Hello, and thank you everybody for joining First Quantum's Capital Markets event. At First Quantum, there is never a dull moment, and today's event will be no different. We are very excited to have our extended team present today on the projects and initiatives that we are working on. Before I hand it over to Tristan, our Chief Operating Officer, there are a few items to mention. A copy of today's presentation can be found on our website. This event is also being recorded and a replay will be available. Our team presenting today is joining us from around the globe, and to keep things simple, we will have two Q&A sessions, one halfway through our presentation and a final one at the end.
If you would like to ask a question, please use the dial-in number that is provided in our press release dated December 15th, 2021, which can be found on our website. Tristan will also address recent developments with regards to Lonmin in his closing remarks, and we ask that questions on this topic wait until the second Q&A session. Finally, today's presentation may contain forward-looking statements, so I encourage you to review slide two of our presentation. As well, all dollar amounts mentioned today are in U.S. dollars unless otherwise noted. With that, I will hand it over to Tristan to start today's event. Tristan?
Thank you, Bonita. Good day, and welcome to First Quantum's Capital Markets Day. Today, I will start by describing the First Quantum culture and our approach to operations. I will then provide an overview of our 2021 production and the three-year guidance, which we released yesterday evening. Zenon Wozniak and John Gregory will then provide an update on our brownfield project portfolio and how we approach projects and studies. John and Zenon are both based in our Perth office, where much of First Quantum's technical expertise resides. John, who is responsible for mining and studies, and Zenon, who is responsible for projects, have been part of the core First Quantum team for almost 20 years and have many valuable lessons from this eventful period, which will be applied to our future projects.
John Dean, who is currently Assistant General Manager at Cobre Panamá and has been with the company for over 10 years, will then provide an overview of our two greenfield projects in Latin America, being Taca Taca and Haquira. We will then take some questions on those topics, and following a short break, Andrew Hester, who is Environmental Group Manager and leads our ESG efforts, and like John Dean, is based out of Panama, will talk through our approach to this area and provide more detail on our targets to reduce greenhouse gas emissions, which we released yesterday evening. Our CFO, Hannes Meyer, who has been with the company for 10 years, will then provide an overview on our approach to capital allocation and outline our new dividend policy before I wrap up.
We are very proud of First Quantum's 25-year history, where we have grown from a 10,000-ton per annum copper tailings processor in Zambia into the world's sixth-largest copper producer. In order to deliver this growth, we have constructed mines of all sizes in a broad range of conditions from the Arctic Circle to the extreme heat of the Sahara Desert, and also in high rainfall near the Equator. We have built and operated underground and open-pit mines across more than eight different countries, tackling a variety of technical challenges along this journey. The last 10 years, in particular, has been a period of significant change and growth for the company. We built and commissioned two of the last largest greenfield copper projects globally in Sentinel and Cobre Panamá. At Kansanshi, we constructed the newest large copper smelter outside of China.
In nickel, we have developed a very strong platform as we have largely built the Enterprise nickel project in Zambia, now awaiting mine startup, and we have ramped up the Ravensthorpe nickel mine in Australia. Looking forward, our strategy is clear. Beyond our immediate focus on reducing debt to efficient levels, we will continue to allocate capital to invest in our business in a disciplined manner. In the near term, we will focus on brownfield projects to increase our copper production to near 1 million tonnes per annum, whilst we carefully assess our opportunities for the next large greenfield development. We also see the need to make clear our approach in returning dividends to shareholders, which Hannes will touch upon later.
While today we wanted to focus on our future and the exciting times ahead, it is worth highlighting the business philosophy that has been core within First Quantum to date, and we believe will be key to our success in the future. First Quantum is recognized as a growth company, and we will continue to seek growth in a financially disciplined manner. To deliver this growth, we have taken on new challenges where others are unable or unwilling, whether through technical innovation or pioneering new jurisdictions. We are very aware, of course, of the challenges involved in developing new projects, and that every new mine is different and requires substantial effort and clear thinking in order to unlock and develop it successfully. Our proven track record is based on four pillars. One, we target economically attractive ore bodies.
Two, we then apply our strong in-house execution capabilities to develop these ore bodies. Three, after building the mines, we drive operational excellence to run them efficiently productively to optimize financial returns for the business. Four, where it is impactful on the ground, we apply technology and fresh thinking in a practical, hands-on way. This approach is guided by two basic principles, which are empowering our people and growing responsibly. Our people remain core to our business, and we are focused on retaining our unique culture. Empowering our people focuses on accountability, teamwork, mutual respect, and most importantly, a commitment to their health and safety. We are investing in the development of current and future capabilities of the people in our business, in particular amongst our national workforces.
We are focused on inclusivity to broaden our knowledge and skills and continuing to make First Quantum an interesting and motivating place to work. While we understand that profitability is the engine that drives the business, our future opportunities, and delivers value for shareholders, growing responsibly has always been core to First Quantum. Responsible growth includes being a leader in environmentally sound practices and socially responsible actions and partnerships. In each of the countries in which we operate, we focus on listening to and learning from the key stakeholders around us and engaging respectfully and ethically with the local community.
Building and operating a mine is about having a real positive impact in the countries and communities in which we operate, not because it's a box that needs to be ticked, but because we believe it's the right thing to do, and which will have lasting benefits long after the mine is closed. Further, we understand that respect for the environment, alongside a holistic approach to safety in the workplace, has always been at the heart of good, productive operations and good business. We pay close attention to reduce our impact on the environment and to improve our legacy. For example, through the many biodiversity programs around our operations, which Andrew will touch on later. This approach is also reflected in our commitment to reduce our greenhouse gas emissions, and Andrew will also discuss this later in the presentation.
As a preview, I am delighted to share that we have set a target to reduce both the absolute as well as the intensity of our Scope 1 and Scope 2 greenhouse gas emissions by 50% by 2030. We have identified tangible solutions to significantly reduce our emissions at Cobre Panamá over time and without significant incremental capital or operating costs to the business. This will strongly position First Quantum to deliver substantially lower greenhouse gas intensity copper production that is essential to meet the global challenges posed by climate change. At First Quantum, we see that increased supply of critical metals, such as copper and nickel, is required to meet the needs of the global transition from fuel-intensive energy systems to lower carbon alternatives, particularly in developed economies around the world.
Both copper and nickel are required in substantially higher volumes for new renewable energy infrastructure and electric vehicles compared to the requirements for thermal energy and conventional internal combustion engine cars. Further, in emerging economies, we see that continued upliftment of populations will entail ongoing demand for copper for construction of housing, industrial growth, and electrical infrastructure on a growing unit per capita basis. We see these as fundamental demand elements over the medium to longer term, even if the market will continue to have some level of uncertainty in the immediate short term as we emerge from the pandemic. A responsible approach to mining is the only acceptable solution in order to deliver new primary production of metals, without which we consider the global transition to a low-carbon economy will not be possible.
We see that the supply side of critical metals, including copper and nickel, will continue to be impacted by higher permitting and regulatory hurdles, and these will continue to push out project timelines and affect the certainty of new mine production on average. Nonetheless, at First Quantum, we believe we are well-placed to deliver the metals required for the global challenges of the 21st century. We absolutely recognize our need to extract metals in a way that continues to be cleaner and more environmentally responsible in order to be a partner of choice in new geographies. Our very competitive brownfield and greenfield pipeline that John and Zenon will outline later positions us to deliver the financially disciplined and responsible growth in copper and nickel supply which are so needed.
At First Quantum, we pride ourselves on an entrepreneurial culture focused on practical, real solutions to technical challenges, and this is achieved by empowering our people with the support and trust to get the job done. Our culture is outcome-driven, based on responsibility and accountability rather than a process-driven or bureaucratic approach. We operate a decentralized operating model with lean corporate offices, with much of the decision-making occurring at the local level where there's a good understanding of the reality on the ground. We believe this approach encourages creative problem-solving, with decisions being made efficiently. It sometimes means challenging accepted norms. Many of the key management have been with First Quantum for the majority of the company's 25-year history, and have been part of embedding this adaptable and entrepreneurial approach.
Continuity of strong leadership across the organization, alongside developing our personnel and growing the diversity inclusivity of our teams, will be a focus of the company into the future. An area where the First Quantum approach is best captured is in our approach to innovation and new technologies. We don't work through top-down corporate driven initiatives. Instead, we focus on implementing practical new approaches which address the real on-the-ground challenges that our mines face. We consider that our implementation of new technology and innovation will also drive continuous improvement in our impact on the environment and climate. We challenge our people to dream boldly and find another way, and in this, we apply both traditional and technology-led innovation.
On traditional innovation, trolley assist in-pit crushing and conveying, to which Zenon, John Gregory and Andrew Hester will speak to in more detail, is used at our existing operations and will be integrated in future brownfield and greenfield projects. As an example of traditional innovation, at Sentinel, we recently initiated a change in method of the haul road construction to the use of what is called a cape seal surface. This involved adapting a paving solution more typically used for highways and modifying its use by the heavy equipment in the mine, which has enabled a 40% reduction in road construction and ongoing maintenance costs. The increased speed of the fleet on this road improves productivity and reduces the intensity of emissions for each ton of copper we produce. This approach is an example of a practical on-the-ground innovation making a very real impact to our business.
We also work very closely with our suppliers to develop and be first movers in new technology. As an example of our willingness to prove up new technologies which can potentially change the game on productivity, profitability and environmental impact, we have worked with our suppliers at the Kansanshi smelter, where we have pioneered installation and successful commissioning of an ISACONVERT continuous converter. We expect this unit will be augmented with more automated matte handling capability in the near future, further making an old batch process into a continuous process with improved off-gas catcher. We are also excited about our technology-led innovations. As an example, here, Sentinel is using machine learning and artificial intelligence to optimize its blasting practices, in contrast to the traditional approach of using blast movement balls.
This has reduced our blast hand over time by 50% and given us the ability to iteratively improve accuracy for plotting ore and waste in broken rock. As we tackle the continuous optimization of our operations and the enhancement of our productivity and profitability, and also our environmental and climate impact, we will continue to apply this First Quantum approach to drive real practical improvements throughout our business. As we say inside the business, we have an insatiable appetite to improve. Yesterday evening, we released our 2021 production results. We are pleased to have met our copper production guidance, while gold production came in better than expected.
The company achieved its highest ever annual copper production of 816,000 tons, a 5% increase from 2020, attributable to record-breaking production at Cobre Panamá and the resilience of our other operations in dealing with the ongoing challenges brought about by COVID-19 over the last two years. Cobre Panamá's performance was very strong, exceeding initial 2021 guidance and achieving the top end of our revised guidance despite facing pandemic-related restrictions for the three quarters of the year. Sentinel achieved strong copper production of 233,000 tons of copper for the full year, despite a ball mill trunnion failure in Q1 last year and a lower grade profile relative to 2020.
Kansanshi achieved copper production of 202,000 tons of copper, 19,000 tons lower than 2020, reflecting the reduction in oxide ore and the ongoing challenge of the selective high ore grade methodology at Kansanshi in advance of approval of the S3 project. We also released our three-year guidance where we forecast continued production growth. Copper production guidance has been revised upwards for each of 2022 and 2023, and is expected to increase to 850,000-910,000 tons of copper in 2024. Nickel production, which was 17,000 tons in 2020, is forecast to grow to 40,000-50,000 tons by 2024.
Our C1 cost guidance for both copper and nickel have increased, reflecting recent inflationary pressures as well as movement in foreign exchange rates, particularly in Zambia. The all-in sustaining cost guidance also reflects higher royalties in Zambia related to copper prices, as well as an increase in sustainable capital expenditures. At this stage, our all-in sustaining cost guidance assumes no change in the royalty regime in Panama. Guidance on 2022 and 2023 capital expenditures has been increased to reflect inflationary and logistical pressures, in particular on project expenditure, as well as acceleration of existing projects and inclusion of new projects. Across the three years of guidance, approximately $700 million will be spent on the Kansanshi S3 project development, with the majority of the spend to occur over 2023 and 2024, although we have not yet approved the project.
Project capital over the guidance period now includes a Southeast Dome pit pre-stripping mining activities of $100 million. The Kansanshi S3 development capital expenditure over the full life of the project is expected to be approximately $900 million and includes the development and construction of the S3 process plant circuit and mining fleet acquisitions. The commencement of the S3 project will bring forward pre-strip mining activities of the Southeast Dome pit, which is expected to be a further approximately $350 million over five years to 2026. Approximately $450 million has been included in guidance for the 100 million tonnes per annum expansion at Cobre Panamá, including development of the Colina pit.
The 100 million tonne per annum project includes ball mill 6, secondary screening, process water works upgrades, crusher relocation, port modifications, and the concentrate shed expansion. New projects not previously included in guidance are the Enterprise Nickel Project, Guelb Moghrein's Cutback 4 in 2022, which will extend mine life by two years, as well as accommodation and facilities expenditure at Cobre Panamá over the three years. Guidance has also been increased for the acquisition of a fifth road shuttle and two additional haul trucks and port modifications at Cobre Panamá. The Las Cruces underground project has not yet been included in capital expenditure guidance. Much of the production growth outlined in our copper guidance is due to our brownfield projects, with the expansion of Cobre Panamá and Kansanshi S3 included in our outlook. Enterprise is also included in our nickel guidance for the first time.
Together with Las Cruces underground, our brownfield project portfolio has us on track to produce around 1 million tons per annum of copper. This brownfield project portfolio represents financially disciplined, low cost, low risk growth, which Zenon and John will highlight further in our presentations today. Our greenfield projects, Taca Taca and Haquira, as John will describe, provides further growth optionality. In many ways, the variety of these four brownfield projects reflects First Quantum's diverse skill set and experience, as well as the ongoing diversification of our business. The four projects span three continents, are a mix of both copper and nickel, and are both open pit and underground expansions. What they all have in common is that they leverage existing infrastructure, operating teams, existing permitting, and strong community relations. This reduces both the risk and capital intensity of these near term growth projects for us.
All four projects will be powered by renewable power and provide critical minerals in the form of copper and nickel for the global energy transition. I will now hand the presentation over to Zenon, who will cover the first of these projects, the expansion of Cobre Panamá. Before he does that, though, he will briefly describe our unique approach to project development at First Quantum.
Thank you, Tristan. One of the central principles with regard to how we execute projects is that we look to maximize our own in-house execution with limited dependence on external firms. Over the last 10-15 years in particular, we have moved more and more capabilities in-house, including having our own construction capability for each discipline. Ultimately, it is our view that developing and retaining a motivated and experienced project team that relies on our own capabilities is our preference. We believe this has a number of advantages, including the ability to approach project designs and construction in an efficient way, and that we can apply learnings in-house from each project as we go forward. We started moving toward this execution model from about 2005, after the original Kansanshi project was constructed largely in a conventional EPCM manner.
At that time, we could see firsthand the associated difficulties of productivity, contract cost claims, inability to amend priorities quickly, and that many of the lessons learned were lost when the EPCM firm moves on to the next project or its people move to another company. In addition, having the project team and commissioning team, both consisting of First Quantum employees, further facilitates smooth handovers of projects to operations, especially with operations personnel also being seconded into the commissioning team. Overall, we believe our approach has demonstrated to be cost and schedule effective and reduces the overall execution risk. Our approach to maximize in-house skills means that the same First Quantum team can move from project to project, taking all previous learnings with them.
On this slide, you can see that these learnings have allowed us to tackle a wide variety of projects, and more recently, many of the learnings from Sentinel were applied at Cobre Panamá. These learnings were principally associated with the challenges of designing, constructing, and commissioning large throughput mines. These continuous learnings can now once again be applied as we plan for S3 and Taca Taca, which have very similar mine designs and plant configurations. Cobre Panamá benefited from this approach, and it has been both very pleasing and very impressive to see the resulting strong operational performance since commercial production was declared. It is now one of the world's largest, lowest cost copper mines with many inherent benefits. It has new best-in-class mining equipment, is located near sea level, and is only 25 km from its own international shipping port.
There is a dedicated wholly owned pipeline to transport the concentrate to the port, further reducing our logistics costs. It is mined using a terrace mining approach and has a very low strip ratio of 1:1 during the overall life of mine, which is one of the lowest among world-class copper mines. The mine fleet includes the largest haul trucks in the world, the majority of which also have electric motors as part of our trolley assist approach, which reduces the diesel required by the fleet at the most energy intensive point of haulage, to which Andrew will discuss in more detail in his ESG presentation.
The plant is the single largest copper processing plant in the world, built in one single stage and includes three 28-MW SAG mills and five ball mills, with all mills and much of the other equipment being among the largest available in the industry. It also has access to competitive labor markets and a skilled Panamanian workforce. Given all these inherent benefits and very strong project economics, it was an easy decision to expand the processing facility from 85 million tons per annum to 100 million tons per annum throughput. This expansion project is now well underway and will eventually take annual copper production at Cobre Panamá to over 400,000 tons per annum.
The original construction of the 85 million tonnes per annum project included significant foresight and flexibility to enable future expansion, including having a conveying circuit which could already deliver 100 million tonnes per annum of ore and a flotation circuit capable of treating that throughput. Works were undertaken to enable relatively simple expansion for other plant areas, most notably milling for additional future ball mills. The expansion of Cobre Panamá to a 100 million tonnes per annum is made up of three principal scope areas. The first is an upgrade to the plant process water system to provide the additional water required to meet the higher throughput rates. The water upgrade is principally an additional large pipeline of 2 m in diameter, bringing more water back from the tailings storage facility decant area.
This addresses the additional water requirements for the throughput increase, and secondly, it will reduce reliance on return of pit water to support operations. The second part of the 100 million tonnes per annum expansion is the installation of a second ball mill into Milling Train Three. Currently, Milling Trains One and Two each consist of three mills, a SAG mill and two associated ball mills. Milling Train Three, on the other hand, currently has a SAG mill and only a single ball mill, and the expansion will provide a second ball mill into this milling circuit, hence making all three milling trains identical. The picture on this slide shows the progress to date on the second ball mill for Milling Train Three.
The third part of the expansion project is a new screening facility which will receive primary crushed ore and will separate fines to a size which can report directly to milling, with only the separated larger size material to be presented to the existing secondary crushers, which will allow for very efficient crushing. This circuit will also complement our ongoing blast optimization efforts. Part of this screening work will also include the addition of two new bypass bins and feeders into the existing secondary crushing circuit, which will allow 100% of the plant feed to bypass secondary crushing if required, hence providing additional operational and maintenance flexibility. All of the Cobre Panamá 100 million tonnes per annum expansion works are scheduled to be completed in Q1 2023 so that the mine will be operating at a 100 million tonnes per annum rate from 2024.
In terms of other side projects at Cobre Panamá, we plan to construct the molybdenum plant in 2023 once the 100 million tonne per annum expansion project is complete. The moly plant is already designed and delivered to site. The concrete has been poured and the equipment simply needs to be installed. At a 100 million tonne per annum throughput, we expect to produce around 3,000-4,000 tonnes of moly in concentrate. The payable percentage is expected to be around 80% at a concentrate grade of approximately 50%. This will have a positive impact on our Cobre Panamá C1 costs of around $0.05 per pound at current moly prices. In terms of infrastructure, the existing shipping port is adequate for the expanded production volumes and logistics. However, we plan to expand the concentrate storage shed for additional buffer capacity.
We are also examining upgrades to the loading terminal to allow for larger vessels and for easier vessel handling. In terms of power, we have now secured the additional 60-80 MW of power required for the 100 million tonne per annum increment. This will be renewable power sourced from the Panamanian grid, which Andrew will describe in more detail later in the presentation. In terms of supporting infrastructure, the COVID pandemic highlighted the need to continue to invest in our people, and as such, we will be building additional housing for our employees at site. One of the real benefits that we had in managing the travel challenges posed by COVID was that wherever possible, First Quantum's approach is to have personnel residential rather than a fly-in, fly-out expat workforce.
It is therefore important for us to make sure the living conditions and recreation facilities at site help with the attraction and retention of staff. With this in mind, we are planning on investing around $100 million over five years in new facilities and accommodation upgrades at Cobre Panamá, all of which is included in our capital guidance released yesterday. This slide shows our tailings facility, and it has been pleasing to see the recent progress, which has it well-positioned to handle the increase in tailings volumes due to the expansion. The TSF has progressed from the initial starter wall design, which linked a number of small valleys to create a tailings impoundment, through to the commissioning of the sand preparation and placement systems, which are required for ongoing construction of TSF walls throughout the life of the operation.
This necessitated going through the demanding early period of raising and linking together the multiple starter walls with the sand to create continuous embankments on the north and east sides of the TSF. These two embankments will continue to be raised as required to manage process plant production levels. Planned future levels of process plant production are managed utilizing just 2/3 of the available sand preparation facility, leaving significant spare sand production capacity available. On the mining side, this slide shows the pit development over the mine life of Cobre Panamá. The Botija pit is now well established, and work is currently underway to develop the Colina pit so that Cobre Panamá has the flexibility of mining from two pits when its throughput expands to 100 million tonnes per annum.
Based on work completed on resource drilling and project planning, redesign of the pits has resulted in merging of the Medio and Colina pit and waste dumps. In 2021, we completed the diamond drilling program at the Colina pit and placed over 10 million tonnes of fill in the corridor, which will be used for the overland conveyor that will service Colina. We also cleared the access roads for the project area at Colina and began work on the in-pit crusher box cut. The development of the Colina mine will continue through 2022 and 2023, with initial ore feed commencing in 2024. The mining techniques and production strategy will be the same as employed at Botija, and both mines will be worked simultaneously from 2025 onwards.
An update of the sequencing and production profile for Cobre Panamá, together with an increased resource and reserve, will be included in a new NI 43-101 technical report, which will be released later this year. Ramping up Cobre Panamá during the pandemic was not a small endeavor, and as one of the largest new mines opened anywhere in the last 10 years, we are very proud of what we have accomplished at our newest operation. Cobre Panamá was always built with an expansion in mind. This expansion is now well underway, with construction already around 35% complete. We expect this expansion to cost $450 million in the guidance period. We are very excited about this next phase of growth for the operation that will add another 50,000-60,000 tonnes of annual copper production at our cornerstone asset.
I will now hand it over to John Gregory to discuss S3 and Enterprise.
Well, thanks very much, Zenon. Before getting into our Zambian projects, I wanted to take a moment to outline the First Quantum approach to the development of studies and how we design our projects. Our approach emphasizes flexibility and avoids rigid assumptions, where the design of the project, usually the processing facilities, are defined and locked in at an early stage of development. Such flexibility allows us time to think and better interpret and create the scope and scale, because we can learn about the region, the communities, the ore bodies, and better understand the variables that will be encountered during the development and design of a new mining project.
In our view, it's quite different from a typical engineering style EPCM feasibility study that attempts to exhaustively quantify every aspect of the operation at a very early stage, and usually results in providing false comfort, ignores non-engineering parameters, which adds to the risk of the project, both in terms of time and cost, as the rationale behind the various assumptions that are typically unknown and result in flaws and errors that are often only discovered too late. A First Quantum study is a concise document that outlines how the operation will be developed and subsequently worked, and is based on a few golden rules. First, we walk the ground, we listen, and we understand the local context. Secondly, understand the geology, the geometallurgy, the geotechnical characteristics of the ore zone and its geological settings.
Establish the mining method and decide the production parameters and profiles and their likely outcomes. In parallel to this, it's critical to understand the needs and concerns of the communities and the local authorities. In essence, we scope the project. There is limited engineering design undertaken until the ore body and production profile is well understood. Our view of that is there is a danger in being too quantitative too early. Also, the initial focus needs to pay attention to numerous soft issues, including logistics, accommodation, industrial relations. Our focus then turns to the processing and infrastructure needs of the project. At the core of our strategic development thinking, we look to keep an open mind, cast a broad net over key aspects, identify what we know, and more importantly, what we don't know, and concentrate on simple, practical solutions.
Let me now turn to Kansanshi and the S3 expansion. The Kansanshi mine has been the cornerstone asset for First Quantum for 15 years, and the remarkable nature of the ore body means that we expect it to continue to be a key part of our business in the decades ahead. The approach to how we study and build projects, as Zen and I have outlined, has been critical to the success of Kansanshi. The ore body is complex, and the Kansanshi processing plant was designed to operate with a high degree of flexibility to suit the various ore types. The current three main process routes independently treat sulfide ore, what we call mixed ore, which is transitional, and oxide ores. Kansanshi began operations in 2004 with a 4 million tons per annum oxide circuit and a 2 million tons per annum sulfide circuit.
These facilities have been incrementally expanded through significant plant upgrade over the years, and now Kansanshi has a capacity of over 28 million tons per annum, comprising 7 million ton oxide circuit, 8 million mixed circuit, and 15 million tons for the sulfide circuit. As the Kansanshi mines expand wider, deeper and longer, the near-surface high-grade oxide decreases. However, the volume of the sulfide ores increases with depth. To set the mine up for the next 20 years of production and to take full advantage of the vast sulfide ore reserves, the mine will transition from the current more selective high-grade medium scale operation to a medium grade, much larger scale mining operation. This expansion, which we refer to as S3, will involve a new larger mining fleet, a standalone 25 million ton per annum processing.
Low-cost, high-grade nickel sulfide project, and is very well positioned to benefit from the projected growth in the battery metals demand. When we built Sentinel, we also wanted to maximize our opportunities in the nickel space. On this slide, you can see that the Enterprise 4 million ton per annum circuit was largely constructed when we built the Sentinel processing complex. Interestingly, the rougher and cleaner flotation cells within the nickel circuit were commissioned and utilized temporarily to process copper ore during the early days at Sentinel. Also, at the same time of construction, the upper portions of the proposed Enterprise starter pit were exposed to test pit wall stability and understand the hydrogeology. As we now turn our attention to the startup of Enterprise, this initial pre-strip has allowed recent opportunities for confirmatory drilling, geotechnical and hydrogeological investigations, and further metallurgical test work.
The Enterprise mine will consist of a single main open pit and one extension to the southwest. The nickel mineralization occurs mainly as sulfide disseminations and veinlets. The pit will be mined using conventional drill and blast, excavator and truck mining methods, adopting 5 m high ore and waste benches. Under full scale operations, ore and waste will be loaded by 250-ton excavators and 100-ton trucks, which are a significantly smaller fleet compared to the ultra- class fleet at Sentinel. Waste will be hauled to external dumps located to the north and the east of the pit, and the ore to the surface ROM pad on the south side of the pit before being hauled by road to the nickel circuit located at Sentinel.
Once crushed, the ore will be milled in a SAG ball milling circuit incorporating pebble crushing, which as mentioned, are all currently installed. The product will then be floated in a circuit comprising talc pre-float, followed by Nickel rougher flotation, and three stages of cleaning. Once thickened and filtered, product will be stored in a dedicated stand-alone nickel concentrate handling facility. This is also being constructed. Tailings will then be pumped to existing thickeners and then on to the Sentinel tailings storage facility. Current test work indicates recovery rates of 85% for primary sulfide and 60% for non-primary sulfide, and provides a final concentrate grade range between 14%-16% nickel. Our nickel concentrate will be transported by truck to the port at Walvis Bay in Namibia or some other South African ports that First Quantum are all very familiar with.
From where it'll be exported by ocean freight to off-takers that include major nickel smelting operations in Canada, Europe, and China. Considering this high value product that comprises low levels of co-payable metals, deleterious components, and with exceptionally low magnesium oxide, hydrometallurgical refining operators will also likely be interested. There has been strong indicative interest for most of the major nickel smelting and refining companies due to the quantity and grade of this high-quality product. Considering that Enterprise nickel concentrate can be treated via the conventional smelter route or via hydrometallurgical refining, it means that Enterprise Nickel is well-positioned in that it can be supplied via several routes into most metal markets, including stainless steel and the electric vehicle and battery metal markets.
During 2021, work on Enterprise saw the completion of an RC drilling campaign, which targeted the improvement of the upper parts of the geological model and provide samples for further confirmatory geometallurgical test work. We also completed the development of the surface water control dams, installation of the water treatment facilities, and in-pit water pumping and pipelines, as well as completing the power line extension from Sentinel to Enterprise. Subject to board approval, the main work stream to bring Enterprise online will be the pre-strip of waste. This is expected to take 12 months. In parallel, mine facilities will be installed, including the satellite administration office, workshop, fuel storage, and other facilities. The ROM pad will be constructed and the haul road will be upgraded. Plant refurbishment, completion, and commissioning will also be undertaken during this period.
These works are estimated to cost $60 million and are included in our guidance as released yesterday. The business case for Enterprise Project is compelling. With most of the process plant built and therefore has little exposure to current inflationary parameters, and the remaining capital spend largely targeting stripping. It will also benefit from the existing infrastructure and skilled workforce at the Sentinel mine. Once Enterprise is operational, it is expected to produce an annual average of 30,000 tons of nickel in concentrate per annum. There is an added benefit to Enterprise, and the operation has the ability to target higher grade portions of the ore body, hence increasing production should the nickel price spike at any time during the life of mine. The 30,000 tons of nickel will place Enterprise as a top 10 nickel sulfide producer.
Together with our Ravensthorpe Nickel Mine, which we will continue to ramp up following the completion of the Shoemaker-Levy project in quarter four last year, First Quantum is expected to become a top 10 global nickel producer. I would now like to hand back to Zenon, who will provide an overview of our fourth greenfields project, the Las Cruces Underground Project.
Thanks, John. At our Las Cruces mine in Spain, we completed mining of the open pit in 2020 and moved on to reprocessing high-grade tailings in 2021, which will continue into 2023. This retreatment project has the benefit of not only producing some low-cost copper, but more importantly, keeping the existing team in place as we advance work on the Las Cruces underground project. This project will involve supplementing the existing copper facilities at Las Cruces with new processing capacity for zinc, silver, and lead. These new facilities are required as the underground project will mine the polymetallic primary sulfide ore body, which is below the now mined out secondary copper sulfide ore body. The Las Cruces underground project has several notable benefits. There is a highly skilled existing team in place that has learned key lessons while operating the open pit phase of the project.
In fact, many of the leadership team at Las Cruces have worked there since its original commissioning in 2007. Secondly, the project will be a very low carbon emitter. Power is expected to be purchased under PPA from solar projects and steam by biomass. Because it will produce cathode, Scope 3 emissions will be minimal. This, combined with the EU's current focus on supply chain security for transition metals, is one of the key reasons that the project has received strong local and federal government support. In addition, the mine will be using the innovative Railveyor system, an electrical hauling system taking ore directly to the plant crusher, further reducing emissions. The project benefits from significant existing infrastructure at Las Cruces. The project will leverage the existing Las Cruces process plant, which will be used for copper and zinc leaching, copper recovery, and effluent treatment.
This represents over $800 million of invested capital, which will be used by this project. Critically, there is also 5 million tons of primary ore stockpiles which were mined as part of the open pit mine. This means the underground mine already has two years' worth of production already mined. The project also has a strong license to operate. All environmental permits and the mining permit for the project have been received. The key pending authorizations are those related to water management, which are expected to be granted in 2022. Las Cruces also has strong relationships with the surrounding communities, given the strong ESG focus that the mine has operated with for more than a decade.
More broadly, as many mining tax regimes are under pressure in various parts of the world and stakeholder management becomes an increasing focus, Spain has proven to be a good place to operate from both a local community and government perspective. The project benefits from the significant metallurgical test work conducted to date. This began in 2014 and lasted five years. On this slide is a picture of the 24-ton per day pilot plant, which we refer to as the polymetallurgical refinery, or PMR, that was built in 2016 to validate the chosen process flow sheet. This will consist of grinding, bulk flotation, copper and zinc sulfate leaching, silver and lead chloride leaching, silver recovery, and lead recovery. The PMR technology, which uses silver present in the ore body as a catalyst in the process, makes it possible to obtain higher recoveries and payables from sulfide ores.
It may also be possible to recover metals from ore bodies that currently are not profitable or from streams which are at present discarded as tails in the conventional flotation processing plants at the other mines in the Iberian Pyrite Belt. We conducted a drilling campaign in 2021 at Las Cruces and released the first NI 43-101 resource on the primary sulfide ore body yesterday evening. The total measured and indicated resource tonnage is 36.3 million tons with a 2.5% copper equivalent grade and remains open at depth and to the northeast. It is worth noting that on a copper equivalent basis, contained copper is approximately 900,000 tons, similar in scale to the original open pit ore body. A long-hole open stope mining approach will be used with access via a twin decline.
Expected production from the underground mine is in the region of 2 million tons per annum. Indicative capital of the project would be in the region of $600 million for a three- to four-year construction to produce around 45,000 tons per annum of copper equivalent production. These estimates are still at an early stage and require additional work as the project design is refined. Work in 2022 will focus on advancing the design of the underground mine and the plant, obtaining the water concession, and release of an initial reserve. Given the work still required, the project is not included in our guidance, but we are hopeful that 2022 can be the year where technical and permitting work is completed for this project, which would position it well for 2023.
I will now hand over to John Dean, who will talk through our two greenfield projects, Taca Taca and Haquira.
Thank you, Zenon. While our current focus in terms of capital allocation is on brownfield projects, we continue to work on our longer term growth projects, namely the Taca Taca and Haquira projects. Taca Taca is the more advanced of the two projects and is one of the largest, highest quality copper projects globally. It will consist of a large open pit copper mine and ore processing plant to produce up to 275,000 tons per year of copper, along with gold and molybdenum byproducts. With an initial mine life of 32 years and a larger resource base and C1 costs of less than $1.40 per pound, Taca Taca is both long life and low cost. The project is located in the Salta province of Argentina, and Salta in particular is increasingly seen as a key jurisdiction for mining investment.
In the Fraser Institute's 2020 annual survey of mining and exploration companies, Salta was ranked 23rd in the investment attractiveness index, placing it ahead of all other provinces in Argentina and making it a leading jurisdiction in Latin America. From an investment perspective, Taca Taca offers an attractive early grade profile with average copper grade of 0.63% for the first 10 years, along with gold and molybdenum byproducts. The slide here shows the production profile as per the NI 43-101 report published in March last year. The project also benefits from relatively low capital intensity with an expected capital cost of $3.6 billion. The project design and execution will be de-risked through building on First Quantum's experiences and lessons learned on previous projects.
The two parallel milling circuits at Taca Taca, for example, will be the sixth and seventh similar circuits built and installed by First Quantum following on from our experiences at Sentinel and Cobre Panamá. In addition to sharing mill sizes and configurations, Taca Taca will also use similar electric-powered ultra-class mining fleet and electric trolley assist. The project is located in a remote, uninhabited area at 3,500 m above sea level, and the site benefits from a relatively neutral environmental and social framework with no current productive land uses, limited precipitation, sparse vegetation and wildlife, and no settlements within 35 km of the site. In addition to the mining and processing facilities, the project also incorporates waste rock and tailings storage facilities, a new electrical transmission line of 125 km, and water supply from regional bore fields.
Project infrastructure also includes a new access road and rehabilitation and upgrades to the existing railway line that runs between Taca Taca and the Chilean ports near Antofagasta. Several important features have been incorporated in the project design for improved safety and environmental protection. Following a detailed analysis of alternatives, new and safer locations were selected for tailings and waste rock storage facilities. These facilities will be placed on flat areas at the lowest elevation in an evaporative basin with no downgradient landforms, no communities, minimal flora and fauna, and no contamination risk to any freshwater sources. The tailings storage facility incorporates a long life, low height, and low risk embankment, and a curtain of boreholes around the waste rock facilities and tailings embankment will provide regular monitoring and potential abstraction of hypersaline water for use in the mine.
Given Argentina's rich endowment of solar and wind energy sources, options are available to source up to 100% of the project's electricity needs from renewables or from a combination of renewables and Argentine natural gas. Greenhouse emissions will be further reduced through application of First Quantum's industry-leading electric trolley assist for haul trucks. Water for the project will be sourced from multiple regional bore fields to ensure sustainable abstraction with increased aquifer storage, precipitation, and recharge capacities. These bore fields are hydrologically separate from community water sources. These factors, together with First Quantum's high standards for safety and environmental protection, which Andrew will discuss in more detail later, position Taca Taca to be a leader for the next generation of sustainable and responsible copper projects. In terms of permitting, the primary approval required for the development of Taca Taca is the Project Environmental Impact Assessment.
This application was submitted in 2019, and following engagement with the authorities, the company is providing additional details on geotechnical and geochemical aspects. Approval of the ESIA is now anticipated later this year. Two additional environmental permits were filed with the relevant authorities last year, including one for the transmission line to connect the project to the national electrical grid, and another for the proposed bypass and access road construction for the project. The project will also require approval of a concession for bore field water supply. The company is completing additional water supply studies and field tests this year in advance of this permit application. This work includes drilling and pump testing boreholes with subsequent bore field design, aquifer modeling, and simulation of long-term pumping.
A program of sterilization drilling of the deposit and extensions is also planned this year to assist with definition of pit limits and site layouts for facilities. Beyond permitting, the main area of focus is engaging with government to put in place a fair and predictable administrative and fiscal regime for the mine. Key topics that the company and the broader mining industry are looking for regarding the investment case in Argentina include export taxes, foreign exchange restrictions, VAT, and fiscal stability. The industry and government are working towards a win-win solution to these aspects to complement the generally robust legal framework for the industry provided by the Argentine Mining Code and the Mining Investment Law. There is certainly a growing appreciation that Taca Taca and other copper development projects could play a vital role in driving economic recovery in Argentina if the right conditions for investment can be established.
That said, we have committed to not make any decisions on Taca Taca until 2023 or 2024 as we focus on de-leveraging our balance sheet. This gives us the time to establish the right conditions for investment in this project prior to making any large capital outlays. As Tristan outlined, First Quantum's commitment at Taca Taca and globally is to work in partnership with host governments and community stakeholders to ensure the operations provide a broad range of economic and societal benefits while minimizing environmental impacts. Through this collaborative approach, Taca Taca is well-positioned to become an engine for social and economic prosperity in Argentina and a high-quality long-term operation for First Quantum. On to our longer-dated greenfield project, Haquira in Peru.
The M&I resource stands at 3.7 million tons of contained copper equivalent, plus an inferred resource of 2.4 million tons of copper equivalent. This would make Haquira comparable in size to Sentinel, and we remain optimistic about further potential of the ore body. Following a period of establishing environmental baseline monitoring processes, a program of 35,000 m of diamond drilling is planned to commence this year. Drilling is anticipated to continue for about two years, utilizing two to four drill rigs. The program will upgrade resource confidence and assist with mine planning and scheduling. The program also includes drilling possible extensions and near mine satellite targets. These targets include undrilled zones of mapped porphyry alteration and multi-element geochemical response consistent with the porphyry target footprint.
In parallel with drill planning and establishment of environmental baseline monitoring programs, a dialogue with community leaders at Haquira has been underway for several months and will continue as drilling progresses. The concerns and issues raised during this community engagement process will be incorporated into an infrastructure layout plan that will focus on identifying mutually beneficial solutions to the coexistence of mining and local community activities. Although Haquira is located in a sensitive region in Peru from a community perspective, we will take the time to build the right relationships in the right way during the years ahead before any decision is required to invest significant capital in this project. Thanks. With that, I'm ready to hand it back over to you, Tristan.
Thank you, John. With that, we would be happy to take any questions on the topics that we have covered so far today in the presentation. During the second half of the event, we will cover ESG, including our greenhouse gas reduction targets and our plans for the power station at Cobre Panamá. We will also discuss the status of discussions with the government in Panama and in Zambia, and the implications for the projects there together with our new dividend policy. As such, we would appreciate if you could hold off questions on those areas until the second Q&A session. Operator, please can you open the line for questions?
Thank you very much. We will now take questions from the telephone lines. If you have a question and you are using a speakerphone, please lift your handset before making your selection. If you have a question, please press star one on the device's keypad. You may cancel at any time by pressing star two. Please press star one at this time if you have a question. There will be a brief pause while the participants register. We thank you for your patience. The first question is from Orest Wowkodaw from Scotiabank. Please go ahead. Your line is open.
Oh, hi. Good morning. Tristan, I'd love to get some color if we could on your guidance upgrades at Cobre Panamá. Specifically, you increased the guidance for 2023 relative to what you had issued a year prior. Obviously the 2024 guidance looks very strong. I'm just wondering if you can explain, I guess, what's changed there. Is it just more confidence in the throughput, or are you seeing upside to the grade? Any color would be appreciated.
Yeah. Thanks, Orest, and hi. Guidance for next year and for the coming years is really built around the platform that we've built and now having a year of continuous production underneath us, we believe we understand the mine plan there well. We do continue to drill around the neighborhood. In terms of delineation for Colina, we are continuing to find more mineralization. In terms of our confidence around throughput and grades in Botija is very strong. That's really. It's the level of confidence more than anything else. As we turn to 2023 and we get the additional installation of ball mill 6, the screening plant, and the process water upgrades, we will see processing capacity and some of that we will get through.
For example, we expect to get the third secondary crusher installed this year, and that will give us capacity this year. Really around the increasing confidence and understanding in Botija. John, would you add any further comments there?
Yeah. Tristan, I think the confidence is there certainly, and our ability to plan and identify our mining regions has improved. We certainly understand that better. Our reconciliation has been exceptionally positive, which has led us to modify some of the dilution and grade parameters that we'd previously used. All in all, the increase in copper is due to confidence, enhanced working areas and a better understanding of the grade profile.
Just following up on that, do you think this is a pervasive confidence? Like, you mentioned earlier that there's gonna be a new life of mine technical report coming out for Cobre Panamá later this year. Do you see potential upside life of mine, or is this specific to-
More detail around that CapEx.
Sure. Thanks, Tristan. Hi, Orest[Greg]. It's been a while.
It has been.
It'd be good to catch up one day. Anyway, good to chat and have some questions. Around that CapEx figure of the $450 million, there's three broad categories. Part of it is for process plant expansions. Part of it is for developing the Colina pit, and part of it is for additional fleet, mining fleet. As we said in one of the slides, we're well into construction, and you saw the pictures, probably about 35% complete in construction of the processing plant facilities. In terms of that, we've probably committed, just having a quick look at some numbers I've got in front of me, probably committed something in the order of about $125 million-$130 million of the $450.
There's some mining work ongoing as well, which maybe John Gregory would comment on. From the processing plant, probably about a third of that figure has been committed and about 35% progress.
On the $450 million, the bulk of that will be this year, I assume, if you're gonna ramp up starting early next year.
Correct. There's still work going into Colina next year, but the bulk of the process plant, which is one of the three portions of the $450, the bulk of that will be this year and early next year, 'cause not all the invoices get paid this year, for example. You get some tail going into next year. Colina will continue to be developed next year as well, and taking that overland conveyor, et cetera, into Colina, more of that would be next year.
Okay. Thanks, Zenon. Maybe I'll turn to John Gregory. On the S3 expansion, it's basically the same question. Just trying to understand how the CapEx flows over the next two or three years of the $900 million, including the pre-strip of the Southeast Dome. One place it says $100 million for that, and then another place it says $350 million. I'm just trying to reconcile all of that so I have a better understanding of how the CapEx slots in over the next several years.
Okay. Hi, Orest[Greg]. Okay. For S3, if we take our position now, we'd be looking at the majority of the infrastructure and the processing facilities. The spend for that would be in 2023 and 2024, with commissioning at the end of 2024, so that come 2025, we have full capacity. The mining fleet needs to be expanded, and we're currently looking at options on that. We would need to make initial commitments later on this year. Delivery timelines are much the focus on that. But as I mentioned, we would have a startup utilizing surface stockpiles, medium-grade sulfide feed, which actually reduces the quantum of the pre-strip required for the full S3 itself.
In terms of the capital numbers, the pre-strip, the larger figure that you mentioned refers to the five-year outlook, whereas the $100 million refers to the guidance period that we're referring to at the moment.
Yeah, Greg, that's the same-
The $900 million, John, is that-
The same for the $900. The $900 is across the four years and the $700 is across the guidance period.
Okay, I'll pass it on. Thank you.
Thank you. The next question is from Jackie Przybylowski from BMO Capital Markets. Please go ahead. Your line is open.
Thank you very much. Thanks everybody for doing this. I really appreciate it. It's been great so far. My question is on the Las Cruces underground project. I guess I just wanted to ask what your thought process was for not including that in the guidance so far. I know you mentioned you've been working on this since 2016, and I think I went to visit the site around then. I remember it was already pretty well contemplated, at least at the point of that site visit.
I recognize, I mean, the permits aren't all in, and you still have some work to do, but it doesn't seem to me, at least, from the outside, to be any less risky or more risky than the projects that you've got at you know, Kansanshi, S3, Enterprise and the Cobre Panamá expansion. Why not include Las Cruces in the guidance but include those other ones? Can you give me maybe just a thought on that? I guess as a follow-up, are you planning to put that in the guidance for next year, like 12 months from now, or is that something that you could issue sort of a mid-year update on things?
Thanks, Jackie, and hi. The principal answer there is it's we don't consider it's quite ready for that decision from the board. Whereas the other projects are really at that phase where it could go to the board immediately for a decision. That's really the reason. Las Cruces, we like the project, and we spoke about the level of certainty around permitting and the environment around there. The workforce there is certainly very strong and extremely capable. What we would like to see is over the next 12 months that we build particular understanding in the mine planning, and John could comment there a little bit more.
It's really around getting to the ore body, through the declines, and establishing in that. That's always, you know, that transition from open cut to underground is important. It's important that it's given the consideration that it needs. Otherwise, you're right. You know, it's a good environment for the project. The capital intensity there, we have been watching, and so it is closely linked to copper price and the market forecast for that, and closely linked to the exchange rate for the euro. Those are very important considerations for Spain. Otherwise, there's a lot going for the project. John, you might just comment more a little bit on the mining side of things.
Hi, Jackie. Look, one of the reasons that we've issued the mineral resource technical report is that we're not in a position to actually define the reserve at this stage. We're getting very close, and it is to do with the underground mine scope, the development. Hydrogeology is one area, geotechnical. We're running a whole series of assessments at the moment. I think once we do have something that we can define as a reserve, we will have a cost profile, both in terms of capital and operating. Once that is determined, then we would be looking at updating the technical report. Plus then it becomes closer, as Tristan has said, to coming into our guidance profile.
Jackie, I think the other comment we would make overall is, you know, a project of this scale requires just as much effort as does, say, the brownfield expansion at Cobre Panamá in terms of engineering effort and it's very important that we give it the full commitment and the full application of people's attention. We're also cognizant of making sure that we stack it in the right sequence among the brownfield projects so that it gets the full attention it deserves.
That makes sense. Thank you, Tristan. Thanks, John. I appreciate that.
Thank you. The next question is from Lawson Winder from Bank of America Securities. Please go ahead. Your line is open.
Hi, everybody. Excellent update, and thank you so much for this. Maybe where I'd like to start is on Kansanshi. It just seemed to me that the 2024 gold production was lower than the feasibility study. That's all well and good, but just to what extent might that persist, or should we expect things to return back to what was forecast in the latest feasibility study?
Thanks, Lawson. John, are you happy to take that question?
Yeah, sure. Look, Lawson, I think one of the things that we are experiencing at Kansanshi is that we might have predicted certain areas that we would be mining and certain cutback sequence that we've had to amend for various reasons to balance our material feed into each of the processing circuits. As that happens, our gold profile can sometimes vary. What we're seeing is that before S3 comes online, the mining sequence does get more complex, and it is tighter than once S3 comes online, we will see those issues resolved, and we would expect to get back to a more standard profile, certainly of our gold, but definitely of our copper.
Thanks so much, John. Another question on Taca Taca. Excellent presentation on that particular asset. I was interested to see that, you know, 2023 is now a possible decision point. Maybe it would be helpful just to get an idea of, like, you know, how early in 2023 could you potentially be in a position? I assume the receipt of the ESIA would be part of that. And then also if you could maybe discuss work that's been done at sort of the federal level in terms of, you know, the export tax that's in place. There was a repatriation tax. I believe that might have actually been recently addressed, but just any comments you could provide with respect to that would be super helpful.
Sure, Lawson. Thanks. Yeah, look, the work program for this year is to be on the ground in Argentina and to give this the effort that's needed. Certainly building towards a decision, I wouldn't expect it, you know, until late 2023 or into 2024. John, you might comment some more on the detail and the effort that we plan to put in there at Taca Taca.
Sure. Thanks, Tristan and Lawson. I think that's right, Lawson. There's still a piece of work there with the government to get comfortable with the, you know, fiscal stability picture in Argentina, and we're really just focused on that work for the rest of 2022 and going into 2023. That's a joint effort really at the industry level. We're engaging both directly with senior government officials at the federal level, but also in the provincial level. Also jointly, you know, with other pre-development project developers to really emphasize the key issues there and the key things that the industry needs to see to get comfortable with major capital investment in Argentina.
Those things really revolve around VAT recovery during the construction phase being one of them. The export duty that's in place in Argentina is a topic of concern and the foreign exchange restrictions and ultimately really getting comfortable with fiscal stability there. There's a strong platform in the Mining Investment Law in Argentina.
Yeah. Thanks for your comments on that, John. I think just one final thing. I'd make a comment and attempt to ask a question. I'd say, you know, congratulations for, you know, we can-
It's just we're only partially covered by that.
Okay. Thanks very much, John. One final comment from me. I'd just like to extend a congratulations on what seems to be a you know concluded fiscal arrangement with Cobre Panamá. I'm not sure if now is the right time to ask the question, but do you just have any sense of when you know that could be finalized and when an effective date might be?
Thanks, Lawson. Thanks for those comments. We were going to push those questions on Law 9 and Panama to the second session of Q&A, only because we will give some comments and so on, and then invite questions at that time, if that's okay.
Yeah. No, that's totally fair. Congratulations on getting that, what seems to be concluded.
Thanks.
Thank you. The next question is from Ioannis Masvoulas from Morgan Stanley. Please go ahead. Your line is open.
Yes, hello. Thanks for the presentation, and a few questions left from my side. The first two questions on CapEx. It would seem that you could start spending at Las Cruces over the next one to two years. If we look at your business planning, is there any ceiling to your annual CapEx budget till you hit your leverage target? Or is it completely driven by growth opportunities in the next couple of years? Related to that, from the discussion in the presentation today, it seems that a number of capital equipment orders are yet to be placed across the different projects, whether it's related to fleet or other orders. Is your CapEx guidance reflective of these risks today?
Is there a risk that we could see some further inflation as you lock in some of these contracts over the next 12-18 months? Thank you.
Thanks, Ioannis. So we're going to give a lot more information around capital allocation and so on in the second half. Certainly on the CapEx side and speaking of Las Cruces, the answer is that we don't see any major impediments in terms of the financial disciplines of the company for Las Cruces. Again, we'll give some more greater clarity in the next section. In terms of the order book, Zenon, you might just comment on some of the major equipment items that we have in place, what you're seeing in the market in terms of lead times and also our positioning there, because I think it is a relevant question. Thanks.
Yes, no problem. It is a very relevant question. Look, we've placed a lot of equipment orders. Some of our projects are in commissioning. For example, Sentinel In-Pit Crusher 4 is being commissioned at the moment. Some of the other projects, like the expansion at Cobre Panamá, which we said is about 35% complete. A lot of that equipment has been ordered and is now queued up for delivery or being delivered during this year, with this year being a strong construction year. We continually go and update our figures because there has been quite a lot of inflationary pressure which you would've seen over the last one to two years. Copper's gone up, which is great. Steel has gone up, freight has gone up. There's been a lot of areas where there has been cost pressures.
What we have tabled now is our updated estimates. In terms of risk going forward, nothing significant in terms of equipment ordering, 'cause as I say, a lot of that has been done. For something that hasn't commenced yet, for example, if we were to talk about an S3 or something like that, we've updated all of our CapEx for current pricing and for current freight rates, et cetera, with some contingency and buffer. We think they're up to date, and we don't believe that there's a serious risk. As I say, a lot of the equipment for what's in play at the moment has been ordered, and certainly all the major equipment that's long lead, that's definitely been ordered.
Okay. Great. That's very helpful, thank you. Maybe one more question on Ravensthorpe. Could you provide an update here? I mean, the guidance for 2022 suggests a significant step up in production and far lower unit costs than what we saw in 2021. Leaving a tough year behind you, how confident are you in the guidance and especially around asset prices and throughput rates? If you could give us a bit of an update, what's going to be changing there, and how confident you are on the guidance. Thank you.
Thanks, Ioannis. I think the major change is certainly in the Q4 results that we'll put out in the near future give some clarity on Ravensthorpe in Q4. Certainly the big change is we have commissioned the limonite circuit in the process plant, and now going forward, all limonite into the process plant will come from Shoemaker-Levy. What we have seen is immediately that material went in, we've seen the expected improvements in grade, but also in materials handling. That's made a big difference to the circuit in terms of recoveries, in terms of the challenges we've had around handling material, that some of the previous stuff from Hale-Bopp was pretty sticky and claggy at times. That's had an immediate impact and hence the certainty around that.
Ahead of us is a lot of delineation drilling that has already been done, and we see those drill holes and we have that understanding of the pit in front of us in Shoemaker-Levy. There is good confidence that that continues on, and hence the guidance there. John, I'm not sure if you would add anything more there on the mine plan or Zenon on the progress. From here we expect you know to be certainly improving the situation after yeah what was a tough year at Ravensthorpe last year.
I can jump in.
For those that know Ravensthorpe, and quite a few of you do, by moving to Shoemaker-Levy, it does give us the opportunity now to treat that ore that we know a lot more about and the ability of this material that we have proven through test work and now production, the upgrade profile and mass recovery data is certainly much more improved than Hale-Bopp. It is actually right at the top end of our expectations. We're actually very buoyed about the whole Shoemaker-Levy process as it comes online. The mine will continue for the foreseeable future for its life of mine.
Hale-Bopp did provide us with a lot of challenge, and because of the various timelines of the development of Shoemaker-Levy, we ended up staying in Hale-Bopp longer than we anticipated. That also amplifies the improvement from 2021- 2022. Zenon?
Yeah, just look, I'll add just a couple of things 'cause I was talking to the guys at Ravensthorpe today. Shoemaker-Levy is a step change from the tail end of Hale-Bopp. The tail end of Hale-Bopp basically was very fine material, which was difficult to beneficiate and struggled to get density. Shoemaker-Levy is very different. Now the plant with the Shoemaker-Levy ore, the limonite ore, is now operating much more in its design criteria envelope. Good beneficiation, good densities and, you know, very, very positive and it's essentially seeing material that the plant was designed for, whereas I think the tail end of Hale-Bopp was just very, very difficult material that may have been to some extent outside of the design window of what Ravensthorpe was designed for.
Ioannis, you asked about the sulfur.[crosstalk]
Great. Thank you very much.
You asked about the sulfur price and just to comment there that, look, certainly, you know, as we've seen in the fertilizer industry, it is having an impact, you know, on fertilizer prices. It does have an impact at Ravensthorpe. We're thinking more strategically about that longer term, seeking longer term contracts, longer term offtake, and in a structure that we'd share with some major producers. That's something we're working on actively. Yeah, certainly the days of those very high sulfur prices, we'd like to get those behind us for sure.
Thank you.
Thank you. The next question is from Abhi Agarwal from Deutsche Bank. Please go ahead. Your line is open.
Yeah. Morning, team. Thanks a lot for your presentation. I have a couple of questions, please. The first question is a follow-up on the growth CapEx. Can you walk us through the split of growth CapEx for 2022, 2023 and 2024? How much of the growth CapEx is for Cobre Panamá through full expansion, Guelb Moghrein cutback, and S3 expansion? Thank you.
Hi, Abhi. Sure. CapEx for which year, sorry? 2022 or 2023, did you say?
For 2022 and 2023, please.
For both? I think we haven't provided a detailed breakdown between each of the sites, but what we have given is the major projects. We've given you what Cobre Panamá will be for the CP100 project, the $100 million upgrade at $450. Really that's the majority of the CapEx on the project side in 2022. The majority of the CapEx in 2023 and in 2024 is related to S3, and we've given you the total across for that project, which is $700 million for the main project works in the project capital side. Then in the stripping which is included in the project capital, there's around $100 million across the guidance period for S3.
Those were the major breakdowns we gave. Enterprise, we gave you the CapEx in 2022, and that's around $60 million. Guelb Moghrein is new capital that's been included, and that's around $15 million for the cutback there in 2022. Yeah, that's the main portions of project CapEx across the years.
Got it. Thank you. My second question is regarding the Taca Taca CapEx number, which we, I think we got from you in November 2020. Are you still okay with the CapEx guidance given back then, or do you think inflation could lead to a step up in the CapEx there?
Sure, Abhi. Look, it's a reasonably up-to-date estimate. We put out the 43-101 at the end of last year. No, we wouldn't address it at this time. Obviously, as we get closer to a commencement date, we will look at that more closely. It's reasonably up to date in terms of the forecasting that's gone there. John, I don't know whether you would add any more to that.
Yeah. That's right, Tristan. We're looking at $3.6 billion as the total development capital and still pretty comfortable with that number. I wouldn't add anything else to that.
Thank you very much.
Thank you. The next question is from Jatinder Goel from BNP Paribas. Please go ahead. Your line is open.
Thank you. Good afternoon and good morning. Two questions from my side. The first one, a strategic one. You mentioned about Salta Province, and you've been present in the region for a long time. It's more of a hotspot for lithium. Is that something which would interest the company as well as a commodity, and which route would it take if it does? Any thoughts there will be very welcome. Thank you.
Hi, Jatinder. Thank you. Yeah, lithium's an interesting one for us. We do watch the space and obviously in terms of our diversification, we are focused on brownfield in the near term and the greenfield projects, including Taca Taca, in the longer term. But we do look around diversification into other product commodities as well. Lithium's certainly interesting, and we think it, you know, potentially with the kind of nickel production that we will see from First Quantum in the next few years, that, you know, there may be some synergies there in terms of producing, you know, more, battery precursors, battery feeder metals such as lithium.
It's something we look at, but you know, at the moment the focus is on the brownfield development and the business and investments in our greenfield opportunities. You know, but where we can deploy our capabilities and skills, where we think they'll add value and think that they can drive benefit, then we will look at it. At this stage, a focus on our own portfolio.
Understood. Thanks, Tristan. Another one on Taca Taca. Are you aiming to go solo on that project? I think a couple of years ago, there were some media articles suggesting First Quantum and Rio Tinto are looking at a potential partnership, and I think the philosophy there was to share risk, both on financial and say country operational side.
Yeah. Jatinder, I don't know whether we refer specifically to Rio, but certainly in the processes we've had and we've demonstrated at Ravensthorpe where we've brought in a partnership for 30% of the business with POSCO, that you know partnership you know perhaps before when we did Cobre Panamá as sole self-perform, that we would look at that, particularly into new regions such as Argentina and John's outlined you know the areas that we're working on there, and there's potentially a partner that can add value you know in our discussions with government or in terms of understanding on the ground or in terms of driving that project forward. I think the likelihood is that would you know it's more difficult with other mining companies, but no reason to exclude it.
Otherwise, in terms of financing and helping with the risk exposure there, it's something that we would look at. We've said publicly that partnerships, we're interested in as well. It's something that we'll evaluate as we develop the project case over the next two to three years towards a development decision whether and alongside that, the finance case and the business case and whether a partnership would be appropriate.
Thank you. Merci. The next question is from Bryce Adams from CIBC Capital Markets. Please go ahead.
Yeah, hi there. Thank you all for the presentation. Just one question left from my list, and maybe it builds on one of the earlier questions. I wanted to ask about the approach that includes some projects into your guidance outlook before they are board approved. Is that because Enterprise and S3 are contingent on discussions with the new Zambian government? And if it wasn't for the government piece, they would otherwise be board approved? Is there anything else needed to formally approve these projects or it just boils down to that government discussion?
Yeah. Thanks, Bryce, and I'll give a little bit more color later on in terms of our discussions with government. We previously said that S3 was around the three major areas in front of us before that decision, where the situation with government, so which you refer to, the copper price environment. You know, certainly we're becoming more comfortable with the copper price and the outlook for it that we see in the market at the present time. The other one was the balance sheet position and the finance capability of the business.
Certainly as we're seeing, the balance sheet improve, and Hannes will speak a bit to that a little bit later on, in terms of the debt reduction and our targets to improve upon that, our ability to finance that project has certainly improved. Yeah, it really comes down to the situation with government. It is a very strong project, as John outlined. It underlines the next twenty years of Kansanshi continuing to be a world-class asset, producing at the levels, you know, around 200,000-250,000 tons of copper a year. It really is that conversation with government, and I'll speak a little bit more about that later on.
Okay, thanks. I'll wait for the discussion around the government, and I'll go back to the event. Thank you.
Thank you. There are no further questions registered at this time. I'll turn the call back to Tristan Pascall.
Thanks, operator. Thanks everyone for your questions. We're now going to take a short break, and we'll be back to resume the call at the top of the hour, around 11:00 A.M. Eastern Time. Thank you very much.
Welcome back. We will now begin the second part of our Capital Markets Day. At First Quantum, the environment and our local communities are a top priority for us. I'm pleased to have Andrew Hester, our Environmental Group Manager, with us today to share with you some of our ESG initiatives, including the new emissions targets that we released yesterday evening. Andrew, I will hand it over to you.
Thank you, Tristan. As Tristan mentioned earlier, our ESG focus is central to what we do at First Quantum. For us, it's never been a nice to have, but a must-have. Earning the respect and trust of our local communities and operating in an environmentally sensitive manner has been an essential part of our history when building and operating mines. Without this work, the growth of First Quantum over the last 25 years would simply not have been possible. Before breaking ground for construction, we undertake a considerable amount of work to ensure that in any country that we operate in, we leave it in a better place than we found it. This work includes protection of biodiversity, enhanced public infrastructure, and improvements in education and healthcare.
Furthermore, we have embraced the role that we at First Quantum have to play in addressing the challenges presented by climate change, both in terms of delivering the energy transition metals and also through our commitment that climate change and energy issues will be a central consideration in all of our decision-making and planning. For this reason, we have implemented carbon pricing into the evaluation of our new projects. Having built several projects from the ground up, there have been many lessons learned and best practices developed from an ESG perspective that we applied in our approach to Cobre Panamá. The focus is always on listening, learning, and then finding practical, real ways to have a positive impact on the world around us. This approach has led to strong community and government support at our operations and will be patiently applied to our greenfield projects in Argentina and Peru.
First Quantum has long strived for continuous improvement in reducing our carbon footprint through our commitment to energy and resource optimization, our innovation projects, and our renewable energy consumption. As reflected in the presentation, in 2020, almost 80% of our purchased energy was renewable. As the global transition to cleaner energy sources accelerates, we have looked to further reduce our greenhouse gas emissions across the group. Yesterday, we published our inaugural climate change report. This is our Task Force on Climate-related Financial Disclosures-aligned report outlining First Quantum's greenhouse gas emissions reduction targets. We've made a commitment to reduce our absolute Scope 1 and 2 greenhouse gas emissions by 30% by 2025 and 50% by 2030. Our targets and associated steps are provided in the waterfall chart.
These targets have been set on absolute basis with the assumption that both S3 and Enterprise will come online through this period. Achieving the targets will put us on a path to achieve better than the 1.5 degree reduction scenario outlined at the COP25 conference, and more recently reinforced at COP26 in Glasgow. Real engineering solutions such as the increased use of trolley assist and electric conveyors and a transition away from coal-fired power in Panama and Zambia are central to achieving the greenhouse gas emission reduction goals that we announced. Our targets are compared to other decarbonization trajectories in our recently released climate change report. In setting greenhouse gas reduction targets, our focus is on our sources of power in Panama and Zambia, which in 2020 accounted for almost 60% of First Quantum's emissions.
The main drivers to achieve the 2025 target will be through the increased usage of renewable power at both our Zambian mines and Cobre Panamá. It's been very pleasing to see the recently enacted Zambian legislation that makes the entry of new independent power producers, also known as IPPs, to the Zambian market. We're in the process of assessing the feasibility of Zambian wind and solar generation in partnership with IPPs, which will allow us to diversify and de-risk our energy supply without the increased use of non-renewables. As a result, we expect to be able to increase our use of renewable energy in Zambia beyond the current 80% level.
Although there will be capital investment required for this wind and solar generation, at this stage, we expect this will be sourced from third parties with the net market price shown to be competitive with current electricity prices in the country. Our single largest source of emissions is the Cobre Panamá coal-fired power station. Achieving our 2025 targets with respect to this operation will take place in two parts. The first part will be addressing the power needs for the 100 million tons per annum expansion, which will require an additional 60-80 MW of power by the end of 2023. This incremental power requirement will be met in full by a recently awarded power purchasing agreement comprising 100% renewable energy. Power costs are comparable to our current cost of coal power.
The second part to reducing our emissions at Cobre Panamá will be to address the power currently provided by the 300 MW, two-unit coal-fired power station. This will involve a progressive substitution of energy currently generated by these two units. Following engagement with country power providers, we have confirmed the feasibility of drawing sufficient renewable energy from the existing grid capacity so that only one of the two units would be required to supply Cobre Panamá's needs from 2025 onwards. This renewable energy will be sourced through further power purchase agreements and is expected to be at a cost comparable to current energy cost, partially due to the strong increase in thermal coal prices in recent years. The achievement of our 2030 target assumes a complete transition away from coal power at Cobre Panamá.
This will require the replacement of power from the second coal unit with a mix of natural gas and renewables. Conversion of both units to natural gas has been considered, but this is a capital-intensive solution as a result of the gas supply infrastructure required, and the resulting converted units would in any case not be particularly efficient. We estimate that our second coal unit could be replaced by 50/50 mix of natural gas and renewables by 2030, which will require the construction of further natural gas generating capacity in Panamá. This could be sited in Colón, approximately 100 km away, where there is existing natural gas offloading and storage capacity. We would consider construction of a power line linking Cobre Panamá directly to Colón to connect to this power, which would also have the benefit of improving national grid stability.
We will consider a range of partnerships and self-perform options for the gas-fired power generation and transmission. First Quantum has considerable experience in both power line and power station construction, and should a self-perform option be selected, we estimate the CapEx would be around $250 million in the 2025-2030 horizon. In the interim, however, we do see some need, particularly at certain times of the year, for the coal-fired power station or at least one of the 150 MW units to continue to operate as a base load feed in order to stabilize the national grid and electricity prices in the country. The renewable portion is likely to be wind-generated, given the relatively poor solar intensity and limited additional capacity for hydroelectricity in Panama.
Our greenhouse gas emissions reduction targets are further aided by our continued focus on optimization, innovation, and technology, which augments productivity, cost control, and also our impact on the environment. Our efforts in mine electrification stand out in this regard. First Quantum has prioritized the use of efficient, reliable, and robust technologies that maximize the use of electrical power within the pit and in the haulage of ore and waste for over 10 years. We have replaced fossil fuels with hydroelectricity through the use of trolley assist for waste rock movement, electric drilling and electric shovels on the pit floor, and in-pit crushing and conveying of ore. As shown in the graphic, we have estimated annual savings of close to 100,000 tons of carbon dioxide equivalent through these interventions. First Quantum has become a world leader in the successful development and operation of trolley assist systems.
Trolley assist involves working with OEM suppliers to install electric motors on large haul trucks, enabling them to connect to overhead electric lines as they exit the pit. This innovation is currently being used at our Kansanshi, Sentinel and Cobre Panamá operations and is part of the plans for future development of Taca Taca. Trolley assist substantially reduces the diesel required by the fleet at the most energy-intensive point of haulage when fully laden on the up-ramp of the pit. Other benefits of trolley assist include higher ramp speeds, a reduction in operating costs and extension of equipment life. We have developed trolley assist hardware to align with specific haul truck manufacturers. This extends development of power supply infrastructure to the mines, such as the transformers and the trolley line deployment systems. Trolley assist offers the potential for future integration with battery technology.
The trolley assist hardware is lightweight and mobile, designed to be efficiently relocated around the pit. In-pit crushing and conveying is another key approach that we use to reduce operating costs and lower our greenhouse gas emissions. As John described when outlining S3, this technology involves semi-mobile independent gyratory crushers operating in open circuits within the mine pit and a conveying system to move ore to the pit. With ore crushed in the pit, conveying vastly reduces haulage cost and dependency on diesel-operated trucks. While fuel is the obvious saving, it also reduces tire usage, maintenance, spares, dust and noise, all resulting in a significant improvement in productivity, cost efficiency and reduced greenhouse gas emissions. Critically, the reduction of in-pit traffic makes a major contribution to ensuring the safety of our employees and contractors, as well as reducing bottlenecks as the pit deepens.
In-pit crushing and conveying is currently in place at Sentinel and Cobre Panamá, will be installed as part of the S3 expansion at Kansanshi, and will be incorporated at Taca Taca, as John outlined. While the operation of the Kansanshi smelter has increased our Scope 1 and 2 emissions, the facility has significantly reduced our Scope 3 emissions and therefore the CO2 equivalent intensity of our copper production. Not only has the Kansanshi smelter significantly reduced the volume of material to be shipped and the resultant Scope 3 emissions, but it has also replaced the use of smelters in Asia, which typically rely heavily on fossil fuel compared with the Zambian power, which has a strong renewable component. Further emission savings are achieved in other areas, such as the transportation of sulfur.
As shown in the presentation, we have estimated the smelter reduces our Scope 3 emissions by approximately 1 million tons of carbon dioxide equivalent annually. While the commitment to reduce our greenhouse gas footprint has been a very strong focus for us and the rest of the mining sector in more recent times, we've not lost sight of our potential impact in another important area, namely local water supply. Water is, of course, essential for our operations and the livelihoods of our neighboring community, with any changes felt locally in the short to medium term. We are fortunate in that our three largest mines, namely Sentinel, Kansanshi and Cobre Panamá, have positive water balances and are located in areas with plentiful water supply. Water supply is not predicted to be a material constraint at any of these operations in the near future.
Our operations that are within or close to areas of high water stress have secured alternative supplies and have limited depends on fresh surface water. More than half of our water withdrawal from Las Cruces and Guelb Moghrein is from industrial wastewater and saline well fields respectively. At Ravensthorpe, almost all of our processed water requirements are met by seawater. As shown in the graphic, our exposure to surface water stress is limited. In keeping with our focus on resource optimization, we continue to look at opportunities to minimize withdrawal, improve operational efficiencies and maximize reuse to manage excess water and the resultant discharge risks. The company has made extensive use of industry-leading predictive tools to not only identify potential safety issues, but also help us to plan around meeting discharge and ambient water standards.
Water reuse across the group is around 70%, with a number of projects earmarked to improve that in the coming years. Our tailings storage facilities are designed and operated in accordance with guidelines issued by either the Australian National Committee on Large Dams, the Canadian Dam Association or the European Union legislative directives. Importantly, each of our tailings facilities is operated in accordance with the design intent and controls that have been considered local conditions. First Quantum senior management and engineering staff work closely with the operators of each tailings storage facility to ensure the facility is managed and operating according to the design intent and controls. Site management ensures regular site inspections are carried out by trained on-site personnel as well as by independent global experts.
In 2021, the company thoroughly reviewed the Global Industry Standard on Tailings Management that has been developed by the International Council on Mining and Metals. We're fully supportive of the standard's intent to improve the industry's performance on tailings management. First Quantum is committed to a phased approach in aligning our operations with the performance aspects of the standard to maintain our excellent track record in tailings management. Biodiversity is another key consideration in the life cycle of mines, and recognition of its importance is central to our values. The Cobre Panamá mine lies within a sensitive ecological region. In recognition of the ecological importance and the scrutiny that we would be under to get things right, Cobre Panamá made three bold biodiversity-related commitments in the early phases of the project. Firstly, the company committed to having a net positive impact on biodiversity in Panama.
Secondly, the company committed to the development and implementation of an exhaustive biodiversity action plan. Thirdly, the company committed to exceeding national regulations for biodiversity management by meeting appropriate international best practice in biodiversity management. In order to meet these broad commitments, First Quantum initiated detailed action plans in collaboration with respected independent conservation organizations. In the protected area plan, Cobre Panamá is committed to provide support to three adjacent protected areas totaling nearly 250,000 hectares, equivalent to approximately 3% of Panama's surface area. The objective is to slow and ultimately reverse the gradual loss of forest cover within these protected areas. Working with and supporting the local government agencies is a key part of this plan. In the reforestation plan, we committed to reforest an area double the size of the projected development footprint.
In order to meet this ambitious target, the company has committed to reforest denuded farming land outside the mine footprint, encourage more sustainable agroforestry practices, and rehabilitate the direct mine footprint where available. To date, we've met our commitment by planting 3,420 hectares. The species-level conservation plans aim to address the management needs of each individual species where the protected areas and reforestry plans may not be sufficient. Each species action plan describes a portfolio of actions aimed at ensuring a net positive impact on species viability. For the species-level plans, we have partnered with experienced independent conservation organizations whose logos are provided in the presentation. An example of such programs is our partnership with Sea Turtle Conservancy. Since 2014, Cobre Panamá has worked in collaboration with the Sea Turtle Conservancy for the protection and conservation of three species of turtles.
At the beaches near our port facility and in specially selected areas further afield, our conservationists patrol the beach to protect newly laid eggs from potential predators. We have estimated approximately 55,000 turtle nests have been protected as a result of our involvement. In addition, we have provided important funding to the Sea Turtle Conservancy for conservation and research activities in other sensitive areas in Panama. We're very proud of the success and extent of our biodiversity initiatives at Cobre Panamá. Some of the numbers showing the breadth and depth of our programs are provided to give a feel for the scale of the undertaking. Our Zambian projects are located in the North-Western Province of Zambia. The North-Western Province still supports vast tracts of relatively undisturbed forest, some within and some outside formerly protected areas.
First Quantum recognizes that the development of any new large infrastructure in such a setting is likely to bring about changes to the adjacent habitat. Landscape changes are typically associated with the influx of people who come either to work or to benefit from the economic opportunities. In what we believe to be a regional first, First Quantum, in partnership with neighboring communities and the Zambian Department of National Parks and Wildlife, have developed the West Lunga Conservation Project. The project aims to contribute to the conservation of almost 12,000 sq km of natural habitat around the Sentinel Mine. Recently, the project received additional financial support through The Nature Conservancy, one of the world's leading independent conservation organizations.
The company believes that our interventions will not only contribute to the direct conservation and protection of large areas of natural habitat and pristine wilderness. It will also form the basis for long-term sustainable management of the area. Since the inception of the West Lunga Conservation Project, First Quantum has provided more than $5 million in financial support to the Zambian government's existing conservation management activities on the ground. Support is focused on resourcing and equipping local staff, infrastructure development, and wildlife management. A number of conservation-related livelihood programs have also been developed in the surrounding communities. Long-term revenue generation will also be facilitated through community game ranching, tourism, and non-timber forest production value chain enhancements.
As a secondary benefit beyond the principal ambition for West Lunga in terms of conservation and habitat protection, we're also examining whether the project can meet the standards for potential offset of carbon in the future. First Quantum strives for relationships that are based on transparency, mutual trust and respect. The company is committed to listening and communicating with stakeholders and local communities directly and openly about impacts, events and issues. Each of our projects and operating mines has a comprehensive community relations program appropriately staffed to engage with our host communities. Furthermore, all of our projects and operations have fully functioning grievance mechanisms to accept, assess and resolve community complaints related to company activities within a predetermined time period. First Quantum regularly engages with a range of independent stakeholders, including international development organizations, civil society organizations, not-for-profit organizations, traditional leadership and community-based organizations.
There have been no human rights violations at any of First Quantum's mines since we began operations at Kansanshi in Zambia in 1996. A comprehensive human rights impact assessment is embedded in our social impact management programs and our land acquisition and resettlement programs. Earning and maintaining community support is fundamental to our company's success. Through partnerships with local communities, government, civil society and other industries, we seek to ensure that the benefits of mining extend beyond the life of our mines, so that we leave a positive impact on the national environment and social capital. In collaboration with our host communities, we're continually refining our social investment strategy to best address community needs, local workforce development, local business and infrastructure development in a manner that benefits communities.
In addition to over $1 billion in direct tax and royalty payments to the governments in our host countries, First Quantum invested more than $20 million in the communities in and around our operations in 2020. While our portfolio of community investment projects is diverse, we have at all times tried to align them with the needs of our local communities. For our larger projects in Zambia and Panama, our community investment is therefore focused on strengthening the services provided by our host governments in areas such as healthcare and education. Our own programs have focused on the development of community livelihoods. In the presentation, we have selected some of the key health and education highlights from our CSR programs around Sentinel over the last few years. Recently, the company has explored a number of different models in an attempt to improve the sustainability of our investments.
Some of the most successful models included greater collaboration between the communities, the Government of Zambia and First Quantum Minerals. We've been blown away at the commitment shown by communities in response to our projects. As an example of our livelihood development programs, First Quantum initiated a conservation farming program in Solwezi in 2010. The program was initiated in recognition that all mining projects have a finite resource, that the positive impacts of formal employment could only reach a few thousand households, and that traditional farming practices were in many respects unsustainable. By teaching improved farming techniques, we could not only have a positive impact on the livelihood of thousands of local stakeholders, but also conserve soils and natural farming systems around our mines. Following the initial success at Kansanshi, we extended the program to the communities around the Sentinel mine.
The program, which has evolved in recent years, has resulted in a dramatic increase in yields, and in 2020 has over 8,000 local farmers enrolled. As the initiative has matured, farmers are required to pay back into the program, thus improving its sustainability and likely long-term success. The program has created a self-sustaining agricultural economy in northwest Zambia. Participants have shifted from subsistence to small-scale commercial farming, with 40,000 farmers having benefited from the program in the last few years. Faced with a similar social setting in Panama in 2014, where local subsistence farmers were feeling increasingly marginalized and frustrated by the lack of opportunities, First Quantum proposed a local community farming program. After meeting with the affected farmers, it was suggested that the 32 families form a cooperative through which they could sell their local produce to the company.
First Quantum facilitated the formation of the Association of Small Farmers of Donoso and La Pintada, also known as DONLAP. After the formation of the group, First Quantum started buying fruits and vegetables from DONLAP to supply the project canteens. Not only did the project make sense in that it supported local communities, but it also reduced logistical requirements associated with the transportation of fresh produce to our canteens. The DONLAP cooperative now sells fresh produce from approximately 200 families around the mine. The roads and local infrastructure built for the mine have enabled the DONLAP cooperative to widen their horizons to other local stores and markets. The cooperative's model and successful pursuit of organic farming have even attracted interest from Nestlé, who in 2019 started buying from them. Discussions are underway to provide tomatoes to a future tomato plant that Nestlé plans to build in the area.
The DONLAP cooperative sales have grown to an estimated $2 million in 2021. I would like to close my section with some comments on COVID-19. The impact of the global pandemic has been different in each of the countries we work in. In terms of reach into our surrounding communities, it has been in Zambia, Panama, and Mauritania, where we have been most active in supporting and augmenting the government's responses to COVID-19. In Panama, the company has been very active in supporting the Ministry of Health of Panama, MINSA, with access and supplies into surrounding communities. We've sponsored the Gorgas Memorial Institute for Health Studies, a medical research institution that has been dedicated for more than 80 years on investigating diseases in the tropics and preventative medicine in order to fulfill its role as a national public health laboratory.
In April 2021, the Gorgas COVID-19 Institute was opened and now provides advanced genetic sequencing of coronavirus samples to help track its mutation and spread in the country. Cobre Panamá has also provided direct support, including emergency livelihood packages, to support its surrounding villages and communities. In Zambia, the company has provided testing and medical equipment and assisted with the construction of COVID-19 isolation facilities for the community. Ongoing support includes the provision of oxygen, consumables, face masks, sanitation stations, and transportation of medical supplies. The company is working with the Ministry of Health in the North-Western Province to provide vaccination stations to employees and affiliated contractors in support of the national vaccination program.
In addition to increased medical facility resilience initiatives at the mine clinics in Mauritania, Zambia, and Panama, COVID-19 protective management measures to minimize person-to-person transmission in the workplace and protect business continuity have been implemented across all our operations. Thank you for your interest in First Quantum's ESG work, and I'll now hand over to Hannes Meyer.
Thank you, Andrew. Yesterday, we were pleased to release a financial policy statement. You will be familiar with our history and the increase in leverage and absolute debt in order to fund the building of a world-class asset in Cobre Panamá. Now that Cobre Panamá is hitting its stride and the major capital projects are behind us, it is appropriate to consider how we will allocate capital in the years ahead. In this year, our principal focus continues to be on debt reduction, and this is the main reason that our dividend policy has started cautiously. In 2020, we committed to reducing our net debt from its peak of $7.7 billion by $2 billion.
We now expect to achieve this goal in the first half of this year and have further increased our debt reduction target by an additional $1 billion in the short to medium term. Our longer-term policy objective is that through this commodity cycle, net debt to EBITDA ratio of less than 2x. This is not a target, but it's intended to be a maximum. This will be one of the key considerations when we consider the next greenfield project to ensure that when we move into the next capital-intensive build phase, we have enough capacity on the balance sheet to not exceed these leverage limits. We will of course, consider other financing options to ensure that we avoid placing excessive strain on the balance sheet. This may include developing new projects with well-capitalized partners to share the capital burden.
The partnership that we announced last year with POSCO at Ravensthorpe is an example of First Quantum's increased openness to partnerships. We are now in a position to improve our return to shareholders from the current nominal dividend. This is due to continued higher commodity prices, continued strong operational performance, and the debt reduction over the last 18 months. We also considered our future plans to assist in formulating the dividend policy. In terms of this dividend policy, the board has approved a cautious increase in the dividend. Under the new policy, we will pay a performance dividend so that 15% of available cash flows generated after our planned capital spending and distributions to non-controlling interest. We will underpin the dividend with an annual base dividend of CAD 0.10 per share, and that's with a CAD 0.05 per share being paid semi-annually.
You should think of this as a minimum dividend of CAD 0.10 per share or 15% of the performance as described, whichever the greater. Through this dividend approach, we will maintain an appropriate capital allocation between debt reduction, investment in the future of the business, and cash return to shareholders. The new financial policy and related dividend policy underlines our confidence in the future of the business, while still enabling First Quantum to both continue deleveraging and advance the strong portfolio of growth projects which John and Zenon described. Turning to our debt profile. Post the partial redemption of our 2023 notes, we have included a slide that presents our updated debt maturity profile. The debt capital market is an important market for us. Although the absolute amount of bonds will reduce, we plan to retain some exposure to this market in the future.
At the same time, we have had a long-standing and supportive banking group that worked with us through difficult times, and we will also retain some of this funding capacity in future. In addition to the dividend policy announced yesterday, our priority for capital allocation in the guidance period is the advancement of our brownfields projects, which Zenon and John outlined. We believe these projects can put us on a path towards 1 million tons per annum of copper production. These brownfields projects are more capital efficient than greenfields projects, and therefore will not place undue strain on the balance sheet during this period where debt reduction remains a principal objective. The greenfield project, which John Dean outlined, are not a current focus of our capital allocation.
Spending will remain low through the next two years, as we do not expect to make a decision on these projects prior to the end of next year or sometime in 2024. Now turning to hedging. Consistent with our strategy of not being natural hedgers, the hedged exposure continues to decline significantly, where hedges represent now less than 7% of our guided production this year. The remaining hedges for this year are under zero-cost collar contracts and have an average floor price of $3.61 and a ceiling price of $4.69 a pound of copper. The hedge book will continue to reduce on a quarterly basis going forward, given the improving strength of our balance sheet. Thank you. With that, I would now like to hand back to Tristan to conclude today's presentation.
Thank you, Hannes. The projects outlined by John, Zenon, and John will enable us to deliver on three critical strategic initiatives, all the while staying within the financial guidelines which Hannes has outlined. Firstly, we want to extract full value from our existing assets. The expansion of Cobre Panamá and the delivery of S3 will enable us to achieve this in our Panamanian and Zambian businesses. The recently completed Shoemaker-Levy project at Ravensthorpe and the installation of a fourth in-pit crusher and expansion to 62 million tons per annum at Sentinel will also help us achieve this. Secondly, we want to replace the medium-sized higher margin mines such as Çayeli and Guelb Moghrein, which will close in the coming years. The development of the Las Cruces underground project and the Enterprise nickel mine will do just that by adding two high-grade, high-margin operations to our portfolio.
Thirdly, we would like to add a third leg of large scale production to add to our Zambian and Panama businesses in order to further diversify our business. The large scale copper projects at Taca Taca and Haquira provide optionality for us to achieve this over the longer term. We have gone into detail today on the technical, environmental, and financial work streams underway at First Quantum. Another critical work stream is the constructive dialogue that exists with the government in each of our host countries. In Zambia, following the inauguration of His Excellency, President Hakainde Hichilema in August last year, it has been pleasing to see the new government target an increase in Zambian copper production from the current 800,000 tons per annum to 3 million tons per annum over the next decade.
We see that a target of this magnitude will require Zambia to attract substantial investment into the country and establishment of the fiscal framework which makes that possible. An important first step was made towards achieving this goal with the reintroduction of the deductibility of mineral royalties for corporate income tax assessment purposes in the new administration's first budget. This became effective at the start of this month and indicates the willingness of the new government to implement the required policy changes to reach their goals for growth of the economy, creation of new jobs, and further development of social infrastructure in the country. We also note the efforts by the new government to improve the ease of doing business in Zambia and their ongoing active engagement with the IMF, which we certainly see as demonstrative of a more constructive environment for economic growth in the country.
Our productive discussions with the government of Zambia to support the approval of S3 and Enterprise continue. They focus on ensuring the appropriate and enduring investment conditions exist for us to advance these important projects, as well as ensuring an agreed mechanism is in place for a predictable repayment of VAT owed to the company. These discussions are constructive such that we are hopeful that we can advance both projects this year as reflected in our guidance. With regard to Law 9 discussions in Panama, we continue to be engaged in formal discussions with a high-level ministerial commission comprising four cabinet ministers. In Q2 of last year, the Supreme Court upheld its ruling in respect of the clarification motions presented by the company to the court in relation to its Law 9 decision announced in September 2018.
This ruling was gazetted in Q4 of last year and adds momentum to the ministerial commission and their process to resolve the matter. In September, the Minister of Commerce announced the culmination of discussions on environmental and labor matters. Discussion on financial matters, particularly the royalty and tax regime that govern the project, have been continuing. On January 5th this year, the Minister of Commerce indicated his intent to conclude and reach an outcome by the end of January, a target date that we are aligned with. Following extensive and robust discussions across the early part of this month, the Minister of Commerce publicly outlined the government's proposal in respect of the fiscal matters last week. This proposal reflects the government's objective that the new fiscal arrangement provides predictable and stable contributions to the country from the mine.
At the same time, the government has committed that it does not want to unreasonably impact the profitability of the underlying business at Cobre Panamá. From our perspective, we support this approach, and we have noted to government that it is important that necessary protections are in place for lower copper price and production scenarios, and that the parties need to ensure that the new contract and law are both durable and sustainable. The discussions are very much live and fast-moving, and within the last 24 hours, there has been agreement on principal items. Namely that the Government of Panama should receive $375 million in benefits per year from Cobre Panamá, and that the existing revenue royalty will be replaced by gross profit royalty.
While both parties now need to finalize the detail behind these principles, including the appropriate mechanics that would achieve this outcome and the protections to the business, we are pleased that there is alignment on the fundamental elements of the fiscal terms for Cobre Panamá going forward. Once the agreement is documented, which is expected in the near term, it is expected that newly drafted legislation would be put to the National Assembly for ratification. The company welcomes the transparency of the robust ministerial commission process, and we are hopeful that we can conclude this matter shortly. We are happy to take questions on this important topic, but would note that we cannot comment on the specific terms which are currently being finalized.
Before we go into our last round of Q&A, I would like to close with saying that we are pleased in the position that First Quantum is in today. We are in a period of solid cash flow generation, and while debt reduction remains a priority for the company, we are pleased to be able to cautiously commence more reasonable capital returns to our shareholders with the announcement of our new dividend framework. At the same time, delivering financially disciplined growth has always been one of First Quantum's core competencies, and reinvestment in the business remains central to our business strategy. In this regard, I am pleased to have shared with you today our path forward to 1 million tons of copper production per year through the advancement of our four brownfield projects.
Our portfolio of growth options also includes the longer-dated major greenfield opportunities, which will be approached in a measured and cautious manner. As we go forward into this exciting new phase of growth, we will continue with the approach developed over the 25-year history of the company. We will continue to listen and learn, and we will continue to stay humble and open-minded as we are always conscious that you're only as good as your last project. As a company, we will focus on developing our projects through our unique in-house execution capabilities. We will look to operate these new projects and our existing mines in an efficient and practical manner. We will continually apply existing and new technology where it can have a direct, real impact on our underlying performance.
All of this will be done with a very real commitment to working with and supporting the communities we live with and using the First Quantum approach to improve the environment around us. Thank you for joining us today. Operator, we are now ready for Q&A.
Thank you. As a reminder, please mute your webcast if you are asking a question over the phone. To ask questions over the phone, please press star one on the device's keypad. Once again, we thank you for your collaboration. The first question is from Orest Wowkodaw from Scotiabank. Please go ahead. Your line is open.
Hi, Tristan. Thanks for giving us some color on the current, I guess, state of negotiations in Panama. Just, you know, if we try to dig a bit deeper here, I'm just trying to get a bit of a better understanding on how the new fiscal regime may work in practice. I know there's been reports of the $375 million per annum.
In payments of taxes and royalties. Is that—does that fluctuate with copper prices, and/or operational, say, challenges? I'm just wondering how that works in a $2 copper environment.
Sure, Orest, thank you. Look, the government has made it clear to us that in their proposal that they are focused on that $375 million headline. It is important that those protections are in place, and certainly there's a realization that we live in a cyclical industry and copper prices and production and so on do go up and down. Look, the detail of fleshing that out is ahead of us in terms of getting to legislation in front of the National Assembly. Those are the principles that it will be around the $375 million per year, and we will move from a net smelter royalty across to a profit-based royalty.
Okay. Across all copper price horizons?
Those protections we'll work on, but certainly in the kind of scenario that you speak about of very low prices. Our agreement with government and the understanding with government is that there will be those protections in place.
Okay. Just as a follow-up, I realize you still need to reach a formal deal, it needs to be approved by the legislature. Do you expect that this becomes live sort of backdated as of now, beginning of January, or is this something that would come into effect later this year?
Yeah, Orest, we'll need to work that through, the functions and so on of that. Certainly in terms of the existing standing of Law 9 and everything that was in 2021, there won't be any looking in the revision as far as our guidance and advice is telling us.
Okay. Thanks so much.
Thank you. The next question is from Matthew Murphy from Barclays. Please go ahead. Your line is open.
Hi. Thanks for all the info today. I got a couple questions, just on the Panama front. Just trying to gauge like how much things might be yet to move versus what the government relief. I mean, you describe it as a negotiation, but is this more about specific mechanics, or might we see, you know, still pretty significant movement on some of those details?
Yeah. Hi, Matthew. Thank you. No, there is an agreement on those headline principles and we've made that clear to the government. They were happy to accept that. The detail in terms of implementation, the mechanics and the drafting and so on are ahead of us.
I have one on just sort of CapEx budgeting. Hannes, you described, you know, some potential capital intensive build phases, but also JV-ing, et cetera. I'm wondering if there's a sort of broad set of thinking what levels CapEx could hit. You know, is it, is it something you wanna keep it like $1.5 billion per year or you'd go to $2? Is it really just about, you know, if you tick the box on enough projects at one time, you can go higher?
Hannes, are you happy to take that?
Sure, Tristan. Matt, I mean, what we're focusing on is sort of the leverage, the maximum ratio, and it's in a through the cycle sort of ratio of not more than 2x net debt to EBITDA. If we look at our current ratios, that is below two. If you look at the consensus prices, that's below the current spot price. We do factor that in. We do expect it to go well below the two. You know, if we get to sort of sometime in 2023 for the next greenfields projects, you know, we're well below those targets and, you know, that can accommodate quite a bit of spend. Now, John Dean highlighted, I think $3.6 billion for the Taca Taca.
It's, you know, it's a lot of effort to spend $1 billion in a year. If you lay over another $1 billion, you know, that's not gonna strain that sort of ratio at all. Tristan, back to you. Thanks, operator.
Thank you. Merci. The next question is from Jackie Przybylowski from BMO Capital Markets. Please go ahead. Your line is open.
Thank you very much. I guess I wanted to come back to the ESG presentation and maybe talk a little bit more about the transition away from coal-fired power at Cobre Panamá. I know it's something that investors are keen on, so I think it's maybe worth asking a little more detail. Can you talk about how exactly the transition would work? It sounds like if I understood Andrew's presentation correctly, that you would still be maintaining some coal-fired power to ensure like a base load availability. Is that the case for the long term? Did I understand that right? Or are you looking to convert all of the coal to natural gas and then have wind power in addition to that as a renewable component?
Hi, Jackie. Thanks. Yeah, principally three phases. The first step is for the expansion to 100 million, which is additional 60-80 MW. All of that will be renewable. As Andrew said, there's a letter of intent in place, and the principal terms agreed there and we're working through the commercial finalization of that. The second phase is dealing with the first 150 MW, and we believe that we can move across to renewable there, and that would be the intent. Then the third phase is the second lot of 150 of the existing. There, we're saying that as we look at the mix across Panama, it will be a combination of factors.
What we do see is the need, at least in the interim, to have at least one unit of the coal-fired power station running at particular times of the year. You know, this part of the world is known for the wind dropping for at least four months of the year. That was evident when you know, they used to talk about the doldrums, sailing through the Caribbean. That certainly remains the case today. As Andrew outlined on the solar side, the solar intensity maps are pretty low in reliability because of the amount of cloud cover in Panama.
We do see that need in the interim, but longer term, we could invest, and there are opportunities to invest in things like gas-fired power generation, and those facilities are existing in Panama. As Andrew said, from 2025, that kind of timeframe, we could look at building a power line across to Colón where there's gas and potentially either sourcing from a third party or ourselves constructing that gas-fired. Andrew, I'm not sure if you would add anything, any further color. Maybe I've covered it there.
Thanks, Tristan. Yeah, you have covered most of it. I think there's, you know, we mustn't forget there's a very strong hydroelectricity component in the Panamanian grid, and some of that should be available in the short term. That would also be a consideration and you know, some of that hydroelectricity is very attractive dam hydro projects, and obviously not suffering as much the seasonal changes as wind and solar. Yeah, I can't really add too much more to that. Thanks.
Thank you. No, that's a really helpful recap. Thank you. I mean, if I'm understanding right, just to make sure, it sounds like First Quantum would not be looking to convert coal to gas until at least 2035. In the meantime, you'd be looking more at constructing additional power with renewables. Is that right?
Yeah, Jackie. Most of that renewable is available in the grid today, and then from 2025- 2030, we would be considering what we do in the longer term. As we said in our targets, we will be looking to reduce our CO2 greenhouse gas emissions by 50% by 2030.
Thanks very much, Tristan and Andrew. Thank you.
Thank you. Next question from Jatinder Goel from BNP Paribas. Please go ahead. Your line is open.
Thank you, operator. I've got two questions. First one on dividend. Is the way to read this policy that 15% is the maximum dividend, or is it more of an ordinary dividend, and then you can always top it up if you feel you've got enough headroom and not much to do with that cash?
Tristan, do you want me to take it?
Yeah. Thanks, Hannes.
How you should think about it is 0.10 is the minimum dividend. We will pay 0.10 dividend, but we will do the calculation to see what is 15% of the cash flow available from operations, less our CapEx and less the minority interest share of that. And if that is greater than the 0.10, then we'll pay that percentage. With the current copper price and, you know, what we are planning for, you should think about it as a 15% dividend of the operational cash flow. There's a base dividend of 0.10, so we won't go below the 0.10 actually. Canadian cents, though.
15% is the ceiling is the way to understand in current environment based on the current guidance period?
Sorry, can you repeat that? I missed that.
15% is the ceiling based on the three-year CapEx outlook that we've got. We, First Quantum will not be paying more than $0.15 even if there is more cash.
No, sorry, it's 15% of the cash flows. That's not a cent, but it's a percentage.
Yeah
... of the cash flow. I mean-
Sure. Yeah, yeah.
It's I mean, the reason for a cautious approach is we still got a lot of debt, so we want to reduce the debt, so the key focus is debt reduction. At the same time we've got brownfields project, and that is the future as well as greenfields project. It's a balance between reducing the debt, investing in these value-adding projects, and then returning some cash to shareholders.
Understood. Question on Panama. Tristan, are you able to say anything on the corporate tax that's been picked up in the original proposal to be implemented with immediate effect? Where are we, if you can comment on anything, because it's hard to align $375 with 25% tax and the royalty rates. And related to that, how much of your development CapEx is still to be recovered under the current regime? Or alternatively, is there a date in mind from which the corporate tax would become applicable under the current regime?
Thanks, Jatinder. I appreciate the interest there, and I understand that, you know, the details there. As I said, it's pretty fast-moving at the moment. What we do have in place is those principles that are agreed and we've outlined. The detail of that we'll work through. We'll give the color on that as soon as we can. Certainly, you know, those are the elements, and how that flows through the mechanics of that that we seek to provide that color as soon as we can.
Fully understood, Tristan. It is a delicate matter, so all the best with the negotiation. Thank you so much.
Thanks, Jatinder.
Thank you. Yes, the next question is from Farooq Hamed from Raymond James. Please go ahead. Your line is open.
Hi there. Thanks for taking my question and good morning or good afternoon. Again, another question about Cobre Panamá and this $375 million annual benefit to the government from Cobre Panamá. You've talked about protections to the downside if the copper price were to fall, and you'd have some protections on that, on that number. I guess from the other side, though, should we look at this $375 million as a cap, or could the annual contributions from the mine be higher than 375 if the calculations of the royalties and the taxes end up being higher because of higher copper prices or what have you?
Yep. Hi, Farooq. Thanks. Look, I won't be drawn on that one, but certainly the government's focus has been to get a stable level of contribution from Cobre Panamá at this level. I can't really go into further around the sort of the details of that until we have that color to provide to you.
Okay. That is something I guess that we'll know as you kind of iron out the details and, I'm just wondering, you know, what do we do if we, you know, if you kind of have copper prices running higher? I guess that's just we'll have to wait to see what the details of the agreement are. Okay, just maybe my next question, just on the just picking up on Jackie's question on this transition away from the coal-fired power plants at Cobre Panamá. Maybe just a point of clarification, or maybe I was just not clear on how it's gonna move forward.
When you get to 2025 and you're only down to the one unit of the coal plants, what is the plan for the coal plants? Are they planned to be decommissioned, sold? What actually happens with these coal plants?
Yeah. Thanks, Farooq. Andrew, do you want to cover that?
Yeah. Look, thanks, Farooq and Tristan. Look, I think there's quite a bit of time now between now and you know 2030. I think we're currently considering a few options with no firm decisions made on the future of those power plants other than we will be running you know we will be dropping one unit 2025 and then running you know a second unit intermittently seasonally up to 2030. Yeah, so a few options, but I'm not aware of any firm decisions yet that have been made by the company.
Maybe just a follow-up to that. Do you know, does the Panamanian grid require all 300 MW from those plants to, you know, kind of service the grid right now? Is it required, or could the grid lose 150 MW of power that's coming from those two plants?
Sure, Farooq.
Um-
Do you want me to take that one, Andrew?
Go ahead. You can start.
Yeah. Farooq, the grid in Panama is around 2,100 MW at this time. There's another 300 MW of gas-fired coming on this year, next year, that kind of timeframe in Colón. At this stage, the 300 MW delivered by the coal-fired power station is pretty important, and we've seen that. We have some maintenance ongoing at the Cobre Panamá, on one unit of the Cobre Panamá power station at this time, and it's you know it certainly we've been able to draw all of that power while we've been doing that two-year maintenance on that unit without problem from the national grid.
It has had an impact on national grid prices, which just illustrates that base load is important to the stability and the good functioning of the grid. The grid does continue to develop, and there's ongoing planning by the government, for example, on transmission line in order to reinforce the national grid. For us, things like the connection between Cobre Panamá and Colón, which would further improve that transmission grid stability, make a lot of sense. All of that will come to bear over the next sort of five years as that planning gets sorted out. Yeah, we would be looking at it on that basis in order to match into that overall plan in the grid.
At this time, right now today, yes, the 300 megs from the coal-fired power station are pretty important in the country.
Okay. Thanks very much for your answers. That's helpful. Thank you.
Thank you. We now have time for one last question. It will be from Dalton Baretto from Canaccord Genuity. Please go ahead. Your line is now open.
Great. Thanks for squeezing me in there. Tristan-
You've mentioned a couple of times in this presentation that you'd like to add a third leg to your production base of some scale. I'm just wondering, is it your intention that this third leg come through your greenfield pipeline or can we expect that M&A will be part of that equation?
Yeah. Thanks, Dalton. Look, M&A opportunities we do look at, they come across the desk, and we do believe that First Quantum can apply some, you know, its unique capabilities. The things that we spoke about today as Zenon on the project side and our execution capability there or in our operations excellence and indeed on the environmental or community side in terms of working on the ground with communities and doing that to a high standard and in an environmentally sustainable manner. We do look at opportunities, but our focus is really the portfolio that we have in front of us. Taca Taca and Haquira, as we outlined today, do give great optionality to the portfolio.
There are options for that in terms of the way we approach those projects, and we spoke a little bit about partnership, as we've done at Ravensthorpe, to bring in and share risk and to share return, as appropriate. But yeah, we would look at other opportunities, but we would need to drive value and create value for shareholders in those opportunities. In the meantime, we're focused very much on our existing portfolio, which we believe is very competitive, compared to, you know, the other copper opportunities out there in terms of new production that potentially can come on.
That's great. Maybe I can ask you just one follow-up before we wrap up. On, you know, when you do consider these M&A opportunities, given your pipeline, is there a preference to looking at more kind of operating assets versus development? How do you think of these opportunities in terms of scale, in terms of commodity, in terms of geography?
Sure, Dalton. Look, it would really be around our capabilities and what we can add to the project. We would look at smaller projects, potentially or medium-sized to replace some of those that are closing. We spoke today about the opportunities from Enterprise and Cobre Las Cruces in that regard, in terms of additional tonnage and high margin, low risk return. In terms of geography, as we said, we would like to add a third leg, and that's why Taca Taca and Haquira beyond our existing operations in Zambia and Panama had diversification. But those are our focus. If we can add value outside that and the right opportunity comes along, we will look at it. We will look at that.
Thank you very much. Great job on the session today, guys.
Great. Thanks, Dalton. Well, thanks everybody for your participation today. We greatly appreciate the interest and your participation and commitment across this time. We look forward to speaking to you again when we put out our Q4 results and the earnings call, which is on the 16th of February this year. Thank you very much.