G Mining Ventures Corp. (TSX:GMIN)
Canada flag Canada · Delayed Price · Currency is CAD
39.85
-1.65 (-3.98%)
Nov 24, 2026, 4:00 PM EST
← View all transcripts

Earnings Call: Q3 2026

Nov 13, 2026

Summary

Q3 production rose 22% QoQ to 45,000 oz, with strong free cash flow and 2026 guidance intact. Oko remains on schedule and fully funded for first gold in H2 2027, while 2027 growth and portfolio expansion are supported by higher grades and exploration.

Operator

Good morning, ladies and gentlemen, and welcome to the G Mining Ventures Third Quarter 2026 Earnings Conference Call. At this time, all participants are in listen-only mode. Following the presentation, we will conduct a question-and-answer session. As a reminder, this call is being recorded. I would now like to turn the call over to Jean-François Lemonde, Vice President, Investor Relations. Please go ahead.

Jean-François Lemonde
VP of Investor Relations, G Mining Ventures

Thank you, operator, and thank you, everybody, for attending G Mining's Third Quarter 2026 Conference Call. In addition to myself, we have on the line today Louis-Pierre Gignac, President and Chief Executive Officer, and Julie Lafleur, Chief Financial Officer. As we will be making forward-looking statements during this call, please refer to the cautionary notes and risk disclosure in our MD&A and on slide two of the webcast presentation. Also, please keep in mind that all dollar amounts mentioned during the call are in USD unless otherwise noted. Now I will turn the call over to Louis-Pierre Gignac to provide you with an overview of the quarter.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thank you, Jean-François, and good morning, everyone. Thank you for joining today's call. I want to start by recognizing the dedication of our teams across all our sites, whose commitment to safety, operational excellence, and responsible mining continues to drive our success. My team and I are pleased to report another solid operating quarter. Our last call, we talked about the step-up in production that we expected in the second half of the year as we moved into higher-grade phase two mineralization, and our third quarter has delivered on that plan as shown on slide four. Production increased 22% quarter-over-quarter to 45,000 ounces. Cash costs and all-in sustaining costs declined 8% and 6% respectively, well below the industry's average in Q3 of approximately $1,400 per ounce for cash costs and $2,000 per ounce for all-in sustaining costs.

All-in sustaining margins remained strong in the quarter at 58%. That translated into $80 million of free cash flow for the quarter, or $1,880 per ounce of gold produced. This is no small accomplishment in the quarter where oil averaged $100 a barrel and the price of diesel almost doubled, and where trade, tariffs, and war are all challenging supply chains and logistics globally. Importantly, even in this difficult environment, we remain on track to deliver our full year 2026 production and cost guidance, albeit at the midpoint of our guidance for production. 2027 guidance for production and cost capital remain unchanged. Turning to the highlights on slide five. TZ continued to perform in line with the mine plan. Mining rates increased 7% from the second quarter to a new quarterly record of 74,209 tons per day, which is at the targeted mining rate.

The key improvement this quarter was driven by the planned higher-grade mine sequencing. Process plant throughput increased 11% from the second quarter to a record quarterly average of 12,372 tons per day, representing 96% of nameplate capacity. During the quarter, average process grades were 1.33 gram per ton versus 1.23 gram per ton in the second quarter and 1.03 gram per ton in the first quarter. Gold recoveries remained strong at 92%. Production is expected to increase significantly in Q4, driven by a full quarter contribution of higher-grade phase two mineralization. Total cash costs and AISC expected to decrease in Q4, bringing full year costs within our guidance.

Julie Lafleur
CFO, G Mining Ventures

Thank you, Louis-Pierre, and good morning, everyone. Revenue in the third quarter was $172.7 million compared with $161.7 million in the prior year quarter. The increase primarily reflects a higher realized gold price, which reached over $4,000 per ounce compared with $3,292 per ounce in Q3 2025. Adjusted EBITDA increased 2.5% year-over-year to $125.6 million, reflecting higher revenue, partially offset by higher labor, royalty, and energy costs. Net income was $99.5 million compared with $123.8 million in the third quarter 2025. The year-over-year comparison was affected by the tax benefit recognized in Q3 2025 following approval of the SUDAM tax incentive for TZ. Cash flow from operating activities before changes in working capital was $115 million, up 9% from the second quarter. Our balance sheet remains strong. We ended the quarter with $137 million in cash and $31 million in total debt.

Including our undrawn $350 million revolving credit facility, total liquidity was $487 million, well above the $417 million of remaining capital required to reach first gold at Oko. We also began returning capital to shareholders. Following TSX approval for our normal course issuer bid in August, we repurchased and canceled 102,500 shares in the quarter at an average price of CAD 49.41 per share. Total capital expenditures were $172 million in the quarter. This include $14.8 million of sustaining capital, $16.2 million of capitalized exploration, and $132.9 million of development capital at Oko Gold. Sustaining capital remains in line with guidance, and we expect sustaining capital to decline in the fourth quarter. Exploration spending is expected to increase as we complete the Oko-Ghanie infill program, while Oko development capital is expected to reach its peak quarterly spend in Q4.

Turning to guidance, we remain on track to deliver within our 2026 production and AISC guidance ranges. Year-to-date production is 114,000 ounces against full-year guidance of 160,000-190,000 ounces. We expect production to increase meaningfully in Q4 as phase 2 ore contributes for a full quarter. Our 2026 AISC guidance remains $1,330-$1,444 per ounce, as we expect fourth quarter costs to decline sufficiently to bring full-year performance within that range. We have increased 2026 capitalized exploration guidance by $11 million to $53 million-$61 million, reflecting the Oko-Ghanie infill program launch in Q3. Sustaining capital and Oko development capital guidance remain unchanged. Looking ahead, 2027 production guidance is 200,000-235,000 ounces, excluding Oko Gold. At the midpoint, this represents approximately 25% growth over 2026. We also expect 2027 cash cost and AISC to decline by approximately 23%-26%, respectively, compared with 2026 midpoint.

Now, I will turn the call back to Louis-Pierre to provide an update on Oko and Gurupi and our outlook going forward.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thank you, Julie. With results largely in line with expectations and with no big surprises, this morning we wanted to spend less time talking about the past quarter, and we want to spend a little more time talking about the substantial and important value drivers of our company going forward. The corporation continues to rapidly advance its large-scale, long-life Oko Gold project in Guyana, which remains on budget and on schedule for first gold pour in the second half of 2027. At the end of the third quarter, approximately $555 million was spent on the project, representing 57% of the approved initial capital budget of $973 million, with approximately $417 million remaining to be spent through completion. Total commitments reached $714 million, or 73% of the approved capital budget. Total capital expenditures guidance at Oko Gold for 2026 and 2027 remain unchanged.

On-site workforce now exceeds 2,100 employees and contractors, with 3.3 million hours worked to date, and over 78% being local employment, demonstrating the corporation's commitment to local content. Overall project progress at Oko Gold has reached 38.4% based on earned value at the end of Q3, with rapid progress being made across several workstreams, as shown on the pictures on slide 10. Mill construction continues to advance, with the mill shells delivered on site, marking the commencement of mechanical installation. Power plant construction continues to advance ahead of schedule, with mechanical installation inside the engine hall, with all generators received, positioned, and aligned. The mining fleet includes eight fully commissioned and operational mine trucks, along with three dozers, and the assembly of the third production shovel nearly complete.

As shown on slide 11, the schedule remains unchanged, with first gold targeted for phase one for the second half of 2027, and commercial production expected in early 2028. With the G2 acquisition completed on July 29, we have consolidated the Oko-Ghanie deposits with Oko Main. We launched an infill drilling program at Oko-Ghanie in the quarter, which we expect to complete by year-end. It will support an integrated mineral resource estimate and an updated feasibility study for the combined project targeted towards mid-year next year. The target is to add 2 million-2.5 million tons per annum of processing capacity, allowing us to get up to 500,000 ounces per year for an approximate 16 years mine life, increasing from the 350,000 per year planned under phase one.

As shown on slide 12, we believe that Oko Gold is the only true tier-one gold asset currently in construction globally. Most importantly, Oko Gold remains fully funded. Our sources of capital are approximately $1.12 billion. This includes $137 million in cash, $632 million of projected TZ free cash flow from Q3 2026 through Q4 2027 at a $4,000 gold price, and our $350 million credit facility that is untapped. Against that, we have about $417 million of remaining Oko construction capital and $88 million of corporate and G&A exploration. That leaves a projected liquidity surplus of more than $600 million. This gives us the flexibility to fund growth, such as the planned Oko expansion, and continue our share buybacks while maintaining a strong balance sheet. Beyond Oko, we continue to advance our pipeline. At Gurupi, drilling continues to expand mineralization at Blanket and Mandiocal.

Maiden drilling at Grodiocal identified near-surface mineralization along a corridor of about five km. An updated mineral resource is expected before year-end, which will form the basis of a PEA targeted by the end of this year. We also remain on track to file the ESIA in the fourth quarter. At TZ, drilling up to 150 meters below the current pit has confirmed mineralization continues at depth, and regional work has identified a 15km-by-3 km mineralized corridor with multiple satellite targets. At TZ, we expect higher production and lower costs from the full-year contribution of higher-grade phase two ore in 2027. At Oko Gold, our focus remains on advancing construction through the peak construction period, commissioning the power plant and grinding circuit, and delivering first gold in the second half of 2027.

We also expect several important catalysts across the portfolio, including the updated feasibility study for the integrated Oko Gold project, a Gurupi PEA, an updated resource, and continual exploration across all our assets. That concludes my remarks. Operator, we are now ready to take questions.

Operator

At this time, if you would like to ask a question, please press star one on your telephone keypad. We will pause for just a moment to compile the Q&A roster. Your first question comes from the line of Fahad Tariq with Jefferies. Please go ahead.

Fahad Tariq
Senior Equity Research Analyst, Jefferies

Hi, thanks for taking my question. At TZ, now that we're halfway through the fourth quarter, can you talk a little bit about what you're seeing in terms of grade and whether it's aligned with your internal model? Secondly, whether that's the run rate grade we should expect for 2027? Thanks.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. We're continuing to make good progress on Q4, so we're continuing to see our grade increase from Q3. That's based on the expectations that we had with our mine plan. I would say also, more importantly, our mining rate and mining plan is really catching up on some of the waste stripping, and we expect to catch up by the end of the year, which really sets us up nice for 2027 in terms of our mine plan and access to high-grade material. Yeah.

Fahad Tariq
Senior Equity Research Analyst, Jefferies

Okay. Maybe switching gears to Oko, 73% of the CapEx is now committed. Can you talk a little bit about what you're seeing in terms of underlying inflationary pressures, if any, across the different, I guess, buckets of costs?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. I'd say for a lot of the equipment items, those were procured a long time ago and locked in, basically. I'd say a lot of the cost pressures that we've had on the project is related to logistics costs. Incoming ocean freight for bringing materials and equipment to site, that's been our biggest cost pressure that we've had to deal with at this point.

Fahad Tariq
Senior Equity Research Analyst, Jefferies

Okay, great. Thanks, LP.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thanks.

Operator

Your next question comes from the line of Ralph Profiti with Stifel. Please go ahead.

Ralph Profiti
Managing Director, Stifel

Thanks for taking my question. Louis-Pierre, we're sitting here, the Brazilian real is sort of depreciated maybe 10%, 12%. It's certainly providing a tailwind on how you think about costs into next year. Just wondering, are you taking advantage of the situation perhaps by hedging out, and can some of these currency tailwinds be partly offset by increased inflationary pressures locally that we may not have been expecting, say, two or three months ago?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. No, that's a very good observation. Since the Brazilian election, like you said, the Brazilian real has weakened. With that kind of movement in the exchange rate, we've taken the opportunity to hedge about 42% of our exposure for next year at forward rates that are quite attractive versus all of our budget assumptions. Yeah, that's going to be a good relief from a cost pressure point of view. Yeah, we've taken the advantage there to lock some of that in to remove the volatility that could happen as we move forward. Yeah, we won't take it for granted, but yeah, it is a good relief that we have, and that also helps support a lot of the guidance that we had produced for 2027.

Ralph Profiti
Managing Director, Stifel

Got you. Okay, that is great. Great to hear. Secondly, as a follow-up, you mentioned in your prepared remarks some of the exploration spending at Oko that has gone up, and just how many meters are we talking about for this infill program? Is this just a matter of bringing the scope of the two assets together when you talk about that expanded spending, or is something like more geology driving that?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah, exactly. So when we closed the transaction, the G2 team had started the infill drilling program, and we have basically just been continuing that program, and we have 55,000 meters that we have budgeted since the transaction close. We are about, as we speak, about 80% complete on that program, and aim to have it fully complete by the end of the year. So, as we say, this is really the building block for the updated feasibility study. The drilling program has gone extremely well. We have 12 drills turning, and it is making great progress. I would say the bottleneck or challenge that we are dealing with is more the assay turnaround from the assay lab. So that is what we are dealing with in terms of being able to update our integrated feasibility study.

Ralph Profiti
Managing Director, Stifel

Understood. Thanks for taking my questions.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thanks.

Operator

Your next question comes from the line of Harrison Reynolds with RBC Capital Markets. Please go ahead.

Harrison Reynolds
Equity Analyst, RBC Capital Markets

Hi, good morning, G Mining team, and congratulations on a good quarter. Wanted to follow up on the Oko-Ghanie infill drilling program. Any incremental observations on how that's going as it relates to grade continuity you're seeing, or mineralization geometry relative to the historical G2 model? Are you expecting to provide any interim results, or just put those in and have that inform the updated resource?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah, I'd say, based on core observation, we've seen the model to be very predictive. When we drill, we hit visually mineralization as we expect based on the model. Again, to the kind of maybe previous comment, we're still waiting on a lot of assays, so that we have a pretty substantial backlog. I think a lot of the drilling is indicating that our model's very good. What was the second part of your question again?

Harrison Reynolds
Equity Analyst, RBC Capital Markets

Just if you were expecting to release the infill results.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah

Harrison Reynolds
Equity Analyst, RBC Capital Markets

As you receive assays.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah, we won't do it as we receive, but I think the objective is once we do have a substantial amount of them in, we'll likely do an exploration update for Guyana. That's one thing that we would do prior to the feasibility study. Give essentially some color on the continuity and the results we've got. Yeah, we'll be doing that. We're targeting Q1 to be able to release some substantial information on that infill program.

Harrison Reynolds
Equity Analyst, RBC Capital Markets

Got it. That's good. Thank you. On Oko engineering, I wanted to ask how that's progressing. Completion of detailed engineering sounds like it's guided for year-end. Any read-throughs to the overall project schedule or first gold timing here? Would you say around September-ish is still your target for commissioning?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah, so the detail engineering is basically complete now. It's only just what we call construction support for the team on site. Yeah, things are going extremely well. We've de-risked now the critical path with the grinding mills being delivered on site and the start of installation. That September target for start of commissioning is still holding nicely at this point. I would say, despite the infill drilling taking some time to complete, that's not holding us back from progressing on, call it, the engineering of phase II , so the actual expansion of the plant and power plant. We're advancing quite well on that. Essentially, we've already placed a purchase order for the additional ball mill to secure that timeline and essentially start the construction of the expanded plant in 2028.

Harrison Reynolds
Equity Analyst, RBC Capital Markets

Great. Sounds good. Thank you for the detail, and look forward to the ongoing progress. Thanks.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thanks.

Operator

Your next question comes from the line of Rabi Nizami with National Bank of Canada. Please go ahead.

Rabi Nizami
Analyst, National Bank of Canada

Thank you, and hi, LP and congrats everybody. It looks like a good quarter, and I see you guided towards the you're tracking towards the midpoint of guidance, so that seems like a good sign for the grade inflection coming in. Looking forward to 2027, I know grades are rising. Are you also seeing some potential to push the TZ mill throughput a bit higher than the nameplate, or is this entirely driven by grade for next year?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

I mean, currently it's mostly driven by grade. I would say, since we've been running the plant, we continue to have continued improvements on throughput and reliability. So, I think essentially we do expect at some point to be able to push above nameplate. We've been working on some debottlenecking aspects in the plant, and one of the CapEx projects of this year was adding tailings pumping capacity, so that's going to debottleneck the back end. We are looking at, for next year, the addition of a pebble crusher on the grinding circuit. So, those are not very high CapEx projects that we're looking at that would allow us to push additional tonnage. So, those are currently at the study stage, but we still see incremental improvements that we can do on the plant.

Rabi Nizami
Analyst, National Bank of Canada

Got you. So, that would be incremental to the guidance that you issued earlier.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. It's not approved at this point, and would take a certain amount of time to execute as well.

Rabi Nizami
Analyst, National Bank of Canada

Got it. Then, just quickly on power costs for TZ, how much of the processing cost there is for electricity right now? Is 2027 cost, is the power contracted or exposed to market prices in Brazil? Is there any clue on that?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

If we look at this year to date, power costs are about 3% of our AISC. It's not a large percentage of costs. We're currently renewing our power purchase agreement for next year, and we're targeting to lock in at least half of it. We do see rates that have increased since the contract that we established three years ago. But yeah, even if that goes up, it's still a small percentage of our costs.

Rabi Nizami
Analyst, National Bank of Canada

Got it. Makes sense. I remember that was a fairly low contract that you began with, so that's good to hear that it's coming along.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah.

Rabi Nizami
Analyst, National Bank of Canada

The main focus really is on Oko West, I think, going forward. TZ seems like it's coming along nicely. A lot of my questions on Oko West have been answered, but you do also have this Gurupi PEA coming up towards the end of the quarter. You've spoken in the past about expectations for that. I mean, if there's anything new, that'd be nice to hear what you're thinking for expectations there. I'll tie another question to that, which is, you're also filing some permit works along with that. Could you walk us through the permit timeline after the PEA comes out and what to expect at Gurupi going into next year?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. I would say just in terms of advancing that project, it's really the permitting that's going to be the main critical path, I would say, as opposed to drilling and study work. That's why we're really keen to submit our ESIA at year end. I mean, anticipation is maybe towards the end of 2027, we could get the preliminary LI, which then triggers the next step to get to the full LI, which would be in 2028. We do have a small amount of people that are within the project footprint that we need to relocate. A big objective of the next year is to advance that resettlement action plan and progress on that as well. Those are the two main paths that we're dealing with on Gurupi at this point.

Rabi Nizami
Analyst, National Bank of Canada

Excellent. We'll look forward to that. Thank you for answering my questions, and congratulations again.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thanks.

Operator

Your next question comes from the line of Anita Soni with CIBC. Please go ahead.

Anita Soni
Managing Director, CIBC

Hi, good morning. Thanks for taking my questions. I just wanted to dig a little bit more into 2027 outlook. I am just looking at the old guidance of 200-235 for next year, and you are tracking to the midpoint for this year. Is there any reason to modify our expectations for 2027, or does that old guidance still stand?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. For production, we feel that that guidance still stands. Also just because our mine plan has been really catching up with some of the deferred stripping that was not done. Yeah, we are really back in a good shape to execute on 2027.

Anita Soni
Managing Director, CIBC

Okay. I think you probably were. I was going to go to the cost, right? That is the assumption on cost, assuming the $4,000 gold price. I just wanted to get an idea of, at the time in January of 2020, before we had this change in the world regime, what kind of inflationary pressures and diesel prices were you embedding into your assumptions around that? I think it is 14% and 20% decline in cash costs and AISC from 2026 to 2027.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. I think the big factor in our guidance was the exchange rate. We had used 5.55 as an assumption for the exchange rate. I mean, currently we are kind of back in that range. That is the supporting factor that we have with respect to our cost guidance that is helping us at this point. Like we were just saying, the electricity might be a factor that goes up a little bit. It is not a big percentage of our costs. Just maybe on the diesel. We are currently at about $1.30 a liter right now. We had about a dollar $1.01 a liter in our budget assumption. Maybe a bit of inflation there that we could expect on the diesel side versus what we assumed in our guidance.

Anita Soni
Managing Director, CIBC

Do you have a rough ballpark on the sort of like every change, 10% change would result in an X dollar per ounce number?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. I think our estimate that we have is 10% change is about a $5 an ounce impact on our AISC.

Anita Soni
Managing Director, CIBC

Okay. Looking at any of the sustaining capital and non-sustaining, is there anything that you would change in there that we should be considering as we think about 2027?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

I mean, we're going through our budgeting process for next year. I think if we do add some CapEx, it's really going to be towards moving our capacity up in terms of milling rate. To me, if we add to what we've guided, it's going to have positive effects on the overall plan.

Anita Soni
Managing Director, CIBC

Okay. All right. Thank you. That is it for my questions.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thanks.

Operator

Your next question comes from the line of Jeremy Hoy with Canaccord Genuity. Please go ahead.

Jeremy Hoy
Director, Mining and Metals, Canaccord Genuity

Hi, LP, Julie, and JF. Just one quick follow-up for me, and it is on Gurupi. You have had a lot of exploration success there. It looks like resources could grow pretty significantly. Following up on Rabi's question and evolution in thinking on what that operation ultimately looks like, we have been asking for details ahead of the PEA, and you have said potentially a plant a little bigger than TZ. Given the exploration results and what you are seeing, is the thinking around scale potentially changing, or is the direction you have provided earlier still really what you would give now?

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. I would say with exploration, it is always difficult to get the full answer. We have had great success, I would say, on drilling new zones that have proved to be mineralized. Maybe not all of that gets transitioned into the PEA, but I would say based on what we know now, we are going to have enough resources, call it mineable resources, to support a milling rate of 5.8 million tons per annum. So, that is essentially closer to Oko phase one in terms of throughput. So yeah, we see it as a resource base that can really support a high-scale operation.

Jeremy Hoy
Director, Mining and Metals, Canaccord Genuity

Great. Thank you. Looking forward to that study, and I'll step back in the queue.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Thanks.

Operator

Your final question comes from the line of David McCausland with Shareholder. Please go ahead.

David McCausland
Private Investor

Excuse me. Good morning. Well, you're doing a really good job on elucidating how much you know about the projects that you're doing, and I certainly appreciate the forthcomingness. I've been a shareholder before G Mining bought the Oko West property from Reunion, and I also have been a shareholder in G2 Goldfields, which they also did a great job in developing their resource. You did some exploratory drilling up near G2 Goldfields' property just before you did the acquisition of G2 Goldfields, and now you're doing a lot of more drilling in the G2 Goldfields property. Is it possible that you're going to make a major change in the size of the pit that you're going to start out with and possibly have it exploit both the property lines, basically, both north and south? Last question is, there's a neighbor of yours, Tajiri.

Are they in the way of a major expansion of the mining there? Thank you.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah. With the combination of all the deposits with the Oko-Ghanie and Oko Main, we do have the opportunity to initiate mining on the Ghanie side ahead of, in an accelerated version, in our integrated project. Yes, we do see the ability to increase the mining rates and actually be mining in Oko West and Ghanie in the early years of the mine life. That's kind of point number one. It allows for a lot of optimization and flexibility in the mine plan. We don't see the pits growing substantially in the sense that it's more of a trade-off between open pit and underground, where it's just beneficial to go underground at some point and reduce the strip ratios. Yeah, with that, we don't see the pits encroaching or getting outside of our boundary limits. Nothing really touches the Tajiri.

David McCausland
Private Investor

Okay

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Mine package. Yeah.

David McCausland
Private Investor

Okay. Well, thank you very much, and I hope all the good development keeps going. We need the gold, so okay.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

Yeah.

David McCausland
Private Investor

Thank you very much.

Louis-Pierre Gignac
President and CEO, G Mining Ventures

No, team is doing a great job, so thanks. Thanks for the question.

Operator

There are no further questions at this time. I will turn the call back to Jean-François Lemonde for closing remarks.

Jean-François Lemonde
VP of Investor Relations, G Mining Ventures

Thank you, everyone, for joining us today and for your continued interest in G Mining. We are, of course, focused on delivering a strong finish to the year as we look ahead to what promises to be a transformational year ahead for the company. On this, have a great day, and if you have any further questions, please feel free to reach out to me directly anytime. Thank you. This concludes the conference call.

Operator

Ladies and gentlemen, you may now disconnect.