Earnings Call: H1 2024

Feb 14, 2024

Operator

Pan African Resources is well positioned to deliver excellent results for the full financial year, so what better time to take stock and remind ourselves what mining for a future looks like in 2024 and beyond. Here are a few of the highlights. Firstly, some great production news. The group produced robust gold production numbers in the first half of 2024, with operations performing in line with or better than forecast. Half-year gold production of over 98,000 ounces positions the group well to deliver into its increased production guidance of 180,000-190,000 ounces for the full financial year. The implementation of continuous operations at Barberton in the previous year, a successful transition from number 8 Shaft pillar to 24 level at Evander, as well as better recoveries from Elikhulu, all contributed to the strong first-half performance.

In a development that should contribute to further production efficiencies for the group, the equipping of Evander Mines' ventilation shaft for the hoisting of ore from 24 to 26 levels remains on track for commissioning before the end of the 2024 financial year. The commissioning of phase II of the underground refrigeration infrastructure is also now imminent. Shareholders can expect attractive returns on the capital invested in this operation in the years ahead. Last but certainly not least is a Mintails update. Construction is progressing on time and in line with forecasts. Foundations for the nine CIL tanks are in place, and the tower crane construction has been completed. This exciting surface remining project is set to add 50,000 ounces or more to the group's annual production in the near future, with first production in the next financial year.

Finally, nothing speaks to our mantra of "Mining for a Future" like talking about our community and environmental projects, so we're especially excited to report that much-needed environmental rehabilitation has started at the Mintails site, dealing with legacy liabilities. The program has commenced with a cleanup of historical spillages and pipelines, a wetlands remediation initiative, and the removal of invasive alien vegetation. The effects are already plain to see, bringing benefits to the surrounding communities and reducing air and water pollution, all part of our commitment to a smarter, more agile, and future-focused approach to mining. Pan African Resources: Mining for a Future.

Cobus Loots
CEO, Pan African Resources

Good morning to all of you and a warm welcome to our 2024 interim results presentation. Thank you very much for taking time out of your schedules to join us today. We will keep the presentation fairly brief with an opportunity for questions afterwards. Joining me in presenting today will be Deon Louw, our Financial Director. You're welcome to refer to our SENS announcements and to the supplementary information available on the Pan African website should you require detail not dealt with in today's presentation. Please note the disclaimers and info on forward-looking statements on slides two and three. Pan African's strategy is to position ourselves as a safe and sustainable, high-margin, and long-life gold producer. I believe the six months again demonstrated Pan African's resilience, our ability to adapt, reconfigure our business, generate attractive returns on our assets, and to grow in a responsible and value-accretive manner.

We are very excited about our prospects for the next years and look forward to sharing some thoughts and further detail on many of our initiatives in the following slides. On slide number four, an overview of the presentation. We will start with Pan African's health and safety performance and then provide an overview of the group and our operating environment, some key features from the half-year past, and detail on asset performance as well as our cost and capital outlook. We will then spend a couple of minutes on ESG before allowing Deon the opportunity to highlight elements of the group's financial performance for the six months. The presentation will then conclude by detailing key focus areas for the months ahead. If we then proceed to slide number six, our safety performance and journey to zero harm.

We continue to focus on safety initiatives and interventions and on maintaining an industry-leading record. We can also celebrate a number of safety milestones achieved during the past half-year. We reported an improvement in overall safety rates and a record number of fatality-free shifts at our Barberton operations. In addition to safety, wellness of our staff is enjoying a lot of attention, specifically a focus on reducing the impact of so-called lifestyle diseases. Sadly, one of our employees at Elikhulu passed away following an accident on the February 1st of this year after the half-year, and our sincere condolences and support have been extended to the family, friends, and colleagues. What makes this accident even more difficult is that this operation recorded almost a year with no notable injuries beforehand. Slide eight, a high-level representation of our unique portfolio of surface remining and underground assets.

The addition of Mintails means that we now have three large mining complexes in South Africa. Surface operations reduce unit costs and turn legacy liabilities into profits, while the underground provides long life of mines, solid returns on investment as a result of a large sunk capital base, and also attractive optionality, which we are bringing to account in a circumspect manner as demonstrated by our progress on the Evander underground. If there is one takeaway from this slide, it is that we are growing profitable production very materially in the years ahead. We expect to be well north of 200,000 ounces of annual production in 2025 with Mintails coming online. Importantly, all of this growth is fully funded, either with banking facilities or with cash generated from our operations.

Slide number nine , ithe coming year will also see us moving towards an even more balanced portfolio of low-cost and stable surface remining and high-grade, long-life underground assets. This asset mix should also reduce our group all-in sustaining cost profile, with both Elikhulu and Mintails producing at an all-in sustaining cost of below $1,000 per ounce. Slide number 11, our operating environment. We continuously seek ways of making our business less susceptible to adverse external impacts in South Africa. Some matters to highlight in terms of our operating environment over the period include the following. We continue to reduce our reliance on Eskom, the South African electricity utility. Some more information on this on the next slide. Pan African's assets have long lives with extended mining rights. The Evander complex's rights are valid until 2038 and those at Barberton until 2051.

The Mintails new order mining right is currently valid until 2029. We will obviously seek extension in due course. In terms of stakeholder interaction, we invest heavily in our social license to operate. Pan African's mines make a meaningful, positive difference in the areas where we operate. Finally, from a security perspective, our efforts to safeguard our people and operations and minimize the impact of illegal mining and criminality are ongoing. I believe the people of Kagiso and Mogale can already see a marked improvement in the area since we started our work on Mintails. To conclude on this slide, Pan African's track record demonstrates that we can operate and grow in South Africa and do so very successfully.

To elaborate further on our renewable energy roadmap on slide 12, with our Barberton solar facility on track to produce first power by the end of June of this year, this will almost double our behind-the-meter renewable energy footprint in the short term. We further anticipate first power from our 40 MW. Sturdee Energy power purchase agreement during 2025. You can also expect other announcements on renewables from Pan African in the months ahead. Hopefully, we can add even more capacity and also possibly diversify into wind energy. The first 10 MW solar plant at Evander is already reducing group oil and sustaining cost by more than $10 per ounce, with this number obviously increasing in the coming years as Eskom tariffs continue to escalate.

If we then proceed to key production cost and financial features from the first half of the financial year on slide 14, some of the highlights for H1 of the 2024 financial year include the following. We produced more than 98,000 ounces of gold, an increase of nearly 7% when compared with the previous period. Our teams did well in managing costs with an all-in sustaining cost below our previous guidance of $1,350 and even lower at $1,149 for 85% of group production, positioning Pan African very competitively on the global cost curve. We are reporting an increase in cash generation of more than 120%, an increase in profit after tax of almost 50% when compared with the first six months of the previous financial year, with very manageable net debt levels and healthy liquidity. And finally, we were able to maintain our sector-leading dividends to shareholders.

If we then move on to more detail on the performance per operation, starting with Elikhulu on slide number 16. This continues to be a flagship asset for the group, 10 years of production remaining, producing at below $1,000 per ounce. Production tons for the period remained stable. However, our team managed to improve recoveries through the mining of the Leslie/Bracken Tailings Facility, with gold production increasing some 9%. We look forward to another year of more than 50,000 ounces of production and clearly excellent cash flows from this asset in the current gold price environment. We generated almost $30 million of EBITDA in only six months. Phase II of the Kinross Tailings Facility was successfully commissioned in December 2023 on budget and on schedule.

As we have said before, we are carrying all of the learnings on building and operating Elikhulu over to Mintails as we ramp up operations on that site. Slide 17, the BTRP, another sterling performance from our first gold tailings retreatment plant, commissioned in 2013, and the lowest cost producer of gold in the group. The BTRP management team also again deserves special mention, managing to reduce unit costs of production. In the coming years, we will substitute the BTRP's feed with run-of-mine material from Royal Sheba and Western Cross, lower-grade but bulk ore bodies, with both having significant potential to further increase resources and reserves. A more detailed investigation into the Western Cross ore body and its association with Royal Sheba was completed and informs the Sheba Fault geological structural model.

Although work is in progress to confirm geological continuity through diamond core drilling, the potential of a larger mineral resource at Sheba is highly probable. Mintails, on slide 18, large-scale construction at Mintails will be completed later this year, with steady-state production expected by December 2024. Importantly, we have now fixed contracts for more than 80% of the upfront project capital. Therefore, the $135 million upfront capital estimate is now very much secure in our view, despite all of the inflationary pressures over the last two years. In the current gold price environment, payback on this investment should be under four years, with a project life of more than 20 years when we include the Soweto resources. On slide 19, a picture of construction progress on the site with commissioning scheduled for later this year.

You can see that we are very much on track in terms of the project's execution timelines. Slide 20, there's no doubting the benefit of Pan African developing Mintails for all legitimate stakeholders. We currently have over 400 contractors on site, approximately 80% of them from local Mogale communities. This number is expected to ramp up to almost 600 contractors in the next month. When steady-state production is achieved, the operation will directly employ almost 400 permanent staff and obviously benefit the local economy in a number of ways. Also, on slide 20, over the life of Mintails, it will dramatically improve the environmental and water situation on site, a win-win for all involved. We calculate that the final closure liability will be less than 40% of what was an unfunded liability of more than $20 million when Pan African became involved.

To conclude then on our surface assets on slide 21, we are building a world-class tailings retreatment business in the next year, with further scope to grow also. I don't believe the market is currently giving us much credit for Mintails, but this should change as the project comes closer to commissioning in the next while. Slide 22, the Evander underground team delivered above expectations, despite electricity constraints and difficult mining conditions within the 8 Shaft pillar, producing more than 21,000 ounces for the six months at an all-in sustaining cost of just over $1,200 per ounce.

We are on track with our capital programs at Evander, and some of the highlights for the six months include progress with our new underground refrigeration infrastructure, with phase II due for commissioning by the end of the financial year, a ramp-up in tons from underground by more than 16% when compared with the corresponding period, despite difficult mining conditions and crew movement to the expanding 24-level mining areas. Good progress with the development of our subvertical waste shaft, with this project scheduled for completion in quarter 2 of 2024. I really believe this shaft, with a waste capacity of some 40,000 tons per month, will be a game changer for the Evander underground. No more cumbersome conveyors, lower costs with a higher mine core factor.

Finally, completion of the dewatering of the Egoli decline to 20 level, with the commencement of ramping activities on the upper levels of this project. If we proceed to slide 25, dealing with Fairview at Barberton, following implementation of continuous operations at Barberton underground in the last year, tons at Fairview have increased to an average of 10,000 tons per month from the underground, a further 14% improvement following the initial improvement to 8,800 tons per month when continuous operations commenced. The improved tons have seen Fairview delivering a 17% increase in gold production, while underground mine grades improved to more than 13 g per ton from approximately 12.5 grams per ton in 2022. Currently, three platforms are mined within the MRC higher-grade ore body, providing mining flexibility. Exploration delineation drilling has been ramping up, with confirmed down dip extensions of a number of ore bodies.

A more advanced and better-informed deformation and structural model has been developed for the MRC Ore Body, identifying additional exploration targets for mining expansion. Work on the existing decline development infrastructure adjacent to the constrained 3 Decline is planned to commence still during this financial year. Once completed, we expect to reduce the constraints currently facing our shaft system, making much-needed shaft time available for the waste of ore. Other important initiatives at Fairview include developing near-surface resources for mining and infrastructure improvements we are implementing, which includes a grout plant to pump cement required for construction activities within the 3 Decline mining areas. The smaller underground operations at Barberton on slide 26, at Sheba, continuous operations continue having a positive impact, enabling increased lateral development into the higher-grade ZK and MRC mining areas and improving mining flexibility.

Ramped-up development into the ZK and MRC ore bodies has resulted in the more consistent availability of higher-grade platforms available for mining, with close to 20% more ore delivered to the process plant in the past half year, at an average of 8,661 tons per month versus 2022, where we had just over 7,300 tons per month, with a slight improvement in mine grade by 2% to 6.73 grams per ton. Consort remains a challenge, with adverse geotechnical conditions limiting development and stoping operations within the PC shaft infrastructure and impacting gold production. A revised mining plan is now being formulated for execution in H2 to increase underground mining tonnage, although at lower grades. The levels identified are of lower geotechnical risk and will provide the required gold production to sustain operations, whilst the PC shaft rehabilitation work is being completed in the next months.

Diamond core exploration drilling continues, aimed at creating underground mining flexibility and ultimately reducing the reliance on lower-grade surface sources, which is currently supplementing the ore feed to the processing plant. On slide number 28, the section dealing with all-in sustaining costs, now 85% of our portfolio produced at an all-in sustaining cost of just under $1,150 per ounce. We expect the unit costs at Sheba and Consort to further reduce in the period ahead, benefiting from the turnaround plans currently being implemented. Slide 29 demonstrates that our cost performance on core operations continues to be very much in line with the average for the global sector, with most producers having experienced significant cost inflation over the last couple of years. Despite inflation, we should be able to maintain all-in sustaining costs at current levels in the coming financial year in U.S. dollar terms.

On slide 31, group capital projects, we continue to invest into our assets and into growth, with most of Mintails' upfront CapEx spent in the next year. For the Evander underground, we expect CapEx to reduce from 2025, as most of the large capital for 24-26 levels would then have been spent. If we then move on to ESG on slide 34, we are very proud of our achievements on this front, particularly on progress with renewable energy and water retreatment, which I have touched on earlier. We have completed school infrastructure projects in communities around our Barberton and Evander operations, which were handed over in November of last year. These fully equipped facilities will benefit close to 3,000 students annually and lead to much-improved learning outcomes. We have also commenced with assistance programs at schools in Mogale around our Mintails site.

These initiatives are much-needed in these areas and were very well received by local communities. I will now hand over to Deon, who will provide an overview of the financial results for the half.

Deon Louw
Financial Director, Pan African Resources

Thank you, Cobus. Slide 36 summarizes the group's interim financial results for the six months into 31 December 2023. Fortunately, the gold price tailwinds of the prior financial year continued into this reporting period, which, combined with a production increase of 9%, resulted in revenue increasing by 24% relative to the six months ended December 31 2022. Although all-in sustaining costs in Rand terms increased by 7.5%, the depreciation of the Rand-dollar exchange rate by 7.8% over the reporting period resulted in all-in sustaining costs actually declining by 0.3% to $1,287 an ounce when translated to US dollars. Although turnover only increased by 24%, EBITDA increased by 41% in dollar terms to $75 million, demonstrating the leverage to an incremental increase in revenue. This relationship held, with earnings and earnings per share increasing commensurately by 46% to $43 million relative to the corresponding reporting period.

Equally encouraging is the 135% increase in net cash from operating activities to $27 million, which contributed to net debt increasing by only 20% to $64 million, despite spending $65 million on capital in the reporting period, of which $22 million related directly to the Mintails project. Slide 37 demonstrates the extent of the group's available debt facilities and funding approach to its capital programs. We differentiate between our core working capital or revolver-type facilities, as is depicted in the left bar chart, and project-specific facilities depicted in the right bar chart. The former provides the group with working capital of $62 million, while the latter provides project-specific senior-term debt of $132 million.

In addition to the Mintails facility of $114 million, which comprised the domestic medium-term note program and senior debt facility, we are well advanced in implementing a renewable energy facility of $19 million to refinance the original Evander solar plant's funding and the new Barberton solar facility of $12 million. This facility also provides for an accordion option of $14 million for the group's third major renewable facility, for either an expansion of the existing Evander solar facility or a solar facility for Mintails. Consistent with our project finance philosophy, the redemption profile of these facilities is sculpted to the cash generation of the underlying projects, to not impinge on the cash generation from the established operations designated for dividends and sustaining capital expenditure.

As part of Mintails' funding package, and in lieu of an equity tranche, we raised ZAR 400 million or $22 million by means of a forward sale of gold in March 2023, which locked in the Rand proceeds on 116,000 ounces at an effective Rand gold price of ZAR 1,135,000 per kg, approximately $1,909 per ounce over a 24-month period. This fixed-price contract, which terminates in March 2025, represents approximately 31% of the guided annual production over the 24-month period, using 185,000 ounces as the midpoint of the current annual production guidance.

Together with two zero-cost collars for 20,000 ounces, with an average floor price of ZAR 1.1 million per kilogram or $1,849 an ounce and an average cap price of ZAR 1.4 million a kg or $2,340 an ounce, approximately 53% of the second half of the 2024 financial year's production is protected from adverse movements in the Rand gold price. These two collars expire on June 30 2024, and the group will participate in further gold price movements until these cap prices, some 16% or $316 an ounce above the prevailing gold price of $2,024 an ounce, are breached. During the reporting period, none of the collar price levels were breached, resulting in approximately 71% of the group's production benefiting from the prevailing elevated gold price during this period.

Slide 38 illustrates the individual redemption profiles of the group's debt facilities, referred to in the previous slide, and the group's total debt profile as it amortizes over the next five years to May 2029. Total debt is expected to peak at approximately ZAR 3.45 billion or $187 million in December 2024, as Mintails' expenditure peaks, with principal debt repayments commencing in March 2025, by which point in time Mintails should be in full production. This forecast assumes the implementation of the new solar funding facility and a dividend payment in December 2024 consistent with the existing dividend policy. This principal debt repayment profile provides a window within which to focus on completing Evander's 24-26 level capital expenditure program, Mintails' construction, and commissioning of Barberton's solar facility.

At forecast peak debt, the total debt-to-equity ratio is expected to be approximately 57% of the existing equity base of $328 million. In reality, it will probably be less, as the ZAR 1 billion RCF facility is seldom fully drawn.

The group endeavors to hold a minimum cash balance of ZAR 200 million or $11 million at any point in time, and profits for the next 12 months to December 2024 are not taken into account. Slide 39 tracks the group's historical dividend yield and the near-record 5.9% yield of the 2023 financial year dividend paid in December 2023 relative to the June 30 2023 closing share price of ZAR 3.03. As already mentioned, the return of cash to shareholders is one of our business objectives, and we endeavor to manage our capital structure in a manner that enables the group to continue paying dividends while simultaneously developing major capital projects.

Return on shareholders' funds is a key parameter for measuring the success of our capital allocation decisions, and the annualized dollar return of 27% on the group's average shareholder funds of $311 million for the reporting period relative to the 20.8% of the 2023 financial year demonstrates that the operational initiatives undertaken by the group to address the production decline experienced in the 2023 financial year are bearing fruit. With Mintails coming into production in the 2025 financial year, we can expect the return on shareholders' funds to revert to its historical level of closer to 30%, given the enhanced profitability mix of the group going forward. Thank you.

Cobus Loots
CEO, Pan African Resources

Thank you, Deon. I think we can now wrap up with an update on Sudan and then also by emphasizing some key focus areas for us in the year ahead. On slide 41, we have in the past detailed our rationale for venturing into the Republic of Sudan for exploration. I'm happy to report that we have now successfully resumed our exploration activities in the Red Sea State, following a detailed assessment of the security and operational environment, which we obviously continue to monitor closely. We would hope to start drilling prospective targets in the months ahead. If we then conclude this presentation on slide 43, Pan African continues to be focused on delivery and execution. Key areas for us in the next year include the following: We will continue our proactive journey to zero harm.

We will monitor optimization and improvement initiatives to increase gold production as per our guidance and also reduce costs. We will successfully execute into our capital projects, including the very exciting Mintails development, that will increase and sustain our future gold production profile at approximately 250,000 ounces per year. We look forward to progressing our ESG initiatives and focus on maintaining our social license to operate. Finally, we will maintain our focus on generating sustainable shareholder returns and creating value for all stakeholders. Thank you very much for your time this morning. We look forward to continuing mining for the future in the year ahead.

Thank you again. I think we can now proceed with the Q&A, and let's do questions from the Chorus Call conference call facility first.

Operator

Thank you. The question comes from Richard Hatch of Berenberg. Please go ahead.

Richard Hatch
Equity Research Analyst of Metals and Mining, Berenberg

Yeah, thanks, Cobus and Deon. Good morning and congrats on a good set of numbers. I've just got three questions for you. The first one's a simple one, just on Evander surface. Can you just remind us how much life we've got left of that particular operation? The second is, Deon, just on the working cap, there was quite a bit built within the first half. I appreciate there was a bit of a release second half of last year, but can you just talk to us a bit about how we should be thinking about working capital second half of this financial year, please? And then the third one, I'm very sorry to hear about the fatality at Elikhulu. Could you perhaps just give us a bit more details on what exactly took place and just what you've done to prevent something like that happening in the future?

Thanks very much.

Cobus Loots
CEO, Pan African Resources

Thank you, Richard. So I'll deal with number one and two, and then have number one and three, and then have Deon come in on the working capital. Yeah, so the surface sources at Evander for some time have not really been making any money or contributing margin. So it's an ad hoc business, effectively us doing rehabilitation, assisting other parties with towing. But again, there's not much in it. So we've sort of had a relook at that business, and to the extent we don't make money, we certainly will not proceed. And that's sort of factored into our guidance for the full year, the fact that we're not banking on getting any material ounces from there in the next six months.

And then in terms of, yes, the very tragic accident that we had at Elikhulu, as I said, it was the first lost time all reportable in almost a year of operations. So Elikhulu has an excellent safety record, very sad. It was a supervisor that was busy doing corrosion control on the plant, and one of our guardrails failed. I don't want to comment too much because obviously the accident is still under investigation. But yeah, we have reassessed all of our guardrails across the group, and where necessary, we've made some changes. Obviously, risk assessments and the like also would need to take cognizance of this. But yes, it's very sad and tragic, and certainly it's quite difficult for all of us, given the safety performance of the group and specifically of Elikhulu. Deon?

Deon Louw
Financial Director, Pan African Resources

Thank you, Richard. Working capital is always a bit of an enigma in this first half, as we invariably have a fairly substantial cash outflow associated with the timing of payables. Inventory naturally has picked up as we need to capitalize the necessary spares and the likes for Mintails. And then on payables, sorry, on receivables, it's just purely a question of timing of the delivery of the gold. So there was a movement in inventory which related to gold which was produced but not delivered timely in the corresponding period. But there's nothing abnormal in that movement. It's pretty much just your normal payables, receivables, and inventory movement as we see from year to year.

Richard Hatch
Equity Research Analyst of Metals and Mining, Berenberg

Okay. Should we be expecting to see anything come back in H2, Deon, or is it were there any particular? I'm just kind of thinking about cash movement in the second half.

Deon Louw
Financial Director, Pan African Resources

Richard, I think it's probably going to be normalizing at these levels. I wouldn't want to say there's going to be any positive movement beyond what we have already.

Richard Hatch
Equity Research Analyst of Metals and Mining, Berenberg

Cool. And then sorry, just one follow-up. I mean, look, the production performance has been very good, and obviously it's lovely to see the cost come down as well. The rand's trading weaker than 19. Your guidance is on 18.5. It feels that there's a very good chance that you'll come in towards the top end of your guidance or even beat it, as you've alluded to. What are the sort of things that you need to see to update the market to give an increase in that production guidance, which I think most of us probably think is likely to be raised? Thanks.

Cobus Loots
CEO, Pan African Resources

Yeah, I mean, I think, Richard, we'd like to be prudent and let's have line of sight of production for the next couple of months. But January was a good month again, and February is bound to be also a good month for the group. And I mean, we don't have to sort of come in and shoot the lights out any more than I think what we have. And ultimately, if we can end the year with a cost that's a bit lower and produce in the order of 185,000 ounces, I think it's a very good achievement. Obviously, as you've said, we have excellent margins at the moment given the Rand gold price. And then from next year, you're going to have a massive kicker in the shape of Mintails. So there's no point in us, I guess, overpromising at this point.

I think 185,000 ounces plus would be an excellent achievement at a lower cost than what we'd guided. So that's sort of what we're aiming at.

Richard Hatch
Equity Research Analyst of Metals and Mining, Berenberg

Okay. Sounds good. All right. Good work. Thanks for your time.

Cobus Loots
CEO, Pan African Resources

Thanks.

Operator

Thank you. At this stage, we don't have any further questions from the lines. Thank you.

Cobus Loots
CEO, Pan African Resources

Great. We'll then go to the online questions.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Cobus. We've got a few questions from the webinar. The first one from Mark Memory at ShareSoc. Please, could you comment on electricity supply disruptions and measures you're taking to mitigate them?

Cobus Loots
CEO, Pan African Resources

Yeah, so Mark, I mean, it's mostly the disruptions relate mostly to ESCOM, our local utilities infrastructure, substations, malfunctioning power surges, etc. So to give you an example, at Sheba, for instance, I mean, we had flooding on the lower levels because we had some of this ESCOM infrastructure degrading. And that's just something we need to manage. Our teams have become quite good. We have a good relationship with the local management and technical staff of ESCOM, and we try and get them to do preventative maintenance where it's possible. We just have become very good in terms of our reaction time when there is something that's down in terms of trying to get the utility to fix it. That's just something we manage. Again, we don't foresee it getting materially worse than what it is currently.

We're able to manage and produce quite well. Obviously, the other mitigant over time is expanding our independent footprint, what we're doing in terms of renewables. We'll have the first 10 MW at Barberton up and running by June, and then quite significant expansion as far as renewables are concerned in the next while. So that certainly will also go some way in terms of mitigating our relationship with Eskom.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Cobus. We've got another question relating to load shedding. It's from Ed Gillespie. He says he understands there's significant protection for the company from load shedding due to zoning and the company's investments in solar. Please, could you let us know if the upper end of production guidance could still be achieved even if load shedding up to level 6 continues for the next months?

Cobus Loots
CEO, Pan African Resources

Yeah, so I mean, Ed, I think we've dealt with in terms of Richard's question on production, if it doesn't get much worse than what it is currently, we can manage. So I think our technical guys are doing an excellent job. And yes, certainly even at stage six, as it's currently the case, we're able to function and operate fairly effectively.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Cobus. Also from Ed, as production steps up with Mintails coming online, what is an efficient balance sheet for Pan African? What are you thinking about in terms of the dividend? And will you consider significant buybacks on this four-times P/E valuation post the CapEx in Mintails?

Cobus Loots
CEO, Pan African Resources

I think Deon will come in on the buyback, but yeah, certainly one of the differentiating factors for Pan African is what we think is the sector-leading dividend. Obviously, we have large capital this year that we need to spend both on completing what we're busy with at Evander, our Barberton projects, and then principally Mintails. So I think, and again, the payback and the cash flows from Mintails are forecast to be exceptionally strong. And case in point would be the performance from Elikhulu, where you can just sort of see how a well-performing tailings business, the sort of cash, very attractive cash margins that these assets generate.

So yes, we'll then have a lot more flexibility, and I can assure you, certainly from my perspective, if the share price remains so undervalued, that would be quite compelling then to do buybacks once we've de-risked the business further in terms of having commissioned Mintails. Deon?

Deon Louw
Financial Director, Pan African Resources

Yes, absolutely. Yeah, Cobus, it is something the board assesses on an ongoing basis, is how best to utilize cash flows and capital to create wealth for shareholders without exposing the business to unnecessary financial risk. So clearly, we're looking at debt peaking at about $187 million once Mintails is fully commissioned. That is probably a level at which we would carefully consider whether there's not more merit in paying down the debt as opposed to doing a share buyback. But I think the continuation of dividends and potentially an increased dividend based on our dividend policy is not out of the question. But as Cobus says, the priority is to finish these projects and then assess the merits of maybe not rather reducing debt to strengthen the balance sheet, given that we're in a cyclical business and we need a certain balance sheet robustness at all times.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Deon. A question from Peter Mallin-Jones of Peel Hunt, "Can you give us a little more detail on the timings around MTR, specifically when you are targeting first gold and when you expect to hit design capacity?

Cobus Loots
CEO, Pan African Resources

Yeah, so Peter, we've been quite clear. Progress on site is excellent. Very proud of what the guys have managed to achieve in a very short time frame. So yes, we'll be commissioning, probably start September, October. And then hopefully by December of this year, we would be at some point reached close to steady state in terms of throughput. That is our plan. And again, I mean, we don't have to do anything more than that. I think having brought a project like this online in less than 18 months would be exceptional, and that's what we're working towards.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Cobus. We've got Sifiso Mhlongo from Sanlam Investments, who says, "Well done on the impressive operational performance. Please, can you highlight current capital allocation priorities in order from highest consideration to lowest? And can management highlight how these priorities could change once the projects are substantially completed and contributing to operational performance?" And the second part of the question is, "What is PAR's target debt gearing levels? And once this gearing level is reached, will management look to improve dividends or potentially take advantage of further growth opportunities?

Cobus Loots
CEO, Pan African Resources

Look, I think in terms of priorities, we try and Deon will come in here, but we try and maintain a balance. And the first port of call for excess cash or cash generated by operations is reinvesting into the sustainability of our business, which we do. And then we try and strike a balance between cash returns to shareholders, dividends, and potentially buybacks versus growth. And I think we've done so quite successfully over the years, which is reflected in the return on equity and other metrics on our balance sheet and other measurables. So it's sort of trying to get that balance right. Growth is good, but then it has to be a value accretive growth given, again, our track record of what we believe is very successful projects over the last while. Deon?

Deon Louw
Financial Director, Pan African Resources

Yeah, absolutely. Clearly, we have to consider the trade-offs between the different opportunities which exist for allocating capital. There is a view that mining companies shouldn't be geared at all, especially towards the small end of the spectrum. Typical mining companies tend to be geared on the larger end, run about 30%, if any gearing at all, 30% debt to equity ratio. We're going to be slightly in excess of that, as I mentioned earlier, slightly probably closer to 50%-55% when Mintails is fully funded. But then it's also a function of the maturity of the operations, the underlying volatility of cash flows, which determines the latitude with which you can apply discretionary cash flows to things such as buybacks, dividends, and the likes. We've stated repeatedly that we are focused on returning cash to shareholders.

But at the same point in time, we are in a business which is declining in value simply through the exploitation of our reserves. And by implication, we have to look at opportunities which not just meet our cost of capital, but exceed our cost of capital that we can execute into and trade those off against the other potential uses of that capital. I don't think we would want to do a transaction which puts our dividend track record at risk. We see that has been one of our differentiating factors relative to the rest of our peer group. So within the priorities that Cobus mentioned, dividends do rank very highly. Dividends/share buybacks do rank very highly in that priority list.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Deon. Bruce Williamson from Integral Asset Management has a couple of questions. "Can you expand on difficult mining conditions at Evander Underground? And secondly, by reducing hoisting constraints at Fairview, what total tons per month will you now be able to hoist from the MRC and other reefs?

Cobus Loots
CEO, Pan African Resources

Yeah, so Bruce, I mean, the mining difficulties relate principally to the pillar. As you will know, Evander had an exceptionally successful pillar extraction of the 8 Shaft pillar and very profitable. It was done in a manner that was safe and also didn't obviously sterilize the future life of the operation. So I think it was very well done by the team. Obviously, as one gets to the end of that sort of pillar mining, it gets even more difficult. But the guys did well in terms of dealing with these challenges. And currently, we have about nine out of our 12 crews operating already on 24 level. So that transition was done successfully. And then yes, I mean, look, I mean, we're still busy quantifying exactly about how much we can expand the hoisting capacity of principally the decline, the MRC decline at Barberton.

I would be surprised if we couldn't sort of expand it or improve by 10%-20%.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Cobus. Arnold van Graan from Nedbank, he says, "You show the 85%, 15% cost split in your portfolio. What is the expected cost trajectory for the high-cost operations? Could it get in line with the rest of the portfolio and when?

Cobus Loots
CEO, Pan African Resources

Arnold, yeah, so certainly we're quite positive about Sheba. If you look at the progress we've made since the implementation of continuous operations, so I expect an even better performance from Sheba now in the next six months. Again, we were unfortunate in terms of Eskom issues, and that caused flooding and quite a lot of disruption at Sheba. But we've been investing a lot in terms of development, and certainly there's some attractive ore bodies at Sheba. So yes, I mean, I'd be surprised if we couldn't get the costs at Sheba or rather the unit costs at Sheba down in the next six to 12 months. And then yes, Consort, which is very small in the portfolio and on a cash flow basis, I think it cost us ZAR 12 million from an EBITDA loss perspective over the six months.

Yes, certainly there was an improvement at Consort. Yeah, we expect Consort to certainly perform better in the next six months. We're doing the development. We're doing the exploration. We're not giving up hope on Consort. If you remember some years ago, it was a big contributor when we were mining the 42-level PC Shaft. We would hope to get back to some level of profitability, and that's what we're working on.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thanks, Cobus. Second-last question is from Raj Ray of BMO Capital Markets. This question is on cost per ton, which at Barberton and Evander Underground seems to have increased about 16% year-on-year. "Are there other drivers in addition to inflation, and should we expect unit costs to come down for H2?

Cobus Loots
CEO, Pan African Resources

So I think one of the primary drivers, Raj, was the fact that we went to continuous operations at Barberton. So that means more people, and hence you have to produce more gold, which is what we did. So that's sort of the mitigating factor. But I think certainly going forward, that inflation should normalize. So you shouldn't in the next year see a similar level of increase again from that perspective. And then on the Evander side, I guess it's also related to capitalization.

Deon Louw
Financial Director, Pan African Resources

Yes, that's quite correct, Raj, is the capitalization of costs in the past that didn't go through the P&L now going through the P&L. So that'll be a one-off adjustment. It shouldn't increase at the same rate, but it will be there now on a permanent basis as opposed to capitalizing as was the case in the past. So yes, that's contributed quite substantially to Evander's underground cost.

Hethen Hira
Head of Investor Relations, Pan African Resources

Thank you. And the last question we have is from one of our local contractors around Mogale. It's Mr. Opa Banda from Opa's Lawn and Garden regarding Mintails, "How many permanent jobs will be created after construction, including subcontractors?

Cobus Loots
CEO, Pan African Resources

So hopefully, there'll be more than 400 permanent jobs only on the plant and our operations. Obviously, I mean, we will endeavor to use as many local service providers as possible, which means indirectly, that number will go up quite a lot. We're very happy with the progress we've made. We're very happy 80% of all the contractors on site at Mogale come from local communities. We're supporting the schools, and there were some great results from the matriculants that we were supporting at the end of last year. So that's encouraging. And I do think, as I said in the presentation, that anybody staying in that area can already see a difference in terms of lawlessness and rehabilitation, everything else. So it's a flagship project for us, and we look forward to working with all of the stakeholders in Mogale to make this a massive success.

Hethen Hira
Head of Investor Relations, Pan African Resources

There are no more questions from the webinar. Thank you, Cobus and Deon.

Cobus Loots
CEO, Pan African Resources

Thank you very much.