Boliden AB (publ) (STO:BOL)
Sweden flag Sweden · Delayed Price · Currency is SEK
513.60
-17.40 (-3.28%)
Apr 27, 2026, 5:29 PM CET
← View all transcripts

Earnings Call: Q3 2024

Oct 22, 2024

Olof Grenmark
Head of Investor Relations, Boliden

Ladies and gentlemen, I'd like to welcome you to Boliden's Q3 2024 results presentation. My name is Olof Grenmark, and I'm Head of Investor Relations. Today, we will have a results presentation led by our President and CEO, Mikael Staffas, and our CFO, Håkan Gabrielsson. We will also have a Q&A session, which we will start here in Stockholm, which I will moderate, and then we will go on to questions on the web. Mikael, welcome.

Mikael Staffas
CEO, Boliden

Thank you, Olof, and good morning everybody here in Stockholm, and also online, and welcome to a Stockholm that today is maybe a little bit of a grayish weather, but what I think is a pretty good and strong performance that we have today, so let me just start and get right into the highlights of the report that we're presenting right now. First of all, we have improved prices and terms compared to last year. Compared to last quarter, they're about the same. They've been changing around during the quarter and ended up on a relatively high level in the end of September. We have improved production, especially in mines, but also in smelters, and we have a record mill production in Garpenberg, actually for the second quarter in a row.

This has now gotten so well underway in Garpenberg that, it's actually now the environmental permit that is our limiting factor for production in Garpenberg, and I'll come back to that question when we look at the outlook going forward. The key projects that we have are all well underway. The other project, of course, had an adjustment of the time plan and the, and the CapEx that we came out with a couple of weeks back, but that now revised plan is still standing. Together with that, the Aitik project is very near to completion. It's very little that's left, and it looks very, very good, and we're having the absolutely last inspections there, and we're very confident that we will reach the full functionality that we wanted to get from the dam in Aitik.

The project in Kristineberg, Rävliden, is also moving along nicely for a commissioning and startup, late first quarter or early second quarter next year. Then, the two very new projects that we have is, of course, early days to tell, but so far so good, both in the tank house project in Rönnskär and in the Paste project in the Boliden Area. The restart of the Tara is also moving according to plan. We had our first blast last week, and, everybody is now, who is supposed to be back, is now back on the roster and back at work, and, the production is now ramping up during the rest of Q4 for full production in Q1, with the new revised production targets that we have.

We've also, during the quarter, we have submitted an application for a mining concession in Laver, and we'll see how long that will take this time to get that one through. The financial performance in the quarter, I would say, is very nice. We've had an operating profit of just SEK 1 million shy of SEK 3 billion. The cash flow is still negative on about SEK 500 million, given the high investment rate that we're having, and we've also been tying some working capital within the quarter. The CapEx of a little bit more than SEK 3 billion is in line with the total guidance for the year of SEK 15.5 billion.

On the key projects, just an update, the on the Odda expansion, we will already, during Q1 next year, be able to go back up to 200,000 tons per year because we will have the new foundry and the new tank house in place, which means that we can run the old roaster at full speed and be able to get that through. But the one that is time limiting is the new roaster, which is the one that is scheduled to be commissioned in late Q1. That's going on, and that's when we will get up to the 350 speed when we have the new roaster in place. The Aitik reinforcement is moving on, as I said before, very nicely. It's planned to be completed in the end of this year, and it looks very, very good.

There are only very small minor things left, and then the final inspections on the quality of the new dam. The Kristineberg expansion, as I said, we are already doing some production from the Rävliden deposit, however, through the old infrastructure. The new infrastructure is online to get commissioned, late Q1, early Q2 next year. The tank house, as I said, very early days so far. The groundwork has started. You see this here in the picture on the slide, where it's going to be and how we've started with the earthwork, and the ramp-up is scheduled for the second half of 2016 - no, 2026, sorry. The Boliden Area extension with the Paste project and the tailings management, the groundwork has started there as well, and that's also moving on nicely.

And the Tara reopening, we have all the people back and onboarded again, and we have gotten all the kind of paperwork done that we need with authority, and we had the first blast last week, and the mill production is going to ramp up a little bit during this quarter, but basically going full from next quarter. On the ESG side, the CO2 emissions are up compared to last year. This is actually according to budget, and it's below the budget, and the main reason why this is going up is the Aitik project, which has, of course, led to lots of diesel consumption related to those movements of material. The LTI frequency is also nothing that we are really proud of in that sense, that we've had, once again, a relatively weak quarter on that.

We are working hard to try to reverse this trend that we're seeing right now. We don't have a very quick fix. If we were to have one, we would have fixed it a long time ago, but we have several leads that we're working on and trying to make sure that we come back on the positive trend that we had for such a long time. The sick leave is very stable on a level which we consider too high. We want it to get down to the levels that we had pre-COVID, which was around 4%. But we seem to have difficulties coming down, all the way down there. This is not unique to us. It's many other companies around where we operate have similar issues, and I think that's something that we're gonna work on.

But still the ambition is to get back to pre-COVID levels, as soon as ever possible. On the market side, the base metal prices have improved. They have improved clearly versus last year, and then they improved during the quarter as well. The precious metal prices are at all-time high, and it's of course, improving versus both periods that we're looking at. The spot TCs are weak for both copper and zinc. This is not affecting us so much. As you know, we have the majority of our feed coming through benchmark. So it hasn't affected us much in the quarter, I should say. And we have a slightly weaker U.S. dollar, and here you can see in the graph how the total index that we have for prices and terms is developing.

If you look on the main metals that we have, our three main metals, you can see both in copper and zinc, it looks like the whole world is becoming more and more cost-efficient regarding mining, because the costs in basically all cost brackets of the cost curve is going down quite a lot over the last two years. But this is a little bit of a fake news, if you want to use that word, because it's about the high precious metal prices, gold and silver, that comes as a credit in these calculations, which pushes down the prices. You can still see that copper is for many reasons, maybe good reasons, still hovering quite far above the cost curve, which means that everybody in copper mining makes relatively good returns these days.

Zinc, that used to be down, that it was difficult on the margin to make money. Now the price have come up a little bit and is now safely above the cost curve structure. Then you can see nickel, where it's clearly an issue where something is gonna have to give on the nickel side. Either there will be clearly lower nickel production coming out, or there will be some adjustment of nickel prices, because at the price levels that we've seen here, it's very difficult to get nickel mining to be sustainable. If you then go to Boliden and look at our production, the Aitik mine has been improving production. Still not really up to the level where we want it to be, but it's coming up, and the ramping up of Liikavaara is coming, although a little bit slow, but it's still coming.

The grade right around where we have guided it to be. Garpenberg, record mill volume. It's been a very good production quarter. Grades around where they should be. Kevitsa, 2.5 million tons, a little bit less than last year, but you know that the permit in Kevitsa is 10 million tons, so 2.5 is right on the permit level, even though you can play between different quarters. So stable production around this capacity and grades around where they should be. Clearly stronger than last year's low, low grades. The Boliden Area is the very strong performer this quarter, with a very strong production. We have record for gold production coming out of the Kankberg mine in general, and very strong grades and throughput coming out of the Boliden Area.

In Tara, there was no production during the quarter, as I said, but we did have the first blast coming here. Moving over to the smelters, Rönnskär has had a series of smaller kind of disturbances, especially in the lead line, but you know everything is integrated, so it kind of spreads across. It is a challenge to run a place like Rönnskär without a tank house. Harjavalta, very strong production, strong cathode production around this, and basically generally good production in Harjavalta. Also nickel doing good in Harjavalta. In Kokkola, I would say outstanding overall equipment efficiency, very good availability, and a very good production coming out of Kokkola. Odda has had some challenges. Partially, it's due to the tank house four that is permanently closed, linked to the project, but also having a maintenance stop.

And then on top of that, you have a project next door that is working all the time. Makes it a little bit difficult to maybe be totally focused on production all the time, so the quarter was not stellar. Bergsöe has also had several minor disturbances during the quarter, but if you look on total production, you see that we're going up both on copper cathodes and, and nickel production is also very strong. With that, I'll leave it over to you, Håkan, to talk a little bit about financial summary.

Håkan Gabrielsson
CFO, Boliden

Thank you, Mikael, and good morning. As Mikael already said, we are reporting an EBIT result, excluding process inventory of SEK 2,999,000 so just shy of SEK 3 billion. This is an improvement of about SEK 1 billion compared to both comparison periods, then adjusting for the one-offs that we had in Q2 relating to insurances. Free cash flow, a negative SEK 500 million. I'll come back to that, and earnings per share, SEK 8.34, which is close to a 70% increase compared to last year. Breaking down the performance by business area, it's evident that we primarily had a very good quarter in mines, reaching in excess of SEK 2 billion. In there, in particular, I'd like to highlight Garpenberg and Boliden Area that contributed very much to this increase.

Solid quarter in smelters and relatively small movements in the eliminations, adding up to close to SEK 3 billion. Moving on then to the comparisons, quarter to quarter, and this is comparing Q3 this year to Q3 of last year. Prices and terms are up SEK 400 million. In there, there is an increase of metal prices, adding up to SEK 1.1 billion, where precious metals, gold, silver, have had a good run. Also copper and zinc, which is then partly offset by lower premiums, lower TCs, and lower exchange rates. Moving on to volumes, we see an increase of SEK 1.1 billion. Out of that, mines correspond or add up to SEK 800 million out of those SEK 1.1 billion. We see improvements across the lines. It's higher grades.

It's some inventory reductions, it's stronger mill production, so a strong quarter for mines. But also an improvement on the smelting side. And there we highlight, in particular, the performance of the Finnish smelters, Kokkola and Harjavalta, that had a good quarter. On the cost side, we have a negative impact of 287 , and of course, with that volume increase, there is some variable cost coming together with that, so that is one part of that. We've also had some general increases in a few of our sites. In Rönnskär, for example, we have, comparing to last year, higher cost for the whole anode handling process, which is a result of the new business model that we're running. In Aitik some costs connected to the Liikavaara start-up and in Odda as well.

But in general, mostly a cost movement related to volumes. Moving on to a sequential comparison with Q2 this year. As you can see, the impact from prices and terms is very limited, SEK 83 million, so small change there. We've had slightly lower metal prices, but slightly higher by-product prices, but again, small movements. Volumes up, 560 million. We have had higher volumes in smelters due to larger maintenance stops in Q2. But again, most of this increase is in mines, where we have higher mill volume and improved grades. I mean, in particular, Garpenberg again, and Boliden Area performing well. Costs are about SEK 600 million lower than the previous quarter.

There is a significant element of seasonality, which is slightly more than SEK 200 million, that we typically spend less in any given Q3 due to vacation periods, but there is also an effect of lower maintenance. Q2 was a quarter with fairly sizable planned maintenance stops in the smelting side that we didn't have in Q3 to the same extent, and then a big chunk here which is related to items affecting comparability, and that was two big items affecting Q2: the insurance income in Rönnskär, and then on the negative side, some restructuring in Tara. Moving on to cash flow, I think I've covered the operating profit side. Working capital, we're tying about SEK 1.4 billion.

Out of that, about SEK 500 million is a function of price movements, and the remainder is a volume increase. In the cash flow, I should also highlight that we have a positive effect, about SEK 200 million, from insurance payments that we have insurance considerations that we have received in the quarter. CapEx is a number that is in line with what we guided for the full year, and then it adds up to a negative SEK 500 million for the quarter. Moving on to capital structure. Fairly similar to the recent quarters.

We are at a net debt to equity of 24%, which is slightly higher than the years 2020 to 2022, but not standing out so much if you look further back in the history of the company. Still strong payment capacity of just over SEK 12 billion, so a balance sheet in good shape. So with that, want to take it?

Mikael Staffas
CEO, Boliden

Thank you, Håkan. Just very briefly, the Capital Markets Day, you know about. It's gonna be held in Odda. We're gonna show off the brand-new smelter to you all, guys. It is the actual capital market information will happen in Bergen, and then we will make the excursion to Odda later that first evening and on the next day. I think that you all who are affected should have gotten a separate invitation. If you haven't, you can contact Investor Relations at Boliden and get that in place. It's getting to be relatively full relatively quickly, so especially if you want to go to the Odda excursion, you should not wait too long to get in there. Now, regarding outlook, let's go through this one step by step. Number one, CapEx.

We came up with this one a couple of weeks back. There are no changes. SEK 13.5 billion next year, SEK 15.5 billion for this year. Regarding maintenance, we will not have any planned maintenance in Q4. There should be no change in any way. We have the insurance income that we just wrote in. We got out of that last SEK 1 billion that we expected, we got SEK 935 million confirmed by the insurance company just a few days back, and that will affect Q4. As a number, someone can argue, "Where are the last 65?" Well, there are lots of, lots of things in and out with an insurance, and we're not done with that totally, but that's this is what we have received as a confirmation as of right now. Tara will continue to run negative through Q4.

We can say basically we have now full costs, but we will not, do not have full production, and we are expecting a negative EUR 25 million result in the quarter. Now, regarding grades, you can see here that we are reiterating the 2024 grades across the board, except for the Boliden Area, where we're guiding up a little bit regarding the grades, and that's because some of you will have made the math, that if you wouldn't do that, there was basically no grades left for Q4, as there's been so strong grades actually throughout the year in the Boliden Area.

We will though have relatively weak. If you make the math here, even though we are guiding up the grade, we will have a relatively weak Q4 regarding grades in the Boliden Area, as we will have to mine the weaker areas as well, that we haven't mined so much of during the earlier part of the year. We should also say regarding Garpenberg, and I pointed that out, that now the environmental permit is now the bottleneck. The environmental permit is 3.5 million tons, and we will not be able to get any kind of exemption from that, which means that we can only do about 780 or so, thousand tons in Q4, which will be a lowering.

We have, as I said before, we have initiated a process to increase the permit in Garpenberg, so that the permit will not be the bottleneck for production, but actually the production will be the bottleneck for production. This is a process we have initiated. We have ambitions to get that in during the end of this year and to get that permit during next year, so that next year, the 3.5 should not be the bottleneck. However, you can never be sure either on the result of such a test or on the exact timing of it. But right now, 3.5 is the bottleneck, and that will affect Q4 negatively. Looking then into the grades of next year, and I don't think there should be any major surprises here to anybody.

We're having one more year of low grades in Aitik, which I think is in line with what has been guided before. Garpenberg is coming along, but as always told, in these underground mines, where we are mining clearly above the average in the R&R statement, we will slowly come down according to these bit by bit pieces. In the Boliden Area, you can say it's not really that much changes. Boliden Area should be no question. In Kevitsa, we have not guided yet, and that's because we are doing a review of the plans in Kevitsa, both related to dam construction and how the dam construction will play in, what kind of parts we have, but also with some geological information and also a potential how we will play to keep the option of a potential Pushback 5 alive.

Maybe we can postpone the actual decision, but we will keep the option live further out. All this is, it's a relatively big equation that might also affect the grades for next year, and we'll get back to you once we have gotten those things under control in a separate communication. So with that, I will then leave the floor to you, Olof.

Olof Grenmark
Head of Investor Relations, Boliden

Yes, ladies and gentlemen, that opens up our Q&A session here in Stockholm, and we will start with Johannes Grunselius, DNB Bank, please.

Johannes Grunselius
Analyst, DNB Bank

Thank you. It's Johannes Grunselius here at DNB. Can I start off by asking you about the grade guidance 2025, Aitik? It's 0.16 . I was more under the impression that 2024 would be the low point year. And then you have Liikavaara, which is a blend of, is it 1/5 , which comes with rich ore. So can you elaborate a bit on that? And you also mentioned that this is the last year with low grades in Aitik, if you can give us any color of beyond 2025?

Mikael Staffas
CEO, Boliden

I cannot really give you any color beyond what we gave on the Capital Markets Day. That's the latest information is out, and if you read that graph, it's pretty clear that there are three pretty low years, which of 2025 will be the lowest, and 2026, it starts a little bit of a pickup. I have no further guidance up on top of that. So we'll come back to guiding exactly how that return should be. But as we always said, that since we have an average in the R&R statement of 0.23, of course, at some stage, we will come back not just to 0.23, but also above 0.23.

Johannes Grunselius
Analyst, DNB Bank

Yeah. A second question on the ore, if you can give us any sort of color, what do you think about, I mean, the design is 45, right, and you're running at 40 , if you see that as achievable for the next few quarters.

Mikael Staffas
CEO, Boliden

Yeah, the design is at 45. You're absolutely right, and we have this year, this quarter, you have basically a 41 as a pace. It should be able to pick up some of these issues that we've had with the startup of Liikavaara should be behind us. That is helping on the amount of tons, so it should be coming up. But you're absolutely right. We've been struggling to reach a 45 in a consistent way, even though we've had 45 at individual quarters.

Johannes Grunselius
Analyst, DNB Bank

Thank you.

Olof Grenmark
Head of Investor Relations, Boliden

Ola Södermark, Kepler Cheuvreux.

Ola Södermark
Analyst, Kepler Cheuvreux

Yes, good morning. Just to follow up on Aitik, is it possible to quantify the, I mean, the impact of ramping up Liikavaara and also the construction of the improved dam facilities you have there? I assume it has impacted the total volume of the mine. Or?

Mikael Staffas
CEO, Boliden

Yes, but the effect is more indirect. It's true that there's been some competition for trucking capacity, which has been negative for the mine, and that should kind of come away. There's also been a little bit, when you have lots of activities in certain areas, of course, you run the risk of kind of being in the way of each other. So the end of the dam project should, on the margin, be positive also for the mine production.

Ola Södermark
Analyst, Kepler Cheuvreux

And a follow-up on the Garpenberg mine and the new permit you have there, what timing? I know it's impossible to say, but with your experience and so on.

Mikael Staffas
CEO, Boliden

Number one, it's not a brand-new permit. It is an alteration of the existing permit, which is good in terms of timing. What we can control is to get all the preparations done that needs to be done to get it in, including, as those of you who read Swedish newspapers know, that we have public consultation, quite a few of them, during the fall, which is out there. Our ambition is to get the actual application in within the next few weeks, clearly within this quarter.

Then we think that we will get the permit, and we think we're gonna get it at SEK 4.5 million, but you never know, and we think we're gonna get it during next year so that it will not be limiting factor for 2025, but we can never be 100% sure until we get it.

Ola Södermark
Analyst, Kepler Cheuvreux

Okay. Thank you.

Olof Grenmark
Head of Investor Relations, Boliden

Christian Kopfer, Handelsbanken, please.

Christian Kopfer
Analyst, Handelsbanken

All right. Thank you very much. Couple of questions. Follow up on Ola's question on Garpenberg, on the new permit, probably during next year. What kind of investments are we talking about to get there? Is it, I guess it's primarily the bottleneck in CapEx, or?

Mikael Staffas
CEO, Boliden

Now, just to be very clear, we are applying for a bigger permit to make sure that 3.5 is not a bottleneck for us. And the 4.5 is picked in the sense that that's a number which is big enough, so it should not really be a bottleneck, but it's still small enough that we can do it within an alteration of the existing permit, not having to apply for a brand-new permit. Those are the kind of parameters. We have not yet said anything about exactly how much we're going to produce or whether we will do any investments to get to a higher level.

We're just saying that we want to get the 3.5 away as a bottleneck, 'cause clearly we can produce 3.5 or maybe 3.6 or 3.7 with the existing infrastructure that we have. That's what we've proven this year. I mean, without any limits, we should probably have reached, or whatever, 3.6 for the year. So that's more about that, making sure that we can utilize what we have. And then, of course, we can think about expansions, but we have not yet communicated any of that.

Christian Kopfer
Analyst, Handelsbanken

Yeah, but when it comes to expansion up to, say, 4.5 million tons, could you do that with the bottlenecking CapEx, or do you need, you know, another line in the, in the mill, or how does it look?

Mikael Staffas
CEO, Boliden

Most likely, the mill can be done by the bottlenecking, but the big problem is the shaft and how to get the ore up. That's the one that is very close to capacity today, and we're looking into that. Here, there are many things that play in here because we will need a second shaft in Garpenberg anyway, even for the same production at some stage, because the mine getting deeper and deeper, so we need to get deeper with the shaft. But exactly how these things play out and when, it's too early to tell.

Christian Kopfer
Analyst, Handelsbanken

All right. On Tara, so let's just assume that everything looks. I mean, the by-product in Tara is lead, right?

Mikael Staffas
CEO, Boliden

Yes.

Christian Kopfer
Analyst, Handelsbanken

Basically, yeah. All right. So if you assume current lead price, what kind of C1 cash cost do you think Tara will be in twenty twenty-five?

Mikael Staffas
CEO, Boliden

A dollar.

Christian Kopfer
Analyst, Handelsbanken

$1, yeah?

Mikael Staffas
CEO, Boliden

One dollar.

Christian Kopfer
Analyst, Handelsbanken

All right. Okay, excellent.

Mikael Staffas
CEO, Boliden

We have even guided for this, Christian, so it's out there.

Christian Kopfer
Analyst, Handelsbanken

All right. Sorry for that.

Olof Grenmark
Head of Investor Relations, Boliden

Any other questions here in Stockholm, please? No more? Y es, one more from Johannes here, DNB Bank.

Johannes Grunselius
Analyst, DNB Bank

Thank you. To take another question, could you give some color on what you see in pricing for the smelters? I mean, we know about the weakness in Asia and the risk that it is spilling over. And, when, just to remind us, when is the next sort of quarter when you will go on new annual contracts? That's more in the second quarter next year, right?

Mikael Staffas
CEO, Boliden

I mean, the contracts are for copper negotiated typically in November, and then, you know, good as of January one, the annual benchmark contracts. On the zinc side, they're typically negotiated in February and March, but then retroactively effective as of January , 1. Then we always have some inventory, typically a month or six weeks or so on, that is delivered before the end of the year, and thus, priced according to the previous year's benchmark, that we will then consume during the first half of the first quarter, both for copper and for zinc. So that's the way the mechanics work out.

Johannes Grunselius
Analyst, DNB Bank

Yeah. What did you see in the spot market in Europe? Was that a major weakness, or was it more stability?

Mikael Staffas
CEO, Boliden

Now, the spot market, in terms of TCs, is a global market, and there, those TCs are very low. Very, very low spot TCs. How that will play into the benchmark negotiations, I don't know. W e're not part of that. What is more European locally are the premiums, and the premiums are on a stable, relatively low level. But as Håkan pointed out, compared to last year, they're lower. They're not moving that much in terms of the premiums, would be my guess right now. And then we have the byproducts that are also relatively stable on a maybe too low level.

Johannes Grunselius
Analyst, DNB Bank

Thanks.

Olof Grenmark
Head of Investor Relations, Boliden

Okay, operator, then we open up for questions over the phone, please.

Operator

If you wish to ask a question, please dial star five on your telephone keypad to enter the queue. If you wish to withdraw your question, please dial star five again on your telephone keypad. The next question comes from Liam Fitzpatrick from Deutsche Bank. Please go ahead.

Ola Södermark
Analyst, Kepler Cheuvreux

Good morning. Two questions from me, the first one on Kevitsa, and then the second on, on M&A. On Kevitsa, I appreciate the review is underway, so there's not too much you can say at this point. But can you give us a little bit of directional guidance in terms of when you think it will be complete, and based on the decision, whether you go ahead or not with the Pushback, what that is likely to mean for grades, you know, versus this year or versus reserve grade?

And then can you give any high-level kind of CapEx guide for the Pushback? I think historically it was talked at around SEK 3 billion-4 billion. That's the first set of questions. And then secondly, on M&A, I know you won't comment on specific assets or processes, but are you on the lookout for, you know, opportunistic acquisitions, or are you very much focused on your internal organic options? Thank you.

Mikael Staffas
CEO, Boliden

I'll start with the second one and say that we are, and as you know, mainly focused on our internal options. We have, apart from the investments we're already doing, we have maybe a handful of, you know, potential options that we're playing with going forward, and that is our focus, and that's where we historically have created most value. Having said that, it doesn't mean that we're not looking. When things show up, we will be looking, and but beyond that, I have no other comments. Regarding Kevitsa. Kevitsa, we are hoping to get either late this year or early next year to come out with the right plan, just to be very clear around that. There are quite a few moving parts.

Those of you who read the R&R statement of last year know that we had to take about five years out of the reserves and put them into resources because of a dam permit issue and dam construction issue that we had in Kevitsa. That in itself is a kind of interesting thing to work around. Looks quite positive in the sense that we're able to sort that out, but t hat needs to be done. That has consequences for mining sequences in itself. And then we also have the potential for a Pushback 5. And here, the idea is, just to be very clear, is not that you should expect that suddenly there is a decision on Pushback 5 coming in the next few months.

No, we are working on keeping that option alive, and keeping the option alive in the sense that we can maybe decide later. The later we can decide, the better, because as you all know, the nickel price is a relatively difficult thing to forecast, especially at this time. And therefore, I will not speculate on the other parts around, you know, how much would it be and when would it come, and all these things. That's way too early.

Liam Fitzpatrick
Analyst, Deutsche Bank

Let's assume you delay Pushback 5 for all of next year. Directionally, what could that mean for grades in 2025?

Mikael Staffas
CEO, Boliden

I care not to talk about it, because one thing is the Pushback 5, yes and no on those options. Another thing is also to get access to some material, you know, how to get access to actually waste material or inert waste material that we use for dam construction, which is another kind of more interesting part of this whole mining sequence.

Liam Fitzpatrick
Analyst, Deutsche Bank

Okay. All right. Thank you.

Operator

Please state your name and company. Please go ahead.

Adrian Gilani
Analyst, ABG Sundal Collier

Hi, it's Adrian here at ABG. A couple of questions from my end. First of all, a follow-up on the Garpenberg permit. I guess, how confident are you that the increased permit will be in place at the start of 2025 ? Is there a high uncertainty of you not getting it?

Mikael Staffas
CEO, Boliden

It will not be in place in the beginning of 2025, but it's enough that it comes in place during 2025, that we can produce 2025. So we will most likely assume that it's gonna happen 2025 and produce without any limitations in the beginning of the year, and if it doesn't come during 2025, we will have a relatively slow second half of the year. That's the reality of how things will work out. How confident? We feel good about it, but, you know, there's, it's, impossible to put any number on those things.

Adrian Gilani
Analyst, ABG Sundal Collier

Okay, I understand. And then also a follow-up on the TC benchmarks. I mean, we're seeing some reports that TC terms could be as low as sort of $20-$30 per ton for the copper benchmark for next year. Would you say that this is roughly in line with sort of what you are hearing as well?

Mikael Staffas
CEO, Boliden

I care not to speculate about that. We are not at the table, and the numbers that come out can have all kind of implication for negotiation tactics and other things at those tables. So I care not to speculate until we get the numbers out.

Adrian Gilani
Analyst, ABG Sundal Collier

Okay, understand. And just a final housekeeping question: the SEK 935 million in insurance income that will be booked in Q4, do you have a timeline for when that will be paid out?

Håkan Gabrielsson
CFO, Boliden

As of today, we don't have a timeline. We received the confirmation of the amount just a couple of days back, and the next step is to sit down and schedule the payment plan. I don't expect much of an impact on this year, but we'll come back to the outlook of the totality for next year.

Adrian Gilani
Analyst, ABG Sundal Collier

Okay, perfect. That was all for me, so thank you.

Operator

The next question comes from Ioannis Masvoulas from Morgan Stanley. Please go ahead.

Ioannis Masvoulas
Analyst, Morgan Stanley

Thank you very much for the presentation. A few questions left from my side. First, on the Odda expansion, with regards to the commissioning delay that you've indicated, for the project, what sort of earnings contribution shall we expect for 2025? I think at the full run rate and using commodity price inputs as of September, you were indicating that EUR 150 million at the full run rate is still the right number. Shall we assume half of that for the full year of 2025, or more or less? Any indication would be very helpful. Thank you.

Mikael Staffas
CEO, Boliden

I 'm really taking this from the top of my head, but the number for the full year effect is still true. It hasn't changed. Exactly how much, you know, exactly what the ramp-up curve will be, is still a bit unclear, so I'm clear not to speculate exactly on that, but the kind of full year effect is still the one that we have indicated.

Ioannis Masvoulas
Analyst, Morgan Stanley

Understood. Thank you. Second question on Laver. You have submitted an application for a mining concession. When do you expect a decision here? And assuming the outcome is positive, how long could the entire permitting process take before you can actually break ground, for this project?

Mikael Staffas
CEO, Boliden

That's an interesting question that is, has many potential outcomes. I think that if I were to guess, when we're speaking in 12 months, we will have a mining concession. This is both that we will get the mining concession and a rough indication of the timing. It could take another 12 months from now. It could take less, it could take more. We are not in control of the process. It's, as you know, a new law in Sweden. It's the first time that that new law is applied, so we'll see what it will entail. Once we're there, things get a little bit interesting because with the new Critical Raw Materials Act, I think it's highly likely that Laver could qualify as a strategic project, although that needs to be confirmed.

If it were to be so, you could say that the environmental permitting process should not take more than 27 months. Now, if this is really true and whether it's really in there, and whether it moves as fast, who knows? But I think that three years is maybe a more prudent way of looking at it, i.e., the kind of first time we could have an environmental permit in reality will be then late 2028. I think that that's still kind of optimistic, and then we're probably not ready to move right ahead. We will probably need to some discussions. So I said otherwise, I think it's very unlikely that we will have much of construction in the next five years. And then from start of construction, it's probably three years until we have anything mining, anything mined.

Ioannis Masvoulas
Analyst, Morgan Stanley

Very clear. Thank you for that. And just lastly, on Garpenberg, shall we think that the Q3 run rate of 3.7 million-3.8 million tons is something you can sustain, assuming you get the permit? Or could you even move a bit higher than that level without any incremental investments?

Mikael Staffas
CEO, Boliden

I think that the first point is true. It's obvious that we should be able to do a little bit more than 3.5 with the just existing things. We, of course, then also always looking at potential debottlenecking around Garpenberg, and we'll see what we'll come out with as a next step once we hopefully have this permit in place. But we're not gonna spend any money on any kind of investment for debottlenecking until we have the permit in place, so we're not risking investments in vain.

Ioannis Masvoulas
Analyst, Morgan Stanley

Yeah. Thanks very much.

Operator

The next question comes from Amos Fletcher from Barclays. Please go ahead.

Amos Fletcher
Analyst, Barclays

Yeah, hi, gents. I had a couple of questions. I suppose the first one is on Kevitsa and the mine plan revisions. Can you just talk us through the dynamics here and why the mine plan is taking so long to reassess? I mean, I remember in Q3 last year, you said there was no mine plan for 2025. So yeah, just to find out what's going on there. Thanks.

Mikael Staffas
CEO, Boliden

Just to take you through again, the first of all, as you will recall from the R&R statement update that we did in February, there was a quite a lot big degrade from ore reserve to resource. That was linked to dam issues and dam construction issues, and the assessment of the likelihood to get a dam permit on that dam plan that was in place at that time. We now have another dam plan in place, that we think is going to get permitted, which is good news, but it will require quite some material to get the dam in place. Most of that material, hopefully coming internally, not having to buy it externally. That could impact the plan, the mining plan.

Then, the second thing that is impacting a plan in Kevitsa is the fact that, the slope angle and other things related to slope angle are a little bit tricky, as we've had some problems with certain wedges in the pit, and that needs to be taken care of. The third thing that is very tricky and complicated in Kevitsa is it's not as Aitik, just to be clear. It's not as Aitik, where you have a very kind of evenly, slowly changing kind of grade in different parts of the area.

Now, the ore in Kevitsa is very concentrated in certain particular places, and you know when to get that and how to access that, and then which means that the way that you choose to do a plan actually makes a big difference to the grade in the grade profile for different years, and not for the totality, 'cause the totality is very relatively safe, but for different years, and all these things play together, and that's just to be very clear, what is happening now is that we have decided not to say anything until we have the full revised R&R statement ready, which typically gets ready in the early part of the year and is released to you guys in February. Maybe we'll consider releasing it earlier in Kevitsa.

Normally, the revised R&R statement doesn't really affect the first-year grades because they are in some way, kind of fixed or not so much to do about, so the first year is finished earlier, and we could then, at this particular time, guide for the grades, even though it's before the R&R statement is ready. In Kevitsa, that's not the case. We have had there are too many things that needs to be settled before we can communicate it, and it does, and it the certain choices does have an effect on the grades for 2025.

Amos Fletcher
Analyst, Barclays

Okay, very clear. And then as a follow-up, can I ask on a question about CapEx, where the spend rate in Q3 went down? It means you have to spend about SEK 5.1 billion in Q4 to meet the guidance. That's gonna be the highest on record. Is that realistic, or should we expect some CapEx to drift into 2025?

Mikael Staffas
CEO, Boliden

I think you're a little bit stating the obvious, that there is a risk or chance, however you wanna look at it, that something will drift. There is quite a big chunk that is coming into Q4, so we might see record levels, but whether we're gonna get everything in that we have in our plans, something might be drifting over to next year.

Amos Fletcher
Analyst, Barclays

And then last one was just on working capital. Slightly surprising size of the build. Have you got any expectations for what we should have seen for Q4, please?

Håkan Gabrielsson
CFO, Boliden

Q4 typically is our strongest quarter when it comes to working capital. We've had a fairly high build this quarter, but clearly less than what we typically have in Q2. So I expect Q4 to be roughly a normal Q4, which is a, you know, working capital release. I don't want to give a number because it's price-related and all that, but it should be a release. Then if you're simulating the working capital specifically, we will booking the insurance incomes, we will also get a SEK 935 million receivable affecting the working capital for Q4. But excluding that, we should see a release.

Amos Fletcher
Analyst, Barclays

Got it. Thank you very much. That's it.

Operator

The next question comes from Marina Calero from RBC Capital Markets. Please go ahead.

Marina Calero
Analyst, RBC Capital Markets

Good morning. Thanks for the call. I just have a follow-up question on Kevitsa. You mentioned the importance of a nickel price for the Pushback 5 decision. Can you maybe give us a range of what sort of nickel prices you will need for that investment to meet your hurdle rate?

Mikael Staffas
CEO, Boliden

No, I will not, but I'll just to get a little bit of shedding light. I mean, the question for Kevitsa Pushback 5 is the price of metals in general between 2035 and 2045, 'cause that's the kind of extension we're talking about for those ten years. And it's about the nickel price, which is important, but it's also about copper and PGM and gold, and that whole totality needs to work out. As you probably understood, because we haven't made a decision yet, it's not that if one used a kind of sports term, that this is a slam dunk. There are lots of issues in and out, and ifs and buts around this.

And one, also given the kind of general uncertainty always with metal prices, but especially so far in advance, the further we can kind of extend this option, that we can then make a decision later without destroying any value, and the way we're doing it is, of course, also creating value.

Marina Calero
Analyst, RBC Capital Markets

All is good. Thank you very much.

Operator

The next question comes from Richard Hatch from Berenberg. Please go ahead.

Richard Hatch
Analyst, Berenberg

Yeah, thanks, thanks very much for the call. Just a couple of follow-ups or just final points. Just on Tara's throughput for 2025, can you give us a steer as to what kind of volumes you think is sensible to put into our numbers? First one, please.

Mikael Staffas
CEO, Boliden

1.8 million tons of throughput at 5.5% zinc.

Richard Hatch
Analyst, Berenberg

Great. Okay, very helpful. Very clear. Thanks. The second one is just, I mean, you've effectively pointed to it, but just for leading grades, Q4, on my numbers, it looks like you're gonna have to do about one and a half grams gold grade to get to the two point three guidance. Is that correct, or do you think there's upside to that?

Mikael Staffas
CEO, Boliden

No, I think you've done the math right. I will not, I will not question your math.

Richard Hatch
Analyst, Berenberg

Okay, cool. Thank you, many do. And then the last one is just on Garpenberg you talking about the expansion. Can you just talk about the TSF capacity you’ve got at site, just in terms of if that’s a challenge or not at all?

Mikael Staffas
CEO, Boliden

The existing tailings facility at the existing production levels is good until about 2034-2035, s omething like that.

That's one of the considerations of kind of only asking for 4.5 , is that that still is kind of doable. It will shorten the life of mine. If we were to go to four and a half, it will shorten the life of mine on the existing tailings facility, but it's still doable to deposit, which is, of course, very important for getting the permit to be allowed to produce, that you can show that if you were to produce on that level, that you can actually handle the tailings. At some stage, there will be needed a new or extended or widened tailings facility. That is work that's ongoing. We are not nervous in a sense, but it's of course always kind of interesting where you're gonna get a new tailings facility in place.

That will be the subject of a later permit, and that will be a new permit, starting from scratch.

Richard Hatch
Analyst, Berenberg

Okay, gotcha. All right. Thanks for your time.

Operator

The next question comes from Daniel Major from UBS. Please go ahead.

Daniel Major
Analyst, UBS

Hi. Yeah, thanks for questions. Two, from me. First one, just perhaps a clarification on the couple of bridge items into Q4. Can you just confirm how much out of the insurance provision you've received as cash? Is it SEK 800 million? I think it was SEK 600 million and SEK 200 million. Is that correct?

Håkan Gabrielsson
CFO, Boliden

Exactly. The guidance that we gave holds, so we received SEK 800 million so far, and we have SEK 200 million that we're expecting for Q4 as a payment. And on the P&L side, we're expecting SEK 935 million as an income in the P&L of Q4.

Daniel Major
Analyst, UBS

Okay, thanks, and then, the second one, looking at your group quarterly bridge, SEK 591 million benefit this quarter from, in the cost line. How much of that is seasonality?

Håkan Gabrielsson
CFO, Boliden

We've typically said that it's SEK 200 million . When I looked into the detail numbers, I would probably round that up a bit, so I'd say SEK 220 million-230 million is probably a correct number. But if you want to round it to even hundreds, then I'd say SEK 200 million .

Daniel Major
Analyst, UBS

Okay. Would you expect the remainder of that to be sustained in terms of that cost benefit into Q4?

Håkan Gabrielsson
CFO, Boliden

Q4 is, I mean, the main part of the rest is that we don't have maintenance, so that should be sustained until next summer. But having said that, Q4 is typically our most expensive quarter. So if you compare Q4 to the cost of any other quarter, it will be fairly high. So I would be quite conservative in the modeling for Q4 specifically, even though I cannot point any single item here that is not sustainable.

Daniel Major
Analyst, UBS

Okay, thanks. And then, last one, just to follow up on Liam's question around M&A. You normally focus on gearing where you're, you know, 24%, I suppose, above your target, but your net debt EBITDA is still quite low, less than 1x . If M&A were an option, can you give us any sense of how high you'd be willing to go in terms of leverage for cash funded M&A, and whether equity would still be an option?

Mikael Staffas
CEO, Boliden

I will answer that question in very general terms, and I think we said this many times before. We are extremely uneasy with ever going over 60% gearing. We simulate a lot of what low turns look like and how what really bad turns look like and what we then can afford. We can be north of 20%, because we don't really go from 20% to 60% in a normal kind of downturn. A normal downturn will be less than that, but exactly how big it is will depend. We are very comfortable with the present 24%, and that could probably be north of that. I've sometimes given the number that when we bought Kevitsa, I think it was 40%, around there, and we were confident around 40% to do that acquisition. Somewhere north of that, the equity will start playing.

Daniel Major
Analyst, UBS

Okay, so 40% would really be what you'd be comfortable going up to on the debt side. Is that right?

Mikael Staffas
CEO, Boliden

It all depends. It depends also what the simulations work out on, but we have proven to be comfortable with 40% once before.

Håkan Gabrielsson
CFO, Boliden

But just to underline what Mikael says, we spend a lot of time simulating. If we do a big investment of any kind, what would it look like if we had a severe downturn immediately after that? And we want to meet our limits where we feel comfortable, even in a severe downturn. So that's how we work it.

Mikael Staffas
CEO, Boliden

You also pointed out, obviously, Håkan. It also depends what other CapEx we have that might be non-M&A-related CapEx as well, plays into all these simulations.

Daniel Major
Analyst, UBS

Okay. Very clear, thanks.

Operator

As a reminder, if you wish to ask a question, please dial star five on your telephone keypad. The next question comes from Liam Fitzpatrick from Deutsche Bank. Please go ahead.

Liam Fitzpatrick
Analyst, Deutsche Bank

Good morning. Second round here. I just wanted to follow up on Aitik, because I've also had some questions from investors on this. I'm still a little bit confused about why the grade is going down year over year, given that the Liikavaara higher grade pit is ramping up. Is this just a short-term ore access issue? Is the mine plan not panning out exactly as you thought? And any color on that would be helpful.

Mikael Staffas
CEO, Boliden

This is fully an ore access issue around where the other workings are. And then, I've told some other people who question why is it 0.16, that, you know, if you put out your ruler and look very closely into what was given at the Capital Markets Day, you can probably figure out that the best case or the expected case was 0.16 for 2025. It depends on how sharp eyes you have. But we were, of course, blurry 'cause we didn't know, but I can say that 0.16 is exactly according to what we thought internally all the time. And it is due to the fact, not so much Liikavaara, because Liikavaara was always planned to be full and is also planned to be full now for next year.

But it's the other positions in the mine that we have, especially on the south side, where we're not really into... And also on the new North 7, where we are not into high grades yet. We need to come down a few benches before we can start hitting higher grades.

Liam Fitzpatrick
Analyst, Deutsche Bank

Okay. Thank you.

Operator

The next question comes from Amos Fletcher from Barclays. Please go ahead.

Amos Fletcher
Analyst, Barclays

Guys, thanks for the follow-up. Just to... Another question on Aitik. Do you think you need to spend more CapEx to deliver 45 million tons consistently at some stage?

Mikael Staffas
CEO, Boliden

That is not our plan, because I think that it's doable without any major CapEx. The mill is clearly ready for it. The bottleneck has been the mine, and then somebody says, "Okay, what if you were to just put in a few more trucks, and then it's all solved?" It's not quite that easy. It has to do with availability of phases and availability of other equipment as well, and that has proven to be a problem over time. And to me, it's not really a CapEx issue.

Håkan Gabrielsson
CFO, Boliden

Just, I agree with what you say, Mikael, and just one addition. We have, for next year already guided for higher maintenance CapEx in Aitik, and that plays a part in that. But that's already in the numbers we've communicated.

Amos Fletcher
Analyst, Barclays

Okay. And so do you think it's reasonable to assume 45 million tons for next year, or is it sort of somewhere between 2024 levels and 45 million tons more reasonable?

Mikael Staffas
CEO, Boliden

I would say that that's more reasonable. Yes.

Amos Fletcher
Analyst, Barclays

Okay. Cool. All right, thank you.

Operator

There are no more questions at this time, so I hand the conference back to the speakers for any closing comments.

Mikael Staffas
CEO, Boliden

Thank you, operator. I just wanted to thank all of you for bearing with us during this conference. I think that you've all... I hope that you've gotten a little bit better sense of what I think has been a very good quarter and also quite good forward-looking statements as well, albeit be it with a little bit of a hinge to Q4. Thank you, all!

Powered by