Q2 operating earnings were $0.62/share, with H1 earnings up 15% YoY; mild weather and Millstone’s outage were offsets. FY guidance held at $3.35-$3.65/share as investment in generation, pipelines, solar and Cove Point advanced.
Good morning, and welcome to Dominion's second quarter earnings conference call. On the call today, we have Tom Farrell, CEO, Mark McGettrick, CFO, and other members of senior management. At this time, each of your lines is in a listen-only mode. At the conclusion of today's presentation, we will open the floor for questions. At that time, instructions will be given as to the procedure to follow if you would like to ask a question. I would now like to turn the call over to Tom Hamlin, Vice President of Investor Relations and Financial Planning, for the safe harbor statement.
Good morning, and welcome to Dominion's second quarter 2014 earnings conference call. During this call, we will refer to certain schedules included in this morning's earnings release and pages from our earnings release kit. Schedules in the earnings release kit are intended to answer the more detailed questions pertaining to operating statistics and accounting. Investor relations will be available after the call for any clarification of these schedules. If you have not done so, I encourage you to visit the investor relations page on our website, register for email alerts, and view our second quarter earnings documents. Our website address is www.dom.com. In addition to the earnings release kit, we have included a slide presentation on our website that will guide this morning's discussion. Now for the usual cautionary language.
The earnings release and other matters that will be discussed on the call today may contain forward-looking statements and estimates that are subject to various risks and uncertainties. Please refer to our SEC filings, including our most recent annual report on Form 10-K and our quarterly report on Form 10-Q, for a discussion of factors that may cause results to differ from management's projections, forecasts, estimates, and expectations. Also on this call, we will discuss some measures of our company's performance that differ from those recognized by GAAP. Those measures include our second quarter operating earnings and our operating earnings guidance for the third quarter and full year 2014, as well as operating earnings before interest and tax, commonly referred to as EBIT.
Reconciliation of such measures to the most directly comparable GAAP financial measures we are able to calculate and report are contained on schedules two and three and pages eight and nine in our earnings release kit. Joining us on the call this morning are our CEO, Tom Farrell, our CFO, Mark McGettrick, and other members of our management team. Mark will discuss our earnings results for the second quarter and our earnings guidance for the third quarter and full year 2014. Tom will review our operating and regulatory activities and review the progress we have made on our growth plans. I will now turn the call over to Mark McGettrick.
Good morning. Dominion reported operating earnings of $0.62 per share for the second quarter of 2014, which was in the upper half of our guidance range of $0.55-$0.65 per share. Excluding the $0.02 per share impact of milder-than-normal weather, second quarter operating earnings would have been at the top of our guidance range. Positive factors during the quarter were lower-than-expected operating and maintenance expenses, lower-than-expected interest expense, and a lower effective tax rate. Offsetting these positives were lower kilowatt-hour sales due to mild weather and the impact of an unplanned outage at our Millstone nuclear plant. On a year-to-date basis, our 2014 operating earnings are $0.22 per share better than the first half of 2013. GAAP earnings were $0.27 per share for the second quarter.
The principal difference between GAAP and operating earnings was a $191 million charge associated with Virginia legislation signed into law in April that permits Virginia Power to recover through base rates 70% of the cost previously deferred or capitalized through the end of last year relating to the development of a third nuclear unit at North Anna and the development of offshore wind facilities. A reconciliation of operating earnings to reported earnings can be found on schedule two of the earnings release kit. Moving to results by operating segment. At Dominion Virginia Power, EBIT for the second quarter was $243 million, which was below the midpoint of its guidance range. Kilowatt-hour sales were below expectations, largely due to milder-than-normal weather. Excluding weather, sales were up about 1% year to date, somewhat below expectations.
Second quarter EBIT for Dominion Energy was $215 million, which was near the top of its guidance range. Higher transportation and storage revenues and lower operating expenses drove the strong results. Dominion Generation produced EBIT of $306 million in the second quarter, which was below the midpoint of its guidance range. EBIT from utility generation was below expectations due to lower-than-expected kilowatt-hour sales, reflecting mild weather. EBIT from merchant generation was impacted by an unplanned outage at Millstone. A loss of off-site power caused both units to shut down automatically, as designed. Millstone Unit 2 was unavailable for three days, and Unit 3 was unavailable for nine days. On a consolidated basis, our effective tax rate was 31% for the quarter, which was below our guidance of 33%. Interest expenses were also a little lower than our expectations.
Overall, we are very pleased with our second quarter and year-to-date operating results. Moving to cash flow and treasury activities, funds from operations were $1.7 billion for the first half of the year. Regarding liquidity, we had $4.5 billion of credit facilities at the end of the second quarter. Commercial paper and letters of credit outstanding at the end of the quarter were $3.2 billion. Taking into account cash and short-term investments, we ended the quarter with liquidity of $1.6 billion. During the second quarter, we executed final agreements with our existing credit providers to increase our credit lines by $1 billion, from $3.5 billion to $4.5 billion, the terms of which will run for five years. Dominion Gas Holdings was also added as a potential borrower under these facilities.
For statements of cash flow and liquidity, please see pages 14 and 25 of the earnings release kit. Now moving to our financing plans. Earlier this month, we issued $1 billion of mandatory convertible securities. The issue was very well received by the market, and we thank those of you who participated. During the second quarter, we also filed the Dominion Gas Holdings Form S-4 registration statement with the SEC. This quarter's Form 10-Q filing will include financials for Dominion Gas for the first time. The $1.2 billion of Rule 144A bonds issued last fall are expected to be exchanged for registered securities next week. We have also filed a combined shelf registration for future debt issuances, including expectations for a debt issue of approximately $1 billion for Dominion Gas in the fourth quarter.
On March 28, we filed an Form S-1 registration statement with the Securities and Exchange Commission for an initial public offering of common units representing limited partner interest in Dominion Midstream Partners, LP, a master limited partnership whose initial asset will be a preferred equity interest in Cove Point. We expect to commence the offering later this quarter after receiving FERC approval to begin construction of the Cove Point export project. Now to earnings guidance. Our operating earnings guidance for the third quarter of 2014 is $0.90-$1.05 per share, compared to $1 per share for the third quarter of 2013. Mild weather impacted last year's third quarter earnings by $0.04 per share. Last year's results also included $0.07 per share from the contribution of the TL388 pipeline to Blue Racer.
The midpoint of this year's third quarter guidance range is flat to last year's results when normalized for weather and the asset drop. Positive factors for the quarter include a return to normal weather, higher revenues from our rider projects, and higher merchant generation margins. Offsetting factors include higher interest expenses and higher operating and maintenance expenses. Our operating earnings guidance for the year remains at $3.35-$3.65 per share. Through the first half of the year, we are up $0.22 per share, or 15%, over last year. As to hedging, you can find our hedge positions on page 27 of the earnings release kit. Since our last earnings call, we have made no changes to our hedges at Millstone. Let me summarize my financial review.
Operating earnings were $0.62 per share for the second quarter of 2014, in the upper half of our guidance range. Excluding the impact of mild weather, earnings would have been at the top of our range. Lower-than-expected operating expenses, interest, and taxes offset mild weather and the impact of an unplanned outage at Millstone. Year-to-date operating earnings were $0.22 per share, or 15% higher than the comparable period in 2013. Our financing plan for the remainder of 2014 include a debt offering for Dominion Gas Holdings and the initial public offering of Dominion Midstream Partners. Finally, our operating earnings guidance for the third quarter of 2014 is $0.90-$1.05 per share. Our operating earnings guidance for the full year remains $3.35-$3.65 per share.
I will now turn the call over to Tom Farrell.
Good morning. Our business units delivered strong operational and safety performance in the second quarter. Our nuclear fleet continues to operate well, completing two refueling outages last quarter. As Mark mentioned, a loss of off-site power triggered an automatic shutdown of Millstone Power Station on May 25. The loss was due to a problem with the local utility's substations, not the generating facility, and backup emergency diesel generators maintained both units in a safe and stable condition until off-site power was restored. We continue to make progress on our growth plan. Construction of the 1,329 MW Warren County combined cycle plant is progressing on schedule and on budget. Startup and commissioning activities are underway, and one of the combustion turbines completed first fire last week. The project is about 90% complete and is expected to be in service during the fourth quarter.
Last August, we began construction of the 1,358 MW combined cycle facility in Brunswick County, Virginia, and expect that plant to be in service by mid-2016. Currently, there are about 680 workers on the site. Procurement is 92% complete, and all major equipment has been delivered. Overall construction is about 20% complete and is on time and on budget. The conversion of Bremo units three and four from coal to natural gas was completed during the second quarter, on time and on budget. Construction is also on schedule for six solar projects totaling 139 MW purchased earlier this year from Recurrent Energy. Long-term power purchase, interconnection, engineering, procurement, and construction, as well as operation and maintenance agreements have been executed for each of the projects. All of these facilities are expected to reach commercial operation later this year.
In the second quarter, Dominion acquired two solar development projects in Tennessee and announced plans to acquire a seventh project in California later this year. These acquisitions will bring our total solar generating portfolio to 232 MW. Once constructed, all of these projects are expected to qualify for the federal investment tax credit. We are working on identifying and acquiring additional solar projects to support our plan to grow the company's solar portfolio by up to 250 MW this year. At Dominion Virginia Power, we have a number of electric transmission projects at various stages of regulatory approval and construction. During the second quarter, $394 million of transmission assets were placed into service, including the Mount Storm to Doubs 500 KV rebuild project, which was finished a year early. The year-to-date in-service total is over $500 million.
Electric transmission's capital budget for growth projects, including NERC, RTEP, maintenance, and security-related investments, continues to remain strong through the remainder of the decade. Progress on our growth plan for Dominion Energy continues as well. Construction is underway on the Allegheny Storage Project, and we've begun to accept injections. Construction is also underway on our Natrium-to-Market project. Both of these are on budget and on schedule to commence full service by November. We've had continued success in providing incremental transportation service as a result of the growing production within our region. We describe these as producer outlet projects, taking advantage of the flexibility of Dominion Energy's pipeline network to provide incremental services with shorter lead times and relatively small capital investment. Dominion Energy signed precedent agreements for two new expansion projects during the second quarter, the Monroe to Cornwall project and Western Access 2.
Since last year, we have announced nine such projects totaling just under 2 billion cubic feet per day by 2016. Two of the projects, Leidy Receipts and Lebanon 2, were placed into service in June, both on time and on budget. On our last call, we announced the Dominion Southeast Reliability Project, a non-binding open season for firm transportation services through a new pipeline extending from the Marcellus and Utica production regions to markets in Virginia and North Carolina. This proposed 42-inch pipeline would extend approximately 550 miles. The Southeast project is designed to provide initial service of up to 1.5 billion cubic feet per day. The response has been very strong. We are in negotiations with multiple parties and hope to secure the necessary agreements to solidify our project plan within the next 60 days.
Subject to the conclusion of negotiations, we expect to submit a FERC pre-filing in the fourth quarter, with firm transportation service available as early as November 2018. The Utica region continues to be very active. Through the middle of July, a total of 1,386 horizontal Utica permits have been issued, and 942 wells have been drilled, an increase of 33% in wells permitted and 39% in wells drilled so far this year. The number of producing wells has increased by 75%, from 270 to 472, also in just the past six months. A second 200 million cubic feet per day processing plant at Blue Racer's Natrium facility became operational in the second quarter, and based on new wells coming online, should be at full capacity soon. Fractionation capacity at Natrium will be expanded from 46,000 barrels per day to 126,000 barrels by March of next year.
In addition, a 200 million cubic feet per day processing plant at Berne, Ohio, is presently under construction and is expected to begin operations in the fourth quarter. Now an update on our Cove Point project. In May, the Maryland Public Service Commission approved the CPCN and air permit. Last week, we received approval from the state's Board of Public Works to construct a temporary pier. On May 15, FERC issued its environmental assessment. We expect to receive a FERC order approving the project in the next few weeks and begin construction shortly thereafter. The Cove Point Liquefaction Project is expected to begin operations during the fourth quarter of 2017. Before I answer questions, I want to comment on the recent greenhouse gas emission goals introduced by the Environmental Protection Agency.
As you know, EPA has proposed guidelines for states to follow in developing plans to reduce CO2 emissions from existing power plants. We, like other utilities, are evaluating the guidelines and the proposed state reduction targets. We certainly believe it will increase the industry's utilization of natural gas for power production, which in turn should increase the need for pipelines and other related infrastructure. As the states develop and the EPA approves their respective compliance plans, we will continue to evaluate the challenges and the many opportunities these changes will bring. To summarize, our business has delivered strong operating and safety performance in the second quarter. The Warren County and Brunswick construction projects are proceeding on time and on budget. Our Blue Racer joint venture, Dominion East Ohio, and Dominion Transmission continue to capitalize on the growth opportunities in the Marcellus and Utica Shale regions.
We look forward to receiving our remaining regulatory approval to begin construction of our Cove Point Liquefaction Project. Finally, we look forward to our initial public offering by Dominion Midstream Partners later this quarter. Thank you, and we are ready to take your questions.
Thank you. At this time, we will open the floor for questions. If you would like to ask a question, please press the star key followed by the one key on your touchtone phone now. Questions will be taken in the order in which they are received. If at any time you would like to remove yourself from the questioning queue, please press star two. Again, to ask a question, please press star one now. Our first question will come from Julian Demoulin Smith with UBS O'Connor.
Can you hear me?
We can hear you.
Excellent. So first, just a little bit of clarity on the Southeast project, if you could. Can you talk a little bit about the competitive dynamics? Obviously, you're talking about a pretty expedited timeline here to get details. Could you just frame it a little bit, where you're thinking about those customers and how you're seeing competitors frame up? I mean, it seems like you're down at the end of the fairway here in terms of getting the project off the ground.
Good morning. We are, as I said, in negotiations with a number of parties. We expect to, assuming they're successful, conclude all that within the next 60 days. It's a big pipe. It's 550 miles, 42 inches is a big pipe. Initial sizing would contemplate $1.5 billion, or 1.5 billion a day of capacity. That necessarily means we're concentrating on end users rather than producers. There's two ways to go about this. One is to get demand from producers, but producers got to sell it to somebody. So our concentration is on developing a pipe that would be useful for end users. But it all, we'll have to see how it goes, but we expect to conclude all of that within about 60 days.
Excellent. Could you just clarify quickly, when it comes to in the next few weeks, what exactly is your expectation for approval? This is, in theory, outside of the context of an open meeting for Cove Point?
The next meeting, your point, Julian, of course, assumes in it correctly that FERC does not have a public meeting in August. Their next public meeting is in September. So the answer to your question is yes. FERC actually does most of its orders these days, Julian, outside of public meetings. The comment period closed in June. All the comments have been posted, and they are going through their work. They work very diligently at FERC year-round, so we are hopeful that we would get what you would call a notational approval in the next few weeks. If not, that would take us to the public meeting in September.
Excellent. The last little detail here, you are almost at the solar mile marker you set for yourself here. Why 250 in terms of total megawatts? I mean, is there a potential to scale up the renewables business a little bit more, or is that really kind of what the tax appetite calls for?
It does not have anything to do with the tax appetite. We thought 250 was a number that would allow us to get real experience with a variety of different technologies and different places to see how they would work, and we are continuing to evaluate our solar strategy as we go through the balance of the year.
Excellent. Thank you very much.
Thank you, Julian.
Thank you. Our next question will come from Greg Gordon with ISI Group.
Thanks. Good afternoon. Julian covered a couple of my questions. Can you talk a little bit about what you're seeing in terms of weather normal demand? I am sorry if I missed it, if you earlier in the presentation, I hopped on a little late, but in particular, it looks like industrial sales were up quite substantially in the quarter. Have you seen your business get back on track after the setbacks we saw last year because of the government issues?
Greg, this is Mark. Actually, we are a little disappointed with sales year to date. We had hoped to be, on a weather-normalized basis, about 1.5% sales growth this year over last, and we are lagging that down around 1%. We have seen very strong industrial sales growth, although again, industrial for us is a pretty small piece of the pie. We have also seen extremely strong data center growth, but at the same time, our residential and smaller commercial growth has lagged what we would have expected to be the growth rate. So right now, we are looking at about 1%. We hope these other two areas recover as we go out throughout the year. To just remind you of the sensitivity, a 1% change in sales for us, depending on customer class, is between $0.04 and $0.05.
It is a manageable number for us, but we would like to see a little stronger.
Okay. You are talking about a $0.02 or $0.03 issue if you are 50 basis points behind.
If we finish up around one versus 1.5, that is right.
Okay. Do you have any sense of what is driving the shortfall in residential? Is it just slower than expected growth in housing? Is it higher than expected conservation? Is it DG, or is it too difficult an analysis to nail that down?
I think we lean much more toward housing is not recovering quite as quickly as we thought. Although we have growth in new connects year-over-year, it is not like we have had historically. We are going to need to have more new housing starts to be able to achieve the residential growth rate that we want.
Okay. Can I ask one follow-up question on the pipeline project? Your body language here is pretty strong on being able to get to the finish line on a rather large project. There are competing projects in the region. What gives you the confidence that you have the competitive advantage on this pipe to bring it to commercial viability?
Well, Greg, first, good morning. There is a lot of gas. There is a lot of infrastructure needed to get out of the basin. I would not necessarily conclude that only one pipe will ever be built out of the basin. You have to draw your own conclusions. We had a very successful open season, and we are working hard to conclude it within the next 60 days.
Thanks, guys. Take care.
Thank you.
Thank you. Our next question will come from Steven Fleishman with Wolfe Research.
Yeah. Hi, good morning. Just first, I know every fall you guys give your kind of five-year CapEx update, and I am sure now is not the time to go through the details of that, but maybe at a high level, you could talk a little bit about thematically where things are headed there.
Steve, yeah, you are correct. We typically give an update on a five-year capital outlook in the fall, and we would expect to continue that trend this fall. I think by way of comparison, as we come in, of course, we will add another year to it, but we expect our capital expenditures actually to be up over the five-year period from what you saw last year. We have announced a lot of new projects, particularly in our energy business. We have announced the solar projects this year, and so we would expect CapEx to be up as we present this fall.
Okay. Then just one technical issue. You mentioned normal weather in terms of your guidance for Q3 and the rest of the year, and it seems like it's been anything but that. So just as you're thinking about kind of the weather issues for the rest of the year, do you have ability to offset if things are a lot below normal this summer, or should we just assume it just is what it is, and you'll just update us when we get to the end of the quarter?
Yeah, I think it's a little too early, Steve. It is true in July, weather's cost us about $0.03 for the month. But August is a strong month for us, and September can be an unusually strong month depending on what the weather pattern is. So, it's not inconceivable that that would be made up just in weather as we go through the rest of the summer or the rest of the year. So, I think we'll hold for an update on that until we see a larger piece of what the quarter's going to look like and what the forecast for the fourth quarter's going to look like.
Okay, great. Thank you very much.
Thank you. Our next question will come from Dan Eggers with Credit Suisse.
Hey, good morning, guys.
Good morning.
Just following up on the pipeline question, with the end user demand kind of being the driver for contracting, is that customer base picking this up because they're trying to get to a cheaper form of gas, or is this incremental demand that they're trying to service with new gas generation and that sort of stuff?
Dan, I don't think we should talk to what our customers are contemplating. But as we said when we talked about the Southeast pipe, as we've gone around and spoken not only to customers but to the communities involved and the political establishments that will be affected, it's important. The Southeast needs more reliability, as there's no question the greenhouse gas rule is going to move people to more gas. It's just going to happen. Southeast does not have enough pipeline infrastructure to deal with that situation. One single pipe can get challenged for operational issues, and you just can't. That's not going to be tolerable for folks as we go through the next few decades.
I think reliability is a very important part of it, and having access to a different basin, and the basis potential differentials between what the folks have been used to for all these years, the Gulf of Mexico, et cetera, having Southeast access to the Marcellus and Utica makes it very attractive. That is why you have all these competing projects. Let us see how it goes. I think that is a combination of reliability, concern about expansion potential for various fleets, and having access to a different basin. Like I said, as you all have noted, there are lots of projects. Maybe ours will not come to fruition. We feel good about where we are, and there may be others.
Okay, thank you for that. Tom, the Artificial Island transmission project was kind of the first test of how Order No. 1000 is going to work. Given that it went to an incumbent with the rights of ways, how do you guys think about these transmission opportunities outside of your footprint, and is that affecting maybe some capital allocation decisions?
Dan, good morning. This is Paul Koonce. The initial decision went to the incumbent, but last week, the PJM board sent a notice to the four finalists, Dominion being one, that they would like to take a second look at the PJM manager's decision. So, we are still very much engaged on the opportunity presented by Artificial Island. We have in the past challenged PJM manager decisions and prevailed. We cannot say for certain that we will do so again, but that decision about who builds Artificial Island is still an open question.
Okay, thank you. I guess just last question on guidance for the quarter. With the $0.03 negative in July, does that kind of calibrate us to a little bit below the midpoint from a starting point today, or did the range already take into account the $0.03 drag in July?
Dan, it's Mark. We always put ranges out based on normal weather. It's just been our practice. If that three cents holds and there's no offsets in other areas, that would guide you to below the midpoint. Let's see what the rest of the quarter presents itself in terms of weather and other earnings drivers.
Yeah, very good. Thank you, guys.
Thank you.
Thank you. Our next question will come from Paul Fremont with Jefferies.
Thank you very much. I guess my first question relates to the 250 in solar. Can you give us an idea of what that would do to your effective tax rate next year? Because this year, I think you are at a 32% projected tax rate.
Our assumption on that, Paul, is that virtually all those projects would be completed in 2014. So, for the effective tax rate for next year, that would not be an impact.
Well, I am saying with the production tax credits, that would presumably lower your effective tax rate next year?
Most of the tax credits associated with these projects are one-time credits, investment tax credits that we would take in 2014.
Okay. Can you just give us a sense of what is driving the decision to either stay at 250 MW or potentially move to a higher level in terms of solar projects?
We're looking across all of our As we do constantly, we're going through a process, looking at all of our capital allocation, what all of our opportunities are. Solar, we think, is going to be an increasing part of the energy infrastructure mix. Being able to do it at utility scale, we think, is going to be important, particularly with this We thought that a couple years ago, which is why we started down this path. But in particular, because of the proposed greenhouse gas rules and the four pillars or cornerstones, whatever you want to call them, that EPA has set out as guideposts for states, we think solar could be useful across our service territories, not like it is in many other parts of the country, but we ought to be able to do some advances here. We're learning.
We're learning about installation, the maintenance, et cetera, as we continue to look at whether we will deploy it elsewhere. I think the short answer is, we're going to continue to evaluate it. We may decide to stay at 250, and we may decide to expand it. But we'll know more about that later in the year.
Hey, Paul, this is Mark. Just to give you a data point on that, this is not new for us. If you recall, eight or nine years ago, we built several wind projects early in the development period for the same reasons that Tom just outlined on solar. But we elected not to expand the wind program because it didn't fit our business profile going forward. The solar development scale here is at about the same level as we started wind. We'll just see what happens to it going forward.
My last question is, with respect to the construction of Cove Point, do you have any provisions with the contractors sort of guaranteeing that it will be completed in 2017?
Paul, this is Paul Koonce. We have a good EPC contract. We have a certain amount of time built into the schedule to provide for certain permitting delays, and none of that has been impacted today.
Okay. So, there is nothing that is sort of ironclad in your contract that it needs to be completed by the end of 2017, but right now everything looks as if it will be completed by 2017?
Everything is right on schedule.
Thank you.
Thank you. Our next question will come from Matt Tucker with KeyBanc Capital Markets.
Hi, good morning. Just another question on the timing of Cove Point and the MLP IPO. You mentioned you would move forward with the IPO after receiving FERC approval. You would, of course, still need the final DOE non-FTA approval to move forward with the project. Just curious how you are thinking about that and what would give you the comfort to move forward with just the FERC approval in hand?
No, well, we have the DOE approval. We got it a year ago.
Okay. I was under the impression that was the conditional approval, and you'd still need a final approval after receiving the FERC approval.
No, I can understand your confusion, but that word appears in all these final approvals because in the law, it can be suspended if something, a variety of things happen. DOE has said it's never going to do that. I think that that's a technical term they use in the DOE permits, but we have a final approval, which we got last September. Once we get the FERC final order, which is a construction permit in effect, we will proceed.
Got it. Thanks. On the Southeast Reliability Project, just wanted to clarify, 1.5 billion is both the expected volume and the CapEx?
No, it's just the volume. I said capital, and I'm correcting myself, I hope quickly, and I appreciate you pointing it out. The 1.5 billion a day in demand, in throughput. The capital will be more than that. We'll talk about that. Assuming we conclude these negotiations, which we hope in the next 60 days, we'll have more details about the capital and how it will all play out.
When should we expect to hear more on that? Will you make an announcement when you have the agreements, or should we just look for the FERC pre-filing to signal that?
Well, we'll just have to let that sit. Assuming we conclude the negotiations, part of the negotiations would be talking to the customers, et cetera, about how they want to go about announcing. We don't do things unilaterally in complex projects like this.
Okay. Would you say that this project is contemplated in your long-term earnings guidance consistent with it, or could it present upside?
Not included in our present plans.
Got it. Thanks. Just one last question, follow-up on the Artificial Island project. I believe part of the reason PJM is going back to the final four was because one of your competitors there offered to, I guess, kind of backstop the project. Is that something you would be willing to do, and do you think that will be necessary to win the project?
This is Paul again. We did notice that LS Power did offer to cap. That sort of brings to bear sort of a philosophical question as to the quality of the construction. It is such an important part of the energy infrastructure, the electric grid. How the commission deals with that is an open question. They also want to revisit, we believe, an alternative solution which we put forward, which would be less costly, technically more interesting. So, I would not base the PJM board's decision totally on the price cap that LS Power offered. I think there is a number of elements there that they want to review.
Thanks a lot, guys. Very helpful.