Investor update

Nov 18, 2026

Summary

The €22.3m rights issue is intended to fund early procurement, regulatory advocacy and production upgrades as projects advance. Operations and rCB development are progressing, though mill throughput improvements remain key to the ramp-up.

Operator

Hello and good day, ladies and gentlemen and dear participants. Welcome to today's investor call from Pyrum Innovations. I am very pleased to welcome the CEO Pascal Klein and CFO Kai Winkelmann, who will begin their presentation shortly. Following this presentation, we will move on to a Q&A session during which you can submit your questions via the chat box. I would like to inform you that this call will be recorded and may be published. By participating in this call, you agree to this. Let me add that unauthorized recording of this call, as well as unauthorized publication in written form, as well as audio or video recording, is prohibited. With that, I hand over the floor to you, Mr. Klein.

Pascal Klein
CEO, Pyrum Innovations

Yes. Thank you for the introduction and also warm welcome here from myself, here from Dillingen, on our headquarter. I will present you today the reasons behind our newest capital increase with subscription rights. Why we are doing this? What are the reasons behind? Why we are not waiting? Why is the right moment exactly now? I will try to keep it as short as possible, but we have done this presentation here already in German, and yeah, it takes some time to explain everything. First of all, and that is one of the very important things that put us under time pressure, is the actual market situation. What is happening right now is exactly what we said will happen since the last 10 years.

Now it is happening quicker than expected and in a more hard way than I ever thought it will be done. Incineration, which was the key for all end-of-life tires in the last decades, so burning them simply in cement plants, is dying out quicker than I thought, or we thought. Last year, it was 35%, so from 50% to 35%. This year, it is already down to 17%, so it is really dying out quicker than everybody thought. Granulates is still holding place with 35%, but the new laws and regulations, which I will tell you in a few minutes, are hardly attacking this sector. The only thing that went extremely up is the export. Export went up from 10% - 23%, which is absolutely not in our interest here in Europe because we are losing a source of critical raw materials.

Tires, from our perspective, are oil, are carbon, and gas. In fact, we are giving that away, and the first countries are fighting to get it. The unknown part, and that is what really hurts me a lot, has risen from under 5% - 22%, because as nobody is taking them anymore, more and more of the tires are ending up in forests, in the nature where they don't belong. For the first time, you see Pyrum with 3% of the German market share, which we are very proud of. What we need to do right now is working to get the regulations done. Regulations are fundamental for the tire industry and also for the secondary raw material market, for the whole waste shipment regulations, for microplastics.

There are so many things that are decided now on EU level, and they are decided now, not in two years, not in three years, now. Since 10 years, we are speaking about that. Since 10 years, we are walking toward these new regulations, and now suddenly they start, and quicker than we all thought. This year, in May, more exactly in the 21st of May, we have the first renewal from the waste shipment regulations. We have a ban of the export of used tires to non-OECD countries, which is already good. That keeps +800,000 tons of tires in Europe per year, and from next year on. There is a huge potential there. We need to expand that to OECD countries. We need to avoid exceptions, because today there are still exceptions for some countries like India, and that needs to stop.

We are really working already hard since about a year as Pyrum in Brussels and Berlin and in other European capitals to convince politicians to be visible, to show them that we exist, that it is a critical resource, that they understand that a pile of old tires is not something we need to get rid of. It is something that is like an oil field that can be explored, and exporting them is not helping. That is extremely time-consuming and expensive. The EU plastic regulation also has started already and will be in full application by 2031. That is banning rubber granulates from soccer fields, children playgrounds, et cetera. The 35% I just told you before is something that is dying out in the future or strongly reduced.

Something needs to be done with that market share, and we are the potential solution for that. It is the good solution because we produce critical raw materials for all types of industries, so we need to work also on that one. We need to secure the supply, and these are two key regulations for that on which we are working, not really publicly because we are not saying that to our shareholders, but we are doing that already since a year. That costs us a lot of money every month, which was not really planned in our budget, but we see that there is an extreme need to do it. Now, new rules are coming out.

The end-of-life vehicle regulation is already published, and I can tell you, the last year, we fought a lot for it because in the first versions, elastomers were excluded completely. The idea behind came from the tire industry because the tire industry said a tire is not a fixed part of a car, and there are other regulations like the EU Circular Economy Act, the waste regulation, et cetera, for tires, so there cannot be double laws for speaking about the same waste stream. The effect of that would have been that our raw materials that we produce, so the oil that we recovered carbon black, as they were originated from elastomers, would not enter into the quotes for new cars. That was not the intention of the tire industry; it was not the intention of the politicians, but they did not know it.

We had to educate them to tell them the consequence of that, because if we make oil out of elastomers and that oil is used to make a new dashboard in a new car, everybody wants that to count into the circularity quotes of new cars. But as it was written beforehand, that wouldn't have worked. Now the end result is the elastomers are still taken out, but secondary raw materials, which is our oil, which is our recovered carbon black, are allowed to apply in the production of new cars. That was a hard fight. Still now that the law is coming out, the law is not 100% clear in every paragraph, so we are working now with lawyers together with BASF on clarifying the laws and making legal statements on how it is intended to be.

The Circular Economy Act is the next big thing that comes, maybe still this year, latest next year. The goal is really to create a strong European market for secondary raw materials. Raw materials that are made from waste streams, that are made from alternative sources and not fossil-based, and that is for us a massive potential for demand for our oil and our carbon black, because then it becomes an obligation. The idea behind the Circular Economy Act is that the circularity quotes are doubled from 12% - 24%, and we try to get that even higher. That is really one of the key laws and regulation that we really need to work on in the next months or even the next year and a half approximately to get our strategic position done. Then we can roll out because then the regulations are set.

We see it from our customers that the first movers that they are already building, like the project in Czech, but the big groups like REMONDIS or the big industrial groups, they are waiting until the laws are finally coming out, and that's why these projects are moving forward, but not quick because they all wait for the regulations. Knowing that we worked since 10 years on these regulations and now they are about to terminate or to enter into force, we need to invest now money. We are doing it already.

We are already investing today between EUR 30,000 and EUR 50,000 per month to make ourself seen on E.U., Berlin, Paris, Italy, et cetera base, but we need to do much more here, and that needs to be done now because when the laws are done, the renewal of these laws will be done earliest in three, four, five years, and then it might be too late. We really have to work closer on that. That is one of the reason why liquidity now is absolutely essential for our future growth, and we cannot wait with that. Now about the projects. We have far over 20 projects in pipeline. We just got a brand new one in south of Europe, which we are not allowed to speak about yet, but very promising project with a very huge group. We have now 10 projects that have started.

You see them on the map on the left side. We have now two joint ventures that have started: the UniPyrum project and the reTIRE project. I am really extremely proud that we sold our first plant in September. It is not just a dream; it has been done. The contracts are signed, the bank financing is signed, the down payment has been done, the long lead items are ordered, and the caterpillars are running on site and digging holes and making the concrete foundations there. We even have a live webcam there in which we can see how the building is going forward. We are very close on starting the same in Greece, and if everything works according to plan, also soon in Sweden. We have received fundamental grant approvals in Europe.

One is in Greece with EUR 29.4 million, a very, very new one in Sweden that is only some weeks old, EUR 24 million in the project in Sweden, and about roughly EUR 20 million in tax holidays in the Czech project. That shows that Europe really wants what we do; otherwise, the project would not be granted these subventions. We have now three plants that are approved. With approved, I mean they have the building permits. Greece has a building permit, Perl, Czech Republic, and hopefully soon the Swedish project that has just received the grant will also receive the fourth building permit. The projects are really going forward at an extremely quick speed now, mainly also because the first one has been sold now and financed. About the project progresses, we have here a small overview on where we are standing right now.

These are just the most important projects. You can see that now, SUAS reTIRE, the Czech project, is in execution now, so the building has started. Thermo Lysi has received our last offer in September that was required also from the subvention, from the EIF, from the European Innovation Fund, that all offers have to be submitted until September. Order can be done, or the project can be awarded in December this year. Everything is planned there to start end of the year. With UNITANK, we started the first joint venture project in Emleben by signing the engineering contract there. GreenFactory, we finally received the green light from our region here to close the gap in the financing in November, so just recently. The GreenTech project in Sweden made a giant step forward by receiving the EUR 24 million grant.

According to them, that pushes them really now very close to FID, and we are already discussing the sales contract. As this is not enough, I thought that it might be of interest to explain everybody where we are more in detail with these core projects, at least with four of them, because that will be the focus in the next, I would say, 18 months to two years, and what is at stake here, and where are the challenges. The reTIRE project, I do not see big challenges anymore. Groundbreaking is done in September. Construction has been in full swing now. It has been ordered, down payments are here, the bank financing is done, and as of now, everything is in plan. The orders are in plan, delivery times are in plan, et cetera, and commissioning is planned in March 2028.

Thermo Lysi project in Greece, everything seems also good. We have the permit for three reactors, which is expanded now to six reactors. Why? Because that was part of the grant. The grant of EUR 29.4 million is asking to build six reactors. In the last six months, we spent a lot of time on changing the planning from three to six reactors, and the order should be placed end of this year. That is why we had to give in all last documents by September, and the down payment is expected early 2027. Then it should be finished before end of 2028. GreenTech in Sweden, the approval process ongoing. According to them, they are near completion to the final investment decision, so EUR 24 million grant received in September, and here we expect the order in Q1.

For the GreenFactory in Perl-Besch, we have finally received the verbal commitment for the funding of our gap from the Ministry of Economy of our region here and Strukturholding Saar, and we expect here the investment to be paid shortly. Finally, the Perl-Besch project would then gain speed because some long lead items are already ordered, so it was only we were waiting all this time for the regional support. That is what we see now extremely clear since we are working on the reTIRE project in Czech Republic, one of the big challenges is that we get only 30% down payment. We ask for 50%, but the banks are limiting that. Our customers are more or less willing to do more.

If it is the Greek, the Swede, everybody would be willing to pay more than 30%, but most of the time, the banks say, no, that is not common to pay more than 30%, so no. The planning we have done works with the 30%, so we get enough down payment to order everything at the right times. You get 30%, then you get 20% or 30%, then you get another 20%, but there are always months between that. We see massive price increases across all areas, primarily chips and memory due to the artificial intelligence boom. Also copper went up by 34.5% in the last nine months. Now copper is going down a little bit. Long story short, we are facing here a giant risk if we order things only in 12 months, for example, because there can be huge price increases until then.

Imagine that until next year, August or September, when we need really to order the chips, the memory, and the copper cables for the plant in Czech Republic, imagine the prices went up again by 100% in average over all these categories, then we would have to pay millions more compared to today. The only solution we see here is strategic purchasing. So lock in the prices that we have now by buying now, and do not wait for the next installments because it might be too late and the prices might be much higher. Of course, that needs more liquidity now. That is also one of the main reasons why we are doing this capital increase, but we really think as the board of Pyrum that it might be a giant risk for the future of Pyrum next year by not ordering now.

We have done it already in the Czech project, all the cabling, all the IT equipment, which needs to be ordered only next year in August, is already ordered now and paid already now because we saw the risk is too big, and that has also touched a little bit our liquidity, but it had to be done. Don't forget that just these three projects, Czech, Greece, and Sweden, represents for us approximately EUR 90 million from sales, excluding Perl. It is really big amounts that we are getting in and also buying products for it in the next months. Now, many people are certainly interested in what is going on with the plant in Dillingen and, of course, the milling pelletizing.

I will give you now very deep insights on what we have done and how we have done it so that you all understand that this is not a science project. We are not playing here around with not knowing what we do. Please understand that, yeah, we do not need to do that, but we want that everybody understands it. The shredder is running on a daily operation quite well. No issues with that. The reactors are also running quite well. Daily operation power plant also finally is running on a daily operation quite well. The milling pelletizer is also running on a daily operation with high-quality product, inspect material production also finally, but we are still not 100% at the throughput that we ordered. More on that in the next slides. First, I want to give you more insights on the shredder.

Since Q2, so end of quarter two this year, we run very stable with the shredder with ±80 metric tons per day. That gave us the possibility to build up a 25-day buffer stock of rubber granulate. You have to know that last year, in 2025, we had eight weeks over the year where we had to stop the reactors due to missing rubber granulate. We could not feed the reactors because we had no rubber granulate because we had crashes in the shredder, so the shredder was down due to metal pieces that arrived in the shredder that did not belong there, and that caused, of course, yeah, we call that a crash. Usually when you have a crash in a shredder, the shredder is down for two weeks, and that happened four times last year and even one time beginning of this year.

To avoid these stops, we have now built up a 25-day rubber granulate storage so we can always run for 25 days, whatever happens with the shredder. More than that, we have replaced the shafts in 2026. We have now replacement shafts, so if something happens again in the shredder, if we have a crash with metal parts in the shredder, now we can change the shafts and the knives within 48 hours and not like before, 14 days. The shredder is more than robust now so that we can fulfill the planning on that side. If you look at the planning for the year, the shredder is, yeah, almost in it with just two weeks of difference due to the crash at the beginning of the year. The power plant works fine now.

Now that it is running all the time, we found out that in case of an emergency, our security flare is a little too small, and a little is enough, because it needs to be able to burn all the gases in case the power plant goes down and the one-hour buffer tank for gas is full. Then the gas needs to be burned for 15 minutes, 20 minutes, half an hour. It depends on how quick we can restart the power plant. Now, in order to fulfill our legal obligations from the permit, we have rented now a second flare so that we can burn the gas in case it is needed. That way, we were allowed to continue to operate the plant. Of course, it was done closely together with the authorities, but we have to order a new larger flare, which costs EUR 300,000.

That was also not planned in the budget, but it has to be done. It is already ordered. We just made a down payment this week, and it should come in Q1 next year. That is a legal obligation that needs to be done, and, yeah, otherwise, we are not allowed to operate the plant. So it's not nice to have it. We must have it. Now coming to our core technology, so what we have invented and what we built ourselves, and in that, we have a research project running since years, which is called Pyrum Boost. The goal of that project is easy: improve our CB qualities, reduce power consumption of the reactors, the better possible, increase the final product yield, so get more product out of the waste that we are putting in, and reduce reactor downtime and maintenance duration.

The last one, we had already nice results this year. We went up from four to eight weeks between two maintenance stops. The downtime for the maintenance, we reduced it by some days. But one of the most important things here is to improve the rCB. The oil is not a big issue. We have more than enough offtake for the oil. We have more than enough market for the oil. But the rCB, so that you all know that, recovered carbon black is replacing virgin carbon black, like they call it officially, but I would rather call it fossil-based carbon black. That fossil-based carbon black is produced since more than 100 years, and it is the floor of the industry.

Without carbon black, there would be no tires, no rubber pieces, no plastics, no pigments, no mascara. Some cosmetics are done with this carbon black and ink, et cetera. You can imagine there's not just one carbon black in the market. There are hundreds of carbon blacks in the market that were developed over the last 100 years. We at Pyrum, we produce now one carbon black quality that we call internally the basic recovered carbon black. That basic was the basis. When we started operation, we produced the first material.

We didn't know how to improve it, so we created a baseline, and that is that basic rCB, and we sold that also to the market, or we are selling that to the market, to Schwalbe, for example, for bike tires, to Continental for forklift tires, for now, since recently, Pirelli for a little percentage in car and car tires, but we need to develop more recovered carbon black qualities, and that is also one of the goals of the Pyrum Boost project. We have changed some parts in the reactor over the summer break. These are the results from the Pyrum Boost research, and we didn't expect it. I can tell you, the optimizations were little. We just changed the isolation a little bit, and some settings in the reactor, but suddenly we have 60% more oil compared to before the summer break, before the modifications.

We went up from approximately two oil deliveries per week to four oil deliveries per week, more exactly 3.6 in average oil deliveries now. Half of that increase comes from a higher oil yield, so we are getting factually more oil out of the same quantity of tires, and that came as a side effect from the improvement of the recovered carbon black. Half of the increase came from higher throughputs in the reactors and longer operation times than expected. We were able to reduce a little bit the electric consumption of the reactors. The reactors are now operating stable at 720 kg per hour. For the very first time, beside of the basic rCB, we have now produced in industrial scale the New Standard, and we call that New Standard.

We have developed that together in a JDA with Continental because it needs to become what will become the New Standard rCB for the tire industry. Lucky us, we were not just able to make that in lab scale, but also now in industrial scale. That new rCB has a real impact on the wear and power consumption of the mill and pelletizer, but a positive one for once. More on that in the next slides. I really want to focus now on that aspect to explain you all, we are not just a recycling company anymore, and what we do in the last two years has very little to do with recycling, but much more with product development because we develop oils, we develop carbon blacks, we develop gases.

We develop some of the most critical raw materials in Europe, and that is more the focus of what we do than in the past because the recycling plant, the reactors are running, so there's not so much to improve there anymore, just the energy consumption, what I already said. The basic rCB, we are able to produce that in a lab scale since 2019. The New Standard and a new one which is not finished yet, the advanced rCB, we are able to produce the two of them since 2024 on lab scale. In large scale, we produce the basic rCB since May 2020. The New Standard can now be produced thanks to the modifications over the summer break since September 26th. The New Standard, the advanced, we don't know it yet. We haven't tried in the new reactors, but it is to be done soon.

The potential market size of the basic rCB is 20,000-30,000 tons per year in Europe. The potential Pyrum plants that you can build with that offtake is three to five plants. With the rollout plan we have already today, it is quite limiting our rollout plan. We did know already in 2024, but with the New Standard, we can sell several hundreds of thousands, some even say up to 1 million ton per year of that material. Here we are far over 50 plants, some calculations go up to 100 plants, potential for the market in Europe. It is really important to solidify our rollout plan by having also that New Standard ready to sell.

The advanced material is more a niche product with some thousands of tons per year per plant, but that will have huge prices. We see there prices over EUR 2,000 per ton. Application, I told it already, the basic material is good for bicycle tires, forklift tires, construction tires, pigments, and in small quantities in passenger car and truck tires. For the moment, we are getting EUR 1,400 per ton for that quality. The New Standard can use in very large quantities in car and truck tires and aircraft tires and special application, high-quality pigments, cosmetic, and so much more. Here we are in the price above or at EUR 1,500 per ton. The special application for the advanced rCB, the applications, they pay thousands of euros for a ton.

Now coming to the mill and pelletizer, which was designed from the beginning on for the basic rCB, because there was no other than the basic rCB when we ordered the mill and pelletizer for Dillingen. The current production capacity in Dillingen for the milling and pelletizing plant is 1,250 kg per hour, and it has been before the summer break and before the summer modification, 750kg. Big increase here. We are now at approximately 80% of the target. By increasing the production hours and adding a night shift, we can reach here 100% and maybe even above. The New Standard, we can produce 750 kg per hour batchwise, which is approximately 35%-45% of the maximum capacity of the mill and pelletizer. Now I will explain you why this is in the next slides.

What happened in the milling and the pelletizer over the year? Please allow me to give you the following infos again from the info box. We purchased this plant. I want really to make clear once again, we are not the designer of the mill and pelletizer. We bought it turnkey. By buying it turnkey, we buy something that somebody else designs, and we have to trust them. The order throughput was 1,600-1,650 kg per hour input. All previous modifications, everything that has been modified until now was paid by the manufacturer. Why? Because he has a legal obligation due to the contract. Pyrum is not paying for this modification, but of course, Pyrum is losing money by not producing during these shutdowns when modifications are done, and that is what hurts us the most right now.

To defend the manufacturer, it is the largest plant of its kind ever built on the globe. It is also for them the very first time, even though they are market leader in this sector. For Pyrum, it hurts on our balance sheet because rCB accounts for 60% of the revenue of a plant. We really see, feel, and it hurts. But we have no other choice developing the material than with the plant we have. Status in May, June was that we were able to produce 750 kg per hour. With that, we passed the Continental audit and the approval for the basic rCB for construction machinery tires, and we started deliveries to Conti and Schwalbe in June. That was approximately 150 metric tons.

But we soon stopped again because the summer retrofit started already mid of July, and we had an eight-week shutdown from mid of July to mid of September, which explains also the numbers for our Q3 report. The plant was down two out of the three months. What was done in the mill and pelletizer was we switched from pressure to vacuum conveying system, [vacuum filters]. I will explain in the next slide what that means. There was an agitator put in HO₃ in the dosing tank to faster deaeration. The goal of that was to slow down the flow of the basic rCB. Now we found out that basic rCB and New Standard behave completely differently. Basic material is very flat. It looks under the microscope like little bolts, and these bolts with air in between have a very fluidized characteristic.

It has floating behavior like water, like a liquid, and you need that material to rest. If it had enough time to settle down and the air went out, then you can dose it properly. With all the modification that have been done over the summer break, we were able to go up to 1,250 kg per hour, and material starts to flow too quick again when we go to 1,350 kg per hour or higher. Then the pelletizer that comes afterwards is floated, and it is not pelletizing properly anymore. We need to stay in that range, 1,250kg-1,350kg, to keep the material stable.

The solution for that, to go to 1,650 kg per hour as it was agreed in the contract, would be a second dosing line, because if you have two dosing line, one can rest, the other one is dosing into the pelletizer, and once the first dosing line had one and a half to two hours to set, then you can operate two, three hours with that dosing line, and during that time, the first dosing line had again time to rest. With that principle, you can easily reach 1,650 kg per hour. But that is the new finding from the last weeks, the New Standard material is behaving completely differently because if you look at the particles under the microscope, they are not flat. They are extremely spiky and extremely coherent and extremely easily blocking. Their flow habit is extremely poor.

It is floating not like a liquid, more like honey. Even having two dosing systems would make the problem with the New Standard even worse, because if the material remains for too long into a dosing unit, it is not coming out at all anymore. The New Standard, you need to try to get it out of the dosing unit as quick as possible, and for that, the solution would be a forced feeding system that pushes the material out of the dosing system into the pin mixer. Now the next slide is, we show you a lot of things that nobody has seen before, but I want you all to understand what happens and to prove that it is not a science project and that we are not playing around here. That is how the dosing system was built at the beginning.

On the left, you have the mill. Under that, you have the pelletizer, and then you have the finished rCB. The milled material comes together with air and is injected in that bunker here that comes before the pelletizer, and you can see there is like a thunderstorm in there because there is a lot of air coming in with a lot of carbon black. The material has never really the time to settle down. That is why we need to stop the feeding of the tank so that the material has time to set down, and once it is set down, you can dose it. But the dosing is static. You can just open and close here, so the material flows out at the speed it naturally flows out due to gravity. What has been done now in the big summer modification is the following. Yeah.

Do you see here again that the main issue is here? The main issue is here, the output where the material comes out, and the modification is. Now it should turn. Yeah. We have done now kind of a blockage inside the tank so that the material is flowing slower. You see that the material needs now to squeeze over tiny openings from the sides, so all that to slow down the material. These parts here are the agitator. They are slowly moving in the material so that the air goes out quicker and easier. But that was not enough, and the following change needed that we take out the whole dosing system through the roof of the plant. We had to take all that out, and here you see a man behind, how big it is.

We had to take all that out of the roof to haul, and now it looks like this. Now you have the so-called [vacuum filters] on the top. Now the air mixed with the carbon goes into these three [vacuum filters]. The air goes out on one direction, and the de-aerated carbon falls into the bunker. There is still air in it. It is impossible to get all the air out, but thanks to that, with the time the material needs to settle down, combined with that blockage here that is slowing down the agitator, made it possible to increase the throughput. But we still have no adjustable static dosing system. You can just open and close here at the bottom, and it flows out at the speed the gravity takes it out. It is like an hourglass. I like very much that comparison.

It is a precise quantity X that comes out over a time, but that one cannot be influenced with conveying system. It is how de-aerated the material is. The basic, we went from 750kg - 1,250 kg, but the New Standard, as it flows badly, is more or less blocking in these areas here. Now we need a system that works for every type of rCB, and even though it is partly our fault because we are developing new carbon blacks, we have ordered a machine that can do basic rCB, the supplier is helping us also now with the New Standard and with the advanced grade. For that, we have now designed a forced output system, which is especially blurred here a little bit, because we don't want to give to our competitors exactly how we are doing it.

This forced output system is tested, so there's a supplier in the U.K., and in Germany, we have tested both grades, so the basic and the New Standard. We have tested it by sending big bags there of the material to test the dosing. It works in industrial scale. You have a guaranteed discharge rate for both materials, which is the 1,650kg that we need. The only problem is that these need to be built for us, and especially under ATEX 20 norms, you cannot buy that from the shelf. It has some delivery time, and right now, we are really thinking out of the box together with the supplier to get that discharge system as quick as possible, but then it will run.

The mill runs fine, the pelletizer runs fine, and once we pass from a static dosing system to a controllable dosing system over the pelletizer, then we don't see any reason why it shouldn't work anymore, because maybe it has been tested already in industrial scale from the supplier of this output system. I hope this gives you a big insight, even though we don't really like to share this because it also helps our competitors to find solution. We want to be as transparent with you as possible so that you understand that we are not playing around. With the oil, we are selling it already since years to BASF, and they use it for textiles, for door handles, for parts for cars, for ibuprofen medicine, et cetera. What is quite new this year is they now produce also synthetic rubber together with Synthos.

BASF is creating the basic chemicals for synthetic rubber manufacturer, and it's called Synthos. Deliveries have started to Schwalbe, Pirelli, and Continental using that synthetic rubber already in tires today. Not only the recovered carbon black is entering into new tires, but now also the oil comes into new tires, at least partly. What is also new is the ISCC EU / REDcert certificate of our oil, meaning that our oil can also be used in green fuels. We are not selling that right now, but we have the permission now to do so. We have a bunch full of requests for it, but for the moment, all of our oil is going to BASF. The more plants we will have up and running, the more we can also sell the oil to other off-takers.

The ThermoTireBlack, our recovered carbon black, goes to Schwalbe, Continental, and now brand new to Pirelli. I have to really thank Pirelli because they are really doing a lot of commercial work, publishing the Tire-to-Tire initiative, making presentation in front of politicians in Berlin, in Rome, in Brussels. Just last week, we had a presentation at the Economic Forum of the Süddeutsche Zeitung in Berlin in the presence of a lot of politicians, where the Tire-to-Tire initiative was presented. Pirelli was there, BASF was there, Synthos was there, we were there. There was a presentation this week in Rome, and a lot of them are planned in the future. Pyrum needs to help there, and that is also a reason why we need to invest more money quick in the legal framework that we need for the next years.

Where we are standing, a small summary. We have now the plant up and running at TRL 9 out of 9, Technology Readiness Level 9 out of 9 . We have proven that the project are now bankable with 70% debt capital, proven now again with the plant in Czech Republic. We have now created for all critical raw materials that we are producing that the required market size is there. The oil, the market is so huge, we will never be able to fulfill that. Now with the new recovered carbon black grades, there is also more than enough demand for recovered carbon black for our rollout plan. We are producing now 720 kg stable in 24/7 operation.

We have received now, beside all of the other certificates and approvals, the new ISCC EU, which has opened us completely the market for green fuels, which is so big that, yeah, you can build endless units, Pyrum units. Fraunhofer, with a saving of 965 kg of CO₂ per ton of used tires, is still proven again. We have a new big offtaker, and that is really a high value that we have in the company. These long-term offtake agreements for our end products, which we had already with BASF, Schwalbe, and Continental, and now very new Pirelli came also in the round, and there are others to come. I can't tell you who, but there are others coming.

We have received now two aids from the European Union, EUR 29.4 million for the Greek project and EUR 24 million for the Swedish project, and also the tax holidays in Czech Republic, and all that proves that Europe wants this. I can tell you that the chance to get the EUR 24 million grant in Sweden was less than 8%, so that proves that how important these projects are for the European Union. We sold our first project finally in September, and we got the first bank financings for external project, which is not our own project, also in September, which are two giant milestones to solidify the rollout plan now. From the ramp-up now, Q4 this year, Q1 next year, we secure the foundation, so we secure our bank financing and the Saarland funding until end of this year.

Until March next year, we will ramp up the operations the quickest possible with the three-shift model. We have already hired the staff. The staff in the mill and pelletizer for the three-shift model is being trained right now, and we will change the dosing system in the mill and pelletizer from a static dosing system to a variable dosing system. I spoke a lot today. Quicker than March 2027. We do all in our power, and the supplier is doing all in his power to do it quicker, but until then, we will produce as much basic rCB and new rCB in the three-shift model as possible, so that next year, we can make up to EUR 90 million potential revenue with just the three plants that are at our gate, Czech Republic, which is sold, Greece and Sweden, which will soon start.

I would say that the next 18-24 months, we have more than enough to do without getting in more and more projects and with the staff that we have today. From the capital increase with subscription rights, planning is EUR 22.3 million. The number comes from the rights that exist. The subscription ratio is 5:1 . The price is EUR 26. The maximum number of new shares is 858,533, and the subscription period is November 19 - December 3. On the right, we put again our actual shareholders, showing the most important ones, and that gave us the permission to show them. One very important information at exactly that moment here. Since yesterday, we had already a lot of discussions with our existing shareholders, asking them if they will participate in the capital increase, and the feedback was super positive.

Everybody I spoke to said, yes, we will participate. Schwalbe said yes, Frank Thelen said yes, Felix Magath says yes. My family is saying yes, we will participate in the capital increase. Benifin GmbH, who is one of our oldest shareholders since 2017, institutional shareholder, that is the word I was searching for, and many more. I spoke, but I had only 24 hours. The feedback is very positive, and they are all going to participate in the capital increase, which makes me really proud, and they give me even the permission to tell that to you. Now let us sum up why we need the money or what is the money planned to be used for. One of the most highest priorities for us is to strategic procurement, which has to be done now, not in half a year, not in three months, now, because prices are rising.

We are facing a big risk next year, and that can really hurt our liquidity next year, before we can close some bigger deals with big infrastructures which we are working on. For them, it is also important to see that we have secured our liquidity also in this rough market situation that exists today, with the Strait of Hormuz, the war that is still going on in several countries, et cetera. The critical prices need to be secured as quick as possible, and the 30% down payment are simply not sufficient enough for strategic procurement. We can procure everything, but only after the different payments have arrived, and that is for some parts too late. Lobby, which is as high in priority as point number one according to us, we have to work more together with our partners in Spain and Italy and Czech Republic.

The more support from more countries you get, the bigger is your influence in Brussels. We are already investing a lot of money today, which is roughly around EUR 30,000-EUR 50,000 per month, but that is not enough. We are seeing here budget in the next year and a half of EUR 2 million to get all the work done that needs to be done. Third, development of new rCBs. You know that we have developed a New Standard, the advanced. Of course, our supplier is also helping us to get the throughput with these two materials done, because he has also to fulfill his throughput with the basic material, but Pyrum will also have to pay partial modifications in the mill and pelletizer to get the higher throughputs for the New Standard and the advanced material.

We told you already that we are working on a refit of reactor one. The planning of it is mostly done, and we found out that we could change it as it is, but it would result in very high operating costs because we would have two different systems running in the same plant, and we would have to hire more people. You need to have then people that are trained on the old reactor and people that are trained on the new reactor, and there are new safety requirements, mainly on emergency shutdowns, et cetera, that the old plant doesn't have. You have to know it is more than 10 years old. All these details that we find in the detailed planning would generate EUR 2 million additional cost to refit reactor one completely, so it goes up from EUR 1 million -EUR 3 million.

Still, the return of investment period here would be under five years, so more than important to do and to quickly increase the throughputs in Dillingen. Of course, we have lost a lot of time in developing the rCBs and making them industrial viable, so we still have a cash burn rate until positive EBITDA in 2027 and positive net cash flow in 2028. The more money we will get now in the capital increase, the more we can also invest in our joint ventures, like the Greek project, in which we can invest up to EUR 3 million, in the Swedish project, in which we can invest up to EUR 3 million, and also the joint venture with UniPyrum, in which we can build up to 10 plants and have up to 49% in each plant.

It depends how much cash we have, and these decisions will be taken before end of this year and beginning next year. We really don't have the time to wait any longer to fix now how much we can invest in these plants, even though we have good and long discussions with CBHH, and we have approached a lot of good investors already, but that will take another month, some months more to get there, the right deal with big infrastructure funds for a bigger roll-out plan, et cetera. I thank you for your attention, and now we have some minutes left for the questions and answers.

Operator

Yes, indeed. Thank you very much for the presentation, and we get to the Q&A session. To all the participants, if you have a question, please feel free to write them in the Q&A chat box. To Pascal Klein and Kai Winkelmann, we already have two short questions, so you may take a quick look in the chat as well.

Pascal Klein
CEO, Pyrum Innovations

Yeah.

Kai Winkelmann
CFO, Pyrum Innovations

Okay, let me come to this clarification of the buckets. Maybe, Pascal, you can move back to the previous page.

Pascal Klein
CEO, Pyrum Innovations

Yeah.

Kai Winkelmann
CFO, Pyrum Innovations

Of course, it depends how much we can generate from a capital increase, in which part we can spend what. What we have identified is that especially all the chip technology, some of the copper wires should be used as soon as possible, especially chip technology and all the plant, let's say, control system. We expect around EUR 500,000 -EUR 1 million per plant. That would sum up to EUR 4 million. EUR 2 million if it's possible for lobbying for the next one and a half years. TAD 1 +EUR 2 million, and Greek and Sweden, we have this option that we can invest that would be up to EUR 3 million per plant. It's not an obligation that we invest this EUR 3 million, so it all depends, let's say, on the capital increase, what we can put in.

Then, last but not least, we have a cash burn rate. We work on it that we can reduce it, but it is there, so some money will still be needed until break-even.

Operator

Yes, thank you very much. Right now, there are no more questions in the chat. I will wait a few more seconds. To all the participants, if you have questions to the management, please feel free to post them in the Q&A chat. We now have the time to answer them. If there are questions coming up at a later date, you will obviously be free to contact investor relations of Pyrum as well. Due to the fact that there are no questions, I would say that we come to the end of this investors call in English language. Thank you very much to all the participants for taking part, and to you, Mr. Klein, for the presentation, Mr. Winkelmann, for the quick answers to both of them. From my side, I wish you a successful end of the week and hand back to Pascal Klein for some closing remarks.

Pascal Klein
CEO, Pyrum Innovations

Yes. Thank you very much for your attention. I know it took long, but I always try to explain as good as possible. We really want you all to understand that we are doing our best here and that we are creating here a new technology for generations. The products of our children, our grandchildren, will depend on what we produce here. It is not something that is done overnight, and sadly, modifications in a plant of that size always take months. We do not count in days or weeks. Usually, it takes months to do even little modifications. But the good thing is that every modification brings us much further forward, and we are now at a state that customers are buying the plant.

They see that the risks are not existing anymore, that we know how to build it in the future, that it is just complicated to change it in Dillingen. I would say that the fact that we sell the plants already is a giant proof. Thanks for your attention. This presentation will be published afterwards, and I wish you all a nice day and a good end of the week.