Thank you, and welcome, everyone. I am joined today by David Park, our CEO and Director, Andy Robinson, President, COO, and Director, Salah Gamoudi, Chief Financial Officer, and Mike Barman, Chief Development Officer. Before we begin, I would like to start with a reminder that some of the statements made during our call today, including any related to company performance, expectations, and timing of projects, may constitute forward-looking statements. Please note the cautionary language about forward-looking statements contained in our press release, which also applies to this call. I will now turn the call over to David.
Thanks, Dan, and thank you to everyone for joining us today. To begin the year, we laid out the four primary deliverables required to be completed before taking FID at our SWA Project: executing key construction contracts, completing a federal environmental review under the National Environmental Policy Act, or NEPA, finalizing our customer offtake agreements, and securing project financing. After completing the first two of these objectives in the second quarter, we were able to conclude the customer offtake process in the third quarter while making significant progress in advancing project financing, now the key remaining work stream prior to reaching FID. These are substantial achievements that are the culmination of years of work by our team and our partners. We secured long-term commercial agreements with one of the world's leading battery producers in LG Energy Solution, as well as one of the largest global commodity traders in Trafigura.
This has been one of the most important and time-intensive work streams, and we now have the volume commitments needed to support finalizing the project debt financing. We continue to advance the project financing process and have been working closely with the export credit agencies, each of which remains focused on supporting the strategic SWA Project. Their comprehensive due diligence review is now substantially complete without any material concerns being raised, and we're now targeting over $1.2 billion in total senior secured project debt, exceeding initial expectations of up to $1.1 billion. The ECA-led financing process has taken longer than initially anticipated. However, we've not lost sight of the tremendous opportunity to put a highly attractive financing package in place that will fund a substantial portion of the project's capital requirements.
It's been worth the effort, and it's important to take the time necessary to structure it optimally to ensure success for all parties. Based on the latest financing timeline, we expect to take FID by the end of the first quarter of 2027, with construction beginning shortly thereafter on a two-to-three-year timeline. Finally, in the third quarter, we released a preliminary economic assessment for the Franklin Project in East Texas, our first of several planned projects highlighting the strength of one of the biggest and highest-quality lithium brine resources in North America. It has the potential to produce up to 70,000 tons of battery-quality lithium carbonate annually and is a key part of our plans to build a world-class portfolio of lithium projects. I'll now turn the call over to Andy.
Thanks, David. Completing the commercial offtakes last quarter was a substantial achievement for the SWA Project. In August, we signed our second binding take-or-pay agreement, this one with LG Energy Solution, one of the world's leading lithium-ion battery producers and the largest outside of China. The project will supply LGES with 8,000 t per year of battery-quality lithium carbonate over a 10-year period following the start of commercial production. Pricing and other key commercial terms are subject to confidentiality, but have been structured to support the project financing. In September, we amended our binding agreement with Trafigura, one of the largest global commodity traders, who provides valuable access to multiple industry supply chains that rely on lithium chemicals, along with a broad suite of customers. Similar to LGES, the original agreement was for 8,000 tons per year of battery-quality lithium carbonate on a take-or-pay basis over a 10-year period.
Under the amendment, our joint venture with Equinor now has the option, at its own election, to supply up to an additional 4,000 tons of battery-quality lithium carbonate in each year of the agreement. Combined with the initial commitment, the maximum possible volumes to be delivered to Trafigura on a take-or-pay basis has increased to 12,000 tons per year. The amendment also provides valuable production flexibility because the additional volume is deliverable solely at our election, and we retain the ability to allocate that volume to other strategic customers in the future if a superior commercial or strategic opportunity emerges. The financing-driven target for the SWA Project was to secure binding customer offtake agreements for roughly 80%, or 18,000 tons, of the 22,500 tons of annual nameplate lithium carbonate capacity in its initial phase.
Between our two customers, total commitments have now reached 16,000 tons of battery-quality lithium carbonate per year, with the additional 4,000 tons that can be sold at our discretion to either Trafigura or another party. The total of 20,000 tons of contracted volumes exceeds our financing thresholds. These agreements give us long-term commitments from two globally leading counterparties, and our expanding partnerships are a testament to the high quality of the SWA Project and the importance of our role in developing a scalable and competitive domestic lithium supply chain. Most importantly, with the customer offtake process now complete, we moved to finalizing and closing the SWA Project financing as quickly as possible before taking FID and moving into construction.
In the meantime, we continued to make meaningful progress with our EPC and Wood, who is overseeing the upstream well field, and our EPCC, S&B, supported by Hatch, who are responsible for the central processing facility. They have been operating under a limited notice to proceed for the last six months, focusing on key activities to de-risk the SWA Project and optimize the construction schedule.
This includes detailed engineering, identifying long lead time items with vendors, completing relevant construction permitting, building the team, and engaging with the community. They are expected to transition to the full and finalized EPCC and EPCM contracts once the JV takes a positive FID. We will also be completing some important pre-FID works in the coming weeks, including tree clearing in key locations, so we are able to support the planned construction schedule. Standard Lithium also achieved an important technical milestone with one of its collaboration partners, Nano One.
Nano One used lithium carbonate from our SWA pilot plant to produce lithium iron phosphate cathode material and battery cells in North America. That result helps to further validate that SWA project's process flow sheet and the suitability of our material in downstream battery applications. It also speaks to our commitment to technological innovation and support for the development of a domestic, fully integrated energy storage supply chain. Separately, in September, we announced a preliminary economic assessment for the Franklin Project in East Texas before filing the underlying report the following month.
The PEA contemplates annual production capacity of up to 70,000 TPA of battery-quality lithium carbonate and is highlighted by attractive economics, including an unlevered pre-tax net present value of $5.9 billion on a 100% ownership basis, assuming an 8% discount rate, an internal rate of return of 26%, and a three-year payback period, along with average annual lithium cash operating costs of roughly $4,200 per ton and a capital intensity of just under $50,000 per ton. Additionally, it includes an upgrade and upsized mineral resource from the maiden resource estimate that was published last year, with some of the highest lithium and brine concentrations reported in North America.
The new indicated resource is 1.77 million tons LCE at an average lithium concentration of 562 mg/L , while the upgraded inferred resource is 2.13 million t LCE at an average concentration of 572 mg/L . The PEA also considers a scenario based on a co-located bromine facility of 50,000 tons per year alongside the lithium operation. Standard Lithium and Equinor plan to further evaluate potential commercial opportunities for both bromine and potash, given the significant scale and quality of the resources, as well as the designation of potash as a U.S. critical mineral in 2025. The Franklin PEA demonstrates the strength of one of the largest and highest quality lithium brine resources in North America.
These latest results establish a strong foundation to advance the Franklin Project as the first of our large-scale projects planned within a much broader East Texas position and underscore the scale and national importance of our resource footprint. It supports our longer-term goal of producing more than 100,000 tons of lithium chemicals annually in Texas across multiple phases and projects, and we will continue to fill in our leasehold and advance resource definition across that position. The joint venture has just commenced additional drilling activity in the project area and will be advancing technical de-risking of the project with the goal of moving the Franklin Project to a Preliminary Feasibility Study. I will now turn the call over to Salah Gamoudi to discuss our financial results and the SWA Project financing in more detail.
Thank you, Andy. For the third quarter ended September 30, 2026, we reported a net loss of $36.7 million compared with a net loss of $6.1 million in the same quarter last year. The main driver of the higher loss was a $41 million loss on the financial assets associated with contingent FID payments from Equinor due to fair value remeasurements. Partially offsetting this loss was the recording of a deferred income tax benefit of $10.9 million for the quarter. Under our agreement with Equinor, a $40 million contingent payment to Standard Lithium was tied to achieving FID at the SWA Project by January 1, 2027. Based on our latest estimate of being in a position to take FID and the resultant change in target date, we no longer expect to reach FID by that contractual deadline.
We therefore reduced the carrying value of the contingent payment to zero, resulting in a $31.4 million fair value remeasurement loss in the quarter. It is important to emphasize that this adjustment solely reflects the expected timing of FID relative to the payment deadline and in no way reflects any change in our assessment of the overall likelihood of achieving FID or a change in our view of the underlying fundamentals or prospects of the project. In fact, our confidence in being able to take FID at SWA has improved, given that we have now secured all required offtake contracts in support of our project finance process, continue to advance limited notice to proceed activities with our EPC contractors, are past most stages of diligence with our ECA project financiers, and continue towards securing final terms and preparing definitive documentation in that effort.
The remaining $9.6 million fair value remeasurement loss for the quarter relates to a separate $30 million contingent payment under our agreement with Equinor that is tied to taking FID at the Franklin Project or any of our other assets in East Texas by January 1, 2029. With the delay at and current focus on taking the SWA Project to FID and beginning construction, and the resultant extension of SWA Project completion timelines, we expect that our attention, capital allocation, and focus on execution at SWA will lower the probability of achieving FID at our first project in East Texas by the contractual deadline for our contingent FID payment. This resulted in a remeasurement of the financial asset down to $10.6 million. This change does not reflect a reduction in our view of the probability or likelihood of achieving FID in East Texas.
To the contrary, with the recent issuance of our PEA for the Franklin Project, demonstrating immense resource production and value creation potential, we are more confident in our ability to develop our East Texas leasehold positions than before. Turning to operating costs, G&A held fairly flat during the third quarter of 2026 compared to the same quarter in the prior year at $3.1 million. Higher personnel costs were offset by lower consulting and professional fees as we brought some functions in-house as we continue to mature the business. Demonstration plant costs were $1.0 million, down from $1.1 million during the same quarter in the prior year, as more of the work was focused on and allocated to Smackover Lithium project development.
Our share of the Smackover Lithium joint venture's loss was $1.8 million compared to a $0.9 million loss in last year's quarter, driven primarily by increased development, commercial, and operating activity at the JV partnership level for SWA as we move closer to FID, and at East Texas as we continue to both expand our leasehold position and advance our understanding of the resource. Interest income increased by $1 million year-over-year to $1.2 million, reflecting higher average cash balances. Foreign exchange impact was immaterial this quarter following a July 1st, 2026 change in Standard Lithium's accounting policy, changing from a functional currency in Canadian dollars to US dollars at our parent company level. This change was effected as currently and for the foreseeable future, the majority of our capital raised and spent has been and will be in US dollars.
We ended the quarter with a strong cash balance of $118.1 million and $114.4 million in working capital. Standard Lithium has no term or revolving debt obligations outstanding. For the quarter, we contributed $19.3 million to Smackover Lithium, with $11 million going to SWA and $8.3 million going to East Texas. Through the first nine months of the year, this was $46.5 million to Smackover Lithium, or $26.1 million and $20.4 million to SWA and East Texas respectively. These contributions supported advancing key required milestones ahead of taking FID at SWA, including entering into our EPC contracts, offtake agreements, continuing to advance the ECA financing process, and limited notice to proceed activities by our EPC contractors, including early-stage engineering and other work that will help de-risk our construction and commissioning timelines.
However, we aren't a one-project company, and we've continued to increase our leasehold position, understanding of the resource, and de-risking of our projects in East Texas, including preparing the PEA for the Franklin project. We raised approximately $300,000 in gross proceeds under our existing at-the-market equity program during the third quarter, bringing the year-to-date total to $22.4 million. This was a significant pullback in activity, particularly in more recent months, in light of the weaker equity market environment. We will continue to be disciplined and prudent in our potential usage of this program. Turning to SWA project financing, we continue to work closely with our selected ECAs, including the Export-Import Bank of the United States, Export Development Canada, and Export Finance Norway, among others. Key diligence work streams have mostly been concluded as we move towards reaching final terms and definitive documentation.
Our SWA project is shovel-ready, and concluding on the ECA process is one of the final steps in enabling us to pick up that shovel and start digging. We are now targeting over $1.2 billion in total senior secured project debt, exceeding our initial expectations of up to $1.1 billion. The company is actively working to finalize all additional lender funding requirements, including a cost overrun facility, other reserve accounts, and contingencies. This will ultimately inform the final SWA project capital funding requirements. Incremental capital requirements beyond the senior secured project debt are expected to be financed by our $225 million grant from the Department of Energy, of which we expect approximately $200 million will be remaining when we take FID, as we have been collecting on the grant as a cost share during this past year, as well as respective funding contributions from Standard Lithium and Equinor.
The equity contribution required by Standard Lithium will be supported in part by the proceeds from our equity raise last year, as well as additional funding sources. We continue to believe the scale, structure, and terms of the debt we are pursuing via the ECAs and a strong syndicate of commercial banks are extremely attractive for the SWA Project when weighed against numerous alternatives that were evaluated. We believe the financing opportunity fully justifies the meaningful time and effort required to complete it, which we expect to demonstrate in due course. Under the current financing timetable, we expect to reach FID by the end of the first quarter of 2027 and to begin construction shortly thereafter. With that, I'll turn it back over to David.
Thanks, Salah. We said last quarter that we expected to complete the customer offtake process and publish the Franklin PEA in the third quarter. We delivered both. These are very important achievements that have been many months in the making. At SWA, the commercial agreements with LG Energy Solution and Trafigura give us clear visibility to finalize the project financing and provide greater confidence and validation as we prepare to move quickly from development into construction. At Franklin, we now have a foundational asset in East Texas on which to build upon while strengthening our first-mover advantage in the Smackover formation. This progress reflects years of technical, engineering, and commercial work by our team and our partners. Our focus, alongside Equinor, is on securing financing, completing the work needed for FID, and being ready to move promptly into construction once that decision is taken.
We are committed to keeping you updated as that work progresses. Before we open the call for questions, I'd like to welcome Ralph Alexander, who joined our board as an independent director in October. Ralph brings more than four decades of leadership across energy, chemicals, power, and infrastructure, and we look forward to leveraging his highly valuable and relevant expertise. Thank you again for joining us today. Operator, I'll turn it back to you for questions.
We will now begin the question-and-answer session. If you would like to ask a question, please press star one to raise your hand. To withdraw your question, press star one again. We ask that you pick up your handset when asking a question to allow for optimum sound quality. If you are muted locally, please remember to unmute your device. Please stand by while we compile the Q&A roster. Your first question comes from the line of Katie Lachapelle from Canaccord Genuity. Your line is now open. Please go ahead.
Hi, all. Thanks for taking my question. Last week, we saw Lithium Americas increase the capital cost at Thacker Pass for 30%. The key drivers that they noted were labor rates in the United States impacting a number of projects, as well as inflation and tariffs. The question is, how comfortable are you guys feeling around the last published capital cost number that you put out on phase I, and is there a plan to update it prior to FID next year? Thanks.
Yeah. Thanks, Katie. We are continuously assessing the situation and tracking our peers. We do not expect cost pressure of that order of magnitude on our project. I think you'll note a different nature of operations and a different contracting strategy. You'll remember that our cost estimate of approximately $1.5 billion was grounded in a DFS and a FEED that was 18 months of work in the making. In the first quarter of last year, or sorry, the first half of last year, we contracted with our EPC contractors who validated those numbers. In our contracts that we let, we built in tariffs and escalation into those contracts. Additionally, we picked a contractor who is supplying their own craft labor, which is different than the situation you cite.
The nature of our construction is modular and doesn't require the large, complex logistics and staffing required to deliver on site. I believe our peak construction at site peaks out at approximately 600 people, not the many thousands of people you'll see in some of the other operations that are cited. In addition, our contracting structure has built in incentives for our contractors to deliver on time and on budget. So, we feel comfortable that the guidance we've provided to date is the best guidance at this point in time. However, we will be updating in the first quarter around FID, providing further guidance.
Okay, awesome. A similar question on the operating costs. Are you seeing areas of potential cost pressure on different inputs or reagents? Or perhaps on the flip side, are you seeing areas for optimization?
Yeah. We're not seeing cost pressure that gives us concern on the operating side. The last six years of operating the demonstration facility, the team has been very focused on developing a process and a flow sheet that minimized the use of reagents and kept reagent costs to a minimum for fear of potential reagent and escalating costs. Both reagents, power, labor, all of those, I think we feel comfortable with the estimates we have on our operating costs.
Got it. Thank you, guys. It's very helpful. I'll turn it back.
Your next question comes from the line of Max Yerrill with BMO Capital Markets. Your line is now open. Please go ahead.
Hey, guys. Thanks for taking my question, and just following up on the last one. If you're still comfortable with the $1.5 billion CapEx estimate, could you provide a little more color on the thinking between needing the $1.2 million of debt, or $1.2 billion, excuse me, of debt? Is that to fund reserve accounts, a change in how you're thinking of the debt equity mix? Anything you can provide is helpful. Thanks.
Salah, do you want to give a breakdown on that?
Sure. Happy to. We do have the $1.5 billion base CapEx, which is grounded in our FEED study and DFS. When you look at the potential targeted senior secured debt of $1.2 billion, plus the $200 million grant, plus the split between us and Equinor for the remaining equity need, being 45/55 to us, that on its face would seem to be a fairly light load. However, what we need to make sure folks are aware of is that as part of the senior secured financing process, there are additional contingencies to that $1.5 billion base CapEx, additional reserves, debt service reserve accounts. There is cost overrun facilities. There are minimum working capital balances. There are additional needs that can increase your total capital requirement beyond base CapEx figures.
While we do not think that we are going to see, as David mentioned, an order of magnitude of CapEx increase as some other projects around the world that have been in construction or approaching construction, there are additional capital requirements which we will need to solve for. As of right now, we are working with the export credit agencies to define exactly what those figures are, and they are still subject to negotiation, which we hope to wrap up here, as we have mentioned, by Q1.
Thanks, Salah. That is helpful color. I will turn it back over.
Your next question comes from the line of Joseph Reagor with Roth Capital Partners. Your line is now open. Please go ahead.
Hey, David and team. Thanks for taking the questions. Following a bit on the financing side, the market has made around these contingent payments. Just for clarity, because the verbiage was a little hard to follow, do you guys still have contingent payments you expect to receive, and did you lose any as a result of this delay? Because I know you took the accounting adjustment, but is there still an opportunity to get Equinor to make these payments, or is the deadline passed, you don't get the payment?
Yeah, I'll take that one, Joe. Thanks for the question. With respect to the milestone payment for SWA, that payment will be lost in its entirety if we do not meet a year-end FID. What we're saying at this point in time is we're now targeting first quarter FID. I think the best assumption is that we will not get that $40 million payment from Equinor.
Okay. Given that, was that part of the reason you went from 1.1- 1.2 on the debt, or is there now an equity need that's not covered? How should we think about the impact of losing that payment?
Well, first, those are really two different issues. At one point in time, we believed with the export credit agencies, we would be able to source up to $1.1 billion, and now we believe we have the potential to source over $1.2 billion. That is more a reflection of the ECAs doing their technical diligence, commercial diligence, and financial diligence, and telling us how much debt they believe the project can support. That is a different issue than the $40 million issue. That said, if we were to have been able to collect that $40 million issue, that would be $40 million less equity that Standard Lithium would need to contribute into the project. I do not know, Salah, if you would like to say that differently. You would like to add to it or say it differently?
No, I think you couched it correctly, David. I mean, it is a one-for-one increase in the equity that we will need to come up with in order to take FID at SWA for our portion of the capital contribution, for our 55%. We were going to receive the $40 million before. Now that our base case targets a Q1 2027 FID, that will be past the date on which we can collect that $40 million. So, $40 million will have to come from somewhere. That can come from a variety of sources, namely our balance sheet, which has significant cash position as of this disclosure, but also any sort of incremental capital that we raise as part of this process.
There is a second FID payment, so not to get too into the weeds, but just to make clear, there is an East Texas FID payment for $30 million, which would be effective if we take FID on our first East Texas project by 1/1/2029. We still, on a probability-weighted basis and on a discounted basis, have reflected that in our balance sheet and still have some expectation that we may be able to collect on that payment for East Texas.
Cool. All right. Thanks for the added color there, Salah. It made it easier. All right, guys. I will turn it over.
Your next question comes from Daniel Magder with Raymond James. Your line is now open. Please go ahead.
Afternoon, everyone. Understanding you're shovel-ready here under the limited notice to proceed, just how quickly can you move from development to construction post-FID?
Yeah, thanks, Dan. Good question. The team is continuing to work, as you said, under limited notice to proceed. We believe that with that, we're advancing engineering, we're advancing, our contractors are advancing their dialogue with vendors. So we should be, assuming a first quarter FID, we should be beginning construction and very active in the second quarter. So, we plan to hit the ground running at this point in time.
Got it. And I guess just shifting focus here, but post the release of the Franklin PEA, have your thoughts around sequencing shifted, I guess, related to SWA and Franklin?
Yeah, I'd say it is premature to give a definitive answer at this point in time. Clearly, the Franklin project is a very attractive project and a high priority for us longer term. Right now, priority one is getting SWA phase I to FID and begin construction. In parallel with that activity, we will continue our exploration program in East Texas, and hopefully sometime next year make a decision with respect to brownfield funding of, whether we advance brownfield SWA or Franklin project next. But right now, priority one is SWA phase I.
Understood. I will back go back in the line. Thanks.
Your next question comes from the line of Eric Boyes with Evercore. Your line is now open. Please go ahead.
Good afternoon, and thanks. Two for me. I think that the $1.5 billion budget, the original one included a 12% contingency. I realize the precise numbers are still being finalized, but given the inflationary environment, does it make sense that we should expect a larger 15%-20% contingency on top of revamped prices?
Yeah, I think it is fair to say that that number did include contingency. When Salah is quoting cost overrun facilities, other contingencies, and other reserve accounts, these are contingencies over and above that number that the export credit agencies would like us to put in place. I do not know, Salah, if you would like to say anything more than that.
No, what I would say there, Eric, is that these are still terms that are matters and subjects of negotiation. We cannot give you a precise set of figures as to what the contingency percentages are, how we are viewing that. The DFS comes up with an estimate at a point in time, based on a very, very detailed engineering analysis, and statistical analysis that supports it. But there are other risks that the ECAs need to round out above and beyond that and get comfort with. As a result, would we expect there to be increased contingencies over and above what is in a Definitive Feasibility Study? Yes, that is very typical, and is within market trends and practices that we have seen on other projects.
Do we expect that the base CapEx figure, including contingency, will increase in order of magnitude as what we have seen in some other recent developments in some lithium projects? At this time, we do not expect that.
Got it. Okay, thanks. Second, would just be what kind of minimum Franklin spending preserves progress there, the PFS in 2027? Thanks.
Salah, why don't you take that one?
Sure. I would say that we haven't put out specific guidance on that, Eric, but as juxtaposed to the capital requirements at SWA, it'll be much, much smaller. I think that historically, we've spent for our portion of the CapEx that has gone into East Texas, in the $20 million-$40 million range per year. I would expect that that would be maybe even on the lower end, the level of spend that we would expect to conduct in East Texas in order to keep advancing those projects. But as we've mentioned, and as I'll say again, reiterating what David said earlier, our focus is taking FID at South West Arkansas, contributing capital to South West Arkansas, and getting to production at South West Arkansas. That is the number one goal of this company at this point in time. We are not a one-project company.
We will continue to develop others, but South West Arkansas is number one and our primary focus.
Great. Thank you.
Your next and final question comes from the line of Noel Parks with Tuohy Brothers Investment Research. Your line is now open. Please go ahead.
Great. Thanks. I guess, as I heard your discussion of the deadline for the payment from Equinor, I guess I'm just surprised that there wasn't some openness to renegotiation on that condition, given that the offtake was in place. I imagine that sort of the Norway ECA's participation probably maybe wouldn't have happened or wouldn't have been in the mix if Equinor had not been the partner. Does this signal some sort of chilling of the Standard-Equinor relationship, that they weren't willing to extend sort of some flexibility on the payment condition?
Yeah, no, great question. First, I'll say our relationship with Equinor remains very strong. We work day in, day out with them. Their team is salt and peppered in the joint venture team, so we work alongside them on a regular basis. We also have an ongoing dialogue with their leadership. They are very excited about the SWA Project and working diligently alongside us to try and get it to a positive FID by the end of the first quarter. Strategically, this is something they want to see get done, and they want to see it get done as quickly as possible. Frankly, this is an item that was a negotiated term when the joint venture was put in place. There was a deadline with an incentive. We missed it, and it was not their doing that we missed it.
We are where we're at on it, but it is not a sign of their commitment to the project, and we continue to work very well together.
Okay, thanks. One thing I was interested in is, could you talk a bit more about how the option with Trafigura works on your option for the additional 4,000 TPA of offtake at Standard's option?
Sure. Mike, would you like to provide some color on that one?
Sure, no problem. The Trafigura option is an option in any year during the term of the contract to have Trafigura take up to an additional 4,000 tons for the following year. The benefit of that option is that it really gives us a lot of flexibility in terms of how we utilize it, how we look for other areas or opportunities for strategic or financially beneficial alternative offtake, effectively with the Trafigura option as a backstop. For example, we were really quite intent on getting long-term offtake, as you saw with the two contracts that we have for 10 years.
10 years is an exceptionally long term for most customers, therefore, we can now look at, for example, a broadened scope of offtake where we can get a five-year contract and then use the Trafigura option as the backstop for the remaining five years to meet the obligations of the lenders. The Trafigura option was very beneficial for our process and allows us maximum flexibility going forward while also meeting the obligations of the lenders in terms of the volume commitment.
Great. I just wondered if you had any thoughts on lithium macro at this point, since there is the I forget the baseline price that is in $22,400 that is assumed in the East Texas PEA. Now, at the moment, we have prices sort of below that. I was wondering if you had any thoughts on just where pricing stands right now.
Sure, great question. We continue to feel that pricing in the long-term pricing in the range of that $20,000-$25,000 a ton is the right range to be using. We see long-term demand growth that requires new builds to come online and incentive pricing for those new builds to come online. Based off our dialogue with our end customers, as well as with others who would like to buy our product, as well as frequent dialogue with leading industry consultants, we continue to think that something in and around $22,000 is the right long-term price forecast.
Great. Thanks a lot.
There are no further questions at this time. This concludes today's call. Thank you for attending. You may now disconnect.