Good afternoon, everyone, and welcome to this earnings call. Arvestet continued its strong financial and operational performance in the Q3 of the year despite the persistent COVID-nineteen related challenges. Our asset base remained fully operational, and we have seen good progress on our construction projects across the different regions. EBITDA for the 3rd quarter amounted to DKK 3,400,000,000, a decrease of 18% compared to Q3 last year. But as you are aware, Q3 last year was significantly impacted by partnership income from Hornsea 1.
Adjusting for partnership income from Hornsea 1. Adjusting for partnership effects, EBITDA increased by 6%. EBITDA from offshore and onshore wind farms in operation increased by 13% to DKK 3,400,000,000 driven by ramp up of Hornsea 1, borsley 1 and 2, Sage Draw and Plum Creek. As expected, we have continued to see some adverse COVID-nineteen related profit impacts in the UK to the June of DKK 100,000,000 in Q3. Based on the very solid year to date performance, we remain comfortable with our full year EBITDA guidance of DKK 16 billion to DKK 17 billion and gross investments of DKK 28 billion to DKK 30 billion.
In August, we reached an important strategic milestone with the completion of the divestment of our Danish power distribution, Residential Customer and City Light businesses, the divestment essentially concludes our transformation into a global renewable energy company. On that same note, our green share of generation reached 90% in Q3 this year, up from 87% in Q3 last year. In the beginning of September, we installed the last turbine at the 752 Megawatt Borsenley 1 and 2 offshore wind farm in the Netherlands. With the first turbine installed back in April, the entire turbine installation process took place during the pandemic, which is quite an impressive achievement that demonstrates the robustness of our EPC capabilities and our dedication to the high safety standards. When fully operational during Q4, Borsley 1 and 2 will be the 2nd largest offshore wind farm in the world and the largest in the Netherlands.
We have been exploring the interest among investors for a potential farm down of Borsley 1 and 2 wind farm. We continue to see a strong demand to become partners in our offshore wind assets and have therefore initiated a structured farm down of Borceli 1 and 2, with signing expected during first half of next year. Farming down Borcelain will crystallize value upfront and enable us to invest in additional green growth opportunities. Our onshore business also continues its strong momentum. In September, we commissioned the 103 Megawatt Willow Creek Onshore Wind Farm ahead of schedule and on budget, which just like Worsley 1 and 2 was successfully constructed during the pandemic.
It is the 3rd onshore wind farm we have commissioned since March. Willow Creek is our 2nd project in the SPP area, and it further diversifies our operational portfolio. In September, we also took the final investment decision on our largest onshore wind project to date, the 367 Megawatt Western Trail project. The Greenfield project will further strengthen our ERCOT West asset base. The wind farm is eligible for 100% PTC, and we expect it to be commissioned in Q3 2021.
In October, we acquired and took the final investment decision on the 298 Megawatt onshore wind development project in Nebraska. The late stage project is adjacent to our operational Plum Creek wind farm and further expands our portfolio in the SPP area. Haystack is expected to be commissioned during Q4 next year and is also eligible for 100% PTC. With the addition of Willow Creek, Western Trail and Haystack, we now have 3 gigawatts of combined onshore wind and solar PV in operation or under construction. And we remain very happy about the expansion of Orsted onshore.
In mid October, the Renaissance plant in Northridge, U. K. Was successfully commissioned after operations at the plant lift up to a set of predefined commissioning criteria. With the commissioning of Renaissance, we reached an important milestone, and we'll now continue to monitor the plant's performance while we explore the broader commercial potential of this innovative waste treatment technology. Moving on to hydrogen.
We have established a foothold in a market that we believe will offer us significant growth opportunities over the coming decades. In October, we joined forces with the world's leading fertilizer company, Yara, to develop 100 Megawatt Offshore Wind Powered Electrolyzer for renewable hydrogen production. The aim of the plant is to replace fossil based hydrogen with renewable hydrogen for ammonia production at Yara's Slaiskill plant in the Netherlands. And it would have the potential to abate more than 100,000 tons of CO2 per year. The renewable hydrogen would generate around 75,000 tons of green ammonia per year based on dedicated renewable energy supply from Orsted's nearby Orsted's 1 and 2 offshore wind farm.
Subject to a confirmed business case, a final investment decision could be taken late 2021 or early 2022. Our business platform and project pipeline within renewable hydrogen continues to evolve, and the project at Slauskill is our 5th renewable hydrogen development project, with the 4 others being the Greenfuels for Denmark partnership and the H2Res project, both in Copenhagen, the Westkoester 100 project in Northern Germany and the Giga Stack project in the UK. These pilot projects will provide valuable insights and experience. The aim should be to mature the renewable hydrogen industry and within a decade make it a competitive alternative source to fossil based fuels. In our view, renewable hydrogen has the potential to become a cornerstone of the future energy supply.
It will further stimulate the need for offshore wind and help decarbonize hard to abate sectors of Directors appointed Mats Nipper as my successor as CEO of Warstead. Mats, as you know, is a highly accomplished leader. And with his visionary thinking, strategic skills and dedication to help build a sustainable future for our planet, continued global expansion is in very good hands. I'm very much looking forward to welcoming Mats on January 1. Let's turn to Slide 4, where I want to give an update on our U.
S. Offshore wind portfolio. Since the Bureau of Ocean Energy Management published a supplement to the draft environmental impact statement for Vineyard Wind in June this year, we have been awaiting further clarity around the federal permitting process for our projects. At this stage, we had expected to receive notices of intent from Bowen for our advanced age development projects. An NOI signifies that Bowen received a construction and operations plan and determined the application as complete, thereby starting the 2 year regulatory clock for BOEM's ultimate approval of the construction and operations plan.
We were expecting our NOIs to get back on track following the Vineyard Wind supplemental Environmental Impact Statement, given the positive indications from the Department of Interior earlier this summer. Since then, we have not seen the anticipated progress and now have been guided to NOIs being put on hold until Vineyard Wind's final environmental impact statement is published. This will expectedly happen within the next few weeks. BOEM has set a deadline for itself at November 13. As a consequence, we must foresee further permitting progress being pushed into early 2021, and this does constitute a significant delay.
In addition to uncertainty around the permitting process, we are also awaiting confirmation on whether BOEM will pursue the consensus developer turbine layout in the Northeast of 1 nautical mile by 1 nautical mile. While we hope for a sense of clarity sooner, it is increasingly likely we won't know the final decision on the project layout until November 13. Subsequently, BOEM is expected to issue its record of decision for the Vineyard Wind project on December 18. Even assuming the permitting process starts moving within the Q1 next year, it appears highly likely that Revolution Wind, Ocean Wind, Skipjack and Sunrise Wind will be delayed beyond the previously expected 2023 2024 construction years. For all four projects, we have some flexibility in the time line, and we have been able to make good progress on some other project milestones in the meantime, which I'll come back to.
However, until there is a clear time line from Bowen, we cannot rebaseline our construction schedules. For South Fork, Bowen reinitiated the permitting process in August, and the project was given a permitting schedule that targets the record of decision in October 2021, making it the only project other than Vineyard Wind to formally advance in the federal permitting process ahead of the Vineyard Wind final environmental impact statement. With the updated permitting schedule, we now expect to commission South Fork by the end of 2023. In the midst of the uncertainty around the permitting, we have taken advantage of the additional time and managed to progress our U. S.
Offshore wind portfolio in a number of areas. Our state permits have been matured, including the decisive support from 5 New York State agencies to site the transmission cable in East Hampton to connect the South Fork Wind project to the onshore grid. In Long Island, we have secured a good location for our O and M center in Port Jefferson. We have further matured our supply chain and logistics solutions, including the announcement of the service and operations vessel contract that and Eversource signed with Edison's West Offshore, being the 1st new build Jones Act qualified vessel of its kind in the U. S.
Moreover, upgrades of certain components will help support project economics, which is quite critical as permitting delays inevitably have a negative impact on our project economics. Despite the permitting delays, we have made good progress on many other critical parts of the portfolio, as I mentioned. And on that basis, we remain confident that we can deliver our U. S. Project portfolio with satisfactory value creation.
And we continue to see solid long term growth and value creation potential in U. S. Offshore wind. Turning to Slide 5. Let me just give you an update on the offshore construction projects.
At the Dutch porcelain 1 and 2 wind farm, as I mentioned, we have installed the last of the 94 turbines. They are now undergoing the final testing before we can commission the wind farm. Once fully operational during this quarter, the wind farm will supply renewable energy to 1,000,000 Dutch households. At the end of September, the 12 Megawatt Virginia EPC demo project delivered 1st Power. And in mid October, the project was completed and handed over to Dominion Energy.
The project is the first to be completed in federal waters, and the U. S. Team and contractors have worked extremely hard to ensure a safe and efficient construction of the project. At both Hornsea 2 and Greater Changwa 1 and 2A, the construction work continues on schedule. At Hornsea 2, the installation of export cables and foundations has commenced.
In total, 165 foundations will be installed at sea in preparation for the site's 8.4 Megawatt Siemens Gamesa turbines at what will be the world's largest offshore wind farm once commissioned. Hornsea 2 still remains construction project most affected by COVID-nineteen. Due to the pandemic, the shipyard in Singapore, where the topside for the offshore substation is being constructed was closed down. The shipyard is now up and running again, and we do not expect the delay to affect the commissioning date of the wind farm nor harm overall project economics. Turning to Slide 6 for an update on the construction projects in onshore and bioenergy.
We continue to see very good progress on our construction projects in onshore. At Permian Energy Center, we have completed more than half of the module installations. And at Mussel Shoals, half of the piles have been installed. At our 2 onshore wind projects, Western Trail and Haystack, the key contracts have been executed and notice to proceed has been issued. As mentioned earlier, we have now commissioned our Renaissance plant after having successfully completed the last performance test.
The commissioning of the plant has been significantly delayed primarily due to the mechanical sorting process, which has now been resolved with upgrades at the facility. During the modification and upgrades, the plant has been downsized. This means that the maximum capacity of the plant is now 80,000 tons of waste per year instead of 120,000 tons per year as originally planned. Let's go to Slide 7 and an update on upcoming auctions and market developments in offshore. We continue to see very significant momentum in global offshore wind growth based on the development in Europe, the U.
S. And Asia U. S. And Asia Pacific. After more than 10 gigawatts being awarded for the first time ever in 2019, we have seen a step down in the number of auctions and awards in 2020.
However, over the coming 15 months, we could see global awards of up to 30 gigawatt, and 2021 will reach a new all time high. We expect 3 auctions to take place in the Q4 of 2020, all three of them in the U. S. With auctions in Maryland, New York and New Jersey. Earlier this year, New York State issued their 2nd RFP.
Bids were due on October 20, and together with our partner Eversource, we have submitted bids in the up to 2.5 gigawatt auction. We're now looking forward to the outcome of the auction expected in December 2020. Maryland's 2nd procurement window is open, and bids must be submitted by year end. Maryland is able to procure around 1.2 gigawatt in this and subsequent rounds cumulatively. Results are known approximately 1 year after bid submission.
New Jersey will also be hosting their 2nd offshore wind auction during the Q4 this year. The bid deadline for the up to 2.4 gigawatt procurement has been scheduled for December 2020 with expected awards in the first half of twenty twenty one. In addition to these 3 U. S. Auctions this year, we expect auctions in Rhode Island, Massachusetts, Connecticut and Maryland to place during 2021.
Before moving on to the other regions, I want to address the recent criticism brought up in New Jersey regarding our investment in local jobs and the local supply chain. Let However, a large project like Ocean Wind is a 5 to 7 year process following the award of the auction. Federal consenting delays, as previously mentioned, inevitably push off the investment. We have to get confirmation from BOEM on our NOIs as well as the turbine layout before we have the visibility needed to finalize our local supply chain investments. Despite the delays in our Ocean Wind project, we continue to progress on a state of the art monopile manufacturing facility in South Jersey and recently signed our preliminary joint development agreement with our supply chain partner, EEW.
This sets the high level terms and conditions for development of this factory. The start of construction will be dependent on certain condition precedents, which still need to be met. Together with our supply chain partner and key stakeholders in New Jersey, we're working hard to keep this on track to be the 1st offshore wind monopile facility in the U. S. Moving towards Asia Pacific.
The draft auction guidelines have been issued for the 1st Japanese round for the Choshi, Noshiro and Yuri Honjo areas. The auction is expected to open in November this year with the deadline for bid submission in first half next year and awards expected in Q4 next year. We expect the auction to comprise a capacity of around 1.5 gigawatts. In South Korea, we're working on initial markets and pre asset development, mainly through early stage greenfield offshore wind development, such as data measurement and permitting work. Moving on to recent developments in Europe.
The consent of our Hornsea 3 site was postponed to December 31 in order to study further information on bird impacts. Following the postponement, we have worked closely with key stakeholders to develop a robust evidence based kitty weight compensation plan for Hornsea 3. The plan focuses on the implementation of onshore artificial nesting structures, specifically designed for kitty weight, which will increase breeding productivity. Climate change remains the primary threat to biodiversity and habitats, and we are pleased that the Secretary of State recognizes the significant contribution Hornsea 3 would make towards the national need for renewable energy. With a potential capacity of at least 2.4 gigawatt, Hornsea 3 could provide clean power to over 2,000,000 U.
K. Homes and offset over 128,000,000 tons of CO2 over its lifetime. We do remain optimistic about receiving the consent. In the beginning of the month, Prime Minister Boris Johnson announced new plans to build that greener by making the U. K.
The world leader in clean wind energy. We welcome this announcement from the government, which underpins the huge opportunity for world class U. U. Offshore wind is the most cost effective way to achieve the U. K.
Net zero ambitions, and we see delivering 40 gigawatt of offshore wind by 2,030 as an essential part of this roadmap. It is a challenging but achievable target if the government and the industry continue to work together to accelerate deployment of the UK project pipeline. It will fuel growth and jobs in coastal communities and beyond, while expediting the progress to a more sustainable low carbon future. The Polish Offshore Wind Act is currently being finalized and is expected to be approved by the parliament in November and implemented into law in December this year. The draft legislation aims to award 10.9 gigawatts of offshore wind by 2020 7.
Up to 5.9 gigawatts will be selected from the most advanced projects in the country's pipeline by the Polish energy regulator. These advanced projects include the 2 projects totaling 2.5 gigawatts, covered by our nonbinding term sheet with PGE. Applications for the individual projects must be submitted by the end of March 2021, and the Polish government is expected to grant awards in June 2021. We are still in the process of negotiating the binding agreements with PGE regarding the Baltica II and Baltica III offshore wind farms, and we expect to conclude the transaction by the end of this year. In addition to the 4th UK CFD CFD round and the 1st Polish awards, we expect tenders in the Netherlands, Denmark, Germany and France during 2021.
With this, I will now hand over the word to Marjane, please.
Thank you, Henrik, and good afternoon from me, too. Let's start on Slide 8, where I will go through the EBITDA for Q3 2020. We realized an EBITDA of DKK 3,400,000,000, an increase of DKK 0.8 1,000,000,000 compared to Q3 last year. The decrease was expected and mainly due to high construction activity at Hornsea 1 during Q3 last year. EBITDA, excluding the construction agreements, increased by 0 point €2,000,000,000 In Offshore, the EBITDA for the quarter totaled €2,600,000,000 a decrease of 0 point 6,000,000,000.
The earnings from operating wind farms was 15% above last year, driven by the ramp up of Hornsea 1 and power generation in Q3 increased 14% due to the ramp up I just described. And the availability last year and amounted to an average portfolio of 2.8.2 meters per second, meters per second, above normal wind speeds in the Q3 of 8.0 meters per second. We have seen adverse COVID-nineteen related impacts of approximately EUR 100,000,000 on our operational earnings, especially related to the UK power market due to the lower demand for electricity. This has led to higher balancing tariffs from National Grid, some hours with negative power prices and lower than expected rock recycle prices. Earnings from partnerships amounted to EUR 200,000,000 compared to EUR 1,200,000,000 in Q3 'nineteen.
The construction agreements in Q3 'twenty related to the construction of Virginia Coastal Wind and minor updates regarding finalized construction projects. In Q3 2019, earnings from construction agreements primarily related to Halt C1. In Onshore, EBITDA amounted to SEK 300,000,000, which was in line with last year. Earnings from ramp up of generation from Sage Draw, Plum Creek and Willow Creek were offset by the very high peak power prices in Texas in August 2019, which led to unusually high earnings at Willow Springs, at Tahoeqa and Locket in Q3 2019. Wind speeds for the portfolio in Q3 was 6.7 meters per second, which was slightly higher than the same period last year and a normal Q3 of 6.6 meters per second.
Availability across the portfolio came in at 97%, 1 percentage point below last year. EBITDA in Markets and Bioenergy was EUR 400,000,000 in line with Q3 2019. EBITDA from the CHP plants decreased by EUR 300,000,000 to EUR 300,000,000,000, mainly due to the reverse €1,000,000,000 to €100,000,000 mainly due to the reversal of a provision following the acquittal in the LSM case in Q3 2019. The lower achieved power prices for our generation were offset by higher Gas Markets and Infrastructure increased EUR 200,000,000 compared to Q3 last year due to a less negative impact from from financial performance and net interest bearing debt. The net profit totaled SEK 12,000,000,000 which was SEK 10,600,000,000 up versus last year.
The increase was primarily driven by the €11,100,000,000 gain on divestment of our Danish power distribution, residential customer and Citylights businesses to CS and V. This was partly offset by the lower EBITDA and the higher from operating activities came in at EUR 1,900,000,000 in the quarter, driven by EBITDA and tax equity contribution from partners at Willow Creek. Proceeds from the divestment of the Danish Power Distribution Residential Customer and Civilite businesses amounted to SEK 20,500,000,000 Our gross investments for the quarter totaled €9,300,000,000 primarily related to our offshore projects, Borsello 1 and 2, Hornsea 2, Greater Shanghua 1 and 2A and Ocean Wind in the U. S. As well as our onshore projects, Permian Energy Center, Muscle Shoals, Western Trail and Willow Creek.
Our net debt at the end of Q3 2020 amounted to SEK 8,200,000,000 and the decrease in the quarter primarily reflected the positive cash flow I described. Additionally, we have received deferred proceeds of USD 150 million from INEOS regarding the ONG divestment back in 2017. Let's turn to Slide 10, which shows our financial and non financial ratios. Our key credit metric, FFO to adjusted net debt, stood at 36% for the 12 month period ending in September. The metric was positively impacted by the proceeds from the divestments of the Power Distribution and 2019 was significantly 2019 was significantly impacted by the farm down gain from Hornsea 1 in Q4 20 due to our continued build out of offshore and onshore wind.
And we remain well on track to meet our Scope 1 and 2 target of less than 10 grams CO2 equivalents per kilowatt hour in 2025. Our target is to be carbon neutral in 2025 by neutralizing any remaining minor emissions with carbon offsets. As always, safety is high on our agenda, and we to prevent accidents and injuries. During the 1st 9 months of 2020, the total recordable injury rate amounted to SEK 3.8, which was a positive development compared to 2019. Our target is a rate of 4.2% or lower this year and 2.9% in 2025.
Slide 11 recaps our 2020 EBITDA and gross and gross investment guidance. Gross investments are expected to amount to SEK 28,000,000,000 to SEK 30,000,000,000 in 2020 and totaled €18,300,000,000 for the 1st 9 months. We expect Q4 2020 to be a big investment quarter, driven not least by Borsello I and II, Changwa I and IIA, Hornsea II and U. S. Offshore and onshore projects.
And we remain comfortable with our long term financial targets, including EBITDA growth, return on capital employed and contracted share of profits. And with that, we will now open up for questions. Operator, please.
This concludes our presentation, and we're now happy to answer your questions. This call will have to end no later than 3:30. Please respect only one question per participant, and then you can go back to the queue for a second question. Our first question comes from the line of Christian Johansen from Danske Bank. Please go ahead.
Yes, thank you. So my question is regarding the U. S. Projects and the potential mitigates of a delay here. What can you do if you run into a delay, which essentially worsens the return to mitigate this?
And particularly, are there any options to switch on your equipment, specifically for some of your projects where I remember you have chosen an 8 megawatt turbine? Is it possible to do a substantial upgrade on these ones?
Thank you, Christian. We are obviously spending the extra time that we, so to speak, have been given here to optimize all parts of the supply chain packages and the total supply chain solution, including our logistics solutions, our harbor solutions, etcetera. So we are spending the time, and we are seeing some benefits from that. Specifically, on the topic of turbines, we are also working to upgrade the turbines. You do know that we have already upgraded the turbine in the Mid Atlantic going for the GV, a 12 Megawatt turbine.
And we are working also to upgrade the turbine in the Northeast where we up until now have been working off. The D8 turbine from Siemens Gamesa, we were working on a solution to upgrade that as well. So that is a meaningful opportunity to offset the financial impact from the permitting delays.
And do you expect to be able to fully offset the impact?
Well, I mean, there are many, many moving parts of it in this question. So I'd be a little hesitant to say that we can offset all of it. Some of it comes back to when we ultimately get these permits. Right now, we're working off an assumption that we'll start seeing these permits being issued towards the end of Q1 next year. So that's our current planning assumption.
And based on that planning assumption, we still see economics being meaningful and the value spreads acceptable to us.
And the next question comes from the line of Peter Bisztyga from BofA Securities. Please go ahead.
Yes. Hi. Thanks for taking my question. Just on the next series of auctions in the U. S.
And I guess the New York one that you've already participated in. Could you tell us which ones you think are going to be purely price based in terms of the decision making? And which ones, if any, still will have the sort of qualitative elements in the award process? Peter, are you asking about the U. S.
Project in particular or more broadly the entire global portfolio? I was asking about the U. S. In particular, but I guess if you could also maybe comment on Poland and Japan, I guess, specifically in that context. Yes.
So would be happy to. I mean in the U. S, the simplified way of saying it is that we typically see the New England auctions being more skewed towards price, where we see New York, New Jersey, Maryland auctions, taking a broader, more holistic view, also emphasizing more local content, local investment, job creation parameters, track record, credibility, etcetera. So that is the broad way of looking at a segmentation of the U. S.
Markets. When it comes to Japan, they have now issued the auction guidelines, and it will be a 5050, so 50% price, 50% non price. And they have also, at a high level, specified what the non price parameters will be, and it would be sort of what you normally expect in terms of experience and reliability, project feasibility, etcetera. Stakeholder management is also a criterion and local economic impact. In Poland, it's going to be a slightly different model given that the government will award the initial up to 5.9 gigawatts directly without a competitive allocation mechanism.
So it will be awarded more on, let's call it, a beauty contest amongst the most mature Polish offshore wind projects. And we would count Baltica 2 and Baltica 3 to be among them. Excellent. Thank you. That's very helpful.
And the next question comes from the line of Deepak Venkateshwaran from Bernstein. Please go ahead.
Thank you. I had a couple of questions on the UK. Would you be able to clarify what kind of auction mechanism you expect for 2021? There were some rumors earlier about going for a negative bid and so on, so maybe your latest expectation. And then broadly, are you supportive of the integrated offshore transmission?
Or do you prefer to stick with the current model, which is a single transmission line to every project? Thank you.
Thanks, Deepak.
When it comes to the format the CFD Round 4, we would expect it to follow the format of the last of Round 3. It is at least not to my knowledge the expectation that we would be looking at what I guess I take it from your question, you are sort of saying could there even be a concession payment type of structure in the format. That is certainly not my expectation. In terms of integrated offshore transmission, I can certainly see there being a rationale for optimizing and thinking through the broader transmission buildout as the UK continues to accelerate the buildout of offshore wind. On the other hand, it is important to make this transmission part of the assets exposed to competition.
And we do see significant benefits from the offshore wind developers being in charge of building these transmission assets as an integral part of building out the generation assets. So you don't start separating the 2. So in some cases, I still believe that single line transmission will make sense. But in other cases, it will make sense to start thinking about integrating some of these transmission infrastructures, but still keeping them exposed to the competition that we know from the CFD routes.
Thank you.
And the next question comes from the line of Markus Belinda from Nordea. Please go ahead.
Yes, thank you. A question regarding the U. S. You showed that on that slide that 7 of the next of the upcoming auctions are in the U. S.
And I'm just wondering how many of those you can realistically participate in given that you only have 2 seabed leases left. And if you could also elaborate what you are doing to sort of build your pipeline in the U. S?
Thank you. Thanks, Markus. Yes, I mean, you're absolutely right. I mean, it's going to come down to how much capacity we might win. Obviously, there is a scenario if we are very successful successful and we get our hands on a number of awards early on across these 7 options that we, over time, can fill up the lease areas.
But we still have meaningful amounts of lease capacity left. So we're talking several gigawatts of offshore wind awards before we would start filling up. So I would expect us to join the vast majority of these auctions. Should we ultimately sell out, I would obviously consider that a positive a positive challenge for us. There will be lease routes coming up in the U.
S. As you know, they have been delayed. But over time, there will be more lease rounds. And of course, we are constantly keeping an eye on our inventory of lease capacity. Today, in the U.
S, we still have, by a wide margin, the most advantageous position auctions over the next 15 to 18 months. So we have a pretty strong position in the U. S. As a starting point. But of course, we keep an eye on refilling our lease capacity over time, not only in the U.
S, but more broadly. Got it. Okay. Thank you.
And the next question comes from the line of Alberto Gandolfi from Goldman Sachs. Please go ahead.
Afternoon, and thank you for taking my call. My call is going again to your very helpful Slide 7. There's 25 to 30 gigawatt of auctions in the coming just over a year and a little bit. Can you please tell us how many gigawatts will you try to effectively bid for? Where do you have a seabed that allows you to bid out of this 25 to 30?
And maybe can you remind us that if your strategy is to go and obtain as many as you can given your return threshold or if you're going to encounter, let's say, some balance sheet headroom constraints. Perhaps you'll be open even to rotate more or to issue equity. So I'm trying to think about your mindset here in the bidding. Thank you.
Thanks a lot, Alberto. To the first question of where can we actually bid, We are in a position where we can bid for all of these U. S. Projects, unless back to the question asked by markets, unless we sell out, so to speak. But that doesn't seem to be the most likely scenario.
So we could join all of these U. S. Auctions from our current lease areas. We based on an expected consent for Hornsea 3, we would be bidding off Hornsea 3 in the U. K.
Around 4. We have Changwa 3 to join in a potential, what we call, a transition auction in Taiwan towards the end of 2021, which hasn't been confirmed yet, but is our hope and expectation that, that may take place by end of 2021. The Polish award, of course, is back to the agreement with PG on Bolsky 2 and 3, so we'll be joining through those projects. And then Japan, we would be joining in the JV with TEPCO for the Chuxi and so on. And then you have the remainder being centralized tenders.
So Germany, the Netherlands and France all being sites that are being offered by the local government. So that's not really there we don't really have to have a site obviously. So in other ways, we can join all of these options. We would expect to join the vast majority of them. I'm not going to say that we will join every single one of them.
We may sometimes decide to prioritize our efforts a bit here. But you should expect us to be covering a very good chunk of this list of auctions. And in terms of our capacity, we do have the balance sheet capacity to do this and to go after them. So it comes back to the return threshold. So to answer your question, will we maximize our awards as long as we can get to a satisfactory value spread on top of cost of capital?
Then the answer is yes. We are going to go after this opportunity over the next 15 months. Thank you.
And the next question comes from the line of Kasper Blom from ABG. Please go ahead.
Thank you very much. A question concerning your guidance for 2020 or the last 2 months of 2020, so to say. Euros 16,000,000,000 to euros 17,000,000,000, you've done €13,100,000,000 year to date. So effectively, you're guiding €2,900,000,000 to 3,900,000,000 in the last quarter of 2020. Last year, in Q4 2019, you did 4.6
percent, then you've divested the
distribution business. But on the other hand, the negative LNG will not impact Q4 either. So what is it that is to drive your earnings down to the guidance level? Thank you.
Thank you, Kasper. I think Mariana will take this one.
Yes. Thanks for the question. Yes, there are several factors. You rightly point out the divestment of RBC. Then we also have quite a lot of project development costs coming in Q4.
We have activities in the U. S, but also in the other markets. Then we will not have construction gains in the Q4 because we don't have any construction projects for partners. We had quite significant construction gains last year. And then we see the normal cushion in a way on uncertainty on the production and also these storage impacts that we have.
So it is a bottom up and solid estimate we are coming up
with. But my and sorry to be a pain here, but there was very little construction agreement earning Yes, it
on the other hand. Yes, it was around €100,000,000
Yes, yes.
So yes, but we will have no yes.
Yes. Are you basically then saying that you're going to spend more than €1,000,000,000 on developing new projects in Q4 in the offshore business?
I will not give you the exact amount, but you're not far from. We will have quite a large spend on project development in Q4. Yes, you're right.
Okay. Thank you. And the next question?
It's a fair question, Casper. But we do expect significant benefits, as Marianne said. And you have to bear in mind, we're working on a very broad set of opportunities around the world at the moment. So our development efforts are quite extensive right now, not least looking into the market opportunity we just discussed.
That's absolutely fair. It just means we need to sort of leave the €2,000,000,000 level behind us then.
For this year, yes.
Yes. Cool.
Thank you a lot.
Thanks.
And the next question comes from the line of Sam Arie from UBS. Please go ahead.
Hello, everybody, and thank you as always for the presentation. Henrik, I realize I'm not sure if you will be presenting again full year results next year. I rather guess you won't be. And if so, this might have been your last presentation. So special thanks this time.
And thanks for all the previous ones.
Thank you, Sam. That's right. This will be the last one. Thank you.
Well, look, we've learned a lot from your presentations over the years, and many thanks for them. And having said that, I then apologize. I'm going to ask a question that, actually, I think Alberto kind of asked already. But I don't think we quite got the answer. Maybe some of us were looking for.
So can I try and ask this in a different way, going back to your 25 to 30 gigawatt market sizing for the next year and a bit? I suppose maybe what we're trying to figure out is, if you won everything, you were able to win out of that 25 to 30 and adjusting for the fact that some of them might be fifty-fifty stakes. And in some cases, you may not have enough leases to do them all or enough pre qualified leases at the right time. What would in theory be the maximum you could win in gigawatts in the next year and a bit out of that 25 to 30 total? Is that something you could give us a view of?
Thank you.
Yes. It's a good question, Sam. I'm not even sure that we have run those numbers ourselves. But if you wanted to look for the max number, you would assume that we max out on our current lease capacity in the U. S, which would add a few gigawatt in itself.
And then you can start adding something for Poland, Japan, maybe more in Taiwan, UK around 4, obviously, could be sizable. So and then you have the centralized tenders. So I could create a number which would be a very unrealistic scenario, but it would obviously it would become a very high number. So that's not a likely outcome. But you have to bear in mind that it's when you look at that Slide 7, we are probably the only developer in the world who actually could join every single one of these opportunities and have a pretty strong starting point for doing so.
So I think that's again, I just want to highlight it as a sign of the scalability and the breadth of our global business platform that we are in a unique position when it comes to pursuing this opportunity. And as I said to the question asked by Alberto, I mean, we are definitely going to go for it. But we'll stay disciplined. We're not going to do crazy things. So whatever we get our hands on, it will be good value creating capacity.
I don't know if that answered the question, Sam. Maybe I didn't give you quite the answer you were looking for. So please follow-up.
No, no, no. That's fine. I recognize it's difficult to do it exactly. And maybe just a quick follow-up then. I suppose out of the 8 to 12 gigawatts in the UK, which is a big number, your total prequalified capacity that you can take to that 21 events, including the next launch of Hornsea?
Is can you remind us how many gigawatts that is?
Hornsea 3 would be 2.4 gigawatt.
So that would be 8 to 12 in the UK, you could your best outcome in the UK is the 2.4 if you get Hornsea 3?
Correct.
Right, exactly. Okay, that's very helpful. I'll leave it there. Thank you very much. Thank you.
And the next question comes from the line of Rob Pulleyn from Morgan Stanley. Please go ahead.
Hi. Thank you and good afternoon. If we can go back to the U. S. Project delays, may and to your comment on the construction window of 2023 to 2024.
Could I just ask, a, does this potentially impact your 2025 guidance for 15 gigawatts of installed offshore capacity? And B, would this affect the scheduling as you as a company tried to balance the construction of these projects you already have with maybe some other ones that you hope to win to the previous questions? Thank you.
Thanks, Rob. When we are looking at these potential delays from a 2023, 2024 construction time line, shifting it into 2024, 2025, there is, of course, always a risk that some of it could slip into early 2026. It's not necessarily our expectation. On the other hand, I can't rule it out given that still don't have full visibility on the permitting. But it doesn't change our commitment to the 15 gigawatt target.
That still feels like the absolutely right target for us, and we're still well on track against that target. When it comes to scheduling, obviously, as we are now bidding into new auctions in the U. S, we have to in these bids, we have to indicate an expected time line. And in there, we have to build in a little bit of flexibility given that we don't have full visibility on the current project portfolio. So we are, of course, making sure we have enough flexibility in the new bids that we submit to optimize the total schedule between the current portfolio and potential new wins over the next few quarters.
I don't know if that answers the question, Raj, if that was what you were asking.
No, it does. Actually, that's very interesting. Thank you very much and reassuring on the target. If I may just try the follow-up, the obvious follow-up to what you just mentioned on the scheduling. Would that therefore put you at a disadvantage versus other bidders who don't have the same, shall we say, construction congestion in the U.
S. Portfolio in your perspective? Thank
you. I don't think it's going to be a disadvantage as such. I think if you take the bids that we're submitting right now, they will be assessed on a broad range of criteria. And I don't think our competitors necessarily will offer a very different time line from what we can do. If we are done constructing the current portfolio towards end of 2025, we could relatively soon thereafter essentially launch the next train and start construction of subsequent projects.
So I think we are in good shape industry.
Excellent. Well, that's great to hear. Thanks very much, and I'll turn it over. And
the next question comes from the line of John Musk from RBC. Please go ahead.
Yes. Hello, everyone. It's actually a similar question to the one we just had in a way. Just wanted to clarify the permitting issues in the U. S.
That are ongoing. Are these very much in your view a whatnot just because we're at the beginning of the industry in the U.
S. You're breaking up, John. I can barely hear you. I don't know. Apologies.
Is it any better now? If not, I'll try again. It's better.
No, it's better, Jon.
Yes. Yes, just checking whether the planning issues in the U. S, in your view, are a one off situation and that we there is no risk of it happening again with the subsequent bits that are coming up in the next 12 to 15 months? And secondly, do you build any risk into these current bids given the issues that we've seen over the last few months?
Yes. Thanks, John. No, I do believe that it is a one off in the sense that this is really all about the federal permitting processes being firmed up and carefully thought through and designed. And of course, Bowen felt what I believe is a legitimate need for understanding the broader long term impact of building out 25 plus gigawatt of offshore wind along the East Coast. So this whole environmental impact statement process, I think, has been warranted.
And obviously, once they have concluded on that, hopefully relatively soon, and they've made a number of key decisions in terms of wind farm layouts, etcetera, and the format of the permitting process, I would expect everything to start running much more smoothly for subsequent projects. So it's not beyond the norm for a new market to go through this process of maturing the whole regulatory framework and the permitting process. We've seen that also happening in other markets in the early stages. So our experience is that once you pass that, things start to run much more smoothly. And yes, we do take this into account in the bids that we submitted.
As to the answer I gave earlier, we have to make sure we have sufficient flexibility in the bids that we submit that we can deliver on the time lines that we commit to.
And the next question comes from the line of Claus Kael from New Credit Markets. Please go ahead.
Yes, hello. Claus Kael from New Credit here. Back at your Capital Markets Day in 2018, you introduced a vision of 30 gigawatts in 2,030. And to be honest, I thought it was a bit crazy back then. But ever since the market has expanded quite a lot.
So could you elaborate a bit on how you see this vision as of today?
It's a good question, Claus. Since that Capital Markets Day almost exactly 2 years ago, we have seen the growth outlook for offshore winds double from what back then was 78 gigawatt by 2,030. We are now counting 150 to 160 gigawatt by 2,030. So obviously, the market is expanding much more rapidly than we imagined back then. And at the same time, we're very pleased with the way our onshore business has developed over that 2 year period.
So I think there is good reason for taking another look at it, and that is something we will do. That's going to be in the very capable hands of Matt Snipper, working with the team to take a look at what is the right long term ambition for Orsted. I think it's probably a good time to take a look at that during early parts of 2021 or first half of twenty twenty one. So I think that's the time line. But again, it's going to be a process that Mats obviously needs to run and own.
But of course, it is very much on our agenda to take a look at whether our 2,030 ambition
next question comes from the line of James Brand from Deutsche Bank. Please go ahead.
Hello. Good afternoon. Thanks for the presentation. I had a question actually on green hydrogen. I know it's not your necessarily your area of expertise, but given that you are starting to get involved in some green hydrogen projects, I was wondering whether you had any views on the different electrolyzer technologies, alkaline versus PEM, which seems to be a kind of increasing debate over which one of those is preferable given the supposed extra flexibility of the PEM technology, but alkaline being a bit cheaper.
Just curious if you've got any news on that.
Too early for us to really comment on it, James. We are developing 4 projects as we speak, actually 5 now. And we will be making procurement decisions probably over the next year or so. We'll start looking at more specific procurement decisions. But until then, it would be too early for me to start commenting on our choice of technology between the two alternatives.
Okay. Thanks.
And the next question comes from the line of Elchin Mamadov from Bloomberg Intelligence. Please go ahead.
Hi there. I have a question on asset rotation, please. So on one side, you finished Renaissance project finally. Would you consider selling it given that SSE and Penang got decent multiples for their project and waste to energy is not really your I mean, not really your core business at the moment. And on the asset rotation side, have you considered buying renewable pipelines in new geographies or technologies, especially in the onshore space?
So thank you.
Thank you. When it comes to Renaissance, we will spend the next couple of quarters just validating the commercial formula behind this waste technology and basically scope out the longer term potential of it. And once we have concluded on that assessment, we'll start thinking about how to take it forward from there. So I couldn't give you a good answer just yet. We need a few more a month or probably more like a couple of quarters to really get our arms around the commercial potential of Renaissance.
I do recognize that waste to energy is not necessarily a core business for us. On the other hand, it's a potentially very interesting technology. So of course, we want to make sure that we make the most of it. When it comes to asset rotation, we're very pleased with the expansion of onshore in the U. S.
And it's not a secret that over time, strategically, it could be of interest for us to take the onshore business elsewhere, including Europe and or Asia. We have no specific plans for doing so. On the other hand, I don't want to rule anything out. I think we want to keep our options open here. If we could find a good way of entering these markets, we would certainly take a close look at it.
But important to emphasize that we don't feel any urgency around it. We are in a very good place with our onshore business, and we still have a lot of growth opportunities in the U. S. But over time, if the right opportunity comes up, yes, we would take a look at it.
Thank you.
And we have a follow-up question from the line of Deepa Venkateshwaran from Bernstein. Please go ahead.
Thank you for taking my follow-up. It's actually on the U. S. So I just wanted to understand the mechanics of the delay and how they impact the project economics, given that you've not started investing any CapEx. So particularly, does this impact the tax credits or are you liable to pay someone something as long as there's a delay?
So that's and I also wanted to check if there was any political pressure on BOEM from the current administration and could this change if we have a different administration in power next year? And would that change anything from your perspective? Thank you.
Thanks, Deepak. We have been able to maintain and optimize tax credit qualification even during this upgrade of the turbines, both for the Mid Atlantic portfolio going for the GE turbine. And as I mentioned in the beginning of the call, we also will be able to maintain an optimized tax credit qualification for the Northeast even when we now have decided to upgrade the turbine. We haven't run into any liabilities as such from these delays towards our supply chain. Of course, it makes life more difficult when you don't have a firm permitting schedule, so you can't make exact commitments on the time line.
And our suppliers are obviously also eager to get confirmed time lines. But so far, we've been able to maintain flexibility together with our suppliers not to incur any penalties or liabilities. So far, we remain in a good position here. When it comes to pressure from the administration, It's something everybody is being asked about at the moment. Do you prefer this or that administration?
And CEOs tend to be a little bit vague about what they expect and whether one is better than the other, and I'm going to be vague as well. I think offshore wind in the U. S. Has a great future ahead of it under any administration. It's a huge, huge opportunity for driving local economic growth in coastal communities that really need this economic boost, and they're going to need it more than ever coming out of the COVID-nineteen crisis.
So whether it's a Trump administration or it's a Biden administration, there is no doubt that with the tremendous support and enthusiasm from the state and the governors, we will see a very meaningful build out of offshore wind in either scenario.
Tax of your delay if it's not the tax credit and there are no liabilities? Is it just the NPV shifting a year out or a couple of years out? Is that the main impact? Or is there something I'm missing?
There is an impact from NPV shifting from the time shifting and there is an impact from keeping the projects running. There is an underlying burn rate in keeping the projects running.
Okay. The directs and the project teams and
so on.
Okay. Exactly. Exactly.
Okay. All right. Thanks.
Thank you.
And the next question is also a follow-up question from the line of Markus Belinda from Nordea. Please go ahead.
Yes, thank you. I just wanted to ask you if you have had any revelations regarding floating wind or any observations you've made lately regarding floating wind?
Thank you. Thanks, Markus. I couldn't tell you that I've had a revelation, but I can tell you we are spending time on it and we are spending more time on it than previously. Not that we are actively engaged in any project, we are not. But we want to make sure that we keep a close eye on all of the different foundation technologies that are being developed.
We're keeping a close eye on the global pipeline And we continue to sort of have an estimate as to how much of the 150 to 160 gigawatt for 2,030 that we currently project, excluding Mainland China, how much of that would in fact be floating. It's still going to be a relatively small technology by 2,030. But when you go beyond 2,030, we do believe clearly there is a role for floating. And whenever the technology offers an attractive opportunity for us, we'll certainly pursue it.
Understood. Thank you.
And the last question is also a follow-up question from the line of Sam Arif from UBS. Please go ahead.
Thank you. Hi, again. Henrik, I remember one other topic that I wanted to be able to ask you about while we still can. And that's this discussion about the political agreement in Denmark under which the government agreed to maintain its majority stake in the company. My expectation has been no change in that position from the government.
But I remember that I think there was a written agreement that had quite a specific end date, maybe at the end of 2020. And I just wanted to check with you what's the latest on that agreement? Is it now lapsing or has it been extended? And what would the and would there be any constraints in the government changing its position now from 2021 onwards? Thank you.
Yes. Thanks, Sam. The political agreement was, in fact, set with 2020 as the time line for a potential revisit of this agreement. It is my clear impression that the political parties behind the agreement, they stand by that agreement. I sense that there's no political appetite for opening up a discussion about the state majority ownership.
I think they feel quite good about the 50.1% stake. So whether you hope for 1 or the other, my personal take on it, and I could certainly be wrong here, but my personal take right now is that you shouldn't expect any change to the state majority ownership anytime soon. I think it's going to stay for a number of years to come.
And it wasn't an end date in 2020. It was just a year mentioned in the agreement, but then it just continues until another decision is taken.
Right. Very clear. Okay. Well, thank you, and thank you again. And congratulations Henrik, and we wish you best of luck with whatever comes next.
Thank you so much, Sam. Just checking with the operator, are we out of questions, so we can wrap it up.
There are no further questions. I'll hand it back to you for closing remarks.
Okay. Thank you. Well, then thank you all very much for joining. Appreciate all of the great questions. And as always, should you have more questions, please don't hesitate, the IR team, if you need to answer them.
As this was indeed my last earnings call at CEO of Rorsted, I'll conclude by expressing my deepest gratitude to the Board of Directors, Versted employees and, of course, all of you analysts and shareholders. It has been a real privilege, and I really appreciate your confidence and support during my tenure and also for you guys always keeping me and the rest of the team on our toes, it has been an exceptional privilege to be part of the Orsted team over the past 8 years. Thank you all very much. Stay safe, and have a continued great day.