Bernstein 42nd Annual Strategic Decisions Conference

May 28, 2026

Summary

Management is focused on increasing throughput and workforce to meet historic Navy demand, with five major ship deliveries planned and a sustainable 6% revenue growth outlook. Margin improvement is expected as higher-margin ships are delivered, and the unmanned segment is positioned for future growth.

Doug Harned
Analyst, Bernstein

Okay. Good morning. I'm Doug Harned, Bernstein's aerospace and defense analyst, and I'm thrilled to have with us today, Chris Kastner, Chairman and CEO of HII. We're going to go right into Q&A here, I think.

Chris Kastner
President and CEO, HII

You promoted me, so.

Doug Harned
Analyst, Bernstein

What?

Chris Kastner
President and CEO, HII

Not the Chairman, but I am the President and CEO.

Doug Harned
Analyst, Bernstein

I didn't

Chris Kastner
President and CEO, HII

That's okay.

Doug Harned
Analyst, Bernstein

Know that.

Chris Kastner
President and CEO, HII

That's okay.

Doug Harned
Analyst, Bernstein

Okay

Chris Kastner
President and CEO, HII

We've always had a split governance structure at HII.

Doug Harned
Analyst, Bernstein

Oh, Okay.

Chris Kastner
President and CEO, HII

That's okay.

Doug Harned
Analyst, Bernstein

That's the first question.

Chris Kastner
President and CEO, HII

That's the first question. Yeah. Got that one right.

Doug Harned
Analyst, Bernstein

Anyway. Let's just start, maybe you can just give us an overview of

Chris Kastner
President and CEO, HII

Sure

Doug Harned
Analyst, Bernstein

What you're seeing now at HII, what some of the opportunities you have, some of the challenges.

Chris Kastner
President and CEO, HII

Sure. First, safe harbor rules apply here, I'm not going to break any news. At HII right now, we're very focused on throughput. We have five deliveries really over the next 12 months, across a number of different programs. We have LPD 30's got to deliver. We have LPD, excuse me, DDG 129's going to deliver, CVN 79, SSN 800, LHA 8. All those deliveries are going to happen in the next 12 months. We're very focused on delivering the fleet for the U.S. Navy. We've set internal milestones and actually external milestones or goals around throughput. We achieved 14% last year. We expect to achieve 15% this year. We're doing that by growing our labor force and distributed shipbuilding.

Both of those have to work in order to execute on our programs, but we're very focused on throughput and meeting the demands, really historic demands, of the U.S. Navy.

Doug Harned
Analyst, Bernstein

On that, right now we're looking at a budget. The Trump administration's proposal is $1.5 trillion.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

We don't know exactly where that's going to go. Maybe as a starting point, and there's a lot of money for shipbuilding in there.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

As a starting point, can you help us understand how you're viewing that process, given that there's uncertainty and the whole way this is going to move through Congress?

Chris Kastner
President and CEO, HII

Well, it's definitely complicated. As my old boss used to say, Mike Petters, who you know very well, "Look, this is the first step of the process." We're in the initial stages of this process. Very complicated when you think about reconciliation, a supplemental, maybe two reconciliations. The great news is that our ships are in the base budget. All of our 6% revenue growth, the midterm revenue growth that we're talking about, that is all protected in the base budget. If that happens, and as that moves through the process, we're going to be fine.

Doug Harned
Analyst, Bernstein

Because one of the worries we've had is that if there is no reconciliation passed and we go to October 1st, then we're back at basically down $155 billion on a CR.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

Unless you do something.

Chris Kastner
President and CEO, HII

Right. Could be. I don't see a threat to our programs. The vast majority of them are under contract already.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We need to get Block VI and Columbia done. DDGs will happen as well. I'm comfortable with those.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We already have the amphib bundle squared away down at Ingalls. We started the Frigate Program down at Ingalls, which is really not even included in our 6% guide.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We're in a really good place and the budget supports it. If the battleship happens, the nuclear battleship and frigate happen, that's upside of the guidance.

Doug Harned
Analyst, Bernstein

Okay. Now, in this budget, there are big increases. You've got those increased Virginia-class, Columbia-class, for amphibs. Right now, you've already got a huge backlog. When you move this money in, one of the struggles we've had is to figure out. It goes back to your comment on throughput.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

How to turn that money into real volume coming out the other side.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

How do you think about this challenge as the funding continues to rise?

Chris Kastner
President and CEO, HII

It's all about increasing your labor force to meet that demand and then doing distributed shipbuilding. Historically, in shipbuilding, when things get great during the Reagan buildup, you pushed work out of the yards. You identify the core work that you need to keep, and you push everything out. That's happening right now. We doubled our distributed shipbuilding last year. We are going to increase it another 30% this year. We're bringing on partners to help us facilitate that additional demand.

Doug Harned
Analyst, Bernstein

Can you elaborate on that a little bit, how you think about the distributed shipbuilding concept? Ten years ago, we wouldn't have been talking about that.

Chris Kastner
President and CEO, HII

We wouldn't have because we didn't need it. We had plenty of capacity in the yards and labor in the yard.

Doug Harned
Analyst, Bernstein

How do you manage that today, and how do you identify the next opportunity to expand on that?

Chris Kastner
President and CEO, HII

Well, we've had challenges before. We've done it incorrectly, and we were punished for it on the LPD program when it originated. We're very careful and disciplined in how we do it with the right QA and the right engineering to ensure that when the units come back, they meet our expectations and we can just continue on building the ship. We go to partners, we do initial pilot programs with them. They'll build one or two units. We make sure they have sufficient capital and labor and the technical know-how to execute on it. Once they do that, we'll expand their scope and we'll grow. It makes sense to have some core shipbuilders, and Gulf Copper does that for Ingalls, so they can handle a lot of the capacity.

You're going to have to go to a few in order to handle all of the work that needs to get done, both at Newport News and at Ingalls.

Doug Harned
Analyst, Bernstein

Are these often traditional players in this space? The reason I ask is, it was such a problem through COVID, when you start to see volumes come down, and you have very specialized suppliers.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

In this industry, and if their volumes come down, they can be in some real financial trouble.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

Are you basically working with the same base or types of people that you've worked with before and expanding the roles, or are you able to actually bring in a broader spectrum of support?

Chris Kastner
President and CEO, HII

It's both. We're working with established partners that we've had for a long time, where we can expand their capacity. We're also bringing in new entrants that have steel experience, because what we're doing is just the upfront part of the work, and you've been to the shipyard.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

It's just the initial unit work where you're creating units

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Prior to them being outfitted. The capability exists. You just need to be able to do the welding that's required to get that done, and have the capacity and the tooling required to get that done. It's both. It's established players and bringing new entrants that already have experience. We're not going to bring someone that has no experience in welding structure together into the space.

Doug Harned
Analyst, Bernstein

If I think back to some of the things that Mike Petters said at one time, and this isn't the greatest example, but when you did the UPI acquisition.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

One of his points there was that there are industries where the type of engineering and production work that you do has similarities to others. That was one of the arguments.

Chris Kastner
President and CEO, HII

There are.

Doug Harned
Analyst, Bernstein

There was some synergy there. I'm thinking the other way around.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

If you're thinking of capabilities, and it could be in energy and other places.

Chris Kastner
President and CEO, HII

It's energy, it's commercial shipbuilding, it's oil and gas. Anyone who's built structure or fundamental simple structure.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

We can go to them and see if they have the bona fides to execute.

Doug Harned
Analyst, Bernstein

One of the things that this administration, when we were here last year, they had just announced the White House Office of Shipbuilding.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

The president talked about bringing in Korean support, which I think you have been doing some of that.

Chris Kastner
President and CEO, HII

We have.

Doug Harned
Analyst, Bernstein

How effective is that?

Chris Kastner
President and CEO, HII

Our partner is HHI, right? Hyundai Heavy Industries. They're very disciplined as we are in how we allocate capital and whether they're going to make an investment or not. We're being very careful. We need to make sure that if there is a significant investment made in the shipbuilding industry, there's work on the back end. We're still in the evaluation phase with that.

The good news is they build ships a lot like we do in the defense space. They've learned from us, we've learned from them. We've been in their shipyards, so we fully understand it. They've been in ours. They've walked our panel line, and really liked it. We're still looking for the right opportunity with them.

I think there is a chance that that is successful.

Doug Harned
Analyst, Bernstein

Is that more in the Ingalls side, I would think?

Chris Kastner
President and CEO, HII

It's definitely Ingalls, right.

Doug Harned
Analyst, Bernstein

Yeah. It's kind of hard to.

Chris Kastner
President and CEO, HII

Right. You don't bring the nuclear work there.

Doug Harned
Analyst, Bernstein

Yeah. Okay. Last year, you got the award for the last two Block V

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

Virginia-class. In that, you got a big boost which was funding to support labor.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

Can you talk through a little bit about how that all works and how that's proceeded?

Chris Kastner
President and CEO, HII

Actually very well at Newport News. We adjusted the contracts for the labor. That's kind of a margin neutral sort of

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Adjustment that we're fortunate that the nuclear shipbuilding enterprise contributed that for us. It's been successful. Their attrition rates are better, their labor situation's better. They met their throughput goals. They're actually ahead of their throughput goals through Q1, especially in the submarine enterprise, which is very positive. It's worked very well.

Doug Harned
Analyst, Bernstein

Yeah. This is one where I was trying to fully understand it. I thought the goal here was to be able to raise wages, wage levels.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

You could attract maybe a stronger workforce through doing that.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

That would ultimately turn into higher quality, better throughput, better performance.

Chris Kastner
President and CEO, HII

No doubt.

Doug Harned
Analyst, Bernstein

Is that the process? It seems like it would be pretty early to already see results from this.

Chris Kastner
President and CEO, HII

No. You see some results in better cost performance on some of the ships.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

Better throughput for sure, because you're attracting more labor.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

It is working.

Doug Harned
Analyst, Bernstein

Okay. You're always talking about the balancing hires versus attrition.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

What does that look like at Newport News now in terms of expanding the workforce?

Chris Kastner
President and CEO, HII

It's positive. There still is some attrition. It's much better than it was before, but the attrition is happening in the right place. We're adding and keeping experienced shipbuilders in Newport News right now.

Doug Harned
Analyst, Bernstein

When we think about revenue, one of the things that's been difficult for us is because some of the increase in revenue in Newport News is due to the pass-through on the labor side.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

If I were to take that out at Newport News, what's your growth rate sort of X the labor?

Chris Kastner
President and CEO, HII

We haven't communicated that externally.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

Revenue growth is a combination of the labor increase, throughput increase, but also material flowing through the system.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

With just additional work. To watch and pay attention to sales growth, you need to pay attention to all three.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

More important than anything, you need to make your ship deliveries, right?

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

If I were to guide people on how to think about HII right now from a shipbuilding standpoint, is if we're getting healthier, those five ship deliveries happen consistent with how I'm talking about it. They're all proceeding, but they're getting into the most difficult part, which is final test.

Doug Harned
Analyst, Bernstein

When you talk about 6% growth, I remember like every earnings call, it was like with Mike.

Chris Kastner
President and CEO, HII

Yeah

Doug Harned
Analyst, Bernstein

Analysts would say, "No, you're going to grow faster than that, Mike." "No.

Chris Kastner
President and CEO, HII

He would say, "We're flat. We're going to be flat.

Doug Harned
Analyst, Bernstein

3%. He'd

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

3% maybe.

Chris Kastner
President and CEO, HII

I still.

Doug Harned
Analyst, Bernstein

Don't put too much

Chris Kastner
President and CEO, HII

I still talk to Mike, and he has a hard time believing what we're doing. He had a lot of confidence in us. He did a great job. Yeah, it was flat.

Doug Harned
Analyst, Bernstein

You were saying four not too long ago.

Chris Kastner
President and CEO, HII

We moved to four simply because we saw it.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Remember that we were dealing with $12 billion budgets, $12 billion-$15 billion annual budgets at the time.

Doug Harned
Analyst, Bernstein

Well, it

Chris Kastner
President and CEO, HII

Thought of now. If you want to really go back to it and put it in context, we were really worried about the Columbia-class, if you recall the conversations we would have.

Doug Harned
Analyst, Bernstein

I do.

Chris Kastner
President and CEO, HII

Columbia-class we thought would be so big that it would cloud out amphibs. What has happened is the Columbia-class is happening and it's big. There's been inflation, everything's more expensive.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We want more amphibs. It just didn't happen like we expected it would.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Fortunately for us, we have the capability and we're creating the capacity to execute on all of it.

Doug Harned
Analyst, Bernstein

When you went to say now you're growing at 6%, which is a number we haven't really thought about

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

Before. This goes back to this labor pass-through. Is that 6% kind of driven somewhat by that, or is that a sustainable 6% rate?

Chris Kastner
President and CEO, HII

It's pretty sustainable. Remember, we're starting on a year that already had wages included, fundamentally, part of the year.

Doug Harned
Analyst, Bernstein

Q3, Q4.

Chris Kastner
President and CEO, HII

Part of the year, right?

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

When you think about a CAGR, it's pretty sustainable. I don't want to go beyond

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Medium range guidance. For the next four to six years, it's definitely pretty solid.

Doug Harned
Analyst, Bernstein

At the 6% type level?

Chris Kastner
President and CEO, HII

Yes.

Doug Harned
Analyst, Bernstein

You've just started the same type of program at Ingalls, right?

Chris Kastner
President and CEO, HII

Yes.

Doug Harned
Analyst, Bernstein

That's when we will see probably a step up.

Chris Kastner
President and CEO, HII

I do expect

Doug Harned
Analyst, Bernstein

The compare is

Chris Kastner
President and CEO, HII

Yeah. I do expect it to step up as well. We see some leading indicators in the labor front with applications, that it will start to grow that workforce at Ingalls. We definitely need it to.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

There's a lot of work down there.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We've already started work on the frigate, which is great.

Doug Harned
Analyst, Bernstein

The frigate's done over where you were doing the NSC, right?

Chris Kastner
President and CEO, HII

Exactly.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right. Yeah. We had the team, a lot of the team's still in place, all the processes still in place. Design is fixed, really on the hard part of the ship. There's some top side changes that the Navy wants us to incorporate that we've agreed to, that are really not a manufacturing challenge. We think we'll do a great job on those first two frigates.

Doug Harned
Analyst, Bernstein

Back in the Newport News , I think throughput was up 14%, I think, last year.

Chris Kastner
President and CEO, HII

Yeah.

Doug Harned
Analyst, Bernstein

I think you're talking about 15%

Chris Kastner
President and CEO, HII

Yes

Doug Harned
Analyst, Bernstein

This year. What does that mean? I'm trying to figure out, and you and I have talked about this a million times.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

I'm trying to translate that into this movement from kind of 1.4 Virginia-class a year, getting to that two per year goal collectively.

Chris Kastner
President and CEO, HII

There's a lot of

Doug Harned
Analyst, Bernstein

How do we

Chris Kastner
President and CEO, HII

There's a lot of fixation on the two, 2.3 per year.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

It's a tough metric to get to. It's not one I really like very much, because we've reset the Block V boats to an adjusted schedule based on when we think the supply chain's going to show up.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

I know the Navy talks about the beginning of the 2030s. I focus on ship deliveries.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

I focus on ship deliveries. We got two a year last year, two a year the year before. As a submarine enterprise, we're out of the first Columbia-class boat. We've already delivered all of our

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Equipment for the first Columbia-class boat. The second Columbia-class is much more efficient.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

It's proceeding at a much more efficient basis than the first one, so we're making progress there. I focus on ship deliveries.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Throughput is simply earned hours. It's not cost.

Doug Harned
Analyst, Bernstein

Oh, okay. Yeah.

Chris Kastner
President and CEO, HII

It's not the cost to earn the hour, because sometimes we have distributed shipbuilding, which is at a premium. Overtime is at a premium. It's actually earned hours.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Productive hours that you have to get done.

Doug Harned
Analyst, Bernstein

Okay. It's a labor number.

Chris Kastner
President and CEO, HII

It's labor

Doug Harned
Analyst, Bernstein

Not materials-

Chris Kastner
President and CEO, HII

It's labor

Doug Harned
Analyst, Bernstein

Is it materials too?

Chris Kastner
President and CEO, HII

Plus the value of distributed shipbuilding, which comes in

Doug Harned
Analyst, Bernstein

Okay

Chris Kastner
President and CEO, HII

As material, but it's really there's an equivalent labor

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Category there.

Doug Harned
Analyst, Bernstein

Okay. I see. Okay. Is this, like the 15% type number, is this something that we should expect to continue? Fifteen percent this year, but is that something a year from now you'd be looking at a similar goal?

Chris Kastner
President and CEO, HII

There will be a new number. I don't know if it's going to be 15%.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We have to finish our plans this year and talk about how we want to guide for next year. The amount of work and earned work will continue to increase.

Doug Harned
Analyst, Bernstein

Okay. At one time you were looking for 20% last year. Fifteen sounds pretty good to me.

Chris Kastner
President and CEO, HII

Pretty high goal. Maybe I pushed them a little bit too hard, right?

Doug Harned
Analyst, Bernstein

Yeah, 20% was Yeah.

Chris Kastner
President and CEO, HII

The good news is the submarine program has got some traction right now.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Which is very positive. Really for national security, not just our financials. It's a top priority. Columbia-class, top priority. Virginia-class right after that, especially with the Virginia Payload Module, which are part of Block V. Having the submarine enterprise getting some cadence is really positive.

Doug Harned
Analyst, Bernstein

The payload modules, those aren't yours, right?

Chris Kastner
President and CEO, HII

We don't build the module, but we do integrate it.

Doug Harned
Analyst, Bernstein

You do the integration.

Chris Kastner
President and CEO, HII

Right. On all the ships that we deliver.

Doug Harned
Analyst, Bernstein

The ones you deliver. Okay. I see. There's extra value for you

Chris Kastner
President and CEO, HII

Sure

Doug Harned
Analyst, Bernstein

Even though the module itself's up.

Chris Kastner
President and CEO, HII

Well, the work

Doug Harned
Analyst, Bernstein

Electric Boat. Yeah

Chris Kastner
President and CEO, HII

There's additional work for us to do the integration, yes.

Doug Harned
Analyst, Bernstein

Okay. Block VI.

Chris Kastner
President and CEO, HII

Block VI.

Doug Harned
Analyst, Bernstein

We going to hear about it today? What are we about to?

Chris Kastner
President and CEO, HII

Yeah.

Doug Harned
Analyst, Bernstein

Very close, right?

Chris Kastner
President and CEO, HII

Very, very close. We essentially are going through the approval process, in the government, to get those contracts done. I fully expect them to be done before the end of Q2. It's just a very large contract. It's a complicated contract. They need to go through the approval processes. I get updated every day on it.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

I still expect it to get done.

Doug Harned
Analyst, Bernstein

I know that so much of the challenge here, and I've talked with Tom a lot before about this, is getting past all of those sort of COVID time

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

Boats and getting where you never got, I think, properly compensated for the inflation.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

Costs

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

You're not alone.

Chris Kastner
President and CEO, HII

Everybody else

Doug Harned
Analyst, Bernstein

Got the same.

Chris Kastner
President and CEO, HII

Things, mine are very large, and they last a long time.

Doug Harned
Analyst, Bernstein

Yeah, yours are bigger than anybody else's.

Chris Kastner
President and CEO, HII

Yeah, the two largest contracts we signed as a corporation are the CVN-81 contract and Block V.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Which were signed in 2019.

Doug Harned
Analyst, Bernstein

Yeah. You didn't get much help with that, right?

Chris Kastner
President and CEO, HII

I will say the Navy's been very fair on looking for ways to make investments to make us more productive.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Especially in the nuclear enterprise. No, we didn't get large equitable adjustments to those contracts, but they have been fair. They contributed wages for the submarine program. They have contributed MIB and SIB funding, and given us incentives.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

There has been an effort by the Navy and the administration to support submarines and Newport News.

Doug Harned
Analyst, Bernstein

That extends down into the supply chain, right?

Chris Kastner
President and CEO, HII

It does. Where you identify areas where there's problems, and the MID money and the SID money go into increasing their capacity, give them technical help, additional capital to be invested.

Doug Harned
Analyst, Bernstein

Because this is one of the things that I've struggled with because the shipbuilding supply chain is so complex. I mean.

Chris Kastner
President and CEO, HII

It is complex.

Doug Harned
Analyst, Bernstein

I don't know. Well, it's funny, last year, I remember Phoebe made this comment. She goes, "You think a bomber is hard? You have no idea how hard a nuclear submarine is.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

In trying to understand that, what does the government and the Navy need to do to really facilitate getting your whole supply chain working? They're helping you with labor.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

Are there further steps that you're looking toward that the Navy can execute on?

Chris Kastner
President and CEO, HII

Well, yeah. First things first is award the contract on time. We're on long lead for Block VI already. We're on long lead and have continuous build authority on Columbia, which means we're going on Columbia.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Which we don't have the final negotiated contract yet. The most important thing is to order the material on time. Second is identify the critical suppliers that are at risk and ensure that they don't bite you at the end. Right? We've done that.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

They've expanded their castings and forging suppliers, which was a real bottleneck for us. We actually buy a lot from the U.K. right now. It's happening. Is it happening fast enough? You can always go faster, right?

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

First things first, order stuff on time, right?

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

Don't miss that and then expect a miracle to happen and a supplier to show up 12 months early, so that we can make a production schedule.

Doug Harned
Analyst, Bernstein

When you look at developing this throughput metric and setting a 15% goal, what are the bottlenecks that you're thinking through? In other words, what determines whether that's a 10%, 15%, or 20% goal?

Chris Kastner
President and CEO, HII

Well, we set our plan every year, based upon where every ship is and the EAC for every ship.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

The supplier schedules, the labor demand, how all the ships interact with each other, where they flow through the yard. That is a complicated process. We've already started it, for next year for our plan. You establish your throughput metric based on all those inputs coming together to say what the schedules will be and how productive the people will be when the suppliers are coming in, when they'll make the deliveries.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

The worst thing in the world in a shipyard is to have a crew show up at a work site and not have the material.

Doug Harned
Analyst, Bernstein

Nothing to do.

Chris Kastner
President and CEO, HII

Right? And then it's like, "Okay, what's your second job, foreman?

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right. "Are you ready? Can you put those people to work, or do they have to sit there all day?" Which is just a bad place to be.

Doug Harned
Analyst, Bernstein

I remember you and I saw that many years ago down at Ingalls.

Chris Kastner
President and CEO, HII

We did.

Doug Harned
Analyst, Bernstein

In the Yes.

Chris Kastner
President and CEO, HII

We did. We did. That's a horrible place to be.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We're working really hard on that in both shipyards, to make sure that everything shows up at the right time, and the work packages are actually workable.

Doug Harned
Analyst, Bernstein

Yeah. Now, Block VI, can you describe, as you look at Block VI, how this can be a much more attractive structure for you guys than IV and V were obviously negotiated at different times?

Chris Kastner
President and CEO, HII

Well, you just said it. First things first is it's a completely different economic environment, right?

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

The inflation's different. The supply chain risk is different. The production schedules are different based on where the workforce is. The amount of work in your yard is different. We had to take all that into consideration in establishing that contract. We think that ultimately it'll be a fair contract where we have a real chance

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

To be successful and make our margin our margin target. It's not overly good or overly bad. It's right down the middle to reflect our current situation. I think back to late 1970s, early 1980s, and how the shipyards performed then when they had a different economic environment.

Doug Harned
Analyst, Bernstein

Right.

Chris Kastner
President and CEO, HII

A lot of demand, a lot of inflation, a fragile supply chain. They did pretty well because they reset their contracts to deal with that. Those contracts got diluted over a long time of no growth and no inflation.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

The protective clauses kind of fell away because you didn't really need them, and you lost them at the negotiation table, or they weren't part of a competitive procurement.

Doug Harned
Analyst, Bernstein

Right.

Chris Kastner
President and CEO, HII

Well, now they're back.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

It's kind of cyclical. It just hit us at a tough time because we had some very large contracts negotiated in 2019.

Doug Harned
Analyst, Bernstein

Yeah. If you think about these new ones coming in, as I try to understand Well, actually, let me back up a second and go to the carriers, because you did have an unfavorable adjustment in Q1.

Chris Kastner
President and CEO, HII

We did.

Doug Harned
Analyst, Bernstein

You've had a couple of these on the CVNs. Can you talk about how that program

Chris Kastner
President and CEO, HII

Sure

Doug Harned
Analyst, Bernstein

Is just going overall in the different boats?

Chris Kastner
President and CEO, HII

Sure. 78 had an amazing deployment, by the way, and when the Navy releases the data on their sortie rate, you're going to see that EMALS and AAG, and the elevators performed amazingly.

Doug Harned
Analyst, Bernstein

That's great, too.

Chris Kastner
President and CEO, HII

It's an amazing ship. The data that comes out of there will be very, very positive. 79 is going to have their second trials here in the summer. It's essentially done. Sailors are operating that ship. We'll get the final delivery if not this year, beginning of next year. 80, as you know, is significantly impacted by the reduction gear and the turbine generators in the bottom of the ship. We've received all of that now. We've done deck over. We've initiated our continued erection of the ship on 80. We'll be 75% erected at the end of the year. They're really making hay on 80. Then 81 will lay the keel this year. It'll be right behind it. Unfortunately, that's a lot of bad performance behind you and a lot of inefficiency behind you.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

If you go into Newport News right now, you're going to see units everywhere. You're going to see units in a parking lot outside staged.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

We're out of space because we're just building them, getting them ready to be put in the dock.

Doug Harned
Analyst, Bernstein

Yes.

Chris Kastner
President and CEO, HII

Which is positive. You'd like to just build them and put them onto the ship and erect them, but we couldn't because we had that space. They're making good progress. 81's making good progress, challenging what's been behind us, and we had a minor adjustment. We're going to have to deal with that over the next couple of years as we clean up that production schedule on 80.

We have to be careful of that and if we have some inefficiencies coming through a quarter, we'll have to deal with them.

Doug Harned
Analyst, Bernstein

Well, the carrier program, there's no more complicated program probably than this.

Chris Kastner
President and CEO, HII

RCOH is more complicated.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

It is.

Doug Harned
Analyst, Bernstein

Well, okay. That's relevant here, too, right?

Chris Kastner
President and CEO, HII

It is.

Doug Harned
Analyst, Bernstein

Now you've got the Ford. It's operating, it's performing well.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

Now that it's in service, does that create any sustainment revenue for you when first in class is in service? I don't know if that's material particularly.

Chris Kastner
President and CEO, HII

It's probably not material.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

There is some sustainment revenue.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Engineering and planning revenue that happens at Newport News in support of aircraft carriers, but it's not significantly material, no.

Doug Harned
Analyst, Bernstein

When you go from 78, 79 to 80, are they very different? There's obviously evolution over time.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

How do those crop up? Are there advances that are being pushed through as you move to 81?

Chris Kastner
President and CEO, HII

Major systems are the same.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

Right. Radar are the same. EMALS, same. AAG, same.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

All the aircraft systems the same. You're going to have potential analysis done for 82 to increase lethality, and they may look to backfit that into 81 or 80 if they can catch it.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

When I talk about minor adjustments from time to time on 80 and 81, it's going to be around inefficiencies related to how we did the construction at the beginning of the program.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

What were our assumptions relative to how we were going to complete that or continue to build the ship, and did we meet that or not?

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

You really don't know. You really don't know, because we were so out of sequence on 80. You have to continue to work through that program.

Doug Harned
Analyst, Bernstein

When you put this together, we've got this holy grail of 9%-10%-type shipbuilding margins.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

You look at Newport News. Block VI should come in, be much more attractive. You've got to work through some of the CVN issues. Columbia -class, my assumption, that may be, at this stage, a little bit below. How do you think about the margins and the ultimate path to get to that kind of number?

Chris Kastner
President and CEO, HII

We'll incrementally improve next year. I'm comfortable with our guidance this year. It's going to continue to improve. It's really predicated upon getting those ship deliveries done and transitioning those people into the higher-margin ships. I think both shipyards should be at 9% to 10%, and maybe even north of that, if they're executing well based on these new contracts. Again, 9%-10% is how we forecast the healthy shipyard margin.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Both of them. It's all transitioning out of the ships that are lower margin into the higher ships. I can't stress enough the value you get from going through a ship delivery.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We're going to have people that are going through ship deliveries for the first time, and we've got five

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Coming. When that happens, the learning just happens. You wouldn't believe the DDGs at Ingalls right now. It's just stacked up, and you've been to Ingalls before.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

You can see it. You can be on LHA 8 right now and look across the yard and see just stacks of DDG-51s. If you can finish your milestone and just walk next door and do the exact same job with the exact same team, you're going to be more efficient. We have lacked that

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Probably for 10 years.

Doug Harned
Analyst, Bernstein

When you're saying Newport News, you could get to that, it totally makes sense, get to that 9%-10%. Does that come at a time when you've at least, you got a lot of Block VI work is just going to start.

Chris Kastner
President and CEO, HII

Just going to start. Right

Doug Harned
Analyst, Bernstein

Do we need to wait until Block VI becomes a majority of the work to get there?

Chris Kastner
President and CEO, HII

I can't really predict it at this point.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

I've obviously got plans on when I think it's going to happen.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

A lot of variables that go into that. You don't have to deliver everything in Newport News, both aircraft carriers and all Block V boats before you get there.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right. That happens out in the early or mid-2030s. I fully expect to get there before then.

Doug Harned
Analyst, Bernstein

Yeah. As I think about this, the margin is always this combination of some double-digit margins

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

On fixed price production programs. You've always got development or earlier stage, and it blends out to 9%-10%.

Chris Kastner
President and CEO, HII

That's right.

Doug Harned
Analyst, Bernstein

a long time ago at Newport News.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

You could get, as we saw, and as Mike always tried to dissuade me from, double-digit margins when you got into Ingalls.

Chris Kastner
President and CEO, HII

You were the one that came out. You were the first. Your price target when we came out at 40, you were the one that believed, right? You had the highest price target, you were proven true.

Doug Harned
Analyst, Bernstein

I'd been there.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

I saw Irwin.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

You know?

Chris Kastner
President and CEO, HII

So did I.

Doug Harned
Analyst, Bernstein

Yeah, I know. I'm sure you did.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

A lot.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

The thing that was so important, and it's what I'm looking for here, is that you could be down there and see everything is moving toward mature ships. People know how to build them.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

They're biased toward fixed price mature ships. You could suddenly find yourself in double-digit margins.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

As much as Mike wanted to say, "Don't assume that." You did.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

I would think at Newport News, if you look at the mix there, and if you can get, and forgetting the time, but if you're getting into sort of maturity on production on Virginia-class, you move through a little ways on Columbia. CVN, I have a very hard time understanding how.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

That works.

Chris Kastner
President and CEO, HII

The RCOH is a cost type contract, where there's a significant amount of growth work that happens on that ship.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We should perform well on RCOHs.

Doug Harned
Analyst, Bernstein

Yeah. Okay. Can you perform above what, can you get margins above?

Chris Kastner
President and CEO, HII

I'm not going to comment specifically

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

On what their margin rates are, but it's a cost type ship where you make an assumption about how much growth work you're going to have.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

If it changes, you get consideration for that. You should do well on RCOHs.

Doug Harned
Analyst, Bernstein

It's helpful to get you to your target, basically.

Chris Kastner
President and CEO, HII

Yes.

Doug Harned
Analyst, Bernstein

Yes. Okay. Going over to Ingalls. This is one where we were just talking about it looks like a pretty mature set of programs today.

Chris Kastner
President and CEO, HII

They are. They really are.

Doug Harned
Analyst, Bernstein

What holds you back from getting that kind of 10%+ level margin there?

Chris Kastner
President and CEO, HII

It's the same story. It's less impactful down at Ingalls. There's, I guess, less beta down at Ingalls because they've had a track record of executing on those programs fairly well, and they don't have a new ship program in there either. They negotiated that last DDG contract and a couple of LPDs prior to COVID, right?

Doug Harned
Analyst, Bernstein

Okay

Chris Kastner
President and CEO, HII

Two ago, right? They have to come through those, and they need to get into the new DDGs. They need to get into the amphib bundle. When they do that, and when they execute on those deliveries, it's going to step back up.

Doug Harned
Analyst, Bernstein

That's a big volume of work, right?

Chris Kastner
President and CEO, HII

It's a lot of work. The DDG work is a lot of work.

Doug Harned
Analyst, Bernstein

Assuming that those DDG contracts are good for you guys now.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

This has all the potential, I would think, to revisit those days of a bias toward fixed price mature contracts at a higher volume.

Chris Kastner
President and CEO, HII

Well, they are.

Doug Harned
Analyst, Bernstein

And higher

Chris Kastner
President and CEO, HII

They are. These are all fixed price

Doug Harned
Analyst, Bernstein

Higher margins.

Chris Kastner
President and CEO, HII

Fixed price incentive contracts with fair margins that we have a chance to be successful on.

Doug Harned
Analyst, Bernstein

The FFX, can you just sort of dimension how large that will be in terms of your work down there?

Chris Kastner
President and CEO, HII

They're about an $800 million-$1 billion program.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

From price standpoint. The first two are sole sourced to us, and we think we're going to do a great job building those. It's a little murky when you think about the acquisition profile subsequent to that. I think there'll be more than one builder. That's what the Navy has said. That acquisition profile, we're not really comfortable with yet.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

If we do the first two very well, we have a great chance to build a lot of frigates.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

It's a ship we know how to build. It was very predictable, a really good team. It's not a lot of content in the shipyard. It's got a very predictable build schedule, where we're very comfortable that we know what that ship costs and how long it takes to build it.

Doug Harned
Analyst, Bernstein

Well, it seemed like this was just a natural for you after NSC.

Chris Kastner
President and CEO, HII

We thought, yeah, I'm not going to comment on the award of that contract

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

To the other company. Very rarely do you get someone say, "Can you help us and build a new ship?" Right. It's usually a very competitive process.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We're fortunate we had a ship design that was very buildable.

Doug Harned
Analyst, Bernstein

Yeah. The Trump-class destroyer.

Chris Kastner
President and CEO, HII

Battleship.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Trump-class battleship.

Doug Harned
Analyst, Bernstein

I can't call it destroyer?

Chris Kastner
President and CEO, HII

Well, it's a battleship.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

It's not a destroyer.

Doug Harned
Analyst, Bernstein

I thought you can call it battleships.

Chris Kastner
President and CEO, HII

It's a nuclear battleship, actually. It's been identified as a nuclear battleship. Newport News is engaging with the Navy on how that's going to proceed, and how that design's going to proceed, and how they would build that in Newport News, because they're really the only place that can build it.

Doug Harned
Analyst, Bernstein

It has to be there, right?

Chris Kastner
President and CEO, HII

It has to be there.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Based on the size, and because it's nuclear, it has to be in Newport News.

Doug Harned
Analyst, Bernstein

What's the trajectory for this?

Chris Kastner
President and CEO, HII

Well, it's just starting.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right. We're in the initial stages of discussions with the Navy on the plans for that. You saw it in the 30-year, the shipbuilding plan and the quantities.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We need to get to the design, understand what the design is, and engage in that with the Navy.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Think about how we'd integrate it into the shipyard if we were to build it there, when we build it there. It's just in the initial stages. It's not in our guidance. I think it's positive, and it's broadly supported in the government.

Doug Harned
Analyst, Bernstein

Okay. Yeah, I mean, I've heard a lot of controversial comments about it.

Chris Kastner
President and CEO, HII

I listen to comments by the President, the CNO, the SECNAV.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

All of those are very positive on the nuclear battleship. That's who I'm going with.

Doug Harned
Analyst, Bernstein

Okay.

Chris Kastner
President and CEO, HII

That's who I'm going with.

Doug Harned
Analyst, Bernstein

What I would ask is, do you invest ahead of this, or do you need to know more?

Chris Kastner
President and CEO, HII

I don't need to make significant investment ahead of this.

Doug Harned
Analyst, Bernstein

Okay. Yeah.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

All right.

Chris Kastner
President and CEO, HII

If I do, we'll be very disciplined in how we do it.

Doug Harned
Analyst, Bernstein

Okay. Yeah. On Mission Technologies, and we've discussed this in the past, so maybe you can just help us understand a little more about what holds that whole business together.

Chris Kastner
President and CEO, HII

Sure.

Doug Harned
Analyst, Bernstein

They're different things.

Chris Kastner
President and CEO, HII

Well, think about the acquisitions that pulled together Mission Technologies.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

There's really three major acquisitions. Hydroid, which is really the largest unmanned underwater vehicle provider in the world.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Made that acquisition. SIS, which was a very good unmanned surface provider. SIS in Virginia Beach. Alion, which is technology. Alion has always been an R&D house. A lot of cost type contracts, electronic warfare, C4ISR training.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Really good cyber capability for Cyber Comm. That pulled it all together. We add nuclear into that mix, which is really bullish on nuclear right now. A lot of opportunity, a lot of projects that we're pursuing and competing on that I think have a good chance to win on those, and generate some revenue in commercial nuclear, actually, where we actually build part of the structure.

That's very interesting. Unmanned is probably the most interesting thing right now when you look at the budget.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

What happened in reconciliation, what happened in this year's budget, I think we are nearing that inflection point in unmanned, where it's going to be a more tangible part of the Navy fleet. They're going to buy more product, and they're going to get it out there and see how it works. We're fortunate we made the investments ahead of this. Not only in the companies that can build a product, but our Odyssey autonomy suite is a combination of the SIS autonomy suite and the Hydroid autonomy suite, and we combined them into Odyssey. Open architecture, like the Navy wants, built to Navy standards. We've got world-class partners like Shield AI that we can plug right into it

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

To compete. There are a lot of opportunities that we're competing on in the unmanned space. Obviously, we've got a large contract for small underwater vehicles. There's both international and domestic competitions in the unmanned surface space. We think we made the right investments. We think we're in a great place to compete. Now, it's low barriers to entry, a lot of competitors. I'd put us up against anyone, and I actually think because of our background, and we understand how manned, unmanned teaming has to happen.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We understand the Minotaur technology, which is on P-8 relative to, not mission management, but the battlefield management of the assets on the battlefield. We understand that as well. The frigate's going to have a module in it to control unmanned boats. There's U.K. initiatives around the armour program or their frigate, which Babcock builds, that we have a relationship with, is going to potentially team with the ROMULUS family vehicle that we provide to expand their presence and their reach in the North Sea. We're all over this in support of the Navy's hedge fleet. I think there's real opportunity there, and we're entering this what we talk about as an inflection point

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

In unmanned in support of the Navy.

Doug Harned
Analyst, Bernstein

Yeah. It is also a complicated market to sort through.

Chris Kastner
President and CEO, HII

It's complicated.

Doug Harned
Analyst, Bernstein

because there's so many different types of plays here.

Chris Kastner
President and CEO, HII

Different acquisition approaches, different investment approaches as well because you have to build these things and demonstrate them before they buy them.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right? Now, fortunately, they're not a billion-dollar ship, right? These are not low dollar value, but less dollar value of $20 million-$40 million sort of products when you think about 150-foot surface vehicles. That's an investment

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

That they're going to have to do. It's worth it when you think about how the Navy is evolving with their hedge fleet.

Doug Harned
Analyst, Bernstein

I mean, the session before was the Anduril, and they're in this market too.

Chris Kastner
President and CEO, HII

Yes.

Doug Harned
Analyst, Bernstein

I'm sure as you've heard, there are others like Saronic

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

Other places, and that they'll all talk about their speed to market, speed of development.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

And there's also, I would call it a favorable

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

View inside the Pentagon today of new entrants, whether or not they can do the job.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

There's a real openness to that.

Chris Kastner
President and CEO, HII

Yes.

Doug Harned
Analyst, Bernstein

How do you look at your positions here, and against these new entrants, but also L3Harris, a lot of people.

Chris Kastner
President and CEO, HII

Yeah, low barriers to entry, and as you recall, I was on Global Hawk.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

For Northrop.

Doug Harned
Analyst, Bernstein

Right, yeah.

Chris Kastner
President and CEO, HII

We thought we were going to dominate.

Doug Harned
Analyst, Bernstein

Unmanned, yeah.

Chris Kastner
President and CEO, HII

UAV space.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right? It was just too expensive and the entrants, GA came in with their product and did very well.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

There's a lot of other UAVs that came into the market and did niche sort of missions. I think this will develop in a similar fashion. There are large quantities of surface vehicles that are going to be bought. The beauty of our position is, we've had a bit of a head start.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right, especially in the unmanned undersea. We have some very large contracts. We've been working very hard on our autonomy for a long time.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We built it knowing that we needed to plug in new commercial tech into it.

We're doing that right now. The other issue is you get to demonstrate it.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

It's not marketing when you're out on the water. First of all, I welcome Saronic, Anduril, all the commercial tech. Bringing young, smart people in the industry, as an American, I like.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

That's positive. I need to be given a fair chance to win. When you're going to a demonstration, there's nothing more fair than that. There's a clear criteria on how you need to execute. If you execute, then you can win.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

All I want is a chance to compete, and I think I have that.

Doug Harned
Analyst, Bernstein

Are there certain segments within the unmanned undersea that are particularly well-suited for you?

Chris Kastner
President and CEO, HII

Well, unmanned undersea, I think all of it is well-suited for us because we've been doing it for so long.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Unmanned surface is a little different.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Right. It's a pretty open market right now.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Very small boats. I'm not really sure if that's suited for us, although we did just deliver some relatively small boats to the Marines a couple of months ago that are working great

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

With the Odyssey software on it. Again, we're going to have to evaluate each opportunity. I think you have to choose, because they're going to settle up on a size-

Doug Harned
Analyst, Bernstein

Okay

Chris Kastner
President and CEO, HII

I think.

Doug Harned
Analyst, Bernstein

In the right place.

Chris Kastner
President and CEO, HII

Swimming towards that

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

That right size.

Doug Harned
Analyst, Bernstein

If we look, it's a hot area, but the revenue dollars are relatively small today.

Chris Kastner
President and CEO, HII

With high quantities, it can start to add up.

Doug Harned
Analyst, Bernstein

That's what I was going to get at.

Chris Kastner
President and CEO, HII

Right.

Doug Harned
Analyst, Bernstein

Well, in five years, how large could you see this business being?

Chris Kastner
President and CEO, HII

I don't necessarily want to project that.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

I do think there's interesting models, not only in how you sell them, but how you monetize it.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

Right, with the software.

If you're able to sell these and sell the software potentially independently, and get recurring revenue streams on the software, and we think we have very good software in this space, that's interesting.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Yes, there are small dollar values for each asset, and I don't really want to project how big it's going to get, although I think if you just look at the budget, you're going to see it's going to get bigger, and we'll get a piece of that.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

I do think there's just great opportunity, both top line and bottom line.

Doug Harned
Analyst, Bernstein

Okay. Overall, you've guided to free cash flow of $500 million-$600 million this year.

Chris Kastner
President and CEO, HII

Yes.

Doug Harned
Analyst, Bernstein

What things should we be looking for to see, could you be the high end of that? What will determine why you've come out in that range?

Chris Kastner
President and CEO, HII

Make the ship deliveries.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We need to get Block VI and Columbia done, which will contribute to free cash flow in the year. We need to make our ship deliveries. They're not all five of them in this year. We need 800 done this year, and we need LPD 30 done this year.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

We need to make our throughput commitment, because our billing clauses are based on earning the hours, deliver our ships, get Block VI and Columbia done, and then we'll be fine.

Doug Harned
Analyst, Bernstein

Okay. I'm just curious, there have been some concepts in the past that we haven't seen actually come to fruition. Like LX(R) was going to be the next LPD.

Chris Kastner
President and CEO, HII

Right

Doug Harned
Analyst, Bernstein

LPDs just keep on going.

Chris Kastner
President and CEO, HII

Well, it's a great ship. A lot of room on that ship, a lot of ability to upgrade it based on technology. I think they'll always evaluate different alternatives, but I think that the LPD, the large deck in the LHAs, and the MEU concept for the Marines.

Doug Harned
Analyst, Bernstein

Yeah

Chris Kastner
President and CEO, HII

I think has got a lot of legs, and it's done a very good job.

Doug Harned
Analyst, Bernstein

Yeah.

Chris Kastner
President and CEO, HII

Why mess with something that's doing very well for you?

Doug Harned
Analyst, Bernstein

Yeah. Okay. Well, Chris, great.

Chris Kastner
President and CEO, HII

Good.

Doug Harned
Analyst, Bernstein

It's great to see you here.

Chris Kastner
President and CEO, HII

Great.

Doug Harned
Analyst, Bernstein

Yeah, we're out of time.

Chris Kastner
President and CEO, HII

Oh, are we? Okay. Great. Well, thanks, Doug.

Doug Harned
Analyst, Bernstein

Thanks a lot.

Chris Kastner
President and CEO, HII

Yeah, appreciate it.

Doug Harned
Analyst, Bernstein

Great to see you.