Earnings Call: Q1 2025

Jul 31, 2024

Operator

Good morning, ladies, and gentlemen, and welcome to Champion's First Quarter Results of the Financial Year 2025. At this time, all lines are in a listen-only mode. Following the presentation, we will conduct a question-and-answer session. If at any time during this call you require immediate assistance, please press star zero for the Operator. This call is being recorded on Wednesday, July 31, 2024. I would now like to turn the conference over to Mr. Michael Marcotte, Senior Vice President, Corporate Development and Capital Markets. Please go ahead, sir.

Michael Marcotte
SVP, Corporate Development, and Capital Markets, Champion Iron

Thank you, Operator, and thank you everyone for joining the call with us here today to discuss our quarterly results. Just for everyone's benefit, if you would like to see this presentation, it is available on our website at championiron.com, under the Events and Presentation tab of our website. I'd also like to highlight that our team will be making forward-looking statements throughout this call. If you'd like to read more regarding our forward-looking statements, risks and assumptions, also, you can also consult our MD&A, also available on our website. Joining me here today is our CEO, David Cataford, who will do the formal portion of this presentation. Our Executive Chairman, Michael O'Keeffe, will do closing remarks, and I'm also joined here by other executives, including Alexandre Belleau, our COO, and our CFO, Donald Tremblay.

With that, I'll turn it over to David for the formal portion of the presentation. David?

David Cataford
CEO, Champion Iron

Thanks, Michael. Thanks, everyone, for being here today. I'm happy to be able to discuss our Q1 Fiscal Year 2025 Results. If we look at the highlights, one of the highlights for the quarter is definitely the fact that we've managed to produce roughly about 3.9 million tons during the quarter and have record sales as well of just over 3.4 million tons. So I'm very proud of what the team has been able to achieve and how we rebounded from the Q4 2024 fiscal year. In terms of cash costs, relatively flat quarter-on-quarter, we'll be able to get into that a little bit later, at just shy of $77 per ton.

These results allowed us to generate about $180 million of EBITDA during the quarter. We did all of that with no significant workplace incidents and no major environmental issues. So again, producing clean tons out of Bloom Lake. In terms of community governance and sustainability, very proud to have hosted the Minister of Mines at our head office down in Montreal. The Minister was here to announce a new program to help local contractors step up their game to be able to work in areas or in companies like Champion. So, good alignment for us to work with the government to help local suppliers, local contractors, be able to increase the level of their companies to be able to come and work with us.

It allows us to strengthen our relationship with the local communities. In terms of our operations, as we mentioned, quarterly production of about 3.9 million tons, an increase of 18%, over the previous quarter. We also acquired additional mining equipment and rail cars. The additional mining equipment is to be able to continue working on our current mine plan and at the same time preparing to be able to eventually increase our nameplate capacity beyond the 15 million tons per year. The additional rail cars do the same, and they also add some added flexibility to be able to bring down not only the stockpiled tons that we have at Bloom right now, but also potentially future tons that we'll be able to increase, when one will be able to increase over our nameplate capacity.

In terms of sales, about 3.4 million tons of sales during the quarter, allowing us to achieve a record, but still shy of us matching our current production. So we'll continue to work with, IOC, but we, we do see positive results in terms of the, increased capacity on the rail. Now, if we go back to a subsequent event to the quarter, but that you've all seen in, recent press releases, there was a significant forest fire that came, close to the operations of Bloom Lake that caused us to evacuate the, mining site.

We had to react pretty quickly, but I think a good testament of the one preparation that we had, because following the forest fires last year in the region, we did build pretty significant contingency plans and emergency plans to be able to, one, evacuate our people, two, protect our infrastructure. Happy to report that even if the forest fires came close to the operations, there was no impact to any of our infrastructure. You can see that picture right there of someone hosing down some trees. We had to cut down bands around the site as well, bands around some critical infrastructure that we have, but very proud of the way that the teams reacted and how quickly we managed to evacuate significant portion of our workforce while continuing to work to protect the site.

The impact, roughly about one week's production when you look at the downtime and the ramp up, but happy to say that right now we're, we're back to pre sort of forest fire levels in terms of production. If we look at the operations overview, so, moved quite a lot of tons during the quarter. Our iron recovery, a little bit shy of our targets. In quarters where we have significant shifts, if you compare Q4 - Q1, there was a pretty big increase in tonnage. Very positive, but at the same time, more difficult to be able to tune in the recovery circuit when that happens. We're able to achieve our best results when we're fairly stable, fairly flat.

So, we should be able to increase that in the coming quarters and be able to go back to our over 80% iron recovery. In terms of the industry, we saw the P65 index decrease by about 7% during the quarter. And we did see some elevated exports out of Brazil and Australia, but still saw all the iron ore that was produced being consumed. So very happy that our material is still in high demand from our various customers. We saw also the premium for the P62 increase for the P65 over the P62 increase during the quarter. Still low compared to historical numbers, but positive sign that fits with the correlation that when the iron ore price goes down, typically the spread for the P65 to P62 increases.

If we turn to provisional price adjustments, there was a positive impact during this quarter. If you remember, we had 1.8 million tons at the end of last quarter on the 31 of March, that were booked at $113 per ton. We managed to realize about $124 for those tons, which makes a positive impact of about $21 million during the quarter. If we look at the 30 of June, we had, again, about 1.8 million tons on the water at the end of this quarter, and the expected price was around $119 per ton for those tons.

In terms of the average realized selling price, so there was a negative impact when you account for the 1.8 million tons that were on the water at a sub-$120 per ton, compared to the $126 average for the quarter. But we still managed to realize close to the P65 index during the quarter, even with that element, allowing us to achieve about $125 per ton, looking at the net realized price of about CAD 136 per ton. If we look at our costs, so we did see some improvements on our costs associated to the higher production and sales. So there was a positive impact there.

It was a little bit reversed by the non-cash items, non-cash items being the revaluation of the stockpile when we account for the cost. So spreading down the costs over the 3 million tons that we have stockpiled, and also an impact on the shutdown that was done in the Q4 fiscal year 2024. To remember, there was two major shutdowns that were done during that quarter, and those costs are spread over two quarters as the shutdowns typically last for about six months. So when we look at the impact for the quarter, roughly about flat compared to the previous quarter. But if you remove the non-cash items, we did about $5 per ton better. In terms of the financial highlight, as we mentioned, about $180 million of EBITDA.

And, when we look at the net income, just over $80 million, allowing us to continue our growth initiatives and to reinvest in the assets. Looking at our cash change, so a little bit lower cash than what might have been expected in the market, mainly due to the fact that there was a change of about $100 million in working capital. The bulk of that was mainly vessels that were or that left the port at the end of June, which we've since gotten paid at the beginning of July. So more of a timing effect than a real long-term potential issue. So, we should see that change in working capital switch in this current quarter.

In terms of our balance sheet, so if we include those, receivables and include the working capital, we're in a net cash position of about $18 million. So, very healthy balance sheet to allow us to continue our growth initiatives. In terms of growth initiatives, if we go to the DRPF project update, which is the main project that we're working on right now, happy to report that we're still targeting on time, on budget. So, the work is advancing as planned. Our main focus right now is to finalize all of the building to make sure that we are, that we are prepared to work inside for the winter. So that's going along very well.

As you can see on the next slide, we have most of our long-lead items, so the equipment that is currently being built at our suppliers' facilities, and everything is on track in terms of long-lead items. So all in all, I feel very confident we'll be able to deliver the project in the second half of 2025 calendar year and be within the budget of CAD 470 million that we've laid out. Now, this project, again, is key for our growth and the valuation of our product. So the main goal is to be able to sell our material to steel makers that will eventually be making lower carbon steel.

We can see that there's significant amount of these contracts that are being signed or that have been signed, to be able to deliver tons, starting 2025, 2026, of lower carbon steel. We have seen, as mentioned previously, that the various governments, if you look at Canada, Australia, U.K., U.S., looking to build infrastructure with lower carbon steel. So we're, we're seeing all of that start to materialize starting next year. So our project is gonna be very well timed to be able to tap into that market in the future.

So very happy of the way that the project is advancing and also the way that the various contracts for lower carbon steel are advancing as well. One other element that, a very big highlight for the previous quarter is the fact that high-grade iron ore is now part of the list of critical minerals in Canada. If you remember last year, high-grade iron ore was positioned in Quebec and in Labrador as a critical mineral, but now, we've also managed to include this in the list on the federal level. So, we're continuing to evaluate the potential positive this has for our growth initiatives, being the current work that we're doing on our projects and also potential future work.

But we see this as extremely positive, that the government of Canada now recognizes high-grade iron ore as critical for decarbonization, and part of the list of the minerals they want to support to be able to achieve lower carbon economy. So, again, very positive for our growth projects, and we'll be able to come back to the market once we finalize all the various elements and all the different impacts this can have on projects like what we have at Kami or others. I'd like to thank all of our staff for achieving those results. I'd say the results for the quarter, very positive, but really the highlight is the way that we reacted during the forest fires.

So very proud of the way that we all got together, not only ourselves, but helping local communities as well, strengthening our relationship with them, with First Nations and with the Quebec government. Showing our credibility as well in the way that we react in various critical situations. So very proud of the way that the team has managed to navigate through that. And, that being said, I'd like to turn it over to you, for the Q&A portion of the call.

Operator

Thank you. Ladies, and gentlemen, we will now begin the question- and- answer session. Should you have a question, please press star followed by the number one on your touchtone phone. You will hear a three-tone prompt acknowledging your request. Should you wish to decline from the polling process, please press star followed by the number two. If you're using a speakerphone, please lift your handset before pressing any keys. Again, should you have a question, please press star followed by the number one on your touchtone phone. One moment, please, for your first question. Our first question comes from the line of Lucas Pipes from B. Riley Securities. Go ahead, please.

Lucas Pipes
Managing Director, B. Riley Securities

Thank you very much, Operator. Good morning, good evening, everyone. My first question is related to the additional rail cars, and I wondered if you could kind of give us a sense for when all of them will be online. And then from a cadence on the destocking side, what is a good run rate to use from here on going forward? Thank you very much.

David Cataford
CEO, Champion Iron

Yeah, thanks for the question, Lucas. So, we were very fortunate to be able to secure a slot to build those rail cars in calendar year 2024. So they're currently being built right now. The first rail cars will be able to be delivered before the end of this calendar year, and then in January and February is when we'll receive also the bulk of our rail cars. So that should allow us to continue the strategy to look at solutions to destock the stockpile, but also allowing us to have that increased capacity when we get our production over the capacity of 15 million tons. So, those have been ordered, they're being built, and, again, they'll be delivered a little bit in 2024, but mostly at the beginning of 2025.

Lucas Pipes
Managing Director, B. Riley Securities

I appreciate that. Thank you very much. On my second question, I wanted to follow up on the addition of high purity iron ore on the critical minerals list. To what extent could this benefit a project like Kami? I appreciate, you know, there's a spotlight and an encouragement of higher high purity iron ore, but if you could maybe speak specifically to Kami and how it might benefit from this designation of the mineral, I would appreciate it. Thank you.

David Cataford
CEO, Champion Iron

Yeah, thanks for the question, Lucas. So, I mean, it's positive to be on a list, but where it really impacts is a lot of programs in the federal level are sort of binary in the sense that if you're on the list, you can access them. If you're not on the list, you can't. There's special funds in the Infrastructure Bank of Canada that can help do infrastructure projects. And if you look at a project like Kami, there's roughly about CAD 700 million of the CapEx that is related to infrastructure that could benefit from a structure like the Canadian Infrastructure Bank. So those are all elements that we're currently evaluating and having discussions with to see how that could potentially help the project, Kami.

It's a little bit preliminary to say what the real impacts could potentially be, but it puts us in a different position compared to where we were before, because in the past, we just couldn't even have those discussions with the various groups because we were not part of the critical list.

Lucas Pipes
Managing Director, B. Riley Securities

That's very helpful. Really appreciate it. And, to you and the team, continue. Best of luck. Thank you.

David Cataford
CEO, Champion Iron

Thanks, Lucas.

Operator

Thank you. Our next question comes from the line of Craig Hutchison from TD Cowen. Go ahead, please.

Craig Hutchison
Director and Base Metals Analyst, TD Cowen

Hi, good morning, guys.... I just wanted to circle back on the question of sales. And just, I think in your last conference call, you mentioned by June you'd hope that your sales would align with production, and now that we're basically going into August here, can you just give us an update on where that stands, whether you can give us a specific number of volume that's getting moved per week or per month, or are your sales now matching production? And then maybe when these cars arrive, the 400 that you're ordering, do you expect them to be matched on the downstream side with IOC in terms of, you know, the locomotives to actually move these volumes? Thanks.

David Cataford
CEO, Champion Iron

Yeah, thanks for the question, Craig. So we were pretty close to matching production with the logistics side. The forest fires obviously put a little bit of a setback, because even if we were able to restart operations fairly quickly, there was some limitations on the rail. If you remember, Labrador City was evacuated, and our rail passes through that section. So we're very fortunate to have the green light from the local mayors and also the Newfoundland province to be able to continue bringing down trains during the forest fires. But there was some limitations in terms of how much we could actually do.

And then when the town was, I don't know how you say, de-evacuated, but when people returned to Labrador City once the emergency evacuation was lifted, well, then there was some ramp-up portion. But I'd say that generally speaking, we're pretty close now to have the operation match the logistics. Now, the next step is to be able to focus on the destocking, and that's where the rail cars that are coming, the new local operators will help, and also the new locomotives that IOC has ordered. So, IOC has ordered extra locos, and we do have some new train operators that have started, some more that are coming in September and some more that are coming before the end of this calendar year.

We could see everything aligning for us to start destocking some tons from the stockpile in the coming quarters.

Craig Hutchison
Director and Base Metals Analyst, TD Cowen

Okay. And just on following costs, I know you guys have settled your, your labor, contract, and I know you guys are trying to kind of get recoveries up above 80%, but is the, is the intention still, with all those factors, to kind of get costs on a long-term basis down into sort of the mid-60s range? Or should we just think about, you know, costs probably moving closer to the, maybe the $70 range, just given some of these factors that have impacted on your cost structure with labor, et cetera?

David Cataford
CEO, Champion Iron

Yeah, if we look at just this quarter now, if we didn't have this, these non-cash items, we'd be closer to $71. So trending down, towards the sub-$70 mark. Now, where will we land? As we had mentioned, there was the increase with the union contract negotiation that was roughly about $1 a ton. But realistically, I do think that we'll be able to get to that sub-$70 number.

Craig Hutchison
Director and Base Metals Analyst, TD Cowen

All right. Thanks, guys. I'll turn it over to someone else.

David Cataford
CEO, Champion Iron

Thanks, Craig.

Operator

Thank you. Our next question comes from the line of Julio Mondragon from BMO Capital. Go ahead, please.

Julio Mondragon
Senior Equity Research Associate, BMO Capital Markets

Thanks, Operator. Thank you. Good morning, David and Michael. So just a couple of questions. The first one will be on production. So you reached 3.9 million tons of concentrate production this quarter, getting close to the 16 million tons per annum capacity that you target, you know, as a target before. So the question is, this is the result of the debottlenecking of your operations, or should we expect maintenance in the coming quarters? And also related to this, do you have a ballpark number figure for investment in the debottlenecking of the operations or this still under study?

David Cataford
CEO, Champion Iron

Yeah. So the debottlenecking project, because it's not one simple project that just allows us to add one machine, let's say, and then the production increases. It's really a synergy between many different things. So that's why it's taking a bit of time for us to evaluate the full picture. But as we had mentioned in the past, it's not gonna be one big project. It's gonna be a sum of many smaller projects that we'll do from quarter to quarter that will allow us to get to that level. If we look at the production of 3.9 million tons during the past quarter, a very good achievement, but we have to be mindful this was in a quarter that there was no major shutdowns.

So, in a quarter that, if you, if you put that on a six months basis with two major shutdowns, well, then that reduces the annual run rate a little bit. So, realistically, we're not at the 16 million ton run rate yet. We do feel that we're, we've achieved the the sort of nameplate capacity run rate, and we'll continue to work to be able to increase towards that 16 million tons and beyond in the coming quarters.

Julio Mondragon
Senior Equity Research Associate, BMO Capital Markets

Oh, thanks a lot. So just going back to, you know, the concentrate shipments, you already said that you are looking for or you're expecting a better performance in the coming quarters. But how would you see the pace of or volumes of sales improving, you know, or what will be your optimal level in the next year of the stockpile or the concentrate of the stockpile, like from 3 million tons to, let's say, 1 million in one year, a year and a half? Do you have any idea of this? Timelines or numbers?

David Cataford
CEO, Champion Iron

Yeah, we currently don't have an official timeline on those numbers. We're working with IOC to try to maximize the tons we get down. Obviously, once we get those rail cars, we get the new locals and the train operators are in position, well, we should be in a much better situation to be able to destock the stockpiles. We're also looking at other alternatives with IOC to see if there's other synergies that we can have to be able to destock that quickly. But we don't have an official sort of number on when that will be destocked now.

Julio Mondragon
Senior Equity Research Associate, BMO Capital Markets

Oh, perfect. Thank you very much.

David Cataford
CEO, Champion Iron

Thank you, sir.

Operator

Thank you. Our next question comes from the line of Brian MacArthur from Raymond James. Go ahead, please.

Brian MacArthur
Managing Director, Raymond James

Good morning, and thank you for taking my questions. Maybe I can ask the last few questions differently, because you sort of said you, you know, your sales might have caught up to the production if we didn't have boats being delayed and the forest fires and we've talked about destocking. But when you're talking about catching up to production levels, should I think about at a 15 million ton annual rate to get around this problem of 3.9 versus 3.4? Is that what you're talking about, or will the rail actually have a capacity with these extra cars to go over the 15 million ton a year rate, and as you said, therefore, help the destocking?

David Cataford
CEO, Champion Iron

Thanks for the question, Brian. So we have a contract for 16, so our main target is to be able to get to that full sort of 16 run rate. That's the main goal that we have. We do know that there'll be some small inefficiencies and so what, but that's the ballpark target that we have when we talk about getting to the right level. So that should allow for fluctuations in quarters that we have shutdowns and quarters that we don't have shutdowns then.

Brian MacArthur
Managing Director, Raymond James

Great, thanks. That’s very helpful. And my second question relates to another thing you mentioned in the quarter, which I think is quite a good achievement, is getting additional power. Could you maybe just talk about, you know, with all the power you have access to now, what it will actually be able to do in your growth initiatives?

David Cataford
CEO, Champion Iron

Yeah, thanks for the question, Brian. So when we look at the achievement in the past quarter, we managed to be one of the only companies to get access to more green hydroelectric power here in Quebec. I think the only company that actually got two blocks of energy. So very proud of being able to achieve that, and this is mainly due to the fact that the government recognizing the impact that we have in terms of decarbonization and the impact we have on the local economy. So very happy to have been able to access that. So as you know, last year, we secured the power to be able to do the flotation project, to get our material or half of our material to 69%, and now we accessed another block to continue in our various growth initiatives.

Could that be, the plant number one, convert to, to 69% or other initiatives to continue decarbonizing? We're very proud to already be the lowest CO2 intensity, high-grade iron ore here in Canada, but I think we can continue to do better, and that will eventually materialize in the price. So we've got a few, potential initiatives to be able to, use that power, but again, very proud that we've managed to secure it then.

Brian MacArthur
Managing Director, Raymond James

Thanks very much for taking my questions.

David Cataford
CEO, Champion Iron

Thank you, Brian.

Operator

Thank you. Ladies, and gentlemen, just a reminder, should you have a question, please press star followed by the number one on your touchtone phone. Our next question comes from the line of Dalton Barreto from Canaccord. Please go ahead.

Dalton Barreto
Managing Director and Equity Research, Canaccord

Thanks. Good morning, everybody. Thanks for taking my questions. David, I wanna stay on this whole issue around the logistics here, and, you know, I wanna ask a slightly different question. Between now and the time you do get the incremental capacity, what happens if there are further disruptions, you know, whether forest fires or otherwise? Really two questions. Number one, how much more finished goods inventory can you stockpile on site before you have to curtail production? And then number two, how does the rail operator allocate the capacity between the different users if there is a curtailment? Thank you.

David Cataford
CEO, Champion Iron

Yeah, thanks for the question. So typically, the rail operator has to deliver on its contracts. Now, realistically, we see when you own your own infrastructure, that's not always what happens. But realistically, we have seen a lot of improvements as of late on the rail. So we do see a lot of positive elements, and we do know that IOC is working to be able to deliver on their contract. So I'd say that there's no sort of official guideline on how that gets allocated, but realistically, I haven't seen a scenario.

Even last year, when you remember, there was the forest fires that halted the rail, we did see once it started back up, there was a split in terms of capacity when the rail was operating at a lower level between all the various clients. So it's not as if, IOC was only moving their ton and not moving ours. So there is some arrangement to make sure that everybody's able to bring down tons. Now, in terms of our actual stockpile capacity, it gets down to a cost down, because as we continue to stockpile, we have to go further and further away from the plant, and that increases the cost to be able to move the material around the mine. So, the...

There's no fixed number as to what is the maximum capacity, but as the stockpile gets higher, then the cost to be able to manage that increases as well. So there would theoretically be a point where we would see if it's still worth producing and stockpiling so far away from the plant. For now, we're still in a territory where the costs are significant, but not impacting our profitability, so we're still continuing to move those tons.

Dalton Barreto
Managing Director and Equity Research, Canaccord

Great. Thanks for that color, David. And then maybe switching gears, I wanted to talk about your projects a little bit and just try and sort of understand what are next steps now for Kami, for the pellet plant, as well as for, you know, upgrading the rest of your capacity to DRPF product. Thank you.

David Cataford
CEO, Champion Iron

Yeah, thanks for the question. So when we look at Kami, the next steps for us, well, as you might have seen, we applied for the environmental process to begin. It was approved by the Newfoundland government, so we're now starting the permitting process of the Kami project. So that's gonna bring us till 2026 to be able to to get a permit. So I don't see significant CapEx being invested in the Kami project until then, and that'll allow us the the time to be able to finalize the work that we're doing to bring in a partner for this project. So, we do have some pretty significant discussions with various groups to be able to have a partnership for the Kami project.

And, I have to admit as well, that being on the list of critical minerals here in Canada has, definitely helped in, in that sense. So that project, quite a lot of work for the, permitting process, but not significant dollars that will be invested. In terms of upgrading, our material, I'd say the main focus for us now is delivering the, the flotation plant on time, on budget, and being able to, realize the price that we, we believe we'll be able to get for this type of material. So that's the work that we're currently doing on this now. We are evaluating, other potential upgrades, but right now the main focus is really the, the DRPF, plant number two.

And when we look at the pelletizing portion, not necessarily the project that is getting the most traction on our side, so finalizing the feasibility study on this. But when we look at the pelletizing capacity and the current pricing environment, difficult to see that project making sense in the short term. Still happy that we secured probably the best land in Canada to be able to build a facility, but not something that we would be investing CapEx in, in the short term, for that. So when we look at our balance sheet, the main focus for us is really one, continuing to improve our actual operations, increasing the nameplate capacity, 'cause I think that's where we're gonna create the most value for our shareholders.

Getting the DRPF project up and running, and then continuing the permitting process on Kami.

Dalton Barreto
Managing Director and Equity Research, Canaccord

Thanks, David. That's great color. If I can ask just one quick follow-up. Based on your discussions so far, can you give us a sense for what sort of pricing you are triangulating into for your DRPF product?

David Cataford
CEO, Champion Iron

Yeah. Right now, the main focus is really to have a formula that exposes us to the DR pellet. So the main discussions that we're having is to slowly remove ourselves from that P62, P65 sort of environment and really get closer to the DR pellet. I think that in the future, there should be a disconnect between typical iron ore and iron ore that is used in this DRI slash EAF process, and we wanna make sure that we're not exposed to more tons of P62 coming into the market. So that's the main way that we're discussing the pricing formulas with the various clients, and we have been getting quite a lot of traction to be able to do that.

Dalton Barreto
Managing Director and Equity Research, Canaccord

That's great. So just to confirm, so you're gonna move from sort of a discount to pellet pricing as opposed to a premium to the current concentrate benchmark?

David Cataford
CEO, Champion Iron

Yeah, the DR pellet pricing, correct. And there might be a mix of both, but the intent is to eventually move away from the P62, P65 market.

Dalton Barreto
Managing Director and Equity Research, Canaccord

Yeah, that's great to hear. Thank you very much, David.

David Cataford
CEO, Champion Iron

Thank you, sir.

Operator

Thank you. There seems to be no further questions at this time. I'd now like to turn the call back over to Mr. Michael O'Keeffe for any final closing comments.

Michael O'Keeffe
Executive Chairman, Champion Iron

Thank you very much, Operator. And look, I'm sitting here reflecting and listening to David talk and, you know, as a major shareholder, I try and put myself outside of the day-to-day goings-on with the company. I mean, David and I talk every couple of days, whether I'm in town or out of town, so I know intimately what's going on and obviously involved in the strategy of how we go forward. But as a major shareholder, I like to just sit back out and look back into the company and say: What are the elements that are facing us today? Well, first of all, it's the effect of China. When China coughs and everyone else gets a cold, especially, you know, no more evident than that in the iron ore business.

So if I was sitting there thinking, you know, "What should I be doing? Should I be in iron ore, or should I be looking at other commodities, diversifying myself?" Well, we effectively are. And if I was sitting in Australia, in the Pilbara with, you know, low-grade iron ore, going to China all the time to their blast furnaces, I would be concerned. And as I discussed in the last quarterly report, it was, you know, how in the hell are they going to microwave the Pilbara? You know, it may happen eventually, but it's not... I don't think I'm going to see it in my lifetime. And I hope I've got a long time to go. But so I look at the elements in the company and say, "What are the indicators for me?" The indicators are obviously people.

So, you know, close representation of that was the forest fires we've just had. You know, the fact that we mobilized the teams, we secured the area, we evacuated, you know, I think up to 500 people. We were on standby with seven, 737 airplanes. We were working with the local community, and I think we had 300 people mobilized to fight those fires and be prepared for them, and that was done efficiently. So one of the things that David didn't mention, these little things I look at, is that we've just completed a new workshop for and quite a large infrastructure for the trucks and the maintenance on trucks and maintenance, what we call a shed, but it's more of a massive building. We'll take on welding and everything else.

So that was completed on time and budget just recently. It sort of doesn't get a mention. I think that we, as operators, need to sometimes reflect back, and one of our board directors said, "Listen, did you have a path or anything for that?" I mean, our problem is today, we're taking that as norm, where other people get quite surprised that they bring on an operation or they bring on a project on time, on budget.

For us, it's becoming the norm, and I think we probably have to stop and look back at ourselves and say, "Okay, start, you know, rewarding the people a bit more for what we're doing, what we're achieving as we're going along." But highlighting for me the fact that if I'm sitting there as a shareholder, I'm very excited that people can deliver on these projects. And the fact we've got the people delivering on the projects, and we're setting down the roadmap of the journey we want to go onto, and that is not looking at other commodities, because, as David said, our pricing system for the product we're going to produce is going to be separated from the index, and it's not gonna be reliant on China.

Now, we're talking about a pretty narrow timeframe, and that we're talking about commissioning the high-grade plant in, you know, under 12 months or around about 12 months' time. So, you know, we're going to endure a pricing system, but, you know, that's everyone else is in that boat. But however, we're fortunate we have a high-grade 66.2 product, and now you're seeing the spread for that, because obviously, the steel makers want, if they can buy high grade, they're always going to want it because it brings their unit cost down. It also helps them with their, with their pollution issues. So let's just take that as a given and then look at the roadmap.

The fact that David's been able to, and his team, have been able to achieve this, Critical Minerals for iron ore is bloody significant. I say that because it does give us access to, government funding on growth and projects. Currently, what we're doing, the fact that we've got power ready for the next phase of this, all that's done, and again, it seems to be taken as a given. Now, with that, that allows us to be able to look at the growth opportunities, and we have the cash to be able to do it, and it, you know, we'll be a different company as we get into that process. So, you know, I'm very excited about where we're going.

We're totally focused on where we need to get to, and we have the people to do that. So, you know, also, we've got very supportive shareholders, and, you know, I'd like to thank you for that. And, you know, we're always available to talk. We're always available to take people up to site, and to see what's happening at the port, what's happening on the with the rail cars, what's happening with the growth in our development there. So, you know, you could be tempted to go out and say, "Jump on the lithium band," or "Jump on some other, you know, commodity," which detracts you from what you're doing.

But at the same time, I'm trying to leave you with a message, and that is this: We totally believe in the commodity, and we believe in the commodity as such that it will be going to a market that is going to be supportive of green steel. So for that, we will get a premium. For that, we're putting our eggs into this basket, and you know, we will look at opportunities as they come along in other areas, and if they're low cost and they're good opportunities, we will no doubt investigate them. But in all, we're totally focused on being in 12 months' time into a position where we're in selling into a total different market.

So, you know, all this emotion that you're seeing today about China and iron ore prices is. We're going to be isolated from that. So exciting times for everyone, and we'll continue over the next 12 months, and in that time, we've been able to, again, give dividends, and we'll continue to do that while, you know, while the iron ore price is where it is, and we can keep our cost structure coming down. So on that note, thank you, everyone, and I'll sign off and wish you all a very nice evening or day, wherever you be. Thank you.

Operator

Thank you, sir. Ladies, and gentlemen, this concludes your conference call for today. We thank you for participating and ask that you please disconnect your line. Have a lovely day.