Good afternoon, ladies and gentlemen, and welcome to Plano & Plano's Conference Call to discuss the third quarter 2026 results. This video conference is being recorded, and replay will be available on the company's investor relations website. The slide deck is also available for download. Please note that all participants will be in a listen-only mode during the presentation. We will then begin the question-and-answer session, at which time further instructions will be provided. Before proceeding, we would like to clarify that any statements that may be made during this conference regarding Plano & Plano's business outlook, projections, and operational and financial targets are based on the beliefs and assumptions of the company's management, as well as on the information currently available to Plano & Plano.
Forward-looking statements are no guarantee of future performance and involve risks, uncertainties, and assumptions as they relate to future events, and therefore depend on circumstances that may or may not occur. Investors and analysts should understand that the general economic conditions, industry conditions, and other operating factors may affect Plano & Plano's future results and may cause actual results to differ materially from those expressed in such forward-looking statements. Joining us today are Rodrigo Von, Rodrigo Luna, João Hopp, and Anselmo Soares, respectively, our Chief Executive Officer, our VP, our Executive VP, and Chief Financial Officer of Plano & Plano. I'd now like to turn the call over to Mr. Rodrigo Luna, our VP, who will begin the presentation. Mr. Rodrigo Luna, you may proceed, sir.
Good afternoon, everyone. Thank you for joining Plano & Plano's third quarter 2026 earnings conference call.
We remain firmly committed to our purpose of expanding access to housing, supported by nearly three decades of market experience, execution capabilities, and operational discipline. During the quarter, we launched five projects totaling approximately BRL 1.1 billion in PSV and more than 3,800 units, an increase of nearly 30% quarter-on-quarter. Among the key elements of our value chain, I'd like to highlight the following. Our land bank, with BRL 34.8 billion in potential PSV. It remains very robust, and we continue to attract new business opportunities, supported by the company's strong market position in the city of São Paulo. Our project approval pipeline is now aligned with our launch capacity, and unlike two years ago, is no longer a bottleneck to our growth, so we can plan according to the different regions.
Our operations reached the highest level in our history, with 47,000 units under construction across 67 construction sites, 12.6% higher year-on-year. We delivered three projects during this quarter, totaling 1,265 units. Both our recent deliveries and all of our ongoing construction projects are on schedule. We continuously seek to improve our relationship with our customers, and I'd like to highlight that in September, for the very first time since we began tracking this indicator, we reached the excellence zone across all five customer touchpoints, with an average NPS of 84 on a scale ranging from -100 to +100. Nonetheless, we continue to focus on our main challenge at present, increasing net sales and improving our SOS in a more competitive environment in our core market, the city of São Paulo. Gross sales exceeded BRL 1 billion, up 6% quarter-on-quarter.
Net sales totaled BRL 775 million, reflecting the seasonal concentration of cancellations among informal income customers during this period of the year. Sales to informal income customers have been gaining share in our overall sales mix, making this an increasingly relevant trend that we have been monitoring carefully. Competition in São Paulo remains fierce, with a high supply of social housing products and consumers having a broader range of options to choose from. Against this backdrop, we have accelerated the implementation of changes to our sales process, which are beginning to produce results in our new launches. in October, S&P affirmed our AA+ rating on a national scale with a stable outlook. In the same month, we strengthened our capital structure by raising BRL 150 million through a five-year debenture issuance under the Eco Invest Brasil. Or Eco Invest Brasil, pardon me.
The proceeds are earmarked for projects featuring sustainability attributes and eligible for the Selo Casa Azul + CAIXA certification. We're working towards our first launch in Brazil's Midwest region, in the city of Goiânia, still in 2026, offering the local population a differentiated product in terms of features and quality under tiers 2 and 3 of the Minha Casa, Minha Vida housing program. We remain committed to sustainable value creation with a focus on operational efficiency, financial discipline, innovation, and execution excellence. I'll now turn the call over to João Hopp, who will present our operating and financial results for the period. Thank you.
Thank you, Luna. Good afternoon, everyone. In the third quarter 2026, Plano & Plano launched five projects, 3,119 units, totaling BRL 1 billion and BRL 70 million in PSV.
This represents an increase of 29.5% quarter-on-quarter and a 50% decrease year-on-year. The average price of the units launched was BRL 280,000, up 6.4% quarter-on-quarter and 10.3% year-on-year. That reflects the mix of products launched. In the first nine months of the year, the company launched BRL 2 billion 882 million in PSV, down 39% year-on-year. We remain focused on the planning and preparation of each launch, seeking to maximize initial sales performance. On a Plano & Plano percentage base, PSV launch totaled BRL 1 billion and BRL 13 million, up 29.6% from BRL 781 million in the second quarter 2026. The company accounted for 94.6%. Year to date, we totaled BRL 2 billion 624 million in the Plano & Plano percentage, down 37.3% from the same period last year.
100% of the gross sales totaled BRL 1 billion and BRL 36 million in the third quarter of 2026, up 6% quarter-on-quarter, with 3,799 units sold, 5.5% higher quarter-on-quarter. Net sales totaled BRL 775 million, down 15.4% quarter-on-quarter and 24% year-on-year. This performance reflects BRL 260 million in cancellations during the quarter, concentrated among informal income customers. For sales to this customer segment, the mortgage transfer process follows the income tax filing calendar, when customers provide proof of income in order to obtain mortgage financing from Caixa. Once the filing period is over, customers who have not yet been approved go through a retention and product matching process to identify the product that is compatible with their income. Cases that ultimately cannot be made viable are canceled. It is worth noting that this customer segment already accounts for 21.5% of our gross sales.
Approximately 70% of these sales convert into mortgage transfers. Year to date, net sales are at BRL 2.534 billion. The construction output continued to grow in the third quarter 2026, reaching 188,000 sq m built, up 8.6% quarter-on-quarter and 21.7% year-on-year. In the first nine months of 2026, construction output totaled 506,000 sq m, 28.1% higher year-on-year. We ended the quarter with a record of 47,000 units under construction across 67 construction sites, with an average of 702 units per site, compared to 623 a year ago. We delivered three projects during the quarter, totaling 1,165 units and 6,310 units year to date, all on schedule. We would like to highlight that despite the strong level of activity in the construction segment in São Paulo, all of our projects remain on schedule for delivery to customers.
The company's net revenue totaled BRL 873 million in the third quarter 2026, up 7.1% from the third quarter 2025 and 4.6% lower from the second quarter 2026. As revenue is recognized in the percentage of completion, or POC method, our results reflect the physical progress of construction on units already sold. The slight decrease compared with the previous quarter reflects the decline in net sales during the period. The private market accounted for BRL 836 million of the revenue in the quarter, and year to date, net revenue increased 14.5% to BRL 2.526 billion, driven by the record construction output. We ended the third quarter of 2026 with BRL 3.3 billion in backlog revenue, with an REF margin of 37%.
It is important to note that the REF margin is calculated based on the backlog revenue and the corresponding costs to be recognized and does not include taxes levied on revenue or other accounting adjustments recognized in the income statement. Therefore, it is not directly comparable to the adjusted gross margin. As our projects remain on schedule, this revenue will be progressively recognized as our results construction advances. In the third quarter 2026, adjusted gross profit totaled BRL 264 million, a 4.1% increase year-on-year. The consolidated adjusted gross margin was 30.2%, 0.5% higher quarter-on-quarter. In the private market, adjusted gross margin reached 30.9%, 0.7%, reflecting the revenue recognition of more recently sold products carrying higher margins. The cost revision carried out in the first half of the year was incorporated into the budgets of the projects under construction and will be gradually absorbed as construction progresses.
Against this backdrop, we expect a gradual improvement in gross margin over the coming quarters, provided current market conditions remain in place, particularly the inflation levels. The breakdown of adjusted gross margin by vintage, by launch period in the private market shows that the more recent projects have higher profitability. The 2025 and 2026 launch periods recorded margins of 34.6% and 35.9% respectively in the quarter. The 2025 launch period already accounts for the largest share of revenue for the period, totaling BRL 470 million. As the 2023 launch period projects are completed, more recent launch periods are gaining weight in our results and contributing to the recovering of consolidated margins. At the end of the third quarter of 2026, the private market REF margin stood at 37.2%. This indicator reflects the profitability of sales already made, but not yet recognized in our results.
Variations between the periods are mainly driven by the mix of product sales and updates to construction costs. The total REF margin was 37%, considering both private and public market segments. The breakdown of the REF margin by launch period shows improved profitability in more recent projects, with margins of 37.3% and 37.1% for the 2025 and 2026 launch periods respectively. The 2025 and 2026 launch periods account for approximately 80% of the backlog revenue. Given an average operating cycle of 36 months from launch to delivery, older launch periods account for an increasingly smaller share of our future results. Selling expenses totaled BRL 90 million in the third quarter 2026, down 8.7% from BRL 98 million in the second quarter 2026, and 5.9% higher from the BRL 85 million in the third quarter 2025.
As a percentage of net revenue, selling expenses decreased from 10.7% in the second quarter to 10.3% in the third quarter of 2026, a reduction of 0.4 percentage points. Excluding Pode Entrar, whose sales did not require a commercial sales effort, the ratio was 10.7% compared with the 11.3% in the previous quarter. This drop reflects the normalization of expenses associated with mortgage transfers, such as the commissions, ITBI, property transfer tax, and registration fees, which had been higher in the second quarter due to the concentration of mortgage transfers involving informal income customers. Over the last 12 months, selling expenses totaled BRL 342 million, equivalent to 9.5% of their net revenue, a healthy level that is consistent with our initiatives to keep customers' acquisition under control.
G&A expenses totaled BRL 45 million in the third quarter 2026, down 11.1% from the BRL 50.6 million in the second quarter 2026, and stable broadly compared to the BRL 45.2 million in the third quarter 2025. As a percentage of the net revenue, G&A expenses represented 5.2% compared with 5.5% in the second quarter of 2026 and 5.6% in the third quarter 2025, a 0.4% decrease year-on-year. Over the last 12 months, G&A expenses totaled BRL 189 million, up 2% from the full year 2025. G&A expenses as a percentage of launches increased to 5.4% due to the lower volume in launches during the period rather than the expansion of our cost structure. In the third quarter 2026, 100% net income totaled BRL 70.5 million, 4.7% up from the second quarter 2026, with a net margin of 8.1%, an increase of 0.7 percentage points.
This performance reflects discipline in the operating expenses with an 8.7% reduction in the selling expenses and an 11.1% decrease in G&A expenses, as well as a lower income tax and social contribution burden. On a Plano & Plano basis, net income totaled BRL 54.5 million, up 2.8%, with a net margin of 6.2%. In the first nine months of the year, 100% net income totaled BRL 182 million, with a net margin of 7.2%. We continue to have positive visibility for the coming periods, supported by the BRL 3.3 billion in backlog revenue, which will be recognized as construction progresses, as well as by recent sales carrying higher margins. The company ended the third quarter of 2026 with an operating cash burn of BRL 115 million. Excluding the effects of receivables assignment transactions, operating cash burn was BRL 152 billion.
The net impact of these transactions reflect BRL 39 million in receivable assignment authorization and a new BRL 76 million receivables assignment transaction entered into during the quarter. The period was impacted by the Caixa Econômica Federal strike from September 10 to September 29, which delayed the receipt of approximately BRL 30 million related to customers, whose mortgage transfers had already been completed. In addition, the Pode Entrar program had approximately BRL 25 million in overdue monthly installments, which are expected to be received in the fourth quarter of 2026. Excluding these one-off effects and receivables assignments, cash burn for the quarter would have been BRL 97 million. During the quarter, we also paid BRL 100 million in dividends. At the end of the third quarter 2026, gross debt totaled BRL 1 billion and BRL 106 million. Our corporate debt consisting of CRIs, or CRIs, has a healthy long-term maturity profile with principal amortization beginning only in 2028.
In October, S&P affirmed our AA+ rating on the national scale with a stable outlook, and we raised BRL 115 million through a debenture issuance under the Eco Invest Brasil program, earmarked for projects that meet certain sustainability criteria. The debentures have a five-year term with a cost of 100.5% of the CDI rate. This is the end of the presentation. We are now available for your questions. Thank you.
We will now begin the Q&A session with investors and analysts. If you would like to ask a question, please click the button Raise Hand. If your question has already been answered, you can lower your hand. You can also send your questions clicking on the Q&A icon at the bottom of the screen and send your question in writing with your name and company name. Our first question comes from Gustavo Cambauva from BTG Pactual. Mr. Gustavo, you may begin, sir.
Hi. Good afternoon. I have got two questions. The first has to do with the volume of launches. In this macro scenario with families with a bit more debt and the changes in credit in the Caixa Econômica bank, what are your expectations in the volume of launches in this fourth quarter and in 2027? Do you expect to have a decrease or maintain the pace? My second question has to do with the product mix. Are you going to be focusing on the tier 1, tier 2, tier 3? Which segment do you understand more attractive or less attractive? How is this to impact the company's operations?
Thank you, Camba, for your question. This is João. As for the volume of launches, this year we made an adjustment. Considering the increased competition in São Paulo, we have made changes to our commercial pipeline.
Also, how we have been approaching sales with our real estate agents and with our clients. In the fourth quarter, we expect an increase in launches quarter-on-quarter. So there should be more PSV launches. This should take place in São Paulo, and if we get the approvals as we expect for the Midwest, it should also happen there. So there should be an increase in São Paulo, and there should be this new launch in the Midwest. As for 2027, considering the approval pipeline, which is on schedule, and we can adjust our launch pipeline with the liquidity, we expect to resume growth in 2027. The volume of launches should be similar to what we had in 2025.
So in spite of the fierce competition, we know that we have a project that stands out from the competition, and we are working to deliver growth in 2027, and we expect to deliver volumes similar to what we had in 2025. This also has to do with the mix. Plano & Plano is meeting the demand in tier 1 and low tier 2, different from most other companies. We launched another product that includes this mix. It is the Meu Plano brand. It should account for 13% of the launches in 2026. Most products are tier 2, and we have approximately 5% PSV in tier 4 programmed or planned. Next year, we expect a strong concentration in tier 2, as in 2026, and depending on the inflation levels, we could have some mix for tier 1 and low tier 2 for 2027.
There are some internal decisions to be made, but we plan to have projects delivered in this market where there is less competition. Thank you, Camba.
Thank you, João.
Have a good afternoon.
Matheus Meloni from Santander will ask the next question. Mr. Matheus Meloni, please.
Hi, everyone. Thank you for taking my questions. We have two. What are your expectations for sales in October and November? The relationship with Caixa and the customers as well. Something that caught our eye is the leverage of the debt, almost 30%. There is a substantial growth. How do you see this, and what do you expect in terms of cash burn for the coming quarters? So these are our questions. Thank you.
Thank you, Matheus. As for sales in October and November, we are working for the fourth quarter to be the one with the highest level of sales this year.
Of course, we have one and a half months ahead of us. We had high liquidity products that we already launched, and that helps. There are not many competitors in this segment that can adjust their construction costs to make the prices possible for tier 1. This question around Caixa has been coming up the last 60-90 days. Caixa has been more restrictive, especially where it is identifying issues. We have not had any of our clients needing an interview with the Caixa bank. Our policies protect our company and protect the customer or the client with the debt they have with Caixa. So delinquency with Caixa is very close to the average in Brazil, and Caixa has not required us to take any actions that have been different. So no restrictions there in mortgage transfers or in credit granting for our clients.
So we understand that Caixa is doubling down on situations where it is identifying problems. Again, just to stress the point, we expect the fourth quarter to have the highest sales volumes in the year. As for leverage, cash generation in the fourth quarter is expected to be. Especially the Pode Entrar program, where there is some money to be paid, then would get to the fourth quarter basically on a break-even, give or take, depending on how November and December fare. We need to be paid what we are entitled to in the Pode Entrar program. We have not closed our budget for 2027, but the cash generation should allow for some deleveraging in comparison to 2026. Let us wait for our budget to be more structured, and we will be able to give you more updates, but we are on a track to reduce leverage.
Thank you very much. Have a good afternoon.
Pedro Perrone from Bank of America, you may ask the next question.
Hi, everyone. Thank you for taking my questions. We also have two. Focusing on margins. First, I'd like to understand this recovery. The company expects a gradual recovery starting in the fourth quarter 2026 and in 2027. What are your assumptions concerning inflation? The REF margin is at 37%. Does that already include all of these reviews in the budget? What is holding this recovery back? What are the main hurdles there? Still talking about the margins. Gross margins per launch period decreased in this quarter. Does that still hold true? Can we expect them to continue to drop, or can we expect them to bounce back in October and start of November, if it's not too early? Thank you.
Thank you for your questions, Pedro.
Around the gross margin, there is the legacy factor. Projects from the launch period 2023, as there's a smaller share of this project, this worse margin starts to leave our results. Of course, a very important factor is the other attributes that we have been using to improve our sales at better margins, so without using discounts. This is the main driver that we're having to improve in the future. We increased the inflation expected. We normally launch the project expecting a higher level of inflation because we have a higher level of uncertainty now than we had some months ago. That calls for a more conservative stance. We have been reckoning with a higher inflation rate.
If future inflation is too different to what is expected, this could put some pressure on the margin, but if the inflation is lower than expected, this could improve our margins. We've already accounted for a potentially higher inflation level. The gross margin, when it changes in sales, that has also got to do with the product mix. Lower tier products require less commercial or selling expenses to actually capture that sale. The commission is also lower for this easier, faster sale. Changes in mix will also impact the gross margin. You'll see some changes in the product mix every quarter. Thank you.
Very clear. Thank you.
Ana Júlia from UBS, you may ask your question, ma'am.
Hi, everyone. Thank you for taking our questions. Would like to talk a little bit more about Goiânia. Can you shed some more light on this initiative? What are your expected margins? You mentioned the REF margin per segment, and the project is probably between tiers two and three. We would like to try and understand if that is what we should expect in margins, and also would like to try and understand the expenses dilution and the net margin for these projects in Goiânia.
This is João again. Thank you for your question, Ana Júlia . We're in the final phase of approval in Goiânia. If everything goes according to plan, we'll be able to launch it. So we don't yet have it in any REF margin calculation. The Goiânia and the Midwest projects in general, we are interested in the whole region, aim at the same profitability base that we have in São Paulo. Financially, we're looking at the projects the same way.
Of course, we have all of the necessary adaptations to the project and to the pipeline for the region, but we expect to have the same margins in tier 2 and 3 there as in São Paulo. We'll effectively know if we'll be able to have a better margin in the Midwest once we've delivered one, two, three projects. The competition is completely different there, so our product may really stand out. We'll only be able to tell in time what it is actually like, but the expected profitability is the same. As for the expenses, it's important to highlight that in the Midwest, we have teams focusing on the pipeline there, but most of the backup staff is in São Paulo, right? There should be a minor increase in fixed costs. We are going to be diluting the fixed costs.
We already have a store in the city with our office on the second story of the same building, and we should have about 15 people working there, and the rest of the back office operating from São Paulo. These projects have an important contribution to reducing the margin. We won't be opening the actual figures for this project, but this is how we plan it.
Thank you, Ana, for your questions.
If I may just ask a follow-up question. This gross margin recovery in 2026, 2027 already accounts for this project that will potentially be launched in the fourth quarter in 2027, right? Just for me to understand if Goiânia is already part of this expected improvement. Is it? Just to make sure we understand it correctly.
Yes. Goiânia's gross margin is going to be one of the projects, but we're talking about 2025 in the year.
This is going to be the first one in the Midwest. There are others to come in 2027. It will gradually compose this mix. By the time we get the POC, it will take a while. Construction works probably start about six months after the launch, and then you start seeing the results. The answer is a shy yes, and should gradually get better.
Pedro Lobato from Bradesco BBI, you may ask your question.
I've got two questions. Thank you for taking them. The impact of informal income clients in the gross margin, there was an increase of this share. Do you expect them to continue to grow, this type of customer, this type of client? Or are you at an ideal optimal level with this type of client? The second question has to do with the covenant. The indicator is quite close to the limit. Does that limit the launches looking forward? Thank you.
Informal income clients, they can't present proof of income immediately, but they can file their income tax in the following year and then confirm that with the Caixa bank. They account for approximately 21%, and three cycles ago, it was about 8%. This changes our cash flow dynamics. When you use the word ideal or optimal, ideally, we should have an immediate transfer. This informal customer, if it's additional, it's great. Any customer that can't have an immediate transfer and is going to be a customer that's only going to have a transfer when they have the income tax filed, they are welcome. But if it's a customer that can in any way have an immediate transfer with an immediate proof of income, that is our job. We want to have more customers for our immediate transfer.
That makes the project more profitable. We are managing this situation. We do not want to lose the client that has informal income and that can get the transfer the following year, but we are maximizing the customers that can have an immediate mortgage transfer with formal proof of income. We are trying to strike a balance there, not losing this group, but keeping a healthy cash flow. We are really focusing on this. As for the covenant, we understand that it could be a limiting factor, but what we have been seeing is that all of our launches match the liquidity needed in the market, and the covenant has not been a hurdle. We are launching as we have the expected liquidity, and when we have an SOS that is adequate. It has not been a limiting factor, but it certainly is an indicator we keep a close eye on.
Deleveraging in 2027, in the coming quarters, this indicator should be not as close to the limit, with us not being able to launch because of it, but we are really watching it closely. We are more concerned about the liquidity of the launch than the covenant itself. Thank you very much, Pedro.
Thank you, João.
João Pedro Rodrigues from XP.
Hi, everyone. Thank you for taking my questions. I have also got two. I would like to talk about the tax reform first. Are you going to start contributing next year, right? The VAT tax reform specifically. The unit economics of the projects, what do they look like based on the VAT reform? Does it make sense to start launching it in the lower tiers and having some advantage there? That is my first question. My second question has to do with Cambauva's question.
At the start of the year, said that the expected growth was due to increased sales, right? Increased SOS. You just said that expectation is to increase launches next year. I understand that implies an increase in sales. Is this optimism more focused on the Midwest or on São Paulo, or what tier? What is motivating you to be optimistic about sales next year? That is it. Thank you.
Hi, this is Anselmo. João Pedro, the tax reform is a very important item on our agenda. We are monitoring up close what is being published to the market, making any adjustments that are necessary. The reform should start at the start of 2027. We are prepared for the implementation, for the rollout. These tests and simulations, they are carried out project by project. The actual scenario to approve credit is progressing. We do not have a definitive answer yet, but there is basically a consensus considering the simulations companies carry out that there is the social reduction, the possibility of deducting that land lot, then there is a potential to reduce it there. We are going to be assessing it on a case-by-case basis.
Hi, João Pedro. This is João Hopp. On the increase in sales and launches, this optimism is our pragmatism. We assessed the launches, the liquidity of the neighborhood, our projects. Some are already selling well, and we can have a good idea of when the next phase is going to be launched. UniMed, PSV in the past years allowed us to look at 2027 with more growth. The market of São Paulo, you asked if there is a change in the competition. There is not much of a change in the past months.
There's a lot that is being offered, so there isn't any decrease in competition in São Paulo. The improvements in tactics and systems and marketing, they start impacting better performance in the launches. This is what allows us to be confident to say that we're going to continue to grow. Obviously, we have to continue with this pipeline in the first and second quarters next year to validate this growth in the course of the year. The Midwest is part of this growth. We had the first one this year, and there are other phases of this launch plan for next year, and a new project for next year as well. It's a bit of a combination of all of that. But we're not planning for a, or not foreseeing a decrease in competition in São Paulo. We're focusing on our good performance. Thank you very much.
Rafael Rehder from Safra has got a question.
Can you hear me? Okay. I've got two questions as well. You talked about contract cancellations in the presentation already, but I'd like to try and understand it a bit better. Customers that did not file their income tax in May, have you already had the cancellations or could it impact the coming quarters still? And how do you expect this to behave till it normalizes? And the HIS, has it been a limiting factor for increase in prices? The HIS being the social or affordable housing.
Hi, Rafael. This is João. The cancellations normally take place in the third quarter. Some of it was in the second quarter, and some of it's going to be in the fourth quarter. The rest comes from the, well, normal behavior of the private market. As for the percentage of gross sales, we expect most of it in the first quarter. In the fourth quarter and the first quarter, and then it should get back to the normal cycle. As for the social housing, Luna will answer.
Hi, this is Rodrigo Luna, Rafael. Well, the social housing program is readjusted from time to time. When inflation is higher, this is quite necessary. During the elections or during the election period, this didn't really make much progress because of the political moment that Brazil was going through. We've been taking this point to the ministries to recompose, to offset some of the loss in income that these families have had due to the inflation. If this happens in the short term, it will really help the customers to be fitted into the new price ranges. Thank you. Thank you very much.
Mariangela de Castro from Itaú BBA, you may ask your question, ma'am.
Good afternoon, everyone, and thank you for this presentation. I've also got two questions. The first has to do with the performance of the gross margin. What are the impacts you expect with the increase in fuel prices, the reduction in the six by one work roster, right? The six days on, one day off. And the second question has to do with the receivables that we can expect in the coming quarters and what the expectations of the company are.
Hi, Mariangela. This is João again. As for the inflation, we have got some, well, inflation triggers out there. The FX rate, it's at 561. We have the six by one that will impact the raw materials, will impact the construction works. The corporate workers are not impacted. We already have a 42-work week, so this does not impact productivity. Also, the diesel subsidies can also have an impact on inflation in the short term. There were publications or reports published yesterday that show that there are these triggers, but there wouldn't be necessarily additional inflation points. This mix could add to the inflation, and Von is going to be commenting the construction resources.
Hi, this is Rodrigo Von. We've been talking in SindusCon a lot with our colleagues with a six-day work week. There are several ways to look at this, but the perspective we understand here in Plano & Plano indicate that there should be an increase of 1% with the 44 to 42-hour week. Justice Dino had some decisions, and SindusCon is going to sign the deal, sign the agreement, pardon me. We understand that there is an inflation in the period.
There is the oil subsidy. There should be some impact when the subsidy goes away, but we understand that the environment is under control. There shouldn't be any major differences to what we're already discussing here. As for the receivables question, we've been using this advanced payment of receivables to cover our covenant obligations. We prefer to have a long-term corporate debt, and we'll be using it as we see the opportunity to launch or to continue to grow and use this early pay to bring forward our covenant. In the five quarters, we have used it. We may use it in the fourth quarter, possibly in the first quarter, but we're hoping not to use it anymore. Then we can remove it from our radar from mid-2027, I'd say.
Thank you, Mariangela.
Very clear. Thank you very much.
This is the end of our Q&A session. Would now turn the call over to Mr. Rodrigo Luna for his final remarks.
Once again, thank you very much, everyone, for joining us. Thank you for joining the third quarter earnings call. We continue to work to increase our margins, increase our SOS. The economy is going through a difficult, challenging moment. Now the elections are over, and we have a country that is seeking to reduce the level of debt of Brazilian households. That, of course, impacts directly the ability to buy your own house. Inflation is also something on our radar, considering all of the points that we already mentioned here. However, demand continues to be quite high. A lot of people coming to see the real estate agents. The stability of our programs and the maintenance of the fund of guarantee maintenance, we hope to continue to have the good results.
We're positive, we're enthusiastic. Again, it's challenging times, but the company is working night and day and night to overcome all challenges. Once again, we wish you all a good afternoon and see you next time.
This is the end of Plano & Plano's conference call. Wish you all a good afternoon.