had continued success adding to our contracted pipeline in 2018 with net module bookings of 5.6 gigawatts. With year to date 2019 module bookings were approximately 1.3 gigawatts were off to a positive start for the year.

Thirdly, we continue to make good progress on our Series 6 capacity roadmap. Early this year, we started production at our 2nd Vietnam factory ahead of schedule, continue to make steady improvements in both throughput and module wattage at our other Series 6 facilities. Our progress thus far in 2018 and nineteen indicates we remain on track to our combined Series 4 and Series 6 production target of 5.2 to 5.5 gigawatts. And lastly, a 5% net neutral movement between ramp and startup costs between COGS and OpEx, we're maintaining our financial guidance range for the year including our EPS range for 2019 of $2.25 to $2.75.

Speaker 4

And with

Speaker 3

that, we conclude our prepared remarks for the call for questions.

Speaker 1

Your first question comes from Philip Shen with Roth Capital Partners. Your line is open.

Speaker 5

Hey guys, thanks for the question. Just wanted to check-in with you on, your shipments to customers now that you're shipping externally. Some of our checks indicate that you may be falling 5 watts per module short in your shipments to customers versus contractual requirements, or obligations and this may be resulting in extra costs we could be wrong on this one, but wanted to just check-in with you on this. Can you comment on whether or not this may or may not be happening? And if true, can you provide some color on this and perhaps talk about how long the issue may endure ahead?

Thanks.

Speaker 4

Yes. So I think the premise of the question is, well, one thing I want to make clear is that falling short of contractual obligations we're not falling short of any of our contractual obligations relative to the commitments of the customers and the product in which we need to ship to them. We have, as we've said before, we have bin adders and binnedy doctors. So we have a we have a contracted commitment that we anchor around and to the extent the the bin is actually higher or lower than there's an adjustment to the price accordingly for that delta could be up, it could be down. So just wanna make sure that that's clear.

There's nothing that that we're doing that would say that we're falling short of our contractual obligation, but to the extent we do have deliver a bin that's a bin down would be five watts, then there would be a bin adjustment to the price. And that is happening in some cases. And part of it was, I think we indicated on prior calls is that the early production in particular, we've been struggling to see the increased penetration of ARC. And so without ARC, you're going to lose almost 2 bins of volume. And one of the things we said on the call is our ARC penetration has increased now, 33 percentage points.

So we're seeing a much better utilization for ARC. And as a result of that, if we go forward and we continue to ramp across the balance of the fleet. Some of the early launch issues that we had will be subsided. And we'll be able to make sure that we hit the committed bin that we initially structured around. But I want to make sure it's clear to understand that to the extent that the bin is slightly above or below the contract allows for that.

And there's appropriate adjustments to the ASP.

Speaker 1

Your next question comes from Colin Rusch with Oppenheimer. Your line is open.

Speaker 6

Great. Thanks for taking our questions. This is Kristen on for Colin. You talked a little bit about this in your prepared remarks, but can you provide some additional color on the geographic diversity of the backlog on an annual basis just sort of the mix of domestic versus international. And then what opportunities are you seeing to pick up broken projects for the system business in the US.

Sort of a corollary to that. What's what's the expertise in integrating, your expertise in integrating solar with storage to your pricing strategy for modules.

Speaker 4

Okay, a lot there. When you look at the geographic diversity of our shipments for it and some of this will come out in the queue. K actually will come out tomorrow.

Speaker 3

You'll see that there's

Speaker 4

a high concentration of module shipments that occurred within in the U. S. In the range of 70% or so of the shipments last year were in the U. S. And the balance were in international markets.

And again, it's largely reflective of where the strength of the demand is. And if you look at our pipeline as you carry forward 7 a little over 7 gigawatts of mid to late stage opportunities about 5.5 of that sits within the U. S. The volumes at which we booked this quarter, were largely U. S.

We had some volume with a European customer, but most of the call 1.6 since the last, since the last earnings call was was focused around the U. S. And it largely has to do with where customers are willing to commit. And I think it's important to understand that of the large order that came through this year, gave a lot of the 1.3. That volume is to be shipped in 2021202223.

You'll see customers in the U. S. Because of certainty around the ITC and wanting to say harbor, you'll see customers having a greater appetite to commit forward and to procure materials that would go out that far in the horizon. When you look at some of the international markets, we We don't see as many customers willing to start procuring in 202120222023. Partly because they have lack of certainty of the underlying projects for those modules where they would go.

And so what we said in the call is that partly that when we look at the bookings for the year, we started off great. We still look to have a one to one book to ship ratio, which is say that we're targeting to book somewhere between 5.5 or 6 gigawatts this year. May see some of that being more back end loaded because I do see more diversity of the bookings as we progress throughout the year being more opportunities in our international markets. Because we're getting to a horizon that towards the end of 'nineteen and we're looking to ship into customers and starting in 'twenty one that we can see that international customer participating in that opportunity. So I would expect our bookings as we progress throughout the year to improve having more of a diversity to U.

S. Versus international. But at the same time, as long as we are still relatively capacity constrained, while it's important that we continue to grow and develop our international markets, if we have opportunities to capture better value in the U. S. Markets, we'll prioritize U.

S. Market. We may prioritize some of the international markets that give us better opportunities capture higher ASPs and we'll focus there first before maybe we chase some of the other markets that we know have traditionally been very low ASP markets. On the storage question, Well, let me go to the systems question first. I think in particularly in the U.

S, there's a lot that's in the market right now. As you can see, there's a lot of call them smaller developers and others that are trying to actively market into, you know, sell their development pipeline, some with contracted assets, some not And I do think that some of that could be related to the capacity of some of the smaller developers to make the investments to capture the IT safe harbor. And we indicated in our last call, we'll be investing somewhere call it $300,000,000 to $400,000,000 to see here call it 5 gigawatts of opportunities between now and 2023. That's a big investment and I think some of the smaller developers may be strained with making those investments. And I think they understand that if they don't make those investments, they'll be less competitive as they're competing for projects that have CODs that go through the end of of 2023.

So I can see a lot coming to market and we're trying to at least get engaged and evaluate and see if some of those opportunities make sense for us. And clearly we've got a great development team and we've proven ourselves with our ability to make acquisitions and integrate development assets and contract them and realize meaningful value associated with that. So that's a good opportunity for us. And then storage, we're actively involved. Our largest storage deal that we announced a few quarters ago with APS, We've got a couple of other projects.

We've been recently awarded a project with the utility in Florida to do a pilot for them, a small addition storage onto their array. We've done some work with utility in Nevada along the same type of opportunity where customers are exploring and learning and wanting to know more about storage and how it can be effectively integrated and it's an area of emphasis and focus for us. It's I look at it, it's somewhat of extension to our normal systems business. It's just part of our offer. And we can add enhanced value through our power plant controls and optimization of how we charge the battery and dispatch the battery and we've proven some capabilities there that has been very interesting to some of our customers in that regard.

So it's still early innings. We picked up some wins and I see more momentum as we move forward as it relates to storage.

Speaker 1

Your next question comes from Julien Duwali Smith with Bank of America Merrill Lynch. Your line is open.

Speaker 7

Hey, good afternoon. Thank you. Perhaps just to pick up where you left off if you can clarify a little bit your comments just now about securing up the backlog here from an ITC perspective, A, how do you think about that accelerating into the year end 2019 given that is the timeline that you need to meet to get to qualify that ITC? And then secondly, I think you alluded to a gigawatt utility customer in the quarter who they were trying themselves to try to lock up some supply. So maybe as you think about the potential orders from what you haven't locked in from an ITC perspective, is that another source of bookings acceleration in the back half?

Speaker 3

Yes, I'll start with what we're looking at from a safe harbor perspective ourselves. And it's similar today to what we talked about on our guidance call in December. So we're still looking at somewhere between $325,000,000 $375,000,000 of spend this year. We haven't explicitly talked about what we're going to spend that on. It's less likely to be on the module side, just given the constraints we have in module suppliers.

As Mark said, we're largely sold out for the rest of the year. So we'll look at the rest of the balance of the plant. There'll be some projects that were far enough along that we can use the physical work test So a small piece of that midpoint 350 number that I talked about will be associated with physical working code. So that'll probably be in the range of of $25,000,000 to $50,000,000. The rest will look to spend on, as I mentioned, balance of plant.

With projects that go out into 2021 from a contracted perspective and then uncontracted sites will take us out beyond that 2021 timeframe. I think we said from our perspective is that if there is opportunity to spend more, to the point of if we are able to pick up projects where other developers are constrained from a capital perspective, in securing Safe Harbor material, it's somewhere we'd be very happy to invest additional capital.

Speaker 4

We believe the returns are good. So somewhere where if we see the right opportunities, we're willing to spend more than that 3 75 top line that we talked about. And from a customer standpoint, Julian, I mean, the order that we secured here, with our one customer, it's a common conversation that our team is having with a lot of our customers and thinking about the safe harbor and how to what their particular strategy is and engaging in conversations with us around that and how we could try to evolve that. In some cases, on this customer, it was interesting. They already had a commitment to some volume for this year.

So we didn't have to, it wasn't an issue of not having the supply, but what we were able to do is that since we already contractually had volume on the books of this customer, we then engage with them. Well, let's leverage that as your safe harbor anchor. And then commit to volumes that out in the horizon and when you will construct the projects in 20212023. So Alex is right. We are constrained as it relates to available supply.

Now starting up, starting up Vietnam a little bit faster than being up too little faster because there's a little bit of supply. If we continue to wrap, you know, accordingly, we may see a little bit of opportunity there. Those are small in the rounding. The bigger opportunity I see is how do we talk to customers today that have contracted volume that's on the books. And then how do we position that as the anchor for the ITC and then contractually commit to the volume that would sit out and deliver in the, you know, 'twenty one, 'twenty two and 'twenty three time frame.

So we're having a number of conversations with customers in that regard.

Speaker 1

Your next question comes from Ben Kallo with Baird. Your line is open.

Speaker 8

So I have 3 questions. First of all, like, slide 12 is kind of confusing. Could you help me through that and then just talk about the cost reductions versus the 40% that you said back at Analyst Day. And like, you know, you're a plus or minus a penny or 2 from there. Number 2, I understand the cost pull forward.

But then I don't see megawatts going up. And then number 3, could you just talk about how your pricing for these out year contracts? Just because, you know, we have a hard time going with the ASGs when we go out to 2022. So how how do you think about pricing those? Thanks.

Speaker 3

Yes, to explain the graph in a bit more detail. So the graph on the left hand side of slide 12 is showing you the Series 6 third party volume think about the guidance we gave, at 5.2to5.5 gigawatts for the year, you take out a couple of gigawatts to Series 4. Then you got to take out the systems piece. So you're left with what is Series 6 through third party module deliveries. And when you take that total number, we're saying this is the breakdown per quarter of the delivery of those modules.

So about 10% of that third party Series 6 volume is delivered in Q1, 15% in Q3 to 30 in Q3, 45 in Q4. It's really trying to show that on a third party module delivery basis, we're back ending the profile pretty significantly in in the year. On the right hand side, looking at the costs, so the question you had around costs, we talked in the guidance call around Lonter, our end of year Series 6 cost being approximately 40% lower than our 2016 benchmark for Series 4. With a roughly penny adder associated with increased costs around the frame. So if you take that point over the end of the year, and say, that's a year ending point.

You can look at what you think the full year average is. We're trying to make a point that on the average basis, for 2019, you're going to see whatever that average is be significantly higher in Q1. In terms of modules delivered, it comes down to Q2 and by the time you get Q3 or fractionally under the year average by Q4, you're 10% under the year average. So again, I was trying to say, when you combine these two left hand side lower volume beginning of the year, the right hand side, higher costs relative to the average, you're going to see pretty negative impacts of results for Q1 and Q2. You start to see that reverse out when you have much higher volume and much lower cost, Q3 and Q4.

Speaker 4

Yes, I think, you know, the way I've said, there's been a real question about our view around the 40% off of our Series 4 reference point, but for the penny or so, penny or 2 for a frame being a piece of a couple of smaller components, that's the fact of where we anticipate to be and nothing's changed there. And we're working on opportunities where we can even revise the frame and even take more costs out there because between the frame and two sheets of glass, that's really where the vast majority of the bill material is and the team's working pretty aggressively on finding a roadmap to figure out how we get everything back to the full entitlement of what we had. And there's some encouraging work being done from that endpoint. The other thing I'll say about that slide is that one of the biggest levers that moves you from where the number is 20%, 30% higher in the first quarter versus the average in trends down to being 10% lower than the average. A big piece of that is the throughput, right?

Because there's still a significant amount of underutilization that sits in the first half of the year. And then as we drive that utilization down, we're at full entitlement across the entire fleet because we're starting up another factory now. So we're going to be utilization while it's significantly higher upon launch after the 1st month or so production relative to our other factories. It's still going to be driving this down and there'll be some under utilization costs that's going to be weighing down on the overall average across the fleet. So that's a piece of it.

And then the other is is the efficiency improvement. So we'll continue to see improvements as we progress from where we are now to to the end of the year and you'll pick up close to another 2 bins from the launching point where we are right now to the exit rate. There's close to that. From Q1 to Q4. So those are the 2 big drivers that have driver that cost for lockdown.

Contracts for the outer year and the pricing around that, Ben. We look at we capture that at fair value, right? And, pricing as we go out into 20212023, you know, we have a road map of where where we, you know, where we go where our cost, we know where our efficiency is going to be. We know what the energy advantage is going to be at that point in time. We price it accordingly.

And, you know, I'm very happy with the, you know, we have now quite a bit of volume, you know, obviously a lot of supply that sits out 21, 22, 23, but I'm pretty happy with the pricing that our team has been able to capture in that window. It's above where my expectations would have been relative to the business case we put together for Series 6. So we're pretty pleased from that standpoint.

Speaker 1

Your next question comes from Brian Lee with Goldman Sachs. Your line is open.

Speaker 3

Hey guys, thanks for taking the questions. 2 for me, I guess, first on that, you know, sort of capacity point, you mentioned in mid December when you guidance for 2019 that you're putting Malaysia 1 conversion, to Series 6 on hold. I mean, you've mentioned capacity constraints and now you're talking about 2023 deliveries throughout this call. So given that backdrop, what's sort of the decision process around bringing that back into the capacity expansion roadmap here. And then, second question, just on slide 12, super helpful with the cadence.

Alex, can you help us think about how that average line moves into 2020? With some of the utilization effects starting to fall off and then, getting, you know, fuller entitlement around the the efficiency targets and so forth and so on. Thanks, guys.

Speaker 4

I'll take the capacity and then I'll take the other one. Tom, so Brian, as we said, when we at the end of this year, we'll ramp down to our fact in Malaysia will immediately start the transition of one of them. The other one is continuing to be evaluated and it's really being evaluated based off of market demand and our ability to capture the bookings that we need 2021 to get to a high level of confidence or ability to sell through that volume. And so it's really it's demand related, demand driven. And as we continue to book, and we'll we'll somewhat crystallize our decision around that and we'll get more and more comfortable.

What I will say though is that every one of those factories that comes up in essence creates pricing power because it creates scale. And that scale enables us to enhance our competitive position and then allows us to to capture volume in other markets that we may not be participating in today. So I'm very motivated to get that factory up and running. But it's highly dependent upon our ability to clear the market at acceptable margins. And as we continue to do that, then I think the likelihood of starting that conversion on that second plant and, really be our 3rd Series 6 factory in Malaysia.

We'll start to crystallize. Yes, Brian, I

Speaker 3

mean, we can't give you guidance out that far. So what I can say, I guess, as Mark mentioned, a lot of the costs, the majority of the costs sits between the two pieces of glass and the frame. So that's why we're going to be spending a lot of our time, on both. So on the frame, we're impacted by the tariff. We are looking to optimize the frame further.

So we had some movements in the frame in terms of design from where we originally came out series 6 and some of the modules we produced. So we're looking at can we optimize design to use less aluminum in that frame? On the glass side, we mentioned on our guidance call in December that we had some projects we were looking at that may impact start up. And one of those we talked a little bit about was trying to optimize some of the glass where we today pay a lot of specialized processes on that glass and that's something that we can either bring in house or try and optimize pricing. So we're continuing to work that route on the glass side and the frame side both.

And then beyond that, we'll continue to work the rest of the materials. But a lot of this will just come from increased scale. So as with scale, we get pricing power and we get efficiency in our supply chain as well.

Speaker 1

Your next question comes from Paul Coaster with JP Morgan. Your line is open.

Speaker 9

Hey, Thanks. A couple of questions. You saw some revenue recognitions slip to 2019, but it didn't raise the revenue numbers for 19. And I'm wondering if it's something to do with PG And E and S and E or whether it's, supply constraints perhaps you can just talk us through the puts and takes there as to why it didn't increase the 2019 revenue guidance. The other question I've got is that the ramp cost seems seems to be increasing.

At least since the first guidance you gave for 2019, what changed if you can just sort of talk us through the process by which we got here? Thanks.

Speaker 3

Yes, sure. So on the guidance, Steve, we've got a broad range in the guidance as we just talked about on slide 12. A significant amount of the revenue and margin is back ended for the year. So obviously that's in the it's in the fact that we have a guidance range, but you can see that small changes in timing could have large impact to results at the back end of the year. That there is some risk around SCE.

When we think about SCE, I don't think it's a significant risk for us. It's hard to evaluate got to look at what's happening with PG And E itself, how California and FERC and the bankruptcy courts will deal with that. And then how that specifically applies to the facts and circumstances around FCE in their territory. So we're monitoring that. We do have assets that we're selling this year.

Have 3 assets currently running competitive process for and we're seeing high demand for those. If you look at SCE's credit today, the bond is still raising pray. You haven't seen the yields have widened incrementally. We haven't seen the gap out like you have on PG And E. So I think we've got good confidence, but there is still risk around those processes.

So that's the piece of it. But then the other piece is we're just we're only 8 weeks into the year. So it's early to make a change. In terms of overall guidance. We'll continue to evaluate guidance as we go through 2019.

On the ramp piece specifically, all you're seeing is a change in geography from startup moving into ramp and it's a function of the timing that's bringing up the Vietnam factory. So effectively, we've decreased startup bring that up early, but it's increased ramp. And you see that in the half percentage point change in the gross margin guidance, and that's offset by a 15,000,000 decrease in the start up costs in the OpEx. So those 2 net out to 0 change to guidance is just geography based on the timing of the Vietnam plant coming up.

Speaker 1

Your next question comes from Michael Weinstein with Credit Suisse. Your line is open. Hi,

Speaker 10

thanks for taking the question. This is Maheep Mandloi on behalf of my Given your shipment visibility, can you talk about how much of the third party sales is fixed or is that fixed versus floating prices for the year? And the second question is on the Series 6 cost structure. Can you talk about when you expect to achieve the target cost structure? Is this still a Q4 target?

Thanks.

Speaker 4

So, as it relates to shipment visibility and the pricing, all of the anything that we recognize as booking has a firm price associated with it. The only impact it has is we've referenced this before. If we deliver a bin that's higher than what we initially anchored towards, right? So the contract will say let's use an example you have to deliver a 4.20 watt module. We can go down 2 bins to 4.10 and we can go up 2 bins to 4.30 or we can average to 4 whatever the math ends up working out to.

And those, there'll be subtle price deltas as you move across. In some cases, it's like a quarter of a cent for each bin. In some cases, it's slightly higher than that. So there could be slight movements in the realized ASP from what the center point of that contract is, but it's a firm fixed price. So they all have firm fixed price.

There is no floating, but for whatever the final delivery is of the product. On the Series 6 cost structure, as we said in the last call, as we exit this year, we'll be within a couple of pennies from our targeted 40% cost reduction. And that's important. And when we get there, we still have an with the frames not fully optimized in the class. So we got issues and we've got past on how to improve that.

Any other is we're not at the average efficiency that we had in targeted for Series 6, right? So we knew it was going to take us a couple of years and we even showed a slide in the Analyst Day of kind of where that average efficiency would be. And then we show a more of a midterm objective of where we want to go with the overall wattage for the product. So a combination of optimizing around the glass of frame and driving the efficiency, we will be in a much better position, as we exit 2020 should be relatively in line with what our original targeted cost reduction was when we launched, Series 6. And again, we launched it in November of 2016.

So it's only a little over 3 years now, since or 2 years, I guess, a little over 2 years. We're not even 3 years into the journey. So just put it that perspective. And I think tremendous progress that's been made over that horizon.

Speaker 1

Your final question come from Joseph Osha with JMP Securities. Your line is open.

Speaker 8

Wanted to go back to the margin comments you made about the systems versus the module business in particular the comments about series 4. I understand, that obviously you've got more 6 allocated to your systems business. But I'm wondering if there is any underloading on the 4 business that's weighing on those margins and also how much that might play out as you ramp the business down.

Speaker 3

Yes. So you're not seeing any underloading on the Series 4. What you're seeing is just the impact of The fact that the Series 6 business is really still nearly all being allocated over to the systems segment from a revenue perspective and from a core comps perspective, but you're seeing all of the, ramp costs coming through in the module segment. So you're seeing a blend of what looks like Series 4, but all the Series 6 kind of noncore costs coming through as well. So that's what's happening there.

It's not a function of there being any and the utilization on the S4 piece.

Speaker 1

This concludes today's conference call. You may now disconnect.

Powered by