Good morning, ladies and gentlemen, and welcome to the Boralex second quarter 2021 results. At this time, all lines are listen only mode. Following the presentation, we will conduct a question and answer session. If at any time during this call you require immediate assistance, please press star zero for the operator. This call is being recorded on Friday, 6 August , 2021. I would now like to turn the conference over to Mr. Stéphane Milot. Please go ahead.
Well, thank you, operator. Good morning, everyone. Welcome to Boralex second quarter results conference call. Joining me today, at the office here with Patrick Decostre, we also have Bruno Guilmette, our Vice President and Chief Financial Officer, and other members of our management and finance team on the line. Mr. Decostre will begin with comments about the highlights of the quarter. Afterwards, Mr. Guilmette will carry on with financial highlights. Then we'll be available to answer your questions. As you know, during this call, we will be discussing historical as well as forward-looking information. When talking about the future, there are a variety of risk factors that have been listed in our different filings with securities regulators, which can materially change our estimated results. These documents are all available for consultation at sedar.com.
In our webcast presentation document, the disclosed results are presented both under IFRS and on a combined basis. Unless otherwise stated, all comments made in this presentation will refer to combined basis figures. The press release, the MD&A, the consolidated financial statement, and a copy of today's presentations are all posted on the Boralex website at boralex.com under the investor section. If you wish to receive a copy of these documents, please contact me directly. It'll be a pleasure to send the information to you. Mr. Decostre will now start with his comments, and please go ahead, Patrick.
Thank you, Stéphane. Good morning, everyone. I am very pleased to present you today physically from our office in downtown Montreal, our second quarter results. Production in the quarter significantly increased compared to the same quarter last year, with the growth being attributable to acquisitions and commissioning. Production was, however, lower than anticipated production, mainly due to unfavorable conditions in the hydro sector. EBITDA for the quarter was 10% higher than the same quarter last year. The growth came from a CAD 24 million contribution from the acquisition of participation of CDPQ in three wind farms in Quebec, the acquisition of participation in seven solar farms in the U.S., and the commissioning of assets. The highlight of the quarter is the addition of 553 MW of solar and wind project and 190 MW of storage project to our pipeline. Seven projects totaling 137 MW also progressed within our growth paths.
Some were added to the secure stage and others moved to the ready-to-build stage. One last point, as you all know, in June, we launched our 2025 Strategy Plan, including new corporate objectives. We got very positive feedback from all our stakeholders. We are very proud of the outcome of this plan, I can assure you that all teams are working hard to achieve our goals in a timely and disciplined manner. I will now cover changes in our pipeline. As you can see on slide five of our presentation, we added 510 MW of U.S. solar projects in our preliminary phase. Simultaneously, we also add some smaller wind and solar project in France, and the solar project in France progressed to the mid-stage phase. Other wind and solar project in France also progressed from mid-stage to advanced stage, and from advanced stage to our growth path.
We added four projects to the secured stage of our growth path for a total of 41 MW. Please note that one of these projects is a repowering, which is not adding capacity, but the wind farm will benefit from a high-performance equipment and a new 20-year contract. Finally, three projects were added to the ready-to-build stage for a total of 96 MW. As you can see on slide seven, with all these movements in our pipeline and growth path, we are making very good progress toward our objective of doubling our capacity by 2025. Moving now to our strategic orientations on slide eight. I will not cover growth and diversification, as I covered most of it already, but I would like to highlight that we're still seeing important demand for corporate PPA.
As mentioned at our investor day, with the approaching end of contract that started 15 years ago in France, additional corporate PPAs and repowering projects are expected in the future. These represent valuable projects providing interesting returns for a fraction of the time required to execute compared to our traditional greenfield projects in France. We are making good progress on the optimization orientation too. We signed a new contract with Vestas in France, which is expected to provide competitive operating costs, combined with production improvement incentive in line with our optimization strategy. We also continue to optimize maintenance in North America and became 100% renewable with the sale of our Blendecques facility. This completes my part. I will now let Bruno cover the financial portion in more detail, and will be back later for the question period.
Thank you, Patrick. Good morning, everyone. First, a little bit out of topic, let me recognize and congratulate all the athletes that are currently competing at the Olympics. They are the best in the world, and we certainly share values of great discipline, hard work, and teamwork with these athletes. A special congratulations to our Canadian women's soccer team for their gold medal that they won just a few minutes ago. Back to our main topic. I will start with a review of the progress made in light of our new 2025 corporate objectives. We recently increased our capacity by 26 MW following the commissioning of our Bazougeais wind farm on May 1st and Extension Plaine d'Escrebieux wind farm on August 1st. These capacity additions were partly offset by the disposal of the Blendecques co-generation plant, resulting in a net capacity addition of 14 MW.
I would also like to take this opportunity to mention that our 4.4 GW targets in 2025 represents capacity as we have been defining it in our financial reporting for a few years now. This means 100% of capacity if we control the asset and our share of it if we don't have control. Moving to our last 12 months EBITDA and AFFO, you can see on slide 10 that we continue to make progress on these two measures, thanks to our acquisitions and commissioning of new assets. Our reinvestment ratio stands at 55%, in line with our 50%-70% target. Moving on to CSR. Most of the achievements mentioned on slide 11 were covered at our investor day. I would, however, like to highlight that we are making good progress with the production of our carbon footprint report.
With the addition of a CSR expert to our team and the creation of a formal CSR committee, we are moving ahead with a lot of rigor on our different ESG initiatives. We will have more to report on this front in the coming quarters. I will now cover the financial results for the quarter, starting with production. Wind production on a combined basis in Canada was in line with our anticipated production and 5% higher than in the same quarter last year, driven by the acquisition of the Quebec assets. Comparable production was lower than last year, reflecting less favorable wind conditions than in the second quarter last year. In France, wind production was 2% lower than anticipated and 23% higher than the same quarter last year, with growth coming from higher comparable production and new commissioning.
Overall, total combined wind production for the quarter, combining Canada and France, was only 1% lower than the anticipated production and 12% higher than last year. Turning to hydro now. It was a difficult quarter for both Canada and U.S. hydro. Hydro conditions were unfavorable during the quarter, resulting in production 24% lower than anticipated and 13% lower than in the same quarter last year. Finally, for solar, our U.S. acquisition continued to perform well with production 4% above anticipated production. In summary, total combined production for the quarter was only 4% lower than anticipated, but 22% higher than last year. Second quarter revenues were up 9% compared to last year. For the second quarter of 2021, combined EBITDA was CAD 117 million compared to CAD 107 million for the same quarter of 2020, a 10% increase.
Net loss was CAD 9 million in the second quarter compared to a net loss of CAD 5 million last year. We generated CAD 66 million of IFRS cash flows from operations in the second quarter compared to CAD 51 million in the same quarter last year. The FFO was a negative CAD 7 million compared to a negative CAD 14 million in second quarter last year, reflecting the improvement in cash flow from operations and also the seasonality of our operations. As indicated on slide 19, our financial position remains solid with our net debt to total market capital ratio of 46% on June 30th, compared to 41% on December 1st, 2020. In conclusion, we received strong positive response from our stakeholders to our 2025 strategic plan. We continue to make good progress toward the execution of our four strategic orientations and six corporate objectives with our team fully mobilized.
We're putting the final touch to our bid in the upcoming Tier 1 RFP in New York, due at the end of this month, and we have a solid financial position to pursue our growth initiatives. Finally, we are working on the optimization of our capital structure to further improve our financial flexibility and lower our costs. Thank you for your attention. We are now ready to take your questions.
Thank you ladies and gentlemen we will now begin the question and answer session should you have any question please press star four by one on your touch-tone phone. [uncertain] your request and your request will be pulled in when received could you wish to decline please do so by pressing star four by two if your using a speaker phone please answer your phone by pressing any keys. Now we move to the first question. The first question comes from David Quezada with Raymond James. Please go ahead.
Thanks. Morning, everyone. My first question here, just on the 190 MW of storage you added to the early-stage pipeline. Appreciate that it's an early development category, but just wondering if there's any color you could provide, be it in terms of a timeline you expect for those projects and maybe even the number and size of them. We'll start with that.
David, good morning. It's Patrick. Part of this project, 100 MW, is in California, where we apply to some optimization finally of the asset we just bought and closed in February. We announced that earlier, but now it's done. We have applied. You know that the Californian process for grid connection is long, so probably something like 18 months, 24 months to have a good answer to it. The other projects are in New York State and will be in our pipeline to be either bid or add to some production projects. Less view on this in term of the time.
Okay. Excellent. Thank you for that. Maybe just a question regarding France. I understand that there was not a huge number of megawatts, but there's an alternative connection offer that has been announced, which I guess has faster potential interconnection. I am curious if you have any projects that could benefit from that.
David, could you be more specific on what you're referring to? Just want to make sure we understand exactly what the.
Yeah, I saw a news report of a 750 MW of alternative connection offer in France that had been announced, I think, in the past couple weeks.
To be transparent, I'm not aware of this specific point. What I can tell you is possibly my team, certainly my team is aware in France. We have different, say, strategy of securing interconnection independent where you are on distribution network or on the transport, the large transmission grid. Sorry, I was searching the word. I don't know this question. We have a constant conversation with the grid operator to improve the things, and I'm sure that my team is aware of that.
Okay, great. Appreciate the color. I'll get back in the queue.
Thank you. Your next question comes from Nelson Ng with RBC. Please go ahead.
Great. Thanks. Good morning, everyone. Just a quick clarification on the storage question from David. Are you proposing to add storage on your existing assets, or are these new sites with just storage? You also grew your solar pipeline by, I think, slightly over 500 MW. Is your storage going to be standalone, or is it going to be attached to new solar plus storage projects, or are you looking to add them to existing assets?
Yeah, good question, Nelson. Good morning. In California, it's really on the site within the fence of the existing solar plants and with an existing grid connection. You have to change the grid connection agreement to put storage on top of the solar existing assets. In New York, the other project, as I mentioned, are in New York. In New York, you don't have the limitation to be on the same site with the same grid connection. This is already something which is available in the NYSERDA framework for the next tender. It's not a question. Virtually, you will be combined, but you don't have to be on the same site. I understand your question is about the development. These developments are in the U.S. and we are ready, as Bruno mentioned, to bid.
I will obviously not declare and go into details about what we will bid at the end of the month, but we are ready to bid a significant amount of project and power.
Okay. Thanks, Patrick. Your MD&A indicates that you have like 840 MW that you could bid, so I presume you'll bid a subset of that later this month.
Yeah. There is always a strategy behind this and more than strategies, some tactics. Yes, we are confident that there will be this round and other rounds afterwards. We will manage that and decide in the next days.
Yeah, just sat on that is, it doesn't necessarily mean that because we have 840 MW ready to bid, that we'll all bid them the next auction. At the end of the day, we want to have the best return on these projects. As Patrick mentioned, it's a question of strategy, knowing that there are other bids coming and the approach is different. Same as it is in France.
Okay. That's clear. Then just one last question on energy storage. Does it make economic sense right now to add batteries to any of your solar sites in the U.S., or do you need to wait for a process?
It's a good question. It depend of the contract that we have and the off-taker. Some are interest to have a shift of the production within the day, and this is already somewhere in the contract, and some are not. The answer to your question is a mix, depend of the site, and there is already some opportunity. If the grid connection are obtained, the commercial part would be probably something not so difficult.
If I'm trying to read between the lines, maybe in California, it would make economic sense to add batteries.
Yes.
My last question before I go back in the queue is agrivoltaics. I think, a few months ago, there was an announcement that you guys have this arrangement with Sun'Agri. Just from looking at some of the pictures, it looks like these are solar projects on stilts that are more kind of spaced out, and they sit above crops. Are there any near-term projects that you're working on the agrivoltaic side right now?
Yeah. In the near term, I think this partnership help us to have a solution in some constrained area, typically in France for the moment, on the agricultural part, because the country is smaller than the big countries of North America. It's a part of the solution that we can bring to municipalities or farmers. It's not a big game changer for Boralex. It's important, I think, in sustainability of development of solar in France.
Okay. It might just make more land available for you to develop solar in France. Is that fair to say?
Yes. Nothing specifically in the short term, but it's important to have this solution in our proposal.
Okay. That's great. Thanks. I'll get back in the queue.
Thank you.
Thank you. Your next question comes from John Mould with TD Securities. Please go ahead.
Good morning, everybody. I'd just like to start with the permitting process in France. I know there was some movement to allow municipalities to potentially have veto the location of wind turbines, but my understanding is that ended up getting changed simply to requiring consultation. I'm just wondering how you're thinking about the state of the permitting process more broadly in France, and whether this consultation requirement has any potential to slow down permitting of projects there.
Good morning. Essentially, my view with the 18 years of experience of development in France, we have had many things like this in the past, like new orders then simplification then another one. We are used, and our team there is used to make this. We are already obviously not starting. When a project enter the preliminary stage in our pipeline in Boralex, it's already, because we have a first, not formal, but sometimes formal, but a first agreement of the municipalities where we are developing. I think it's not a big issue, but it depend of the way it will be implemented. As I mentioned, 10 years ago, there was something like this. We went through it then they modified the thing. It's classical development in France.
I think it's important globally for France as a social acceptability of the project. That's not bad. We are used to play with this kind of conditions.
Okay. Now, that makes sense. Then maybe just moving to Quebec and the planned RFPs there. Appreciating you don't want to get into details, just like the New York process, but can you maybe just give us a sense of scale of the projects you might be able to submit or that you're working to advance there, and maybe a sense of how much capacity could be remaining on the Seigneurie de Beaupré lands there?
I think for Seigneurie de Beaupré , I will refer to preview disclosure of Boralex. There is room for development in term of connection there. If you go back some years ago, I think we announced another potential gigawatt on the site, which is in term of connection. In between, the size of the turbine has increased, so the number of turbines has decreased for the same power. It's definitely a good site for development. On the RFP, we have started more than one year ago to negotiate the Apuiat project with the government. We were somewhere informed of and have the vision that this door of new RFP will open again. We are prepared, and our side are prepared. I don't want to give figures today, but we are happy with it, and we are prepared to bid when it will come.
Okay. Great. I'll leave it there. Thank you very much for taking my questions.
Thank you.
Thank you. Your next question comes from Mark Jarvi with CIBC. Please go ahead.
Thanks. Good morning, everyone. Question on France, in terms of you adding some more projects to the identified growth path. How many more megawatts or projects exist that were successful in prior RFP but don't have full permits and that could get onto the identified growth path? Just wondering how many more of these projects there might be in the queue to get into that identified growth path in France.
Could you, Mark, just repeat your question?
Yeah.
We kind of missed a part of it.
Yeah. Sometimes you won contracts through RFPs, but they don't immediately show up in the identified growth because you need to get either board approval based on some permitting. I'm just wondering how many projects that were successful in prior RFPs still aren't in your identified growth path. Just wondering what we could see in the coming quarters from projects with, I guess, price certainty but not full authorization to move ahead with the projects.
Okay. You mean projects that would be, just to make sure that we get it right, that would be like in an advanced stage? Not exactly ready to go into the growth path and the secured stage, but having a contract?
Yes. Exactly.
Is that what you mean?
Yeah.
I think we have actually, but Stéphane will come back with the exact figures, but I think we have two projects at least which have obtained a contract, and are still in advanced stage because of the development stage of the authorization itself.
Seeing from today, we will not be able to connect before 2025. That's also another point. When we put a project in secured stage is because we think we will be able to connect it before end of 2025. That's the thing.
Got it.
The important point is, this project, there are some periods of development. It's project on which there is a third-party recourse, but we think we will win. There is no reason we get the authorization from the state, and the third party challenged the project. The period of the challenge before the court are frozen. There is no question of a cliff date to lose the contract we have already obtained. For the next tender in France, I mentioned the last tender was the eighth round. There will be other rounds. The definition, the conditions of the rounds are under discussion for the moment, but they will continue to have 1.85 GW per year of tender. We will have some project to bid in the next tenders.
Okay.
We are also playing project between tenders, RFP, and CR 2017 at EUR 72 a megawatt hour, which is still available....
Available
...for project of a power up to 18 MW.
Okay. Bruno, for you hinted at this optimization of capital structure. Is that something that you can give us a bit more detail in terms of what's underway? If you can't give us any detail, when should we be expecting an update in terms of what you're trying to do on the financing side of things?
We certainly expect to be able to give an update before the end of the year. Not that it will be final, but we expect to be on the way in our analysis of our ability to get an investment-grade rating during the fall. That's as I think we explained before, you're not certain until you actually go to credit agencies. Since we've never felt the need in recent past, we have to go through a process before we can give you an answer. That process will start during the fall, at least internally.
Is there anything about any of your existing credit agreements or project-level debt or non-recourse debt that makes that more challenging to accomplish? Does it seem like so far things are progressing as expected?
It's more of a process and analysis, again, with the credit agencies, which we have not, to be clear, contacted yet. It's more of a process than us seeing challenges.
Got it. Then a question for Patrick around the upcoming RFP for solar projects in New York. Last year, you always take sort of a disciplined approach and didn't want to bid on, certainly around ITC extension. Now we're seeing a lot of chatter and discussion around inflation and either transient or longer-term pressures on module costs for solar. Just wondering, do you guys have enough visibility on costs and some sort of indicative pricing that you can bid with conviction? Where does that kind of play into your thinking in terms of your ability to be aggressive or other competitors being more aggressive than you this fall in the RFPs?
Yeah, it's a good question, but I think there is an important difference between the two situations, because last year it was on/off the ITC, but today we are more used to manage inflation. In the past it was a kind of deflation, the reduction of the cost of the turbine, and we have bid in some RFP with the view of a potential reduction of the cost of the turbine. Everybody was doing that. I think it's a risk that we know better than the one last year. On top of this, I think there is also different potential optimization during the development of the project themselves after having obtained the contract that can compensate if we have to compensate inflation. With the ITC question, it was a binary situation, so it was not possible to compensate ITC with project optimizations.
Okay, that makes sense. That is all I had. Thank you.
Thank you. Your next question comes from Naji Baydoun with iA Capital Markets. Please go ahead.
Hi, good morning. Bruno, just wanted to follow up on Mark's question about financial priorities. I appreciate the corporate credit rating process is going to get underway, but any other significant progress you can report on, maybe related to minority stake sales or other priorities?
Well, we're always looking at our portfolio just to see if there's other re-financings we can look at. Also in terms of partnerships or asset sales, you've seen that we sold the Blendecques facility in France. We'll continue to look at assets to see whether they fit with our long-term view strategically. That's for selling all assets. Then in terms of financial partnerships, it is a key element as we've mentioned it a few times. For us, it's really to find the right approach to create these partnerships on the right approach, the right pool of assets, in which region, and have discussions with financial partners. That is certainly one of the key elements that we look forward to develop more.
Okay, got it. Just maybe on New York, I know the focus is on the Tier 1 programs, but can you maybe talk about how you're thinking about maybe participating in some of the other or the different tiers for clean energy procurement in the state?
Yeah. I think this creates opportunity we hope Hydro-Québec typically will be one of the awarded candidate for Tier 4, because it has an indirect impact on the demand in Quebec and the electricity available here. I think my personal view, it could be a good thing for New York State, New York City, and Quebec and Canada. Hopefully, with an indirect impact on Boralex for development of wind here.
Okay. Great. Just maybe one last question on asset optimization. You're in-housing some O&M in Canada, but you've done the 15-year contract with Vestas in France. I guess, one, can you quantify maybe what the potential savings from these initiatives could be? Maybe just how you're thinking about the trade-off between what you do in Canada and what you're doing in France, and how that fits within your strategy.
Well, the key element with the Vestas contract is the competitive aspect of that offer, which we hadn't seen before from a manufacturer O&M contract. They really, Vestas came to us with, again, pricing that was much more competitive than previously. In general, the key element to that contract is a guaranteed availability by Vestas, so they take the risk. They also have an incentive to exceed this minimum availability threshold. I unfortunately cannot give you the precise number of guaranteed availability, but I can tell you its advantages for us. That's the key element. It's hard to give precise numbers. We expect that certainly, because otherwise we would not have signed this kind of agreement. We expect added value from this contract and it also allows us to deploy our workforce on other O&M work on other types of assets.
Again, it's over the life of the contract, we get a very positive number, but we just don't want to disclose on a year-by-year basis because it really depends on the availability difference that we're going to get.
Yeah, maybe I could add, it's good to have, as Bruno mentioned, to manage our risk and to have a part which is insourced and a part which is outsourced. It depends of the competitive situation of suppliers in the area. Typically, today, in Quebec, there is no competition except Boralex itself to perform maintenance on ENERCON turbines. It's not the situation in France. People like Vestas or GE or Siemens Gamesa are proposing us multi-turbines, multi-brand maintenance, and competition is completely different. It was not the case five years ago, and it was even not the case 10 years ago. We did the right thing to insource during a certain period and create the skills internally to be able to challenge the manufacturer.
When Vestas came with this offer, we look at it and we say, "Okay, we are agnostic to have it in or out, but we're not agnostic to the risk and the reward and the contract is interesting." As Bruno mentioned, we will be able to concentrate our team where we think we can create more value, and we have transferred risk to Vestas in this case for a long period, which is also good in term of planning.
Understood. That's a good detail. Thank you.
Thank you. Your next question comes from Andrew Kuske with Credit Suisse. Please go ahead.
Thank you. Good morning. I think the question is for Patrick, and it really revolves around carbon pricing and just the potential impacts you see from carbon pricing. I guess the gist of the question is, how much benefit do you think you'll see in the future from carbon prices escalating in most jurisdictions? The state of play in Canada is fairly clear, but how do you think about the U.S. opportunity as it relates to carbon pricing, which is uncertain at this point, and then things like the cross-border taxes that are being proposed in Europe?
Yeah. It's a good question. My view, specifically, I will start with Europe, continental Europe and the U.K. It really creates an opportunity because you have seen the commitment of the proposal, actually, from the European Commission about the Fit for 55. This is the goal to reduce by 55% the emission in Europe compared to 1990. It was 40, now it's 55. This put pressure on the carbon pricing. This has an impact on the electricity cost. For when you're producing with gas and even more with coal, there's still some coal. The fact is that this is an opportunity for us for different reason. The short term, it increased the price of the corporate PPA, and because the alternative for the corporation to buy electricity on the market at a higher price instead of buying green electricity from Boralex. This is the short-term impact.
The long-term impact is to create also some opportunity, and we are in the discussion with some corporation, where it could be of interest to build a project with a counterpart, which is not typically in France, EDF, but which is a solid corporation that also sometimes it's a good opportunity instead of going to an RFP with a lot of competition in solar, typically in France. I think that's good. That's also good for in the U.K., you have seen the price of, I think it's more than 45 pounds per ton. This is also a good sign for our project in Scotland to find a corporate PPA when the project will be re-optimized. I think we mentioned that previously, that we are optimizing the Limekiln project. In the U.S., clearly, I have no view, but I think the same cause would create the same effect.
The main question with my experience, I'm following the European ETS market since 2005. The main question is, the policy should be maintained on the long term. Otherwise, you have volatility, and you cannot do something on the long term. I think with the general trend of the fighting against climate change and the event of the last months in North America and Europe will hopefully put long-term policy on carbon pricing too. That's my view.
That's very helpful color. Maybe just on the corporate PPAs and a bit of flavor around that. Are you having conversations with a greater number of corporates, or is it really the current roster of corporate clients that you have, but they want more power, they want larger PPAs and larger engagements with you?
Yeah. Today, the demand, and I said that three months ago before the increase of the price of the gas and the carbon, the demand was already higher than the offer some months ago. The trend is there, and we are discussing with different corporation. We have made a segmentation of the potential customers, because the price of electricity they have, the fact that they are or not in connection with the end customers, the fact that they have or not a real ESG plan. All this make a difference when you're speaking about the customer. We are discussing that, and I think I am quite optimistic about the fact that we will be able to build project with another counterpart in the future with a corporate PPA.
Okay. That's very helpful. Thank you.
Thank you.
Thank you.
Your next question comes from Justin Strong with Scotiabank. Please go ahead.
Thanks. Hi, guys. Just a quick question on tax equity in proposals in U.S. infrastructure bills, specifically around the portions that relate to direct payments and expanding eligibility to storage projects. Just wanted to get your outlook as to whether If you think these are going to make it into law and what the implications would do for Boralex and your development plans.
I'll just make one comment, and Patrick can then also add certainly to that. Certainly, it's hard to know, especially at this moment, to see how the progress will be made on whether it will make it into law or not. There's also other types of discussions on the tax equity side, which could result on other types of positive developments, such as tax credits, direct tax credits, as opposed to going to or needing a partner. I think there's quite a few evolutions, but timing and certainty from our position is very hard to call.
I think it's wise, Bruno, to say it like this. Globally, it's interesting for us today if there is direct payments, because we don't have a big tax exposure in the U.S. We need to have confirmation and see how it works in the model, really, in the Excel file.
Great. Thanks. Patrick.
Thank you. Your next question comes from Vivek Punjabi with National Bank. Please go ahead.
Hi, this is Vivek on behalf of Rupert.
Could you comment on inflation and power prices and any benefits you may be seeing from higher power prices?
Yes, sure. There are two things. The first is on the existing assets. It depends on the contract, but we have inflation clause, which range from 10% in some solar plant in France to 60% with I cannot give you exactly the weighted average inflation clause, but this is in the range, and globally, it protects us from increase of the cost. Sometimes it could be positive because the costs are the percentage of the revenue is smaller than the percentage which is inflated. That's good news. This inflation, just to be clear, is not on power price. It's the power price for the contract, which is inflated on some external index, like API or sometimes some, how to say in English, a service and goods, specific service and goods basket.
On new project, as I mentioned on speaking about corporate PPAs, the inflation on power price is a good sign. It's a good sign for corporate PPAs, and it's a good sign also because the subsidies that is seen on existing project or new project through RFPs is seen smaller or sometimes negative. When you sign today a wind project at EUR 60 in France, and when the price is around EUR 90 to even EUR 100 sometimes during the day, EUR 60 during the night, then the subsidies is going from you to the state and not from the state to you. That's also good news in term of public finance and the view of our sector from the authorities.
Sure. Thank you for that color. Just one more question. With the Molitg-les-Bains project in France moving to construction, just wanted to know if there any pushback or challenge to the project we could see, given the previous attempt at construction.
Were you referring to Molitg-les-Bains project?
Yeah, you referred to Molitg-les-Bains, but I'm not sure I got your question.
Okay. I think we lost part of the question. Could you just repeat the question, please?
Sure. No problem. Just wanted to know you know...
....With the project moving to construction stage, is there any pushback or challenge you could see to the project, given the last time around there were some challenges?
I think every project in France is somewhere sensitive. This is a project which is in a forest that is in operation. It is not a protected forest. I don't see any more problem than generally we can have in project, and we will obviously take care of the relation with the community locally. Even if this project was long to develop, we have long, good relation with the municipality, and there was only nine people who were opposing the project, was helped by an association, the Conseil d'État which is based in Paris. It is not a local opposition. As in every project we are doing, we will continue to communicate with the municipality, with the mayors, and with the people to be sure that this goes the right way.
Sure. Thank you so much. I'll leave it at there.
Thank you. There are no further questions at this time. Mr. Milot, you may proceed.
Thank you, operator. Thank you, everyone for your attention. If you have any additional questions, you know how to reach me, so 514-213-1045. You can call me. You can text me. You can email me. I'll make sure I answer your question quickly. Our next conference call to announce third quarter results will be on Friday, November 12th. I hope you all remain healthy. Have a great day and great vacations for those like many of us who have not taken vacation yet and who are heading towards vacation. Thanks a lot. Have a good day.
Thank you.
Thank you.
Ladies and gentlemen, this concludes your conference call for today. We thank you participating and ask that you please disconnect your lines.