Good morning. My name is Marcella, and I will be your conference operator today. At this time, I'd like to welcome everyone to the Agnico Eagle 4th Quarter Results 2019 Conference Call. All lines have been placed on mute to prevent any background noise. After the speakers' remarks, there will be a question and answer session.
Thank you. Mr. Sean Boyd, you may begin your conference.
Thank you, operator, and good morning, everyone, and thank you for calling into our Q4 and full year 2019 results conference call. Before we get into the slides, please be aware that this presentation includes forward looking statements. I'd like to begin by just summarizing 2019 and the 4th quarter. In the Q4, we had record gold production as we brought on the 2 new mines in Nunavut. We also have record cash generation in 2019.
With that added production, we see 18% production growth from 2019 out to 2022. And we'll provide some details on that production growth in a minute. Although we had a very strong 2019 and in 4th quarter 2019. We still have some work to do in Nunavut through the Q1 of this year as we ramp up those 2 newly built mines. So we'll also talk about that.
When we look at the 4th quarter numbers in a bit more detail, we produced almost 500,000 ounces in the 4th quarter, which is record production. For the full year, we exceeded our full year guidance, which had been increased during the year. We finished at 1.782 1,000,000 ounces at a total cash cost of $6.73 per ounce. Our unit costs in the Q4 were impacted by the slower than expected ramp up in Nunavut, and we'll talk about the details as we said in a minute. With the record cash generated from operations in 2019 and the ability to continue to grow production while generating free cash flow, our dividend was increased in the quarter to a quarterly rate of $0.20 per share.
From the 3 year guidance perspective, as we said, we've got production growing 18% off of the record production level in 2019. We should see costs decline in 2021, 2022. When we look at our 2020 guidance, our number is down 4% from previous guidance in terms of total production to 1,875,000 ounces, which is largely driven by the Q1 expected Q1 impact as we ramp up Nunavut and we do additional ground support at LaRonde and we'll get into the details of that in a minute. In 2021, there's no change in the production guidance, although our cash cost guidance is up $50 an ounce. So that's due to increases in cost, but also just inflationary cost pressures in the business.
When we look at Nunavut and LaRonde, starting with Nunavut, as we said, the ramp up was slower than we had expected, and that's clearly on all of us. We should have done a much better job in anticipating and reacting to some of these issues. We have high expectations and we didn't meet those expectations. Fortunately, we continue to make steady progress in productivity and efficiency efforts at Nunavut, and we expect to see production increase and cost decrease in Q2 and through the second half of twenty twenty. At Meadow Bay, essentially as we have explained in 2019, we did get delayed due to excess water.
We had the entire pit was pumped out in October of 2019 and that allowed us to improve the efficiency in the open pit, although we were still limited in the Q4 with a smaller footprint due to having just pumped out the pit in October. We are seeing improvements in the mining right now and drilling performance. There's still optimization efforts around those initiatives in the pit. We will also see optimization efforts as we ramp up construction and eliminate costs that still are on-site after the construction. One of the areas that we are focused on is equipment availability and maintenance.
We have made major headway there. The warehouse is now complete. We have begun the changeover in terms of stocking that warehouse from Meadowbank. So all of those things will help with the performance at Amaruq and Meadowbank as we move through 2020. We're still assessing the underground opportunity there at Amaruq.
We would expect to have more information in the second half of this year and we could expect production to begin from the underground in 2022. At Meliadine, we continue to ramp up at Meliadine. Mining is actually going well. At Meliadine in December, We were approaching budget levels in terms of mine performance. We mined almost 4,000 tonnes a day in December of 2019, which was a significant improvement over what we were doing in the Q3 of 2019.
So there's more work to do in underground maintenance on mobile equipment, but that's more optimization efficiency. Where we did have more of a challenge is not in recoveries in the mill. Our recoveries are, as expected, approaching 95%. The plant can handle and did handle in the Q4 an average of over 3,500 tons a day. What we're experiencing now is at the front of the plant in the apron feeder area.
So we have a temporary fix there that's limiting the amount of tons that we can get through the plant. We should have that fixed as we move into the Q2 of this year, which will result in a much more efficient operation of the plant. We've also decided that we're moving forward the Phase 2 expansion that provides more flexibility in the mine plan and that is currently underway and we'd expect to see production from that as we move through 2021, 2022. At LaRonde, we've decided that as we move into the West mine area, which is our highest grade area, to add additional ground support. As we said, LaRonde had outstanding performance in the Q4.
It had record production from that mine. It had cash costs of $4.22 an ounce. It had an average grade in November of over 7 grams per ton. So that's a big part of the future of the mine at LaRonde and the cash generating ability of LaRonde. LaRonde actually last year set a record for safety performance, an all time record for safety performance.
As we moved in to the West Mine area, geology is a bit more complex and we thought that it was prudent and cautious to add additional ground support in the major infrastructure. So that includes additional bolting, additional screening, additional shotcrete. We expect this to be completed in a few weeks at minimal capital cost and also has a very minimal effect on future cost per ton. So you combine that in the Q1 with a slower ramp up in Nunavut and you have the impact that we have on guidance going down 4% for 2020, but also you have the impact on unit costs and most of that is being felt in the Q1 of 2020. And as we move into Q2 and beyond, not only does production increase, but unit costs go down.
Moving beyond the 3 year guidance, just on the production growth. As we mentioned, the production growth is 18% from 2019 to 2022 with the newly released guidance in 2022 of 2,100,000 ounces with a focus now on the project pipeline to see which projects actually make sense to allocate capital to and grow the business in a steady measured fashion beyond 2022. So we continue to do work on Amaruq underground and on Kirkland Lake on Odyssey, East Malartic. Our reserves, we used a $1200 gold price to calculate our reserves. Our reserves were down slightly, but our grade increased almost 5% to 2.83 grams per ton from 2.7 grams per ton, but we saw a significant increase in our mineral resources and our inferred mineral resources.
Our indicated grew by 4% and our deferred grew by 19%. So it's those resources in our project pipeline that we're currently studying now to see how we allocate capital and which projects we decide to build to continue the growth beyond 2022 from 2,100,000 ounces. Just looking at some of the mines, in particular, in more detail in the Q4, we mentioned LaRonde at record performance. When you combine LaRonde and LaRonde complex, 100 and 12,000 ounces at LaRonde almost 100,000 ounces as we mentioned at $4.22 per ounce. We also had good solid performance at Goldex, which continues to exceed budget.
Goldex actually had its best year ever from a safety performance. Canadian Malartic, steady producer, good cash costs at $6.30 an ounce. Kittila, better performance, also set an all time record in safety in 2019. You can see the impact of Meadowbank in the 4th quarter, a little over 60,000 ounces, but cash cost of $1400 which skews the entire combined cash cost number up. And that's the issue in Q1 of this year as we continue to ramp up at higher unit costs in Nunavut, which skew all of 2020.
So that's why we're looking for better cost performance in Q2 and beyond. And in Mexico, we continue to get good cash generation out of that business. From a financial highlight perspective, we mentioned earlier in the call, we had record cash provided from operating activities of almost 900,000,000 dollars in 2019 on 1,782,000 ounces of production, which was also a record. From a financial position perspective, we continue to add to our cash position. We closed essentially with $328,000,000 in cash at the end of December.
Our $1,200,000,000 credit line is fully undrawn. We have a debt maturity in April and we've got several options to pay that, draw down some cash, draw down a bit of a line of credit, potentially term some
of that
$360,000,000 out, not all of it, we could do some of it. Interest rates would be less than half of what we're currently paying on the $360,000,000 maturity. So really good financial flexibility as we move forward in a way that allows us to grow production as we said 18% and generate free cash flow. On Page 12 on the slide deck, we see continued growth in operating margin coming out of the mines with relatively flat CapEx as we go forward. We still haven't decided how we're going to allocate that CapEx.
We're still doing assessments on the pipeline, but our focus is on stretching those projects out and stretching that CapEx out. So while we're growing, we're still generating net free cash flow to invest in the business, pay down debt and increase the dividends. And before we take questions, I'll just end on the dividend slide. Our dividend is now $0.80 a share with the increase in the quarterly amount of $0.20 this quarter. You can see that we've increased our total cash paid out in dividends in the last 6 years, and that was during a period of heavy construction as we built the expanded Nunavut platform.
So I'll close on that. And operator, if you can, please open the line up and we'll be happy to take care of questions.
Your first question comes from the line of Fahad Tariq from Credit Suisse. Your line is open.
Hi, good morning. It's Fahad from Credit Suisse. What are the critical steps really to right size Amaruq in Q1? I'm just curious, it sounds like the dewatering is kind of done. It's more to do with logistics like equipment availability, moving the workforce.
Like if you could just walk us through like what are the kind of steps that are needed to kind of get back on track at Amaruq? Thanks.
Well, the hi, it's Hugo. We're presently the drilling is essentially progressing very well drilling and blasting. That's pretty well under control at this stage. Our inventory of broken material is also under control at this stage. We're opening up more surfaces in the pit and getting access to the remainder of the pit that's under lake bed.
So a lot of digging in these areas.
So that's still a little bit
of a challenging because in some cases we're still getting some influence from the water. But overall, at this stage, other than weather issues presently, we're progressively ramping up and getting progressive increase in production on basically month by month. And this will continue into the pretty well into the second quarter, mid second quarter at which point we're pretty well be on a rhythm of normal mining going forward.
Okay. And just on like the specifically in the release, there was something on equipment availability moving in the workforce and like how what are the issues that you're encountering there?
Well, I think in the beginning late December and beginning of the year, a lot of focus has been put towards improving use of utilization for the equipment. We've had a lot of progress in that area where we're still lagging a bit and we're getting some support internally and externally is basically on maintenance. And I think we've sort of restructured their maintenance areas where because of delivery late delivery of some of the infrastructure, all our maintenance now done on the long haul truck is done exclusively through our Meadowbank maintenance facilities. And the hauling fleet and mining fleet at Amruth is essentially done at site with the warehouse present. So the reassembly of the team, the redistribution of the people essentially completed in Q4 and they're in the process of putting in the rest in place.
I think up until Q4, we still had significant amount of major rebuild going on. Those are not all complete, but they're less of a burden on the total crew. And basically, it's trying to get the availability up over the next few months.
Thank you.
Your next question comes from the line of Matthew Murphy from Barclays. Your line is open.
Hi. Just a question on costs. I mean, there's some discussion in the release about inflation, specifically consumables and labor. And I guess, how recent have you been seeing that? And to what degree do you think this is kind of a permanent move versus the fight to sort of improve productivity and get cost back down?
Well, I think the inflation has been relatively steady over the years. I think one of the biggest factors we're probably dealing with is we still have a fair proportion of contractor usage. And I think the with the current economical cycle, the quality of some of this manpower and the productivity of some of this manpower is sort of not necessarily helping, which is contributing to some cases greater costs. I think that has been more of the issue and probably more predominant in Nunavut actually.
Okay. And I mean depending on the trajectory for costs and the gold price, I got a question on the dividend. If we saw costs remaining fairly sticky and the gold price going back to $1400 or something like that, what's the thinking on funding the dividend?
The dividend at $0.80 is secure. From a cost perspective, as we said in the release, we expect to have unit costs lower as we move through 2020 and into 2021 2022, and we have a growing production base. So a combination of the growing production base and costs that are trending down on a unit cost basis allows us to pay that dividend of $200,000,000 roughly $200,000,000 a year.
Okay. Thank you.
Your next question comes from the line of Josh Wolfenstein from RBC. Your line is open.
Thank you. Going back to the Nunavut costs, I think historically if you had looked at the life of mine cost for Amaruq guidance, there was around $800 an ounce. Amelidin was in the low $600 per ounce. Would you expect changes to those long term numbers and what sort of order of magnitude would that be?
The cost for I'll start with the cost at Amaruq for now. I think this year's 2000 numbers, 2020 numbers are mostly aligned with the higher stripping ratio and the lower grade overall in the pit, which contributes to the lower production profile and essentially higher cash costs. We're also processing some low grade material also contributing to some of the cost but the proportion of high grade ore increases. But the proportion of high grade ore increases and that's the from year to year the production profile at Amruk will increase I think 120,000 ounces more next year. So the cost structure will come down with time.
At Meliadine, I think we have available capacity in the plant and so far the mine has responded quite well and we'll continue to ramp up tonnage wise. I think so far early in the year we're surpassing 4,000 tonnes per day from the underground mine. And we have stockpile on surface. So we will maximize that tonnage through time. And the cost will also come down a bit and go back to the life of mine numbers that we're showing at this stage.
Stage.
Okay. Maybe put another way on the I guess the historical cost targets. Is it safe to assume that the inflation experience Nunavut would be above that roughly 3% to 5% that was discussed in terms of the underlying sort of input related items?
Well, I think the first half of the year will show similar or some cost pressures. But as we pursue the ramp up and we get to, I guess, steady state, the costs are expected to go down because we've added quite a bit of resource to support our continuous improvements initiative to get productivity and cost structures down. So at this stage, we're expecting some and we've already seen some results so far. But the we're not just hoping that cost will go down. We're putting efforts and an action plan in place to ensure that.
Okay. And then second question on the cost side of things. For Mexico, we saw a general increase in 2019 costs over 2018 and the guidance seems similar year over year for 2020. Should we be assuming kind of steady state lanes yet Pinosalto's costs going forward at their current figures?
In short, yes. I think the cost that we saw last year cost we saw last year are from some instabilities that we had at Pinos Altos mainly. At La India, it was the effect of clay in the ore. But measures taken during 2019 were to mitigate those into bringing the cost down and bring the production up which is the underlying in 2020. So we'll see the cost reduce during 2020, but essentially where we are.
Okay. That's very helpful. Thank you.
Your next question comes from the line of Anita Soni from CIBC. Your line is open.
Good morning. Can you hear me?
Yes, we can.
Thanks. So my question, I guess, is a little bit on more on Meliadine. Not to put a too fine a point on it, but in terms of the throughput rates, you mentioned that you were at 4,000 in December. So once you have the apron feeder fixed, I guess, in the Q1, would you expect to get back up to the 4,000 tonne per day? Is like really low in Q1 and then Q2, Q3 rebound?
Well, when I said we're at 4,000 tons per day, that's the underground mine.
The
mill has been operated actually in 2019 anywhere between 3,000 up to almost 5,000 tons per day. So once the crushing part of the equation is out of the picture, it is expected to bring back up past 4,000 tonnes per day. And then in Q4, as we sequence mining wise with the pit comes into play, it's already expected that the mill will ramp up around 4,600 tons per day at that stage, but we'll probably be in a catch up mode before that.
Okay. And then just on the costs, not to beat a dead horse on the on Amaruq, but $145,000,000 how much of that is just equipment availability issues? And how much of that is just the fact that the mill is kind of or the milling rates are sort of 7,700 tonne per day and that's a 10,000 tonne per day mill? Like how much will it how much is it dependent on getting new ore sources in 2022?
Well, I think at this stage is mostly mining cost and grade. That's the big issue. I think our processing costs have been a little bit higher because we've been operating at lower tonnage, but that's part of the reality as we're ramping up. So I'm not sure I'm answering your question here.
I think you are. And then just in terms of the LaRonde sequencing, so you're moving to sort of a 350, level on the unit costs. Are the sorry, on the production side of the equation. Are the unit costs like is there room for improvement on the unit cost once you get the rock mechanics issued settled and figure out how to improve upon your mining there?
I'd have to say probably not. I think our biggest challenge going forward is that the as we continue to advance the mining sequence in the Laron deep, the overall tonnage per day keeps going down in life of mine sequence. So productivity is actually going down. So it will put pressure on the cost. We're doing some work on the adapting strategies around manpower and automation down the road, which will eventually become like the template for LR3 at depth.
But I think at this stage, I think our cost structure currently is pretty is going to stay pretty well in that range.
Okay. And the last one on Canadian Malartic. So Wendy, I think there I was discussing with Brian last night that there was issues in accessing some of the higher grades in the old stope workings. When do you think that will be resolved and when you'll get back into sort of more stabilized mining there?
Well, just adding to Larone, I think the although tonnage will be going down, the grade is going up and as the proportion of ore being mined from the western sector of the mine, Grades in that area are in excess of 8 grams per ton. So that sort of stabilized, although cost per ton are going up, the cash costs are basically staying flat. As far as Malartic is concerned, I think we have about 2.5 years of mining left in the pit. We will continue to deal with underground workings like we have in the past. I think the challenge will be to essentially continue to ramp up and we're getting good progress in Barnat.
We'll probably sequence some of the Barnat differently potentially. But it's a day to day challenge with the blasting. And at this stage, the biggest issue has been related towards the remote mucking basically. That's the biggest challenge that we've had and we're finishing some access work on the main ramps and on the walls that will be in the second half of the year will be easier for the operation.
Okay. And then sorry, can I just revert back to LaRonde? You mentioned the higher grades of 8 gram per tonne. Obviously, that's there are 2 ore sources there, right? So that's not going to be straight 8 gram per tonne material.
Yes. That's correct, yes.
But when you hit the 8 grams, what does that do to the rest of the byproducts? As I recall, is it gold, copper and silver zinc? Is that so you probably get higher copper, but lower silver and zinc?
Correct, yes. Okay. Copper goes up and zinc is almost non existent. Okay. All right.
That's it for my question. Thank you.
Your next question comes from the line of John Tamos. Your line is open.
Thank you for taking my call and thank you for your service to the company. Could you give us your philosophy on share buybacks? We all hate volatility and we got a little taste this morning. And second, could you talk a little bit about the step up in inferred resources this year? And you've got 55,000,000, 60,000,000 ounces total reserve and resources, which of the zones might get into reserves in year end 2020, 2021, 2022?
I know the documentation always takes longer.
Sure. Just on share buybacks, I think our focus with the increased cash flow will be to reduce overall debt. At this point, we're not contemplating share buybacks. I think we prefer to improve the strength of the balance sheet. As far as the increase in resources, I'll let Guy provide some of his color on that.
Hi, John. So basically, as you saw this year, we've been bringing more resources in Kukulun Lake, for example, as we are continuing to drill and grow the footprint of those deposits. Same thing Amaruq where we've been adding more drilling and enable through a study on the portion of the deposit above the permafrost limit to bring it into reserve and in Malartic as well where a continuous successful drilling at East Goldie has grown the newest Goldie zone. On the latest one, I think more drilling will be needed. So we're going to continue to expand the footprint to infill it.
So it's not going to end it up into the reserve anywhere soon because much more drilling will be needed to get there and better assess the viability. But we're making good progress and all expanding the footprint as well in Mexico on the Santa Clarotis where we've been a good contributor to the addition of the inferno. So I think we've been getting good news on several fronts from growing resources. And as you can understand, once in a while some of those projects will ended up being supported by a study and be converted into reserve. So it's an ongoing process.
This year we've brought additional satellite open pit at Meliadine into the reserve and brought them Europe underground. And we're working on the next big block that will be moved from resources to reserve.
Your next question comes from the line of Ralph Profiti from 8 Capital. Your line is open.
Hi there. Thanks for taking my questions. Firstly, I see that you've outlined the proportion of the West area at LaRonde terms of the ore feed. Just wondering what the plan or the mitigation strategy if you get into 2020 and in 2021 and those ground conditions sort of don't really support the mine plan as it stands now or your visibility, what would be the mitigation plan then?
We're sort of applying that already in Q1 because we've re sequenced the development into the eastern sector to compensate for the lost tonnage and the team has been quite successful at that. I think longer term to that, we're also in the process of developing other areas within the satellite ore bodies like Zone 11.3 at Busquay, which will bring some production down the road. So we are thinking all the time about providing not just risk tonnage, but also incremental tonnage to the plant because we've got available capacity. So I think that's the plan at this stage. And as far as the current period as far as increasing support in the Western sector is essentially to ensure production in that area.
And we're pretty confident at this stage that the activities that are being put in place will secure that production for the rest of the year.
I think I'll just add on that Ralph. As far as sort of strategy at LaRonde, the strategies into as we go deeper to take a very measured approach. So essentially, the cautious mine plan calls for about a 13% reduction in tonnage from the original plan as we move into the deeper part of the ore body. And the strategy over time is to ensure that we can access that higher grade material by boosting up the ground support in the major infrastructure. So that's just being cautious and that was a recommendation that came to us in January from the team there who have developed a pretty unique skill set around rock mechanics.
So I think that's critical to the future of LaRonde to be measured as we go deeper. But I think what we're finding in the Abbotipi is we look at some drilling we're seeing on the old Bousquet property, drilling we're getting at East Malartic, at East Goldie, there's still a lot of life in these old camps. But in order to access and take advantage and build value, as these resources grow, like John said, you need the skills to be able to go deeper. And we certainly see that also at Kirkland Lake, another old camp where we have a buildable mine at Upper Beaver. So I think the opportunity is there.
We just have to be measured cautious in the approach there, but we have some really good skills that have been developed that are all in house and we sort of take our lead from the team there on how we should approach it.
Yes. Thanks for that. Sean, if I
could stay with you on a different topic, You talked about this $360,000,000 payment due in April, 50% of it, which would be refinanced. It differs a little bit from what I've heard before, which is paying down debt as it comes due. How are you thinking about sort of capital allocation? Has this changed sort of in the first half of twenty twenty? Or is this cost of financing just too attractive?
I think it's cost of financing is very attractive. I think the stuff we're retiring now is 6.4% or 6.6%, 6.6%, Dave reminds me. And you probably replace that for an interest rate of less than half of that. So we will repay some of the gross debt. That's part of the plan, but we're just reviewing those alternatives over the next week or 2.
Got it. Okay. Yes, good clarity. Thank you.
Your next question comes from the line of Tanya Jakusconek from Scotiabank. Your line is open.
Good morning. I think that's me.
Good morning.
Yes, I know, right? Got to get an easier name. I just wanted to circle back, if I could, to Laurent, so that I just understand what's happening. How I interpreted it, what Yvonne was saying is that we've had a change in the mine plan in that as we've gone deeper with this, the rock mechanics, looks like this is going to be more a 360,000 ounce long term mine. Is that a correct way to interpret it?
I think the way you need to interpret it is that we cannot sequence as quickly as we had earlier anticipated in the Western sector. And that has been evident from the start of development in that zone. The biggest challenge that we have in that sector has not been mining so far, it's been the development. And the protocols that are necessary in the various headings are like much more important in that area. And the sequence at which we can adapt the rest of the sequence is like affected by it.
So this area is a very high grade sector and we just need to ensure that we do the mining properly. And so far we've had a lot of success production wise. We've had very little minimal impact on the production side and we intend to keep it that way. So that's part of why the reasons we're taking this pause to increase the support.
Yes. No, I appreciate that. I'm just thinking more from a longer term perspective. I think the camp when we talked about it was going to be ultimately about a 400,000 ounce producer camp. Is that still what you see excluding this area that you've talked about?
I think we talked a bit about lowering the tonnage. Ultimately, we've got to get to reserve grade. So I'm just wondering if the balance of lowering the tonnage and getting to reserve grade still keeps us at this 360,000 ounce rate or do we move back to that 400,000 ounce longer term?
We'll be in between the 2, I guess. We'll be in the 360,000 to 400,000. A lot of it will come from greater production from LZ5. As we get more productivity from that site, we also have a lot more flexibility from that site. We're going to maximize it to make sure the complex stays near its objective as much as possible.
Okay. Okay. That's helpful. Okay. Well, thank you for that.
If I can still just come back to none of it so that I, again, just summarize on my understanding of what has to be done at Amaruq to get the mine back on track. It appears that in the pit, what you need to get is just more surface areas exposed in there to get to your mining throughput, which you think you'll get there by mid year. And it looks like the maintenance now has been adjusted between what you're doing at Amaruq site versus what you're doing at Meadowbank. Is it just the utilization improvement of utilization of equipment that still has to be done to get you there? And if so, what else what's the timing on that?
Well, it's getting everybody up to speed and it's time. I think the we are doing all of this. We're trying to optimize probably in the most difficult period of the year under very difficult climatic conditions. So the speed at which we'll do this in Q1 is 1. We'll accelerate significantly in Q2.
But at this stage, more the equipment availability, particularly on the loading side. There's still some challenges equipment availability wise on the drilling side, but it's mostly on the loading side that we need to focus and get some of our digging equipment with more hours. The rest is okay at this stage.
Okay. Then just maybe on the Amaruq underground, if I could just ask, saw that you have some of the that guidance for production into your 2022 numbers and ultimately beyond, is it safe to assume on the capital side that that's most of the spend is in 2020, 2021?
It would be mostly second half if we would approve it and in 2021. Yes.
The most okay. And it would be in that $650,000,000 to $700,000,000 range that would be accounted for in that range in that guidance range?
Hello?
Yes, for next year. Okay.
Yes, yes. Thank you.
$650,000,000 to $700,000,000 in next year.
In next year, so it would be in there. Okay, perfect. And then if I could just ask one question on Meliadine. We talked about what's happening at the mill in terms of dealing with the apron feeder. Is that something that Yvonne we're going to need to replace or is it something that is fixable short term?
Yes. We're waiting for parts. It's a unit that's fabricated at Italy. It's a custom unit. So parts and delivery are very long.
So we're looking with a local supplier to provide parts that are fabricated to replace them. And the plan is to replace the unit after Bard Season later this summer. But once the new parts are put in, in March, we expect it to be back and running at normal capacity.
Okay. And then maybe just on the underground because we also have changed the mining sequence in the underground for lower grade. Can you just talk about what happened there for the 2020 plan?
Mostly, I think the sequence was pretty well mine as planned. The only area or RP3 area, which was we had a little bit more saline water in that sector and we needed to understand the behavior in that area. Some of these soaps were significant tonnage and significant grade, which sort of put pressure on the overall grade profile for the rest of the year. This will reserve itself probably in the second half of this year and we expect that the restart mining in that area. So I think we'll be back on grade profile from there.
Okay. So second half of the year. Okay, great. Thank you so much.
There are no further questions at this time. I turn the call back over to Mr. Boyd.
Thank you, operator, and thank you, everyone. If there's any sort of additional information as a follow-up to this call, please feel free to reach out and we can set up separate calls if you like. Thank you very much.
This concludes today's conference call. You may now disconnect.